CN102535302B - Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof - Google Patents
Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof Download PDFInfo
- Publication number
- CN102535302B CN102535302B CN201110460705.8A CN201110460705A CN102535302B CN 102535302 B CN102535302 B CN 102535302B CN 201110460705 A CN201110460705 A CN 201110460705A CN 102535302 B CN102535302 B CN 102535302B
- Authority
- CN
- China
- Prior art keywords
- pavement
- bedding
- ramp
- main
- standard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Road Paving Structures (AREA)
Abstract
本发明涉及一种用于超浅埋暗挖地下工程的临时路面铺盖结构及施工方法,包括主铺盖结构、橡胶垫、斜坡道铺盖结构、反压钢板铺面结构及道钉;主铺盖结构由若干主铺盖结构标准套件焊接构成,主铺盖结构标准套件由若干底部缀条板、若干中部工字钢以及一块顶部印花钢板焊接构成,斜坡道铺盖结构由若干斜坡道铺盖结构标准套件焊接构成,斜坡道铺盖结构标准套件由底部缀条板、中部斜向变高度工字钢以及顶部印花钢板焊接构成;临时路面铺盖结构下方满铺有橡胶垫,在斜坡道铺盖结构与两侧路面相交的位置设置有反压钢板铺面结构。施工时,倒边施工的办法。本发明的结构及施工方法结构简单、施工方便快捷、对地面交通影响小、对地下工程减载作用效果显著。
The invention relates to a temporary pavement pavement structure and a construction method for ultra-shallow underground excavation, including a main pavement structure, a rubber pad, a ramp road pavement structure, a counter-pressure steel plate pavement structure and spikes; the main pavement structure consists of several The main bedding structure standard kit is welded. The main bedding structure standard kit is composed of several bottom strips, some middle I-beams and a top printed steel plate. The ramp bedding structure is composed of several ramp bedding structure standard kits. The ramp The standard set of pavement structure is composed of slatted boards at the bottom, I-beams with variable height in the middle and printed steel plates at the top; rubber pads are fully paved under the pavement pavement structure, and rubber pads are installed at the intersection of the bedding structure of the ramp and the road surfaces on both sides. Counter pressure steel plate pavement structure. During construction, the method of downside construction. The structure and construction method of the present invention are simple in structure, convenient and fast in construction, have little influence on ground traffic, and have remarkable effect on load reduction of underground engineering.
Description
技术领域 technical field
本发明涉及一种铺设在城市道路路面上施工的临时路面铺盖结构,尤其涉及一种用于超浅埋暗挖地下工程的临时路面铺盖结构及施工方法。The invention relates to a temporary pavement pavement structure laid on urban roads, in particular to a temporary pavement pavement structure and a construction method for ultra-shallow buried excavation underground projects.
背景技术 Background technique
在浅埋暗挖地下工程下穿道路施工中,常采用超前支护及初期支护的方法加固地下工程的围岩,尤其是顶部围岩,使其保持稳定且不产生过大的变形,能够承受上方土体重量和路面车辆荷载的作用。但是,由于岩土条件差、覆土厚度薄、地下管线多等因素的不利影响,超前支护和初期支护不能有效实施,或经加固的地层承载能力仍然不足以抵抗上部地层及荷载的作用,造成路面塌陷,危及行车安全,甚至带来生命财产损失。目前,对于浅埋地下工程,常在地面铺设10~20mm厚钢板作为辅助措施。但是由于厚度有限,抗弯刚度小,扩散降低荷载的作用是有限的,根据材料力学原理分析,单纯增加钢板厚度取得的收效甚微。另外钢板在车辆荷载作用下,发生竖向振动,反而会增加竖向动力荷载;钢板受到车辆行驶或制动过程中水平力的反复作用,发生纵向窜动。In the construction of underground roads under shallow buried underground excavation, the method of advanced support and initial support is often used to reinforce the surrounding rock of the underground project, especially the top surrounding rock, to keep it stable without excessive deformation, which can Bear the weight of the soil above and the load of the road vehicle. However, due to the adverse effects of factors such as poor rock and soil conditions, thin covering soil, and many underground pipelines, advance support and initial support cannot be effectively implemented, or the bearing capacity of the reinforced strata is still not enough to resist the upper stratum and the load. Cause road subsidence, endanger driving safety, and even bring loss of life and property. At present, for shallow buried underground projects, 10-20mm thick steel plates are often laid on the ground as an auxiliary measure. However, due to the limited thickness and low bending stiffness, the role of diffusion to reduce the load is limited. According to the analysis of the principles of material mechanics, simply increasing the thickness of the steel plate has little effect. In addition, under the action of the vehicle load, the steel plate vibrates vertically, which will instead increase the vertical dynamic load; the steel plate is subjected to repeated horizontal forces during the driving or braking process of the vehicle, resulting in longitudinal movement.
