CN110080237A - It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure - Google Patents

It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure Download PDF

Info

Publication number
CN110080237A
CN110080237A CN201910407566.9A CN201910407566A CN110080237A CN 110080237 A CN110080237 A CN 110080237A CN 201910407566 A CN201910407566 A CN 201910407566A CN 110080237 A CN110080237 A CN 110080237A
Authority
CN
China
Prior art keywords
construction
pile
floating
concrete
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910407566.9A
Other languages
Chinese (zh)
Inventor
邹俊峰
雷斌
雷帆
叶坤
刘治军
沙桢辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Gongkan Geotechnical Group Co Ltd
Original Assignee
Shenzhen Gongkan Geotechnical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Gongkan Geotechnical Group Co Ltd filed Critical Shenzhen Gongkan Geotechnical Group Co Ltd
Priority to CN201910407566.9A priority Critical patent/CN110080237A/en
Publication of CN110080237A publication Critical patent/CN110080237A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Anti-floating construction method is excavated the invention discloses a kind of shallow earthing subway tunnel pit earthwork in hole bottom and structure, the construction method include: support construction, carries out supporting construction by Foundation Pit Support Design requirement;Resistance to plucking pile driving construction lays row's uplift principle respectively on the outside of safeguard protection line;Excavation carries out excavation by the way of excavation section by section;The construction of anti-floating plate, carries out anti-floating plate construction by the way of section construction;The constructing structure includes uplift pile and anti-floating plate, and the uplift pile is arranged in rows in tunnel two sides, and two rows of uplift piles are arranged at other than the safety line of tunnel two sides, and the anti-floating plate is cast in the upper end of uplift pile and across two rows of uplift piles;The shallow earthing subway tunnel pit earthwork in this kind hole bottom excavates anti-floating construction method and structure have the advantages that anti-floating effect is good, construction technology is simple, construction efficiency is high, construction cost is low, not available for the prior arts such as environmentally friendly.

Description

It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure
Technical field
The present invention relates to the realm of building construction, especially a kind of shallow earthing subway tunnel pit earthwork in hole bottom excavates anti-floating and applies Work method and structure.
Background technique
Nowadays the domestic big and medium-sized cities underground close net of subway line is distributed, and is frequently encountered in Process of Urban Development in subway tunnel The case where building all kinds of buildings or structures at the top of road, when excavating the earthwork of buildings or structures subterranean excavation, along with tunnel top Off-load caused by the soil body is transported outward, can cause the change of the original soil stress filed of tunnel perimeter, produce when tunnel cladding earth pressure is less than When raw tunnel upward floating power, the floating of tunnel structure certainly will be caused to deform, safety of subway operation is caused a significant threat when serious.
When typically encountering such situation, to ensure that safety must carry out Anti-floating design and the processing in tunnel in advance.It is general Way is that slip casting or whirl spraying is taken the soil body at tunnel top to foundation pit bottom to expire hall consolidation process, is opened with increasing earthing weight resistance Buoyancy caused by digging.It but is the inherently safe for ensuring subway tunnel, the range of soil stabilization processing must be maintained to few The safe distance certain apart from tunnel side, the consolidation process of this earthing shallow for tunnel top are difficult to meet floating requirement.
In view of this, the purpose of the present invention is to provide a kind of new technical solutions to solve existing technological deficiency.
Summary of the invention
For overcome the deficiencies in the prior art, it is anti-to provide a kind of shallow earthing subway tunnel pit earthwork excavation in hole bottom by the present invention Floating construction method and structure, solve existing construction means and constructing structure is difficult to meet the shallow earthing floating requirement in tunnel top, apply The technological deficiencies such as work low efficiency, complicated construction technique, construction cost height.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of shallow earthing subway tunnel pit earthwork excavation anti-floating construction method in hole bottom, including construction procedure below:
Step 1: support construction carries out supporting construction by Foundation Pit Support Design requirement;
Step 2: resistance to plucking pile driving construction lays row's uplift principle respectively on the outside of safeguard protection line;
Step 3: excavation carries out excavation by the way of excavation section by section;
Step 4: the construction of anti-floating plate carries out anti-floating plate construction by the way of section construction;
The step 3 and step 4 recurrence interval are carried out up to complete design boundary of works area.
