CN102561389B - Construction method of underground diaphragm wall joint pipes - Google Patents

Construction method of underground diaphragm wall joint pipes Download PDF

Info

Publication number
CN102561389B
CN102561389B CN201210071470.8A CN201210071470A CN102561389B CN 102561389 B CN102561389 B CN 102561389B CN 201210071470 A CN201210071470 A CN 201210071470A CN 102561389 B CN102561389 B CN 102561389B
Authority
CN
China
Prior art keywords
concrete
diaphragm wall
perfusion
junction block
setting time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210071470.8A
Other languages
Chinese (zh)
Other versions
CN102561389A (en
Inventor
马文旭
李兴林
谭永强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal Jiangnan Construction Development Group Co Ltd
Original Assignee
JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI filed Critical JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI
Priority to CN201210071470.8A priority Critical patent/CN102561389B/en
Publication of CN102561389A publication Critical patent/CN102561389A/en
Application granted granted Critical
Publication of CN102561389B publication Critical patent/CN102561389B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a construction method of underground diaphragm wall joint pipes, which belongs to the technical field of construction of underground diaphragm walls and technically characterized by including the steps: firstly, excavating a trench on a reserved foundation and placing a reinforcement cage in the trench; secondly, hoisting joint pipes at reserved intervals; thirdly, pouring concrete with different initial setting and final setting times, and allowing the upper concrete and the lower concrete to simultaneously solidify and stand in pipe extracting after pouring; and fourthly, pulling the joint pipes when the upper concrete and the lower concrete solidify to the same extent to allow extraction of the pipes. The construction method is simple in operation, pipe extracting resistance is small, and the construction method is used for casting of underground diaphragm walls.