发明内容 Contents of the invention
本发明的目的在于提供一种结构简单、施工方便快捷、对地面交通影响小、对地下工程减载作用好的用于超浅埋暗挖地下工程的临时路面铺盖结构及施工方法。通过采用临时路面铺盖结构,采用型钢组合结构,大幅度增加铺盖结构的抗弯刚度,同时在铺盖结构两侧设置斜坡道,保证路面车辆以一定的限速安全行驶,减少车辆荷载直接对地下工程顶部围岩的作用。The purpose of the present invention is to provide a temporary pavement structure and construction method for ultra-shallow buried excavation underground engineering with simple structure, convenient and fast construction, little impact on ground traffic, and good effect on underground engineering load reduction. By adopting temporary pavement pavement structure and steel composite structure, the bending rigidity of the pavement structure is greatly increased. At the same time, ramps are set on both sides of the pavement structure to ensure that road vehicles can run safely at a certain speed limit, reducing vehicle loads directly to the underground works. The role of the top surrounding rock.
本发明采用的技术方案如下:The technical scheme that the present invention adopts is as follows:
一种用于超浅埋暗挖地下工程的临时路面铺盖结构,其特征在于:在浅埋暗挖地下工程上方路面设置有临时路面铺盖结构,其铺设范围沿道路纵向长度以能够覆盖地下结构施工可能影响到的范围为宜,横向能够覆盖所有机动车道。临时施工路面铺盖结构包括主铺盖结构、橡胶垫、斜坡道铺盖结构、反压钢板铺面结构及道钉;所述主铺盖结构由若干主铺盖结构标准套件焊接构成,所述主铺盖结构标准套件由若干底部缀条板、若干中部工字钢以及一块顶部印花钢板焊接构成,顶部印花钢板、底部缀条板与中部工字钢直接焊接,每两块底部缀条板间隔0.5m~1.0m距离,从而使工人在此间隔距离能够将顶部钢板与中部工字钢进行焊接。顺桥向并排设置的主铺盖结构标准套件之间采用纵向通长钢筋焊接构成主铺盖结构;主铺盖结构两端设置有斜坡道铺盖结构,主铺盖结构与斜坡道铺盖结构之间的横桥向采用横向通长钢筋焊接,纵横向通长钢筋的直径根据顶部钢板的厚度来选用,以保证铺面平顺为宜;所述斜坡道铺盖结构由若干斜坡道铺盖结构标准套件焊接构成,所述斜坡道铺盖结构标准套件由底部缀条板、中部斜向变高度工字钢以及顶部印花钢板焊接构成,底部缀条板、中部斜向变高度工字钢以及顶部印花钢板的焊接方式与主铺盖结构标准套件的焊接方式相同,中部斜向变高度工字钢是采用完整的工字钢斜向切割而成,顺桥向并排设置的斜坡道铺盖结构标准套件之间采用纵向通长钢筋焊接构成斜坡道铺盖结构;在主铺盖结构和两侧斜坡道铺盖结构下方满铺有10~15mm厚橡胶垫,作为施工临时路面铺盖结构连续弹性基础;在斜坡道铺盖结构与两侧路面相交的位置设置有反压钢板铺面结构,反压钢板铺面结构中的反压钢板一端通过横向通长钢筋焊接于斜坡道铺盖结构上,另一端通过道钉与路面连接固定,道钉通过在路面上打孔后植入锚固的方式把反压钢板固定在路面上。A temporary pavement pavement structure for ultra-shallow buried excavation underground engineering, characterized in that: a temporary pavement pavement structure is arranged on the pavement above the shallow buried underground excavation project, and the paving range is along the longitudinal length of the road to cover the construction of the underground structure The range that may be affected is suitable, and the horizontal direction can cover all motor vehicle lanes. Temporary pavement pavement structure includes main bedding structure, rubber pad, ramp bedding structure, counter pressure steel plate pavement structure and spikes; said main bedding structure is composed of several standard sets of main bedding structures welded, and said main bedding structure standard set consists of Several bottom slats, several middle I-beams and a top printed steel plate are welded. The top printed steel plate, the bottom slats and the middle I-steel are directly welded. The distance between each two bottom slats is 0.5m~1.0m. This enables workers to weld the top steel plate to the middle I-beam at this distance. The main bedding structure standard kits arranged side by side along the bridge direction are welded with longitudinal long steel bars to form the main bedding structure; the two ends of the main bedding structure are provided with ramp bedding structures, and the transverse bridge direction between the main bedding structure and the ramp bedding structure It is welded with horizontal full-length steel bars, and