CN101225742A - Construction method of shallow buried underground excavating tunnel super large section using PBA method - Google Patents

Construction method of shallow buried underground excavating tunnel super large section using PBA method Download PDF

Info

Publication number
CN101225742A
CN101225742A CNA2007100599130A CN200710059913A CN101225742A CN 101225742 A CN101225742 A CN 101225742A CN A2007100599130 A CNA2007100599130 A CN A2007100599130A CN 200710059913 A CN200710059913 A CN 200710059913A CN 101225742 A CN101225742 A CN 101225742A
Authority
CN
China
Prior art keywords
tunnel
construction
section
arch
pba
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007100599130A
Other languages
Chinese (zh)
Other versions
CN100464055C (en
Inventor
童顺军
黄广锴
安建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CNB2007100599130A priority Critical patent/CN100464055C/en
Publication of CN101225742A publication Critical patent/CN101225742A/en
Application granted granted Critical
Publication of CN100464055C publication Critical patent/CN100464055C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to a method of shallow embedment and concealed excavation based on the PBA method for construction on super large cross-section of tunnel, comprising the following steps: 1. to detect the geologic cavity over the wide span tunnel structure; 2. to arrange the ground dewatering well and the tunnel horizontal well; 3. to take the horizontal channels of vertical well as the front large pipe shed on the arch part of the main body and to inject for strengthening the terrain formation; 4. to carry out the supporting arch construction on the side span of small pilot tunnel and the supporting major arch construction on the main body; 5. to excavate the soil mass of lower cross section as the extended foundation and the central partition wall; 6. to remove the bottom central partition wall section by section, construct bottom underlayer and waterproof layer, pour the reinforced concrete; 7. to remove the central partition wall of the upper part section by section and temporary steel shotcrete in the small pilot tunnel, construct the waterproof layer and concrete of the side wall and the main arch. The method of shallow embedment and concealed excavation based on the PBA method for construction on super large cross-section of tunnel has the advantages of guaranteeing the safety, quality and time limit of the construction, saving cost and enhancing work efficiency.