As an improvement of the above technical solution, in support construction, construction procedure includes:
Step 1-1: advance support construction is carried out by Foundation Pit Support Design requirement, is parallel to the two sides foundation pit branch of tunnel trend The bored concrete pile or hole-drilling interlocking pile of diameter 1000mm-1200mm can be used in shield, and the two sides foundation pit of Vertical tunnel trend is using classification Slope is excavated;
Step 1-2: implementing water-stop curtain construction by Foundation Pit Support Design requirement, deep using diameter 600mm in foundation pit surrounding Layer mixing pile or high-pressure rotary jet grouting pile set water-stop curtain, guarantee water-stagnating effect,.
3m must be met apart from tunnel top or side in the two collateral shields and water-stop curtain of Vertical tunnel trend;
Before carrying out advance support construction, according to field condition can Dewatering well and inverted well in advance, in excavation of foundation pit In use process, it can be needed to implement to cheat interior precipitation or recharge according to anti-floating.
As a further improvement of the above technical scheme, the resistance to plucking pile driving construction takes full-sleeve full-rotation construction technology, Including construction procedure:
Step 2-1: uplift pile preparation of construction verifies buried pipeline situation before resistance to plucking pile driving construction, smooth construction site, And ram packing reality;
Step 2-2: the setting-out of stake position carries out setting-out to stake position, and confirms stake top absolute altitude;
Step 2-3: full circle swinging host is in place, hangs full circle swinging chassis, and center chassis is overlapped with pile center's point, then hangs Host is mounted on chassis, finally installs counter-force fork;
Step 2-4: steel pile casting is placed in lifting, after host is in place, hangs installation steel sleeve, carries out rotary drilling, and revolution is driven Casing is pushed while dynamic casing, realizes that casing quickly pierces stratum;
Step 2-5: measurement adjustment verticality, before steel sleeve is crept into, with 2 laser transits in XY both direction or use Plumb bob adjusts casing verticality;
Step 2-6: steel pile casting drilling takes soil to designed elevation, after correcting casing verticality, with pressing sleeve under full-rotating drill Pipe;
Step 2-7: pore-forming inspection, when drilling depth reaches design requirement, to hole location, aperture, hole depth and gradient etc. It is checked, using ultrasonic wave measuring for verticality;
Step 2-8: first time borehole cleaning after pore-forming, fishes for sediment with Spiral digging machine or punching grab bucket in time;
Step 2-9: fabrication of reinforcing cage installation, pile foundation steel bar cage are concentrated in reinforcing bar field and are made;
Step 2-10: secondary pile hole cleaning, pipe inner wall is smooth, smoother, and internal diameter is consistent, and interface is tight;
Step 2-11: pouring underwater concrete checks and pours underwater coagulation immediately after sediment thickness after borehole cleaning, borehole cleaning are qualified Soil;
Step 2-12: extracting conduit and steel pile casting, when pouring underwater concrete, by casing merogenesis situation, pulls out when pouring Conduit, then pull out conduit.