the diameter of vertical and horizontal full-length steel bars is selected according to the thickness of the top steel plate to ensure that the pavement is smooth; the ramp bedding structure is composed of several standard sets of ramp bedding structures welded. The standard set of bedding structure is composed of bottom slatted plate, middle oblique variable-height I-beam and top printed steel plate welded. The welding method of the suite is the same. The oblique variable-height I-beam in the middle is cut obliquely from the complete I-beam. The ramp bedding structure standard sets arranged side by side along the bridge direction are welded with longitudinal long steel bars to form the ramp. Pavement structure; 10-15mm thick rubber pads are fully paved under the main bedding structure and the ramp bedding structures on both sides, as a continuous elastic foundation for the construction temporary road bedding structure; Pressure steel plate pavement structure, one end of the reverse pressure steel plate in the reverse pressure steel plate pavement structure is welded to the ramp pavement structure through a horizontal long steel bar, and the other end is connected to the road surface through spikes, which are implanted and anchored after drilling holes on the road surface Way to fix the anti-pressure steel plate on the road.
所述主铺盖结构按车道宽度分块预制,分块数即主铺盖结构标准套件数等于上下行机动车行车道的总数,分块的长度大于等于地下工程的跨度,其中,主铺盖结构标准套件的宽度按具体车道的标准宽度选择确定,分为3.0m、3.5m、3.75m、4.0m这4种,主铺盖结构标准套件的长度按地下结构的跨度确定,且大于等于地下结构的跨度;斜坡道铺盖结构也按机动车道数来分块,分块数即斜坡道铺盖结构标准套件数同样等于上下行机动车道的总数,斜坡道铺盖结构标准套件的长度按3.5%的坡度确定,以保证行车较为顺畅,斜坡道铺盖结构标准套件的宽度与主铺盖结构标准套件的宽度相同。路面铺盖结构的总长(为主铺盖结构标准套件长加两个斜坡道铺盖结构标准套件的长度),按式计算,其中,b为地下工程结构的宽度,H为地下工程结构下边缘底面到路面的深度,φ为H深度范围内各土层的内摩擦角加权平均值。The main bedding structure is prefabricated in blocks according to the width of the lane. The number of blocks, that is, the number of standard sets of the main bedding structure is equal to the total number of up and down motor vehicle lanes, and the length of the blocks is greater than or equal to the span of the underground project. Among them, the standard set of the main bedding structure The width is determined according to the standard width of the specific lane, which is divided into 4 types: 3.0m, 3.5m, 3.75m, and 4.0m. The length of the main bedding structure standard kit is determined according to the span of the underground structure, and is greater than or equal to the span of the underground structure; The ramp bedding structure is also divided into blocks according to the number of motor vehicle lanes. The number of blocks is equal to the total number of up and down motor vehicle lanes. The traffic is smoother, and the width of the ramp pavement standard kit is the same as that of the main pavement standard kit. The total length of the pavement pavement structure (the length of the main pavement structure standard kit plus the length of the two ramp pavement standard kits), according to the formula Calculation, where b is the width of the underground engineering structure, H is the depth from the bottom surface of the lower edge of the underground engineering structure to the road surface, and φ is the weighted average value of the internal friction angle of each soil layer within the depth range of H.