Description

Utilize the PBA method to carry out the job practices of shallow buried covered excavation tunnel large section
Technical field:
The invention belongs to a kind of construction techniques, the particularly a kind of PBA of utilization method is carried out the job practices of shallow buried covered excavation tunnel large section.
Background technology:
Present domestic construction technology level of striding the tunnel greatly, the job practices that is fit to select for use mainly contains cut and cover method and shallow burial hidden digging.Wherein shallow burial hidden digging comprises the double side wall pilot tunnel method again and is striding " PBA " method that adopted the subway station greatly.But, these methods for the surrounding enviroment complexity, underground utilities are intensive, geological conditions is poor, rich groundwater, and the big construction environment of section span all exists different defectives and limitation.
1, the operating mode that cut and cover method is various for traffic above-ground, underground utilities are various must be carried out pipeline and be changed to move with traffic and discongest during construction, the suffered interference of therefore constructing is big, long in time limit; In addition, carry out pipeline change temporarily move and sapce charge with high, less economical.
2, the shallow buried covered excavation double side wall pilot tunnel method of Cai Yonging,, surrounding enviroment complexity poor, relate to and influence the various construction environment of underground utilities for the tunnel geology condition, totally unfavorable to superstructure pipeline and surrounding enviroment security control, construction risk is big, analyzes theoretically to be difficult to guarantee safety.
And the PBA method is because its scope of application is wider, be applicable to stratum, the tunnel excavation that geological conditions is very poor, span is big, surface settlement is strict, and can reduce surface settlement, to remove the temporary lining workload less relatively, simplified construction technology, work efficiency is higher, thereby be applied in the construction of striding the subway station greatly, still also be not applied in the construction of longspan tunnel.
Summary of the invention:
Purpose of the present invention just is to overcome above-mentioned the deficiencies in the prior art, and provide a kind of PBA of utilization method to carry out the job practices of shallow buried covered excavation tunnel large section, this job practices can guarantee construction safety, quality and duration, but and cost saving, improves work efficiency.
Technical scheme of the present invention is: a kind of PBA of utilization method is carried out the job practices of shallow buried covered excavation tunnel large section, it is characterized in that: carry out according to the following step:
(1) detects for cavity, longspan tunnel superstructure stratum;
(2) arrange horizontal well in surface precipitation well and the hole;
(3) utilize vertical shaft transverse passage-way (pipe canopy operating room) to apply the leading bassoon canopy in main body arch, and pre-grouting and reinforcing stratum;
(4) little pilot tunnel of construction and pre-buried connecting reinforcement;
(5) set up little pilot tunnel grid bow member, and be connected with pre-buried connecting reinforcement;
(6) to just propping up concrete perfusion fill concrete behind in the pilot tunnel;
(7) excavation left and right side arch is set up the main arch grid, and is connected with pre-buried connecting reinforcement;
(8) pilot tunnel under pilot tunnel and the right side applies mid-board and bottom to support temporarily under on the left of the excavation;
(9) the section soil body applies expansion basis and median septum under the excavation;
(10) bottom median septum is removed in segmentation, and construction bottom cushion, waterproofing course are built steel concrete;
(11) segmentation remove temporary steel support in top median septum and the little pilot tunnel, apply abutment wall and main arch waterproofing course, concrete.
Above-mentioned bassoon canopy apply the method that adopts the seamless steel pipe segmentation to set, longitudinal lap joint between every section.
The construction of above-mentioned bassoon canopy adopts the boring static pressure to head into method construction, equipment choosing HXY-500M geological drilling rig.
The detection in cavity, above-mentioned longspan tunnel superstructure stratum adopts ground penetrating radar to detect the GPR technology.
Above-mentioned little pilot tunnel grid adopts overlap welding to be connected with embedded bar, and the main arch grid adopts overlap welding to be connected with connecting reinforcement, makes it to connect into integral body with little pilot tunnel grid.
The present invention has following advantage and good effect:
(1) broken through in the past " PBA " method and only limited to and be used for multispan multilayer underground station and parking lot shallow buried and underground excavated engineering project project, " PBA " method that solved is applied to an integrated technology difficult problem in the shallow buried covered excavation single span large section tunnel.
(2) adopt ground penetrating radar to detect the detection in cavity, stratum, the section of striding tunnel structure top greatly of (GPR) technology, it is poor to have solved at formation condition, and the surrounding enviroment complexity is constructed and disturbed under the big situation, carry out how carrying out the difficult problem that the cavity, stratum is detected before shallow buried covered excavation strides constructing tunnel greatly;
(3) adopt the treatment measures of horizontal well precipitation in well point+hole, ground, " PBA " method that solved is effectively striden the difficult problem of tunnel shallow buried covered excavation groundwater treatment when constructing greatly at water enrichment area.
