CN203668815U - Concrete prefabricated section assembled pier - Google Patents
Concrete prefabricated section assembled pier Download PDFInfo
- Publication number
- CN203668815U CN203668815U CN201320758471.XU CN201320758471U CN203668815U CN 203668815 U CN203668815 U CN 203668815U CN 201320758471 U CN201320758471 U CN 201320758471U CN 203668815 U CN203668815 U CN 203668815U
- Authority
- CN
- China
- Prior art keywords
- sections
- concrete prefabricated
- anchor block
- prefabricated section
- bridge pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 18
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 6
- 239000010959 steel Substances 0.000 claims abstract description 6
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 17
- 239000003822 epoxy resin Substances 0.000 claims description 4
- 229920000647 polyepoxide Polymers 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 9
- 238000004873 anchoring Methods 0.000 abstract 5
- 229910000754 Wrought iron Inorganic materials 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000011065 in-situ storage Methods 0.000 description 2
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 2
- 239000011178 precast concrete Substances 0.000 description 2
- 230000002421 anti-septic effect Effects 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005538 encapsulation Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000003755 preservative agent Substances 0.000 description 1
- 230000002335 preservative effect Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Abstract
The utility model discloses a concrete prefabricated section assembled pier which comprises M first sections, N second sections, steel base plates, bolts, pre-stress ribs, anchoring blocks, a foundation and a top plate, wherein the M is larger than or equal to one, and the N is lager than or equal to one. One ends of the pre-stress ribs are anchored in the foundation, the other ends of the pre-stress ribs are anchored on the first section connected with the top plate, the M first sections and the N second sections are alternatively arranged between the foundation and the top plate, the anchoring blocks are arranged on the inner walls of the first sections, the pre-stress ribs are arranged along the inner walls of the first sections, penetrate through through holes pre-formed in the anchoring blocks on the inner walls of the first sections, and are fixed to the anchoring blocks through the bolts, and the steel base plates are arranged between the bolts and the anchoring blocks. According to the concrete prefabricated section assembled pier, the temporary supporting cost during pouring is reduced, and the construction period is shortened.
Description
Technical field
The utility model belongs to civil engineering bridge field, is specifically related to a kind of concrete prefabricated section assembling bridge pier.
Background technology
Precast assembly bridge pier, due to advantages such as its easy construction, duration are short, good endurance, is studied abroad and is applied, and is widely used in Oversea bridge engineering and offshore construction platform.The research of domestic section assembling construction technology is relative less with application, mainly concentrate in bridge superstructure, the nearly more than ten years just start for lower bridge pier structure, and the larger bottom precast construction recently completing is the constructure scheme of section assembling bridge pier as employings such as Donghai Bridge, Hangzhou Gulf Great Bridge, Changjiang River Bridge Shanghais.
From construction angle, bridge pier can be divided into integral cast-in-situ and prefabricated installation.Wherein, integral cast-in-situ bridge pier has good resistance to overturning, but its support cost is very high, the duration is relatively long.Precast Concrete Segmental Bridges bridge pier is by bridge pier vertically, be divided into some parts by certain modulus, builds then on-site consolidation at precasting yard on the ground.In China's Practical Project, section assembling bridge pier at present adopts wet seam to connect, adopt the mode of posttension prestressing with bond that sections is connected into entirety, but, between sections joint face, often can cause rod iron or steel hinge line corrosion owing to contacting leakiness, in addition, also need in preserved pipeline, be in the milk, working procedure complexity.
China is in extensive transport development period, the suitable application area of substructure section assembling construction technology just such as overhead road of city and bridge pier over strait.Therefore, study the assembled bridge pier of a kind of assembled precast concrete segment easy, durable practicality and just seem particularly urgent.
Summary of the invention
The purpose of this utility model is to provide a kind of concrete prefabricated section assembling bridge pier, while solving in prior art monobloc cast concrete pier, temporary supporting cost is high, the construction period long and while adopting wet seam splicing between sections contact closely, easily do not grind one's teeth and the problem such as rod iron easy-to-rust.
The technical solution that realizes the utility model object is: a kind of concrete prefabricated section assembling bridge pier, comprises M the first sections, N the second sections, billet, bolt, presstressed reinforcing steel, anchor block, basis, top board, wherein M >=1, N >=1; One end of presstressed reinforcing steel is anchored in basis, the other end is anchored on the first sections being connected with top board, between basis and top board, be arranged alternately M the first sections and N the second sections, on the first sections inwall, anchor block is set, presstressed reinforcing steel is along the inwall setting of the first sections, and through the through hole of offering in advance in the anchor block on the first sections inwall, be bolted on anchor block, between bolt and anchor block, be provided with billet.