Description

A kind of job practices of underground diaphragm wall joint pipe
Technical field
The present invention relates to a kind of job practices of diaphragm wall, more particularly, relate in particular to a kind of job practices of diaphragm wall plane tie pipe.
Background technology
Diaphragm wall is exactly to carry out in advance grooving operation, forms the groove section of certain length, and then install reinforcing cage, pour concrete forming unit wall section in groove section couple together unit wall section and form one continuous underground reinforced concrete wall.Diaphragm wall can be constructed at complex condition, and construction depth is large, and support unit supporting capacity is large, and barrier performance is good, is the most reliable support pattern in pattern foundation pit supporting structure.Especially in layer of sand, reach stagnant water effect, must adopt diaphragm wall to be only support pattern the most reliably.At present, diaphragm wall, not only as interim space enclosing structure gear soil and sealing, is also made the form of three wall unifications of the permanent load-bearing external wall structure of basement simultaneously.
Diaphragm wall is that a width is constructed, and the method that underground continuous wall connector adopts is conventionally that the forms such as junction block, i iron, cross steel plate connect.Junction block is to apply at present the most general wall section type of attachment.
Existing junction block diameter is equal to or slightly less than groove section width, and adopts several sections of connections according to the groove section degree of depth, and junction will make periphery smooth, is convenient to extract.After grooving, junction block is lifted by crane to connect section by section and put into groove.Junction block after concrete cast casting complete certain hour, concrete can fixed self-support after, with very heavy jack-up, pull out junction block, until junction block is all pulled out.
It is very important in construction, correctly rising and pulling out junction block.Rise and to pull out too fast meeting and cause concrete to cave in because initial set is not fixed.Rise and to pull out late, concrete solidifies, rises to pull out resistance and increase, and can cause junction block to rise pulling out difficulty even pulling off.Selected the time of pulling out to extract junction block construction diaphragm wall vital.While extracting, should guarantee that concrete does not flow and caves in, and has made to pull out resistance minimum again.
Occur at present the larger diaphragm wall of many degree of depth, the degree of depth reaches 60 meters or higher, and often a width wall needs fluid concrete to reach 300 cubes~400 cubes, and the duration of pouring is long.Conventionally bottom concrete has reached curdled appearance, and top concrete casting complete not also.Therefore, concrete brings very large resistance to junction block, will bring difficulty as previously mentioned while pulling out junction block.Junction block cannot be extracted and will bring very many inconvenience to construction diaphragm wall.
Summary of the invention
The object of the present invention is to provide a kind of simple to operate, tube drawing resistance is little, can extract smoothly the job practices of the underground diaphragm wall joint pipe of junction block.
Technical scheme of the present invention is achieved in that a kind of job practices of underground diaphragm wall joint pipe, comprising following step: (1) excavates groove on predetermined ground, places reinforcing cage; (2) at predetermined interval location lifting junction block; (3) the perfusion initial set concrete different with final setting time makes the concrete that has poured into rear middle and lower part and middle and upper part can reach fixed self-support state when tube drawing simultaneously; (4) when top and the bottom concrete all reaches same solidifying and can extract state, pull junction block.
In the job practices of above-mentioned a kind of underground diaphragm wall joint pipe, described step (4) is specially: when junction block employing once pulls mode, concrete perfusion adopts the mode of disposable perfusion; When junction block adopts segmentation to pull mode, concrete perfusion adopts the repeatedly mode of perfusion, during each perfusion, pour into respectively the initial set concrete different with final setting time, make the concrete that has poured into rear lower and top can reach fixed self-support state when tube drawing simultaneously; Then sequentially complete perfusion and the tube drawing of each section, until poured into, junction block extracts ground.
In the job practices of above-mentioned a kind of underground diaphragm wall joint pipe, the described perfusion initial set concrete different with final setting time is: in predetermined influx height, to the groove of constructing diaphragm wall by under sequentially pour into the shorter and shorter concrete of initial set and final setting time upward.
In the job practices of above-mentioned a kind of underground diaphragm wall joint pipe, the described perfusion initial set concrete different with final setting time is specially: in predetermined influx height, to the middle and lower part of diaphragm wall adopt initial set and final setting time all long retarded concrete pour into a mould; To the middle and upper part of diaphragm wall, adopt conventional concrete to pour into a mould, after whole pouring concretes complete, top and the bottom concrete can reach same solidifying simultaneously can extract state.
The present invention adopts after said method, by regulating the top and the bottom concrete setting time, makes top and the bottom concrete when tube drawing, reach fixed self-support state simultaneously.Have advantages of that tube drawing resistance is little, effectively avoid occurring because resistance pulls off greatly the situation of junction block, meanwhile, the construction depth of connection wall under base area, can adopt identical method subsectin bottler, and according to concrete concretion state, junction block is extracted in segmentation.Adopt above-mentioned method, even if the very dark diaphragm wall of the casting degree of depth also can be extracted junction block easily, thereby guarantee the smooth construction of diaphragm wall.
Accompanying drawing explanation
Below in conjunction with the embodiment in accompanying drawing, the present invention is described in further detail, but do not form any limitation of the invention.
Fig. 1 is the construction schematic diagram of the embodiment of the present invention 1;
Fig. 2 is the construction schematic diagram of the embodiment of the present invention 2.
The specific embodiment
The job practices of a kind of underground diaphragm wall joint pipe of the present invention, comprises the steps: that (1) excavate groove on predetermined ground, places reinforcing cage; (2) at predetermined interval location lifting junction block; (3) the perfusion initial set concrete different with final setting time makes the concrete that has poured into rear lower and top can reach fixed self-support state when tube drawing simultaneously; (4) when junction block employing once pulls mode, concrete perfusion adopts the mode of disposable perfusion; When junction block adopts segmentation to pull mode, concrete perfusion adopts the repeatedly mode of perfusion, during each perfusion, pour into respectively the initial set concrete different with final setting time, make the concrete that has poured into rear lower and top can reach fixed self-support state when tube drawing simultaneously; Then sequentially complete perfusion and the tube drawing of each section, until poured into, junction block extracts ground.The wherein said perfusion initial set concrete different with final setting time is: in predetermined influx height, to the groove of constructing diaphragm wall by under sequentially pour into the shorter and shorter concrete of initial set and final setting time upward, adopt the concrete kind of different initial sets and final setting time, depending on Specific construction situation, if the diaphragm wall degree of depth is shorter, can adopt two kinds or the concrete of three kinds of initial sets and final setting time, if the degree of depth is longer, also can adopt a greater variety of concrete, or adopt the mode of segmentation to pour into.
Embodiment 1
Consult shown in Fig. 1, the job practices of a kind of underground diaphragm wall joint pipe of the present invention, comprises the steps: that (1) excavate groove on predetermined ground, places reinforcing cage; (2) at predetermined interval location lifting junction block; (3) in predetermined influx height, to construct the groove middle and lower part of diaphragm wall adopt initial set and final setting time all long retarded concrete pour into a mould; To constructing the groove middle and upper part of diaphragm wall, adopt conventional concrete to pour into a mould, make the concrete that has poured into rear lower and top can reach fixed self-support state when tube drawing simultaneously; (4) when top and the bottom concrete all reaches same solidifying and can extract state, directly pull junction block to ground.Be applicable to the to cast construction of diaphragm wall degree of depth junction block when dark of this method.
Embodiment 2
Consult shown in Fig. 2, the job practices of a kind of underground diaphragm wall joint pipe of the present invention, its implementation method is substantially the same manner as Example 1, difference is, pull junction block and adopt segmented mode, its concrete operations are: diaphragm wall to be cast is divided into tri-sections of A, B, C from lower to upper, first pours into a mould A section height, during perfusion, pour into respectively the initial set concrete different with final setting time, make the concrete that has poured into rear lower and top can reach fixed self-support state when tube drawing simultaneously; When top and the bottom concrete all reaches same solidifying and can extract state, by the height of junction block jack-up A section, make the lower end of junction block be positioned at the lower end of to be cast section of B, and then sequentially perfusion and the tube drawing of complete B, C section, until poured into, junction block extracts ground.Be applicable to the to cast construction of the darker junction block of the diaphragm wall degree of depth of this method.