(4) adopt the boring static pressure to head into, and set up pipe canopy operating room way at the agent structure middle part, it is limited to have solved construction operation space, and upper pipeline is intensive, under the high situation of pipe roof construction precision, settlement request, and the technical difficult problem that the pipe canopy of growing up applies;
(5) after the grid steelframe connects job practices, solved that to stride tunnel " PBA " worker's method button arch working security greatly poor, twice button arch connects the not high technical difficult problem of precision;
(6) select rational temporary lining dismounting, support replacement method and two lining concrete support systems for use, guaranteed to stride greatly the safety of structure in the tunnel double-lining construction temporary lining demolishing process, guaranteed the construction quality of large section concrete structure.
Description of drawings:
Fig. 1 is construction process figure of the present invention.
Fig. 2 is a precipitation well construction process chart.
Fig. 3 is that bassoon canopy in main body arch is provided with schematic diagram.
Fig. 4 is a pipe canopy section construction floor map.
Fig. 5 is the pipe roof construction flow chart.
Fig. 6 is a button arch construction schematic diagram.Wherein, Fig. 6-the 1st, construct little pilot tunnel and pre-buried connecting reinforcement schematic diagram; Button arch schematic diagram in Fig. 6-the 2nd, little pilot tunnel; Fig. 6-the 3rd, backfill pilot tunnel inner concrete schematic diagram; Fig. 6-the 4th, arch grid schematic diagram is also set up in excavation arch (No. 1 pilot tunnel), left side; Arch grid schematic diagram is also set up in Fig. 6-5 excavation arch, right side (No. 2 pilot tunnels); Fig. 6-the 6th, the excavation left side is pilot tunnel (No. 3 pilot tunnels) down, applies the bottom and supports schematic diagram temporarily; Fig. 6-the 7th, excavation arch, right side (No. 4 pilot tunnels) applies the bottom and supports schematic diagram temporarily.
The specific embodiment:
The yellow interval large section tunnel of reviving is four, No. ten line interconnection sidings of Beijing Metro section, is that single hole is three-way by the transition of single hole two-wire, and vault stalk type section is adopted in design.Simultaneously the section of striding tunnel is divided into the section of three kinds of different sizes again according to line alignment greatly: section E, mileage K2+240.3~K2+262.5, long 22.2m, span 15.076m, highly 9.3m; Section E ', mileage K2+262.5~K2+282.3, long 19.8m, span 15.937m, high 9.855m; Section F, mileage K2+282.3~K2+296.3, long 14.0m, span 17.5m, height 10.5m.Its job practices is carried out according to the following step: (as shown in Figure 1)
1, detect for cavity, longspan tunnel superstructure stratum:
This detection operations has adopted the advanced at present high-resolution U.S. to produce SIR-2 type ground penetrating radar detection system both at home and abroad.This ground penetrating radar configuration center frequency 100MHz antenna, the reliable detection degree of depth can satisfy this engineering demand about 6m.
Get along agent structure center, tunnel and tunnel external structure line outside 5m direction and arrange 3 surveys line, receive and carry out the data processing by the get off situation of back wave of instrument record according to reception antenna.
2, arrange horizontal well in surface precipitation well and the hole:
Survey data show the influence that the yellow interval section of striding greatly of Soviet Union is dived under water by tableland diving, interlayer mainly in the cutting depth scope according to geology is detailed.Tableland diving mainly is distributed in the scope of structure roof top 0.8~3.60m, and the top board top covers thicker farinose argillic horizon, the silty clay of Fu Shui is very easily liquefaction after the construction disturbance, become stream mud shape, tunnel excavation process kind is prone to caves in, falls the piece phenomenon, tunnel excavation disturbance and underflow are turned pale and are easily aggravated ground settlement in addition, have increased construction risk.According to " PBA " worker method characteristics, and, adopted the treatment measures of horizontal well precipitation in well point+hole, ground in the construction, guaranteed the safety of work progress in conjunction with the hydrology, geological condition.
(1) arranges the surface precipitation well.The precipitation well is arranged along the both sides, tunnel along line direction, spacing 6~8m, and cloth precipitation well is 20 altogether, adopts φ 400/50mm not have the sand cement pipe, and well casing twines 80 order nylon gauzes, and pipe is outer fills out φ 20~40mm filtrate to below ground 1.5m place.Anti-circulation and Churn drill rig pore-forming are adopted in construction, aperture 600mm, and the employing high-lift submersible pump is taken out, draining.As shown in Figure 2:
Concrete work progress is as follows:
A, the location of well
According to precipitation well location map, underground utilities distribution map and coordinate control point dispensing precipitation well well location.For guaranteeing safety, answer physical prospecting to verify the well location place after the location of well and have or not underground utilities, underground obstacle in conjunction with artificial luoyang spade.
B, artificial inspecting hole
Borehole diameter 1000mm whenever digs into 800mm, does retaining wall one time, and template supports between two parties, boxes out seam all around evenly, guarantees 10cm thickness.Every upper and lower two-layer retaining wall must overlap 50mm-100mm.Suspicious atural object to running in the borehole mustn't directly destroy, and can continue construction after site administrator's approval.
C, digging pit assembles mud pit