所述的一种用于浅埋暗挖地下工程施工的临时路面铺盖结构,铺盖结构由主铺盖结构、斜坡道铺盖结构、反压钢板铺面及底部密铺橡胶垫等套件组成。主铺盖结构由顶部印花钢板、中部工字钢及底部缀板组成,按标准车道宽度预制,现场整体吊装铺设;斜坡道铺盖结构由顶部印花钢板、中部斜向切削的工字钢及底部缀板组成,也按标准车道宽度预制,现场整体吊装铺设;反压钢板铺面在道路横向上按单幅路宽设计,在道路纵向上宽度设计以4~6m为宜。各标准套件之间顶部钢板采用敷设填缝钢筋焊接的方法联接,反压钢板通过锚固在路面内的道钉固定在路面上。The above-mentioned temporary pavement pavement structure for shallow buried underground engineering construction is composed of a main pavement structure, a ramp pavement structure, a counter-pressure steel plate pavement, and a densely paved rubber pad at the bottom. The main bedding structure is composed of printed steel plates at the top, I-beams in the middle and decorative plates at the bottom, which are prefabricated according to the standard lane width and hoisted and laid on site as a whole; the bedding structure of the ramp is composed of printed steel plates at the top, I-beams cut obliquely in the middle and decorative plates at the bottom The composition is also prefabricated according to the standard lane width, hoisted and laid as a whole on site; the anti-pressure steel plate pavement is designed according to a single road width in the transverse direction of the road, and the width design in the longitudinal direction of the road is preferably 4-6m. The top steel plates between the standard kits are connected by laying and filling steel bars and welded, and the counter-pressure steel plates are fixed on the road surface through spikes anchored in the road surface.
上述用于浅埋暗挖地下工程的临时施工路面铺盖结构的施工方法为:The construction method of above-mentioned temporary construction pavement covering structure that is used for shallow buried underground excavation engineering is:
铺设临时施工路面铺盖结构时采用倒边施工的方法,即先封闭一侧的半幅道路进行临时路面铺盖结构铺设,铺设完成后开通该单侧道路临时路面铺盖结构的运行;然后,封闭另一侧道路进行另一半幅道路临时施工路面铺盖结构的铺设,铺设完成后设置中间隔离栏和两侧护栏;最后,临时施工路面铺盖结构双方向开通运行,其具体施工步骤为:When laying the pavement pavement structure of temporary construction, the method of pouring side construction is adopted, that is, half of the road on one side is closed first to lay the temporary pavement pavement structure, and after the laying is completed, the operation of the temporary pavement pavement structure of the road on one side is opened; then, the other side is closed The pavement pavement structure of the other half of the road will be paved temporarily. After the paving is completed, the middle fence and guardrails on both sides will be set up; finally, the pavement pavement structure of the temporary construction will be opened in both directions. The specific construction steps are as follows:
第一步:测量放线,确定施工路面铺盖结构的位置;The first step: measure and set out the line, and determine the position of the construction pavement pavement structure;
第二步:先封闭一侧的半幅道路进行施工路面铺盖结构铺设,首先铺设作为施工路面铺盖结构连续弹性基础的橡胶垫;The second step: first close the half-width road on one side to lay the pavement pavement structure, and first lay the rubber pad as the continuous elastic foundation of the pavement pavement structure;
第三步,在橡胶垫上铺设若干主铺盖结构标准套件,主铺盖结构标准套件在工厂焊接成整体,运到现场后整体吊装安放;The third step is to lay a number of standard sets of main bedding structure on the rubber mat. The standard sets of main bedding structure are welded into a whole in the factory, and the whole set is hoisted and installed after being transported to the site;
第四步,铺设斜坡道铺盖结构标准套件,斜坡道铺盖结构标准套件在工厂焊接成整体,运到现场后整体吊装安放;The fourth step is to lay the standard set of bedding structure of the ramp. The standard set of bedding structure of the ramp is welded into a whole in the factory, and it is hoisted and installed as a whole after being transported to the site;
第五步,顺桥向并排设置的若干主铺盖结构标准套件之间通过纵向通长钢筋焊接连接,构成主铺盖结构;顺桥向并排设置的若干斜坡道铺盖结构标准套件之间也采用纵向通长钢筋焊接,构成斜坡道铺盖结构;主铺盖结构两端与斜坡道铺盖结构之间横桥向采用横向通长钢筋焊接;In the fifth step, several standard sets of main bedding structures arranged side by side along the bridge direction are welded and connected by longitudinal long steel bars to form the main bedding structure; The long steel bar is welded to form the bedding structure of the ramp; the cross-bridge direction between the two ends of the main bedding structure and the bedding structure of the ramp is welded with transverse long steel bars;
第六步,重复第二步至第五步,封闭另一侧道路进行另一半幅道路临时施工路面铺盖结构的铺设;The sixth step is to repeat the second step to the fifth step, to close the road on the other side and carry out the laying of the pavement pavement structure for the temporary construction of the other half of the road;
第六步,在斜坡道铺盖结构上铺设反压钢板,反压钢板的上部一端通过横向通长钢筋焊接于斜坡道铺盖结构中间,下部另一端通过道钉与路面连接固定;The sixth step is to lay the counter-pressure steel plate on the bedding structure of the ramp. One end of the upper part of the counter-pressure steel plate is welded to the middle of the bedding structure of the ramp through a horizontal full-length steel bar, and the other end of the lower part is connected to the road surface through spikes;
第七步,设置中间隔离栏和两侧防护栏,恢复双向通车。The seventh step is to set up the middle isolation fence and the protective fences on both sides to resume two-way traffic.