As a further improvement of the above technical scheme, in step 2-2, two rows of uplift piles are laid in subway tunnel two sides Outside protective wire, the distance of protective wire is not less than 3m, and the drilling position of uplift pile need to be on the outside of protective wire, and work progress is forbidden to cross Protective wire operation, to prevent from having an impact tunnel in pore forming process;Reinforcement protection is carried out to stake position with mortar or concrete, In case testing in drilling process to stake position;Stake position is carried out to check to ensure that fender pile must not be displaced;
As a further improvement of the above technical scheme, in step 2-6, start to be grabbed with punching as casing compression distance 3m Bucket takes soil out of casing, grabs soil on one side, continues to push casing on one side;According to Different Strata, using punching grab bucket, block stamp, mud bucket is taken It is used interchangeably;Remain that casing bottom is ahead of the depth of excavation face not less than 2.5m, cannula tip cannot beyond drilling machine platform Lower than 50cm;When being bored into rock stratum, Spiral digging machine can be cooperated to construct;According to field geology situation, different drill bits is selected;Rotation When digging drilling machine drilling, confirmation such as rock depth, hole termination depth and hangs muscle length in time.Moment records in drilling process differently Hydralic pressure gauge torque data in layer, when changing on drop-down mention the casing that shakes up and reduce frictional force, be lost to prevent casing and drill bit;
As a further improvement of the above technical scheme, in step 2-8, bottom hole sediment thickness is not more than 5cm, and borehole cleaning is complete Clear supervising engineer is reported to check and accept by quality personnel after Bi Hou, depth of pore forming and sediment thickness acceptance(check);
As a further improvement of the above technical scheme, in step 2-9, steel reinforcement cage is every 2m along the uniform cloth of pile body surrounding 4 chucking lug muscle are set, the pile crown reinforcing bar for protruding into cushion cap part is wrapped up using pearl cotton casing, in order to which the later period carries out pile crown It cuts;Steel reinforcement cage is transported to scene storage after processing is completed, uses bracket support pad below, is covered above with colour bar cloth;According to live real Border situation uses connecting sleeve or welded reinforcement cage;Steel reinforcement cage installation uses crawler crane, is captured by single machine and hangs steel reinforcement cage, and It transfers, is fixed on the positioning after the completion of decentralization in aperture section by section, avoid that floating cage phenomenon occurs during concrete perfusion, it is ensured that Steel reinforcement cage is overlapped with hole location center, and hangs muscle length is accurate;The welding of main reinforcement uses single welding, fusion length 10d;In same section Splice be not to be exceeded the 50% of main reinforcement sum, the spacing of two connectors is not less than 500mm;
As a further improvement of the above technical scheme, in step 2-10, conduit diameter uses 30cm, uses preceding progress Examination is spelled and pressure testing test;Conduit assembles the 0.5% not larger than 10cm that posterior axis deviation is no more than drilling depth;Pressure testing power position hole 1.5 times of bottom hydrostatic pressure;When conduit hangs load hole, rubber ring or Rubber washer are placed straight, tight, it is ensured that good seal; Sediment thickness is checked again for before pouring underwater concrete;Secondary pile hole cleaning is carried out using gas lift reverse circulation, iterative cycles are until bottom hole Sediment thickness reaches code requirement;
As a further improvement of the above technical scheme, in step 2-11, pile foundation concrete is all mixed and stirred using concrete It stands centralized mixing, concrete tank car is transported to scene;Field test, slump are carried out to the concrete shown up by experimenter before perfusion Degree, divergence, gassiness figureofmerit have to comply with mix-design requirement;Mouth is buried not less than 1m in concrete, less under conduit In 3m;Underwater gliders guarantee is carried out continuously, and conduit is in buried depth control in concrete between 2-6m in filling process;Water Lower concrete pours top surface by design of pile top elevation 1m control is higher by, to guarantee the quality of stake top concrete;Before telephone-moving, again It measures concrete and sets depth;
As a further improvement of the above technical scheme, in step 2-12, vertical tremor when above mentioning conduit makes concrete It is closely knit;After underwater gliders, extracts remaining conduit and steel pile casting at a slow speed by full-rotating drill, reuse, and Stake holes is covered with steel plate, carries out next operation.
As a further improvement of the above technical scheme, in the construction of uplift pile, the stake diameter of uplift pile, pilespacing, stake be long, Enter the arrangement of reinforcement of rock depth and pile body, concrete strength is designed according to live physical condition must satisfy excavation of foundation pit The anti-floating requirement in tunnel;The stake diameter 1000mm-1200mm of uplift pile, stake spacing are not more than 1.5m;It is many that stake grows into middle decomposed rock Decomposed rock is no less than 2m in 3m or in a subtle way.
As a further improvement of the above technical scheme, the excavation includes construction procedure below:
Step 3-1: excavation prepares;
Step 3-2: excavation of foundation pit surveying and locating;
Step 3-3: section gap excavates the soil body;
Step 3-4: deburring and clear bottom;
As a further improvement of the above technical scheme, need section gap to excavate when tunnel upper excavation of foundation pit, according to every One principle for digging one separates excavation pit, and when the excavation pit earthwork, every section of excavation length is no more than 8m.