For guaranteeing the drilling process water circulation and preserving boring and slag tap, enclose mud pit with aerated blocks at the scene, and in mud pit, lay Polypropylence Sheet, prevent that slurries from exposing, outsidely support with soil, after construction finishes with last residue except that clearing out a gathering place.
D, in place, the adjustment of rig
Need adjust the planeness of rig and the verticality of boring tower when rig is in place, real after the contraposition with the board headblock, guarantee that rig lays steadily.
E, boring
Should guarantee that in boring procedure the mud liquid level protects on the bucket at steel in the hole.Under the situation that formation condition allows, use the stratum from making the mud pore-forming as far as possible, if boring by the hole of easily collapsing drifting sand layer or during the serious stratum of lose returns, can adopt artificial pulping retaining wall to creep into, mud balance transfers to 1.1~1.3.
F, following pipe
Whether on request following Guan Qianying checks well casing looping nylon wire; No sand cement interface tube place will use Polypropylence Sheet Bao Yan, will guarantee verticality and weld tight when hypomere welds on the steel pipe.Well casing must be guaranteed in wellhole placed in the middle.
G, fill out filtrate
Filler must evenly slowly be inserted around well, avoids causing arch formation in the hole, if finding filtrate sinks should in time replenish filtrate, packed height is filled to underground 3m by designing requirement behind the well-flushing.
H, well-flushing
Adopt the pressure fan well-flushing, if sinking should be injected clear water when not enough in the well.
(2) arrange horizontal well in the hole.
From vertical shaft transverse passage-way excavation situation in early stage, arch and face water percolating capacity are bigger.Particularly the arch, tunnel is arranged in argillic horizon, and the ground deep-well precipitation can not form the precipitation funnel, forms stream mud in the digging process easily, causes that a large amount of peripheral soil layers run off, and cause face of land excess to sink easily.Through after the earnest analytical study, decision utilized vertical shaft transverse passage-way space before the section of striding constructing tunnel greatly, set up horizontal well to striding the tunnel direction greatly, and local backwater is shifted to an earlier date drainage, played the effect of leading precipitation during excavation.
Horizontal well is provided with 6 altogether, 30~40 meters of length.HXY-500M geological drilling rig pore-forming is adopted in construction, and the aperture is 108mm, lays φ 50mm spray of molten steel pipe then in the hole, and spray of molten steel pipe is outside and swathe two-layer 80 mesh filter screens, sees Fig. 7-2-4 for details.
Concrete work progress is:
Dispensing well location → rig is in place → and the pipe → sealing of hole → diversion of rig leveling, contraposition → spiral pore-forming → down is outside vertical shaft → draining goes out vertical shaft.
3, utilize the vertical shaft transverse passage-way to apply the leading bassoon canopy in main body arch, and pre-grouting and reinforcing stratum.
Φ 159 is adopted in the leading bassoon canopy design in the Soviet Union yellow interval three-way section of striding greatly arch, t=10.0mm, and the seamless steel pipe 1 of l=56.0m, spacing is 0.4m, carries out slip casting after pipe roof construction finishes, injecting paste material adopts cement paste.As shown in Figure 3.
Because disposable the setting of 56m long tube canopy is unfavorable for the control of pipe roof construction precision, the superstructure pipeline is various in addition, also is difficult to guarantee the superstructure pipeline safety.Comprehensive each side factor, we determine to adopt the scheme that the segmentation of 56m long tube canopy is set, and longitudinal lap joint length is 3m between the pipe canopy.
At first utilize the vertical shaft transverse passage-way as first section Guan Peng operating space, it is 25m that the pipe canopy sets length; When little pilot drive is to the K2+279.3 place in both sides then, little pilot tunnel of left line and the little pilot tunnel of right line are communicated with, be arranged to manage the canopy operating room, second section and the 3rd section pipe canopy utilize the operating room space to apply and each 20 meters long bassoon canopies to little mileage (E ' section) and big mileage (F section) direction respectively, as shown in Figure 4.
The construction technology employing of pipe canopy is subjected to the operating space to influence the less boring static pressure method of heading into and constructs equipment choosing HXY-500M geological drilling rig.Construction technology as shown in Figure 5.
4, detain the arch construction, and finish according to following operation; As shown in Figure 6.
1. the little pilot tunnel of constructing is pre-buried connecting reinforcement 2 also; 2. set up grid 3 in the little pilot tunnel; 3. to a concrete perfusion backfill 4 behind just in the pilot tunnel; 4. excavate arch (No. 1 pilot tunnel), left side and set up arch grid 5; 5. excavate arch, right side (No. 2 pilot tunnels) and set up arch grid 6; 6, pilot tunnel (No. 3 pilot tunnels) under the excavation left side applies the interim support 7 in bottom; 7, excavation arch, right side (No. 4 pilot tunnels) applies the interim support 8 in bottom.Above-mentioned little pilot tunnel grid adopts overlap welding to be connected with embedded bar, when main body is excavated, adopts overlap welding to be connected main arch grid and connecting reinforcement, makes it to connect into integral body with little pilot tunnel grid
5, the section soil body applies expansion basis and median septum under the excavation;
6, bottom median septum is removed in segmentation, and construction bottom cushion, waterproofing course are built steel concrete;
7, segmentation remove temporary steel support in top median septum and the little pilot tunnel, apply abutment wall and main arch waterproofing course, concrete.