The utility model compared with prior art, its remarkable advantage: mutual socket joint between (1) sections, can form the machine-processed horizontal loads of resisting of effective shearing resistance; (2) by external stretch-draw prestressing force rod iron or steel hinge line, can guarantee to connect closely between sections contact surface, there is good impermeable and durability performance, in reducing rod iron easy-to-rust risk, also facilitate operating personnel's construction and detected; (3) adopt and carry out preservative treatment on presstressed reinforcing steel surface, avoided this working procedure of duct grouting, the phase, assembled speed was fast, effectively the reduction of erection time; (4) meet with after earthquake, the convenient effective prestress size that checks, can mend if desired tension prestress or change rod iron.
Accompanying drawing explanation
Fig. 1 is the intersegmental connection diagram of concrete prefabricated section assembling bridge pier of the present utility model.
Fig. 2 is the A-A sectional drawing of concrete prefabricated sections 1 of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail.
In conjunction with Fig. 1 and Fig. 2, a kind of concrete prefabricated section assembling bridge pier, comprises M the first sections 1, N the second sections 2, billet 3, bolt 4, presstressed reinforcing steel 5, anchor block 7, basis 8, top board 9, wherein M >=1, N >=1; One end of presstressed reinforcing steel 5 is anchored in basis 8, the other end is anchored on the first sections 1 being connected with top board 9, between basis 8 and top board 9, be arranged alternately M the first sections 1 and N the second sections 2, on the first sections 1 inwall, anchor block 7 is set, presstressed reinforcing steel 5 is along the inwall setting of the first sections 1, and through the through hole 10 of offering in advance in the anchor block 7 on the first sections 1 inwall, be fixed on anchor block 7 by bolt 4, between bolt 4 and anchor block 7, be provided with billet 3.
Also comprise connector 6, between adjacent presstressed reinforcing steel 5, connect by connector 6.
On the joint face between the first sections 1, the second sections 2, basis 8 and top board 9, apply epoxy resin.
Presstressed reinforcing steel 5 is prestressed steel bar or prestress wire.
So that being set between basis 8 and top board 9,1 and 3 the second sections 2 of 2 the first sections briefly explain as example, first, should complete at the scene that basic 8 templates are set up, assembling reinforcement and reservedly wear muscle through hole, penetrate afterwards prestress wire 5, water underpin 8 concrete and fixing prestress wire 5, then with lifting machine, second sections 2 is vertically placed on basis 8, on the second sections 2, put again first sections 1, by brushwork epoxy resin to sections with basis, joint face between sections and sections carries out joint treatment, subsequently will be through antiseptic prestress wire 5(external surface brushwork epoxy resin or zinc-plated) aim at through the reserved through hole 10 in anchor block 7, employing jack pair prestress wire 5 carries out stretch-draw and is fixed in the top of anchor block 7, lift by crane successively more afterwards another two second sections 2 and another first sections 1, until each sections lay in place after, interspersed prestress wire 5, adjacent prestress wire 5 connects by connector 6, joint is positioned at the second sections 2, the same jack that adopts is anchored at the presstressed reinforcing steel of upper end 5 in the first sections 1 being connected with top board 9, finally, place a block concrete top board 9 at prefabricated subsection 1 top and carry out encapsulation process, so just each prefabricated subsection closely can be assembled into a common stressed bridge abutment integral.Can guarantee closely to connect between prefabricated subsection by this connected mode, can effectively improve sealing and the durability performance of bridge pier.
Claims (5)
1. a concrete prefabricated section assembling bridge pier, it is characterized in that: comprise M the first sections (1), N the second sections (2), billet (3), bolt (4), presstressed reinforcing steel (5), anchor block (7), basis (8), top board (9), wherein M >=1, N >=1, one end of presstressed reinforcing steel (5) is anchored in basis (8), the other end is anchored on the first sections (1) being connected with top board (9), between basis (8) and top board (9), be arranged alternately M the first sections (1) and N the second sections (2), on the first sections (1) inwall, anchor block (7) is set, presstressed reinforcing steel (5) is along the inwall setting of the first sections (1), and through the through hole (10) of offering in advance in the anchor block (7) on the first sections (1) inwall, be fixed on anchor block (7) by bolt (4), between bolt (4) and anchor block (7), be provided with billet (3).