通车过程中,设专职安全员24小时值守,发现局部部件脱落或不平顺时,及时采取补救措施或防护措施,确保行车安全。During the opening process, a full-time safety officer is on duty 24 hours a day, and when some parts are found to be falling off or not smooth, remedial measures or protective measures are taken in time to ensure driving safety.
有益效果Beneficial effect
本发明的用于浅埋暗挖地下工程的临时施工路面铺盖结构及其施工方法结构简单、施工方便快捷、对地面交通影响小、对地下工程减载作用好,其低高度的型钢与钢板组成的施工路面铺盖,抗弯刚度大幅度增加,在车辆通过时荷载由施工路面铺盖结构通过分载作用,减轻了路面车辆荷载对地下工程顶部围岩的作用。在铺盖结构与路面间铺设一层10~15mm厚橡胶垫层以增加铺盖结构与路面间的摩擦力,减少竖向和纵向振动,降低了车辆动荷载的作用,同时对路面也起到一定的保护作用,防止破坏路面。在斜坡道的与地面接触处,设有反压钢板,防止斜坡道端部翘起,危及行车安全。铺盖结构通过锚固道钉固定在路面上,不会发生纵向窜动。因此此结构具有很好的应用前景。The temporary construction pavement pavement structure and its construction method for shallow buried underground engineering of the present invention are simple in structure, convenient and fast in construction, have little impact on ground traffic, and have good load reduction effect on underground engineering. The construction pavement pavement, the bending rigidity is greatly increased, and the load is divided by the construction pavement pavement structure when the vehicle passes, which reduces the effect of the road vehicle load on the top surrounding rock of the underground project. Lay a layer of 10-15mm thick rubber cushion between the pavement structure and the road surface to increase the friction between the pavement structure and the road surface, reduce vertical and longitudinal vibration, reduce the effect of vehicle dynamic load, and also play a certain role on the road surface Protection against damage to the road surface. At the place where the ramp is in contact with the ground, there is a counter-pressure steel plate to prevent the end of the ramp from lifting and endangering the driving safety. The pavement structure is fixed on the road surface by anchor spikes, and there will be no longitudinal movement. Therefore, this structure has a good application prospect.
附图说明Description of drawings
图1是本发明的结构平面示意图;Fig. 1 is a schematic plan view of the structure of the present invention;
图2是本发明图一的施工路面铺盖结构纵截面示意图;Fig. 2 is the schematic diagram of the longitudinal section of the construction pavement pavement structure of Fig. 1 of the present invention;
图3是本发明图一的施工路面铺盖结构横截面示意图Fig. 3 is the schematic cross-sectional view of the construction pavement pavement structure of Fig. 1 of the present invention
图4是本发明图二的主铺盖结构标准套件平面示意图;Fig. 4 is the main bedding structure standard suite plan schematic diagram of Fig. 2 of the present invention;
图5是本发明图二的主铺盖结构标准套件纵截面示意图;Fig. 5 is the schematic diagram of the longitudinal section of the main bedding structure standard suite of Fig. 2 of the present invention;
图6是本发明图二的主铺盖结构标准套件横截面示意图;Fig. 6 is the main bedding structure standard suite cross-sectional schematic diagram of Fig. 2 of the present invention;
图7是本发明图二的主铺盖结构标准套件缀板结构详图;Fig. 7 is a detailed view of the main bedding structure standard kit panel structure of Fig. 2 of the present invention;
图8是本发明图二的斜坡板铺盖结构标准套件平面示意图;Fig. 8 is a schematic plan view of the standard kit of the slope slab bedding structure of Fig. 2 of the present invention;
图9是本发明图二的斜坡板铺盖结构标准套件纵截面示意图;Fig. 9 is a schematic diagram of the longitudinal section of the standard suite of the slope slab bedding structure of Fig. 2 of the present invention;
图10是本发明图二的斜坡板铺盖结构标准套件横截面示意图;Fig. 10 is a schematic cross-sectional view of the standard suite of the slope slab bedding structure of Fig. 2 of the present invention;
图中:In the picture:
1-主铺盖结构标准套件;2-斜坡板铺盖结构标准套件;3-反压钢板铺面结构;4-路面;5-橡胶垫;6-底部缀条板;7-中部工字钢;8-顶部印花钢板;9-通长钢筋;10-中部斜向变高度工字钢;11-道钉;12-反压钢板;13-地下工程;14-潜在破裂面;15-道路边沿线;16-中间隔离栏。1-Standard set of main bedding structure; 2-Standard set of slope slab bedding structure; 3-Reverse pressure steel plate pavement structure; 4-Pavement; 5-Rubber pad; Printed steel plate at the top; 9- long steel bar; 10- oblique variable height I-beam in the middle; 11- spike; 12- counter pressure steel plate; 13- underground engineering; 14- potential rupture surface; -Middle divider.