Claims (5)

1. job practices of utilizing the PBA method to carry out shallow buried covered excavation tunnel large section is characterized in that: carry out according to the following step:
(1) detects for cavity, longspan tunnel superstructure stratum;
(2) arrange horizontal well in surface precipitation well and the hole;
(3) utilize the vertical shaft transverse passage-way, promptly manage the canopy operating room, apply the leading bassoon canopy in main body arch, and pre-grouting and reinforcing stratum;
(4) little pilot tunnel of construction and pre-buried connecting reinforcement;
(5) set up little pilot tunnel grid bow member, and be connected with pre-buried connecting reinforcement;
(6) to just propping up concrete perfusion fill concrete behind in the pilot tunnel;
(7) excavation left and right side arch is set up the main arch grid, and is connected with pre-buried connecting reinforcement;
(8) pilot tunnel under pilot tunnel and the right side applies mid-board and bottom to support temporarily under on the left of the excavation;
(9) the section soil body applies expansion basis and median septum under the excavation;
(10) bottom median septum is removed in segmentation, and construction bottom cushion, waterproofing course are built steel concrete;
(11) segmentation remove temporary steel support in top median septum and the little pilot tunnel, apply abutment wall and main arch waterproofing course, concrete.
2. the PBA of utilization method according to claim 1 is carried out the job practices of shallow buried covered excavation tunnel large section, it is characterized in that: above-mentioned bassoon canopy apply the method that adopts the seamless steel pipe segmentation to set, longitudinal lap joint between every section.
3. the PBA of utilization method according to claim 1 is carried out the job practices of shallow buried covered excavation tunnel large section, it is characterized in that: the construction of above-mentioned bassoon canopy adopts the boring static pressure to head into method construction, equipment choosing HXY-500M geological drilling rig.
4. the PBA of utilization method according to claim 1 is carried out the job practices of shallow buried covered excavation tunnel large section, it is characterized in that: the detection in cavity, above-mentioned longspan tunnel superstructure stratum adopts ground penetrating radar to detect the GPR technology.
5. the PBA of utilization method according to claim 1 is carried out the job practices of shallow buried covered excavation tunnel large section, it is characterized in that: above-mentioned little pilot tunnel grid adopts overlap welding to be connected with embedded bar, the main arch grid adopts overlap welding to be connected with connecting reinforcement, makes it to connect into integral body with little pilot tunnel grid.
CNB2007100599130A 2007-10-17 2007-10-17 Construction method of shallow buried underground excavating tunnel super large section using PBA method Expired - Fee Related CN100464055C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007100599130A CN100464055C (en) 2007-10-17 2007-10-17 Construction method of shallow buried underground excavating tunnel super large section using PBA method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007100599130A CN100464055C (en) 2007-10-17 2007-10-17 Construction method of shallow buried underground excavating tunnel super large section using PBA method

Publications (2)

Publication Number Publication Date
CN101225742A true CN101225742A (en) 2008-07-23
CN100464055C CN100464055C (en) 2009-02-25

Family

ID=39857920

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007100599130A Expired - Fee Related CN100464055C (en) 2007-10-17 2007-10-17 Construction method of shallow buried underground excavating tunnel super large section using PBA method

Country Status (1)

Country Link
CN (1) CN100464055C (en)