2. concrete prefabricated section assembling bridge pier according to claim 1, is characterized in that: also comprise connector (6), between adjacent presstressed reinforcing steel (5), connect by connector (6).
3. concrete prefabricated section assembling bridge pier according to claim 2, is characterized in that: connector (6) is not arranged in anchor block (7), must be complete through the presstressed reinforcing steel (5) of through hole (10) in anchor block (7).
4. concrete prefabricated section assembling bridge pier according to claim 1, is characterized in that: on the joint face between the first sections (1), the second sections (2), basis (8) and top board (9), apply epoxy resin.
5. concrete prefabricated section assembling bridge pier according to claim 1, is characterized in that: presstressed reinforcing steel (5) is prestressed steel bar or prestress wire.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320758471.XU CN203668815U (en) | 2013-11-27 | 2013-11-27 | Concrete prefabricated section assembled pier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320758471.XU CN203668815U (en) | 2013-11-27 | 2013-11-27 | Concrete prefabricated section assembled pier |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203668815U true CN203668815U (en) | 2014-06-25 |
Family
ID=50965131
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320758471.XU Expired - Lifetime CN203668815U (en) | 2013-11-27 | 2013-11-27 | Concrete prefabricated section assembled pier |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203668815U (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612038A (en) * | 2015-01-22 | 2015-05-13 | 宁波大学 | Flange-connecting concrete-filled double-wall steel pipe prefabricated assembly piers with additional dampers |
CN105369739A (en) * | 2015-12-07 | 2016-03-02 | 中铁大桥局上海工程有限公司 | Bridge prefabricated structure assembly connection method and bridge |
CN105386405A (en) * | 2015-12-09 | 2016-03-09 | 北京工业大学 | Precast segment assembled concrete filled steel tube bridge pier based on bolted connection |
CN105714673A (en) * | 2016-02-18 | 2016-06-29 | 东南大学 | Self-restoration FRP-steel-concrete composite structure pier stud and construction method |
US9777499B2 (en) * | 2015-03-13 | 2017-10-03 | National Applied Research Laboratories | Precast segment, stacking structure and energy dissipation column thereof |
CN108179696A (en) * | 2018-01-31 | 2018-06-19 | 中交第二航务工程勘察设计院有限公司 | A kind of post-tensioned prestressing precast hollow formula bridge pier rod structure and construction method |
CN108411770A (en) * | 2018-03-02 | 2018-08-17 | 中国市政工程西北设计研究院有限公司 | The lateral anchor bolts of modularization precast pier construct and its construction method |
CN110820545A (en) * | 2019-11-08 | 2020-02-21 | 冯涛 | Assembled concrete pier |
CN110847018A (en) * | 2019-11-12 | 2020-02-28 | 山东交通学院 | Assembled concrete pier and construction method thereof |
CN110886230A (en) * | 2019-12-13 | 2020-03-17 | 安徽文天信息科技有限公司 | A high strength rapid Assembly type bridge strutting arrangement for construction |
CN114517440A (en) * | 2022-01-28 | 2022-05-20 | 中铁二十局集团第四工程有限公司 | Large-section arch rib and construction method thereof |
-
2013
- 2013-11-27 CN CN201320758471.XU patent/CN203668815U/en not_active Expired - Lifetime
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612038A (en) * | 2015-01-22 | 2015-05-13 | 宁波大学 | Flange-connecting concrete-filled double-wall steel pipe prefabricated assembly piers with additional dampers |
US9777499B2 (en) * | 2015-03-13 | 2017-10-03 | National Applied Research Laboratories | Precast segment, stacking structure and energy dissipation column thereof |
CN105369739A (en) * | 2015-12-07 | 2016-03-02 | 中铁大桥局上海工程有限公司 | Bridge prefabricated structure assembly connection method and bridge |
CN105369739B (en) * | 2015-12-07 | 2018-01-12 | 中铁大桥局上海工程有限公司 | The method and bridge of the assembled connection of bridge prefabrication structure |
CN105386405A (en) * | 2015-12-09 | 2016-03-09 | 北京工业大学 | Precast segment assembled concrete filled steel tube bridge pier based on bolted connection |
CN105714673A (en) * | 2016-02-18 | 2016-06-29 | 东南大学 | Self-restoration FRP-steel-concrete composite structure pier stud and construction method |