具体实施方式 Detailed ways
某地铁出入口采用超前埋暗挖下穿一繁华街道,通道长49.99m,结构顶覆土厚度1.79~2.94m,地下结构型式采用平顶直墙单层单跨结构,开挖断面为7.60m×4.95m、9.50m×6.35m(人防段)、7.80m×4.95m 3种断面。The entrance and exit of a certain subway is excavated in advance to pass through a busy street. The length of the channel is 49.99m, and the thickness of the top covering soil of the structure is 1.79-2.94m. m, 9.50m×6.35m (civilian air defense section), 7.80m×4.95m 3 kinds of sections.
如图1-10所示,本发明的一种用于超浅埋暗挖地下工程的临时路面铺盖结构,在浅埋暗挖地下工程13上方路面4设置有临时路面铺盖结构,临时施工路面铺盖结构包括主铺盖结构、橡胶垫、斜坡道铺盖结构、反压钢板铺面结构及道钉;主铺盖结构由若干主铺盖结构标准套件1焊接构成,主铺盖结构标准套件1由若干底部缀条板6、若干中部工字钢7以及一块顶部印花钢板8焊接构成,每两块底部缀条板6间隔0.5m~1.0m距离,顺桥向并排设置的主铺盖结构标准套件1之间采用纵向通长钢筋9焊接构成主铺盖结构;主铺盖结构两端设置有斜坡道铺盖结构,主铺盖结构与斜坡道铺盖结构之间的横桥向采用横向通长钢筋9焊接;斜坡道铺盖结构由若干斜坡道铺盖结构标准套件2焊接构成,斜坡道铺盖结构标准套件2由底部缀条板6、中部斜向变高度工字钢10以及顶部印花钢板8焊接构成,顺桥向并排设置的斜坡道铺盖结构标准套件2之间采用纵向通长钢筋9焊接构成斜坡道铺盖结构;主铺盖结构标准套件1和斜坡道铺盖结构标准套件2在金属加工场内焊接拼装而成,整体运输至施工现场,采用100t汽车吊整体吊装铺设就位。在主铺盖结构和两侧斜坡道铺盖结构下方满铺有10~15mm厚橡胶垫5;在斜坡道铺盖结构与两侧路面4相交的位置设置有反压钢板铺面结构3,反压钢板铺面结构3中的反压钢板12一端通过横向通长钢筋9焊接于斜坡道铺盖结构上,另一端通过道钉11与路面4连接固定。As shown in Fig. 1-10, a kind of temporary pavement pavement structure that is used for ultra-shallow underground excavation underground engineering of the present invention, the pavement 4 above shallow buried
其中,主铺盖结构按车道宽度分块预制,分块数即主铺盖结构标准套件1数等于上下行机动车行车道的总数,分块的长度大于等于地下工程13的跨度,其中,主铺盖结构标准套件1的宽度按具体车道的标准宽度选择确定,分为3.0m、3.5m、3.75m、4.0m 4种,主铺盖结构标准套件1的长度按地下工程的跨度确定,且大于等于地下工程13的跨度;斜坡道铺盖结构也按机动车道数来分块,分块数即斜坡道铺盖结构标准套件2数同样等于上下行机动车道的总数,斜坡道铺盖结构标准套件2的长度按3.5%的坡度确定,斜坡道铺盖结构标准套件2的宽度与主铺盖结构标准套件1的宽度相同;路面铺盖结构的总长L按式计算,其中,b为地下工程13的宽度,H为地下工程下边缘底面到路面4的深度,φ为H深度范围内各土层的内摩擦角加权平均值。Among them, the main bedding structure is prefabricated in blocks according to the width of the driveway. The number of blocks is equal to the total number of up and down motor vehicle lanes, and the length of the block is greater than or equal to the span of the
上述用于超浅埋暗挖地下工程的临时路面铺盖结构的施工方法,其特征在于:The above-mentioned construction method for the temporary pavement covering structure of the ultra-shallow underground excavation project is characterized in that:
铺设临时施工路面铺盖结构时采用倒边施工的方法,即先封闭一侧的半幅道路进行临时路面铺盖结构铺设,铺设完成后开通该单侧道路临时路面铺盖结构的运行;然后,封闭另一侧道路进行另一半幅道路临时施工路面铺盖结构的铺设,铺设完成后设置中间隔离栏16和两侧护栏;最后,临时施工路面铺盖结构双方向开通运行,其具体施工步骤为:When laying the pavement pavement structure of temporary construction, the method of pouring side construction is adopted, that is, half of the road on one side is closed first to lay the temporary pavement pavement structure, and after the laying is completed, the operation of the temporary pavement pavement structure of the road on one side is opened; then, the other side is closed The other half of the road is paved with a pavement pavement structure for temporary construction. After the pavement is completed, the
第一步:测量放线,确定施工路面铺盖结构的位置;The first step: measure and set out the line, and determine the position of the construction pavement pavement structure;
第二步:先封闭一侧的半幅道路进行施工路面铺盖结构铺设,首先铺设作为施工路面铺盖结构连续弹性基础的橡胶垫;The second step: first close the half-width road on one side to lay the pavement pavement structure, and first lay the rubber pad as the continuous elastic foundation of the pavement pavement structure;
第三步,在橡胶垫5上铺设若干主铺盖结构标准套件1,主铺盖结构标准套件1在工厂焊接成整体,运到现场后整体吊装安放;In the third step, several main bedding structure standard kits 1 are laid on the rubber pad 5, and the main bedding structure standard kits 1 are welded into a whole in the factory, and are hoisted and installed as a whole after being transported to the site;
第四步,铺设斜坡道铺盖结构标准套件2,斜坡道铺盖结构标准套件2在工厂焊接成整体,运到现场后整体吊装安放;The fourth step is to lay the ramp bedding structure standard kit 2. The ramp bedding structure standard kit 2 is welded into a whole in the factory, and it is hoisted and installed as a whole after being transported to the site;
第五步,顺桥向并排设置的若干主铺盖结构标准套件1之间通过纵向通长钢筋9焊接连接,构成主铺盖结构;顺桥向并排设置的若干斜坡道铺盖结构标准套件2之间也采用纵向通长钢筋9焊接,构成斜坡道铺盖结构;主铺盖结构两端与斜坡道铺盖结构之间横桥向采用横向通长钢筋9焊接;In the fifth step, several main bedding structure standard sets 1 arranged side by side along the bridge direction are welded and connected through longitudinal
第六步,重复第二步至第五步,封闭另一侧道路进行另一半幅道路临时施工路面铺盖结构的铺设;The sixth step is to repeat the second step to the fifth step, to close the road on the other side and carry out the laying of the pavement pavement structure for the temporary construction of the other half of the road;
第六步,在斜坡道铺盖结构上铺设反压钢板12,反压钢板12的上部一端通过横向通长钢筋9焊接于斜坡道铺盖结构中间,下部另一端通过道钉11与路面4连接固定;The sixth step is to lay the
第七步,设置中间隔离栏16和两侧防护栏,恢复双向通车。The seventh step is to set up the
通车过程中,设专职安全员24小时值守,发现局部部件脱落或不平顺时,及时采取补救措施或防护措施,确保行车安全。During the opening process, a full-time safety officer is on duty 24 hours a day, and when some parts are found to be falling off or not smooth, remedial measures or protective measures are taken in time to ensure driving safety.