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101555798B (en) * 2009-05-14 2011-03-23 中铁一局集团有限公司 Reverse puncher and method for using the puncher for implementing PBA side pile construction
CN102174894A (en) * 2011-03-15 2011-09-07 中铁十二局集团第一工程有限公司 Follow-up pipe shed construction method
CN102226403A (en) * 2011-03-30 2011-10-26 中铁一局集团有限公司 Construction method of large-span subway station main body by using arched cover method and station main body structure
CN101812991B (en) * 2009-10-30 2011-11-16 西南交通大学 Construction method for loop type hypobaric holes of railway tunnel
CN102287195A (en) * 2011-05-13 2011-12-21 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN102305075A (en) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 Vertical shaft construction method under unfavorable geological condition
CN102505708A (en) * 2011-10-21 2012-06-20 中冶建工集团有限公司 Construction method of tunnel at oversized cross section open cut area in track traffic
CN102518454A (en) * 2011-12-22 2012-06-27 中铁工程设计咨询集团有限公司 Grating device for underground excavation engineering and manufacture method
CN102535302A (en) * 2011-12-31 2012-07-04 北京工业大学 Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof
CN103075163A (en) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN103244129A (en) * 2013-05-22 2013-08-14 中铁十六局集团有限公司 Construction method for three-dimensional intersection concave-convex fulcrums
CN103306248A (en) * 2013-07-01 2013-09-18 中国水电顾问集团中南勘测设计研究院 High dam spillway foundation drainage system and excavation method
CN103469817A (en) * 2013-09-30 2013-12-25 中铁一局集团有限公司 Existing subway station main structure broadening construction method
CN104265305A (en) * 2014-08-05 2015-01-07 中铁二十一局集团有限公司 Enlarging and excavating method for merging two small-cross-section caverns into one large-cross-section cavern
CN104695983A (en) * 2013-12-09 2015-06-10 中铁十三局集团有限公司 Method for welding embedded steel bar welding joints of two end nodes in initial supporting arch
CN104695877A (en) * 2013-12-06 2015-06-10 中铁十三局集团有限公司 Large pipe shed construction method by using Luoyang shovel
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN103527204B (en) * 2013-11-06 2015-10-14 中铁第四勘察设计院集团有限公司 A kind of method for tunnel construction of first wall rear arch intersection median septum
CN105484777A (en) * 2015-05-08 2016-04-13 中铁隧道勘测设计院有限公司 Connection structure for pilot tunnel and main body steel arch frame of station constructed by pile-beam-arc method
CN106437726A (en) * 2016-11-02 2017-02-22 中铁二十局集团第五工程有限公司 Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN106703814A (en) * 2015-07-30 2017-05-24 宏润建设集团股份有限公司 Mined metro station hole pile construction method
CN107023300A (en) * 2017-04-13 2017-08-08 中铁十六局集团地铁工程有限公司 A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN107288656A (en) * 2017-06-20 2017-10-24 清华大学 A kind of water seal cave depot country rock actively carries the construction method of system
CN107503755A (en) * 2017-09-08 2017-12-22 中铁十六局集团地铁工程有限公司 A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station
CN108729919A (en) * 2018-06-07 2018-11-02 深圳市市政设计研究院有限公司 One kind is rockfilled stratum arc variable cross-section Tunnels in Shallow Buried excavating construction method
CN110566223A (en) * 2019-09-16 2019-12-13 北京市市政四建设工程有限责任公司 deep-buried PBA subway station section design method
CN110593893A (en) * 2019-11-01 2019-12-20 中建八局轨道交通建设有限公司 Main body structure construction method and system for intersection of main tunnel and construction transverse channel
CN111155542A (en) * 2020-01-14 2020-05-15 中铁隧道集团二处有限公司 PBA construction method tunnel waterproof curtain construction method based on hole guiding technology
CN111764932A (en) * 2020-07-06 2020-10-13 高军 Low-risk construction method for muddy water-rich broken shallow tunnel
CN113027495A (en) * 2021-05-26 2021-06-25 中国铁路设计集团有限公司 Underground excavation large-span station construction method implemented by interval tunnel organization
CN113153414A (en) * 2021-01-06 2021-07-23 西南交通大学 Disposal measure for gas tunnel to penetrate through underlying coal seam goaf and construction method thereof
CN113898348A (en) * 2021-08-04 2022-01-07 中铁二院工程集团有限责任公司 Ultra-shallow-buried large-span underground excavation subway station tunnel construction method
CN114320340A (en) * 2021-12-28 2022-04-12 中铁第六勘察设计院集团有限公司 Large-span pillar-free underground tunnel structure and method based on advanced pilot tunnel and counter-pulling anchor cable

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1021986C (en) * 1991-05-25 1993-09-01 北京市城建设计研究院 Construction of large underground space
JP2002242583A (en) * 2001-02-22 2002-08-28 Ishikawajima Constr Materials Co Ltd Tunnel structure and method for constructing the same
JP3834571B2 (en) * 2003-10-15 2006-10-18 誠 植村 Construction method for underground structures
JP4396433B2 (en) * 2004-07-27 2010-01-13 株式会社大林組 Advanced arch pipe roof construction method
CN2839559Y (en) * 2005-08-09 2006-11-22 同济大学 Arcading tunnel