As a further improvement of the above technical scheme, the anti-floating plate construction includes construction procedure below:
Step 4-1: anti-floating plate surveying setting-out;
Step 4-2: anti-floating slab muscle fabrication and installation;
Step 4-3: anti-floating plate binding;
Step 4-4: anti-floating board concrete pours;
As a further improvement of the above technical scheme, it in the anti-floating plate construction, is applied with soil body sequential segment is excavated Work armored concrete anti-floating plate, anti-floating plate thickness, width, length, using concrete grade, reinforced steel bar strength view field condition it is true It is fixed;Anti-floating plate uses section construction, and in section construction, the reserved steel bar lap of splice and anchorage length are stood after excavating the soil body It carves the arrangement for carrying out anti-floating slab muscle and is bound and welded with the reserved steel bar of uplift pile;In combination with base when anti-floating plate designs Hole back-plane design considers jointly or is designed anti-floating plate as a part of base plate of foundation pit;Anti-floating plate is existing for armored concrete Plate is poured, plate thickness is not less than 1000mm, and main reinforcement arrangement of reinforcement is not less than HRB400, and concrete strength is not less than C30.
Anti-floating construction method is excavated based on the above-mentioned shallow earthing subway tunnel pit earthwork in hole bottom, the present invention also provides one Kind of the shallow earthing subway tunnel pit earthwork in hole bottom excavates anti-floating constructing structure, including uplift pile and anti-floating plate, the uplift pile at Row is arranged in tunnel two sides, and two rows of uplift piles are arranged at other than the safety line of tunnel two sides, and the anti-floating plate is cast in resistance to plucking The upper end of stake and across two rows of uplift piles, the part that anti-floating plate is located at two rows of uplift piles is located at tunnel top.
As an improvement of the above technical solution, the safety line is greater than 3m at a distance from tunnel-side, the uplift pile The stake spacing of stake diameter 1000mm-1200mm, uplift pile are not more than 1.5m, and the stake of uplift pile grows into middle decomposed rock and is no less than 3m or enters Micro- decomposed rock is no less than 2m;
The anti-floating plate is situ Concrete Slabs, and the plate thickness of anti-floating plate is not less than 1000mm, and the main reinforcement of anti-floating plate is matched Muscle is not less than HRB400, and the concrete strength of anti-floating plate is not less than C30, and anti-floating plate is poured in such a way that section gap pours, The distance of each section of anti-floating plate is 4-8mm.
It as a further improvement of the above technical scheme, further include supporting construction, the supporting construction includes being parallel to tunnel The bored concrete pile or hole-drilling interlocking pile of the diameter 1000mm-1200mm of road trend and setting in foundation pit surrounding and use diameter 600mm Deep-mixed pile or the water-stop curtain of high-pressure rotary jet grouting pile setting.
The beneficial effects of the present invention are: the present invention provides a kind of shallow earthing subway tunnel pit earthworks in hole bottom to excavate anti-floating Construction method and structure, have the advantage that
1, anti-floating effect is good, and the technical program forms compound float Structure, uplift pile using uplift pile, anti-floating plate and earthing Using middle weathering or micro- decomposed rock is entered, enough withdrawal resistances can be provided, are constructed with the armoured concrete slab of foundation pit bottom setting The float Structure of complete covering subway tunnel, globality, anti-floating ability are strong;
2, construction technology is simple, is mature bored concrete pile, coagulation used by the construction method that the technical program provides Native construction technology, technical maturity, specification are clear, and quality safety can press, and operate conveniently simple;
3, construction speed is fast, and in the technical program, bored concrete pile is using full circle swinging full casing construction, and direct geotome is into applying Work speed is fast;
4, to surrounding enviroment close friend, the technical program uses the full casing construction process of bored concrete pile of full circle swinging, work progress pair The influence of subway tunnel is small;Pit earthwork is excavated to be excavated using section gap, has minimized the influence to subway tunnel;
5, overall cost is low, and the armored concrete anti-floating plate at this technology foundation pit bottom can sufficiently combine building infrastructure Bottom plate Synchronization Design, locally can dual-purpose;Anti-floating pile can be replaced according to site condition using foundation pit supporting construction or engineering pile;Separately Outside, this technology has also given full play to the anti-floating effect of foundation pit subsoil body, and overall the technology of the present invention comprehensive cost is low.