以上是本发明的一个典型实施例,本发明的实施不限于此。The above is a typical embodiment of the present invention, and the practice of the present invention is not limited thereto.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110460705.8A CN102535302B (en) | 2011-12-31 | 2011-12-31 | Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110460705.8A CN102535302B (en) | 2011-12-31 | 2011-12-31 | Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102535302A CN102535302A (en) | 2012-07-04 |
| CN102535302B true CN102535302B (en) | 2014-01-01 |
Family
ID=46343211
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201110460705.8A Expired - Fee Related CN102535302B (en) | 2011-12-31 | 2011-12-31 | Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102535302B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6375334B2 (en) * | 2016-04-19 | 2018-08-15 | 植村 誠 | Road lining method |
| CN106759367A (en) * | 2017-02-24 | 2017-05-31 | 中铁大桥勘测设计院集团有限公司 | The temporary road laying method of open-cut foundation ditch |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003055905A (en) * | 2001-08-07 | 2003-02-26 | Nikko Co Ltd | Temporary road mat footboard |
| CN101225742A (en) * | 2007-10-17 | 2008-07-23 | 中铁十八局集团有限公司 | Construction method of shallow buried underground excavating tunnel super large section using PBA method |
| JP2010007348A (en) * | 2008-06-26 | 2010-01-14 | Save Machine Co Ltd | Method of temporarily paving manhole recessed area during repairing of manhole |
| CN202090263U (en) * | 2011-05-10 | 2011-12-28 | 长安大学 | Emergency road slab capable of being assembled quickly |
| CN202482727U (en) * | 2011-12-31 | 2012-10-10 | 北京工业大学 | Temporary road surface pavement structure for ultra-shallow burying excavation underground project |
-
2011
- 2011-12-31 CN CN201110460705.8A patent/CN102535302B/en not_active Expired - Fee Related
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003055905A (en) * | 2001-08-07 | 2003-02-26 | Nikko Co Ltd | Temporary road mat footboard |
| CN101225742A (en) * | 2007-10-17 | 2008-07-23 | 中铁十八局集团有限公司 | Construction method of shallow buried underground excavating tunnel super large section using PBA method |
| JP2010007348A (en) * | 2008-06-26 | 2010-01-14 | Save Machine Co Ltd | Method of temporarily paving manhole recessed area during repairing of manhole |
| CN202090263U (en) * | 2011-05-10 | 2011-12-28 | 长安大学 | Emergency road slab capable of being assembled quickly |
| CN202482727U (en) * | 2011-12-31 | 2012-10-10 | 北京工业大学 | Temporary road surface pavement structure for ultra-shallow burying excavation underground project |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102535302A (en) | 2012-07-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103518019B (en) | rail track sleeper support body | |
| CN104213514B (en) | A kind of earthing corrugated steel-concrete combination arch bridge add strong method | |
| KR100814388B1 (en) | How to raise a bridge while driving | |
| US7470092B2 (en) | System and method for reinforcing aggregate particles, and structures resulting therefrom | |
| CN103711056A (en) | Steel tool type temporary construction road and construction method thereof | |
| CN111254779A (en) | Embedding structure and method for improving pavement cracking around luminous floor tiles | |
| CN102535302B (en) | Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof | |
| CN202482727U (en) | Temporary road surface pavement structure for ultra-shallow burying excavation underground project | |
| KR100571525B1 (en) | Extension method of bridge using concrete structure | |
| JP6144726B2 (en) | Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method | |
| CN202849877U (en) | Split type roadbed structure | |
| CN113944107B (en) | A kind of land low pier bridge roadbed filling type upper bridge channel and its construction method | |
| CN111926649A (en) | Reinforced integrally-built crossing plate for railway special line and line rail fixing device | |
| Salamak | Typical damages and protections of concrete bridges located on areas with ground deformations | |
| CN219690300U (en) | Frame bridge supporting structure | |
| CN219033054U (en) | Guardrail of buttress type retaining wall | |
| CN221988992U (en) | A highway subgrade structure | |
| CN110644308A (en) | A construction method for paving road on soft foundation of debris flow | |
| CN223269028U (en) | Concrete platform slab and level crossing | |
| CN117005290B (en) | Assembled steel temporary bridge and construction method thereof | |
| CN104278623B (en) | A kind of construction method of energy dissipation type semi-integral bridge abutment structure | |
| CN215758299U (en) | Prefabricated assembled steel-mixed cantilever structure system for widening roads | |
| CN219793507U (en) | Assembled construction passageway | |
| CN204356627U (en) | A kind of jointing apparatus of cement concrete pavement | |
| EP4372150A1 (en) | Double-profile concrete barrier |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140101 Termination date: 20161231 |