Cited By (51)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101555798B (en) * 2009-05-14 2011-03-23 中铁一局集团有限公司 Reverse puncher and method for using the puncher for implementing PBA side pile construction
CN101812991B (en) * 2009-10-30 2011-11-16 西南交通大学 Construction method for loop type hypobaric holes of railway tunnel
CN102174894A (en) * 2011-03-15 2011-09-07 中铁十二局集团第一工程有限公司 Follow-up pipe shed construction method
CN102226403B (en) * 2011-03-30 2013-11-13 中铁一局集团有限公司 Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102226403A (en) * 2011-03-30 2011-10-26 中铁一局集团有限公司 Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102287195A (en) * 2011-05-13 2011-12-21 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN102287195B (en) * 2011-05-13 2014-09-17 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN102305075A (en) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 Vertical shaft construction method under unfavorable geological condition
CN102505708A (en) * 2011-10-21 2012-06-20 中冶建工集团有限公司 Construction method of tunnel at oversized cross section open cut area in track traffic
CN102505708B (en) * 2011-10-21 2014-05-07 中冶建工集团有限公司 Construction method of tunnel at oversized cross section open cut area in track traffic
CN102518454A (en) * 2011-12-22 2012-06-27 中铁工程设计咨询集团有限公司 Grating device for underground excavation engineering and manufacture method
CN102535302A (en) * 2011-12-31 2012-07-04 北京工业大学 Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof
CN102535302B (en) * 2011-12-31 2014-01-01 北京工业大学 Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof
CN103075163B (en) * 2012-12-28 2015-02-18 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN103075163A (en) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN103244129A (en) * 2013-05-22 2013-08-14 中铁十六局集团有限公司 Construction method for three-dimensional intersection concave-convex fulcrums
CN103244129B (en) * 2013-05-22 2015-04-29 中铁十六局集团有限公司 Construction method for three-dimensional intersection concave-convex fulcrums
CN103306248A (en) * 2013-07-01 2013-09-18 中国水电顾问集团中南勘测设计研究院 High dam spillway foundation drainage system and excavation method
CN103469817A (en) * 2013-09-30 2013-12-25 中铁一局集团有限公司 Existing subway station main structure broadening construction method
CN103469817B (en) * 2013-09-30 2015-05-13 中铁一局集团有限公司 Existing subway station main structure broadening construction method
CN103527204B (en) * 2013-11-06 2015-10-14 中铁第四勘察设计院集团有限公司 A kind of method for tunnel construction of first wall rear arch intersection median septum
CN104695877A (en) * 2013-12-06 2015-06-10 中铁十三局集团有限公司 Large pipe shed construction method by using Luoyang shovel
CN104695983A (en) * 2013-12-09 2015-06-10 中铁十三局集团有限公司 Method for welding embedded steel bar welding joints of two end nodes in initial supporting arch
CN104695983B (en) * 2013-12-09 2017-02-01 中铁十三局集团有限公司 Method for welding embedded steel bar welding joints of two end nodes in initial supporting arch
CN104265305B (en) * 2014-08-05 2016-06-01 中铁二十一局集团有限公司 What be merged into room, a big cross section hole from room, two light section holes digs method
CN104265305A (en) * 2014-08-05 2015-01-07 中铁二十一局集团有限公司 Enlarging and excavating method for merging two small-cross-section caverns into one large-cross-section cavern
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN105484777A (en) * 2015-05-08 2016-04-13 中铁隧道勘测设计院有限公司 Connection structure for pilot tunnel and main body steel arch frame of station constructed by pile-beam-arc method
CN106703814A (en) * 2015-07-30 2017-05-24 宏润建设集团股份有限公司 Mined metro station hole pile construction method
CN106703814B (en) * 2015-07-30 2019-07-12 宏润建设集团股份有限公司 Tunneling subway station hole pile construction method
CN106437726A (en) * 2016-11-02 2017-02-22 中铁二十局集团第五工程有限公司 Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN106437726B (en) * 2016-11-02 2018-04-13 中铁二十局集团第五工程有限公司 Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN107023300A (en) * 2017-04-13 2017-08-08 中铁十六局集团地铁工程有限公司 A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN107288656A (en) * 2017-06-20 2017-10-24 清华大学 A kind of water seal cave depot country rock actively carries the construction method of system
CN107288656B (en) * 2017-06-20 2019-12-13 清华大学 construction method of water seal cave depot surrounding rock active bearing system
CN107503755A (en) * 2017-09-08 2017-12-22 中铁十六局集团地铁工程有限公司 A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station
CN108729919A (en) * 2018-06-07 2018-11-02 深圳市市政设计研究院有限公司 One kind is rockfilled stratum arc variable cross-section Tunnels in Shallow Buried excavating construction method
CN108729919B (en) * 2018-06-07 2019-07-05 深圳市市政设计研究院有限公司 One kind is rockfilled stratum arc variable cross-section Tunnels in Shallow Buried excavating construction method
CN110566223A (en) * 2019-09-16 2019-12-13 北京市市政四建设工程有限责任公司 deep-buried PBA subway station section design method
CN110593893A (en) * 2019-11-01 2019-12-20 中建八局轨道交通建设有限公司 Main body structure construction method and system for intersection of main tunnel and construction transverse channel
CN110593893B (en) * 2019-11-01 2024-04-12 中建八局轨道交通建设有限公司 Main body structure construction method and system at intersection of main tunnel and construction transverse channel
CN111155542A (en) * 2020-01-14 2020-05-15 中铁隧道集团二处有限公司 PBA construction method tunnel waterproof curtain construction method based on hole guiding technology
CN111764932A (en) * 2020-07-06 2020-10-13 高军 Low-risk construction method for muddy water-rich broken shallow tunnel
CN111764932B (en) * 2020-07-06 2021-11-02 高军 Low-risk construction method for muddy water-rich broken shallow tunnel
CN113153414A (en) * 2021-01-06 2021-07-23 西南交通大学 Disposal measure for gas tunnel to penetrate through underlying coal seam goaf and construction method thereof
CN113153414B (en) * 2021-01-06 2023-02-28 西南交通大学 Disposal measure for gas tunnel to penetrate through underlying coal seam goaf and construction method thereof
CN113027495A (en) * 2021-05-26 2021-06-25 中国铁路设计集团有限公司 Underground excavation large-span station construction method implemented by interval tunnel organization
CN113027495B (en) * 2021-05-26 2021-07-23 中国铁路设计集团有限公司 Underground excavation large-span station construction method implemented by interval tunnel organization
CN113898348A (en) * 2021-08-04 2022-01-07 中铁二院工程集团有限责任公司 Ultra-shallow-buried large-span underground excavation subway station tunnel construction method
CN114320340A (en) * 2021-12-28 2022-04-12 中铁第六勘察设计院集团有限公司 Large-span pillar-free underground tunnel structure and method based on advanced pilot tunnel and counter-pulling anchor cable
CN114320340B (en) * 2021-12-28 2023-09-12 中铁第六勘察设计院集团有限公司 Large-span non-column underground tunnel structure and method based on advanced pilot tunnel and opposite-pulling anchor cable