Claims (4)

1. a job practices for underground diaphragm wall joint pipe, is characterized in that, comprises the steps: that (1) excavate groove on predetermined ground, places reinforcing cage; (2) at predetermined interval location lifting junction block; (3) the perfusion initial set concrete different with final setting time makes the concrete that has poured into rear middle and lower part and middle and upper part can reach fixed self-support state when tube drawing simultaneously; (4) when top and the bottom concrete all reaches same solidifying and can extract state, pull junction block.
2. the job practices of a kind of underground diaphragm wall joint pipe according to claim 1, is characterized in that, described step (4) is specially: when junction block employing once pulls mode, concrete perfusion adopts the mode of disposable perfusion; When junction block adopts segmentation to pull mode, concrete perfusion adopts the repeatedly mode of perfusion, during each perfusion, pour into respectively the initial set concrete different with final setting time, make the concrete that has poured into rear lower and top can reach fixed self-support state when tube drawing simultaneously; Then sequentially complete perfusion and the tube drawing of each section, until poured into, junction block extracts ground.
3. the job practices of a kind of underground diaphragm wall joint pipe according to claim 1 and 2, it is characterized in that, the described perfusion initial set concrete different with final setting time is: in predetermined influx height, to the groove of constructing diaphragm wall by under sequentially pour into the shorter and shorter concrete of initial set and final setting time upward.
4. the job practices of a kind of underground diaphragm wall joint pipe according to claim 3, it is characterized in that, the described perfusion initial set concrete different with final setting time is specially: in predetermined influx height, to construct the groove middle and lower part of diaphragm wall adopt initial set and final setting time all long retarded concrete pour into a mould; To constructing the groove middle and upper part of diaphragm wall, adopt conventional concrete to pour into a mould, after whole pouring concretes complete, top and the bottom concrete can reach same solidifying simultaneously can extract state.
CN201210071470.8A 2012-03-16 2012-03-16 Construction method of underground diaphragm wall joint pipes Active CN102561389B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210071470.8A CN102561389B (en) 2012-03-16 2012-03-16 Construction method of underground diaphragm wall joint pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210071470.8A CN102561389B (en) 2012-03-16 2012-03-16 Construction method of underground diaphragm wall joint pipes

Publications (2)

Publication Number Publication Date
CN102561389A CN102561389A (en) 2012-07-11
CN102561389B true CN102561389B (en) 2014-02-19