CN105714673B (en) * | 2016-02-18 | 2017-05-10 | 东南大学 | Self-restoration FRP-steel-concrete composite structure pier stud and construction method |
CN108179696A (en) * | 2018-01-31 | 2018-06-19 | 中交第二航务工程勘察设计院有限公司 | A kind of post-tensioned prestressing precast hollow formula bridge pier rod structure and construction method |
CN108411770A (en) * | 2018-03-02 | 2018-08-17 | 中国市政工程西北设计研究院有限公司 | The lateral anchor bolts of modularization precast pier construct and its construction method |
CN108411770B (en) * | 2018-03-02 | 2023-12-08 | 中国市政工程西北设计研究院有限公司 | Transverse anchor bolt connection structure of modularized precast pier and construction method thereof |
CN110820545A (en) * | 2019-11-08 | 2020-02-21 | 冯涛 | Assembled concrete pier |
CN110847018A (en) * | 2019-11-12 | 2020-02-28 | 山东交通学院 | Assembled concrete pier and construction method thereof |
CN110886230A (en) * | 2019-12-13 | 2020-03-17 | 安徽文天信息科技有限公司 | A high strength rapid Assembly type bridge strutting arrangement for construction |
CN110886230B (en) * | 2019-12-13 | 2021-05-07 | 江苏省交通工程集团有限公司 | A high strength rapid Assembly type bridge strutting arrangement for construction |
CN114517440A (en) * | 2022-01-28 | 2022-05-20 | 中铁二十局集团第四工程有限公司 | Large-section arch rib and construction method thereof |
CN114517440B (en) * | 2022-01-28 | 2023-12-12 | 中铁二十局集团第四工程有限公司 | Large-section arch rib and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203668815U (en) | Concrete prefabricated section assembled pier | |
CN104929034B (en) | A kind of modularization steel reinforced concrete rapid construction small box girder bridge and its construction method | |
CN110512647B (en) | Partial assembly type subway station structure design and construction method | |
CN107165272A (en) | Prestressing force assembly concrete frame joint attachment structure and its construction method | |
CN207194146U (en) | Prestressing force assembly concrete frame joint attachment structure | |
CN108342982B (en) | Self-anchoring structure at bearing cable beam end of cable crane of cable stayed bridge of mixed composite beam | |
CN103266574A (en) | Simply-supported box girder bridge strengthening method with oblique cables | |
CN108867310A (en) | The short rib T beam bridge of pretensioning prestressed concrete and its construction method | |
CN103938546A (en) | Simple-supported continuous construction method and structure thereof | |
CN104153287A (en) | Segmental assembled concrete frame pier system with self-reset function and method | |
CN109610315A (en) | The dry joint connecting structure of prefabrication and assembly construction floorings and implementation method | |
CN110258789A (en) | A kind of beam-column connection and its construction method that energy consumption rod iron is replaceable | |
CN103924680A (en) | Precast concrete beam and square-rectangular concrete-filled steel tube column combining joint employing unbonded prestressed and ordinary reinforcement for connection | |
CN203768810U (en) | Prefabricated bridge deck space steel pipe concrete truss combined beam | |
CN108411769A (en) | A kind of assembled device of prefabricated pier shaft and prefabricated bent cap | |
CN204753604U (en) | A excavation supporting system for expanding soil district | |
CN205046464U (en) | Prefabricated assembled concrete bridge mound | |
CN103614974A (en) | Prestress sectional steel reinforcing system of reinforced concrete arch shell bridge body | |
CN107100322B (en) | Post stretching vertical prestressing cast-in-place concrete rod structure and construction method | |
CN204059179U (en) | A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck | |
CN206887745U (en) | A kind of section assembling FRP using SMA strengthens concrete pier of steel tube | |
CN103924679B (en) | Prestressed concrete beam and circular steel pipe concrete column combined joint connected with regular rebars | |
CN107246094B (en) | Superposed reinforced concrete slab structure capable of bearing heavy load and manufacturing method | |
CN103510458B (en) | Pile type continuous rigid frame bridge and construction method thereof | |
CN203475289U (en) | Pile type continuous rigid frame bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20140625 |
|
CX01 | Expiry of patent term |