Also Published As

Publication number Publication date
CN100464055C (en) 2009-02-25

Similar Documents

Publication Publication Date Title
CN100464055C (en) Construction method of shallow buried underground excavating tunnel super large section using PBA method
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN101864960B (en) Carst region double-arch road tunnel construction method
CN102865103B (en) Distributed using method for mine underground water
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN106837353A (en) Filling karst tunnel construction treatment method
CN110080237A (en) It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure
CN102425421B (en) Novel water control method suitable for mine shafts
CN102352757B (en) Method for controlling upward floating of pipe piece during shield machine air pushing through mining tunnel
CN106907164A (en) A kind of water-bed combination of mine shield tunnel docking structure form and its construction method
CN103603689A (en) Curtain grouting construction method for treating mined-out areas
CN103628912A (en) Goaf management filling grouting construction method
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN110512593A (en) Ultra-deep diaphragm wall structure in sea reclamation area and construction method thereof
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN101205721A (en) Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN206888992U (en) A kind of water-bed mine shield tunnel combination docking structure form
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
CN109518699A (en) Miniature steel pipe pile adds grid spray anchor deep foundation ditch combination supporting scheme system and its construction method
CN108678753B (en) Reverse-slope tunnel construction method
CN102808627A (en) Underground excavation construction method of steel pipe shed

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 300222 No. 18 South Dagu Road, Shuang Gang Town, Jinnan District, Tianjin

Patentee after: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

Address before: 300222 Liulin, Hexi District, Tianjin

Patentee before: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 300222 Tianjin Town, Jinnan District

Patentee after: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

Address before: 300222 No. 18 South Dagu Road, Shuang Gang Town, Jinnan District, Tianjin

Patentee before: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090225