Family

ID=46407869

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210071470.8A Active CN102561389B (en) 2012-03-16 2012-03-16 Construction method of underground diaphragm wall joint pipes

Country Status (1)

Country Link
CN (1) CN102561389B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113062324A (en) * 2021-03-15 2021-07-02 中国水电基础局有限公司 Concrete pouring method for concrete cut-off wall
CN113550312A (en) * 2021-07-28 2021-10-26 青海大学 Method for lowering and pulling joint pipe of seepage-proofing construction wall

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02266013A (en) * 1989-04-06 1990-10-30 Kajima Corp Constructing underground continuous impervious wall
CN101886402A (en) * 2010-07-13 2010-11-17 中铁三局集团有限公司 Diaphragm wall seam waterproof method and diaphragm wall construction method based on same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02266013A (en) * 1989-04-06 1990-10-30 Kajima Corp Constructing underground continuous impervious wall
CN101886402A (en) * 2010-07-13 2010-11-17 中铁三局集团有限公司 Diaphragm wall seam waterproof method and diaphragm wall construction method based on same

Also Published As

Publication number Publication date
CN102561389A (en) 2012-07-11

Similar Documents

Publication Publication Date Title
CN102535441A (en) Construction method of underground diaphragm wall
CN103981898A (en) Integral open-excavation node top-down underground engineering construction method
CN206298900U (en) A kind of diaphram wall built-in type steel encloses purlin plug system
CN107023032A (en) A kind of cast-in-place method of pipe gallery
CN106284362A (en) A kind of construction method of single catheter perfusion Large Underwater bottom concrete
CN105155562B (en) For the construction method of deep basal pit spring sealing
CN206467695U (en) A kind of joint for sinking type empty stomach diaphram wall
CN102561389B (en) Construction method of underground diaphragm wall joint pipes
CN104790381B (en) Lining wall concrete pouring inversing method based on UEA micro-expanding agent
CN106930278A (en) A kind of method that compromise joint pipe is used for support pile occlusion
CN103122642A (en) Construction method of vertical post support change
CN105178356B (en) Setting-up construction method for vertical joint bars of columns in reverse building method
CN104032742B (en) A kind of Placement of Underwater Concrete for Casting technique based on DLC four hopper
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN203782691U (en) Underwater pouring type pipe column provided with retaining wall and internal mold system thereof
CN106436721B (en) The construction method of diaphram wall built-in type steel purlin plug system
CN108104112B (en) A kind of underground wall body construction method based on the slurrying of original soil original position
CN206448276U (en) A kind of reverse construction short section borehole wall pouring structure
CN203049588U (en) Pit-in-pit cylindrical mould
CN214993751U (en) Novel embedded sleeve milling joint
CN204509922U (en) Underpasses structure
CN112854283A (en) Round platform type connecting structure of pile column structure of penetrating structure bottom plate and construction method thereof
CN206319362U (en) Partly water plant concrete structure under water
CN207469308U (en) A kind of prefabricated assembled inspection shaft of circle
CN108018859B (en) Emergency treatment method and structure for sudden surge of foundation pit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 510170 East Finance Building 1002-1007, 140 Dongfeng West Road, Guangzhou, Guangdong Province

Patentee after: China Coal Jiangnan Construction Development Co., Ltd.

Address before: 510170 East Finance Building 1002-1007, 140 Dongfeng West Road, Guangzhou, Guangdong Province

Patentee before: Guangdong China Coal Jiangnan Foundation Engineering Co., Ltd.

CP01 Change in the name or title of a patent holder
CP03 Change of name, title or address

Address after: Unit 1002-1007, 140 Dongfeng West Road, Yuexiu District, Guangzhou, Guangdong 510000

Patentee after: China Coal Jiangnan Construction Development Group Co., Ltd

Address before: 510170 East Finance Building 1002-1007, 140 Dongfeng West Road, Guangzhou, Guangdong Province

Patentee before: CHINA COAL JIANGNAN CONSTRUCTION DEVELOPMENT Co.,Ltd.

CP03 Change of name, title or address