In short, the shallow earthing subway tunnel pit earthwork in this kind hole bottom excavates anti-floating construction method and structure solves existing apply Work means and constructing structure be difficult to meet the shallow earthing in tunnel top float require, construction efficiency is low, complicated construction technique, construction cost High technological deficiency.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is construction process schematic diagram of the invention;
Fig. 2 is the process flow chart of resistance to plucking pile driving construction in the present invention;
Fig. 3 is the process flow chart of excavation in the present invention;
Fig. 4 is the process flow chart that anti-floating plate is constructed in the present invention;
Fig. 5 is the setting schematic diagram of tunnel safety line in the present invention;
Fig. 6 is the layout diagram of uplift pile on the outside of tunnel safety line in the present invention;
Fig. 7 is the plane layout diagram of uplift pile in the present invention, anti-floating plate;
Fig. 8 is the cross-sectional structure schematic diagram perpendicular to tunnel of uplift pile in the present invention, anti-floating plate and soil;
Fig. 9 is that uplift pile in the present invention, anti-floating plate and soil are parallel to tunnel the schematic diagram of the section structure;
Figure 10 is the structural schematic diagram of foundation pit segmentation exploitation in the present invention;
Figure 11 is the schematic diagram of the foundation pit supporting construction of one embodiment of the invention;
Figure 12 is the floor map of the tunnel float Structure of one embodiment of the invention;
Figure 13 is the diagrammatic cross-section of the tunnel float Structure of one embodiment of the invention.
Specific embodiment
It is carried out below with reference to technical effect of the embodiment and attached drawing to design of the invention, specific structure and generation clear Chu is fully described by, to be completely understood by the purpose of the present invention, feature and effect.Obviously, described embodiment is this hair Bright a part of the embodiment, rather than whole embodiments, based on the embodiment of the present invention, those skilled in the art are not being paid Other embodiments obtained, belong to the scope of protection of the invention under the premise of creative work.In addition, being related in patent All connection/connection relationships, not singly refer to that component directly connects, and refer to can according to specific implementation situation, by addition or Reduce couple auxiliary, Lai Zucheng more preferably coupling structure.Each technical characteristic in the invention, in not conflicting conflict Under the premise of can with combination of interactions, referring to Fig.1-13.
Referring in particular to Fig. 1, a kind of shallow earthing subway tunnel pit earthwork excavation anti-floating construction method in hole bottom, including it is below Construction procedure:
Referring to Fig. 5, step 1: supporting construction 1 is constructed, and carries out supporting construction by 2 design of its support requirement of foundation pit;
In step 1, construction procedure includes:
Step 1-1: advance support construction is carried out by 2 design of its support requirement of foundation pit, is parallel to the two sides foundation pit of the trend of tunnel 3 The bored concrete pile or hole-drilling interlocking pile of diameter 1000mm-1200mm can be used in supporting, and the two sides foundation pit that Vertical tunnel 3 moves towards, which uses, to be divided Grade slope is excavated;
Step 1-2: implementing water-stop curtain construction by Foundation Pit Support Design requirement, deep using diameter 600mm in 2 surrounding of foundation pit Layer mixing pile or high-pressure rotary jet grouting pile set water-stop curtain, guarantee water-stagnating effect;
3m must be met apart from tunnel top or side in the two collateral shields and water-stop curtain of Vertical tunnel trend;
Before carrying out advance support construction, according to field condition can Dewatering well and inverted well in advance, excavated in foundation pit 2 In use process, it can be needed to implement to cheat interior precipitation or recharge according to anti-floating.
Step 2: uplift pile 4 is constructed, and lays row's uplift principle respectively on the outside of safeguard protection line;
Referring to Fig. 2, Fig. 6, Fig. 7, Fig. 8, in step 2, full-sleeve full-rotation construction work is taken in the construction of uplift pile 4 Skill specifically includes following construction procedure:
Step 2-1: resistance to plucking, 4 preparations of construction verify buried pipeline situation before the construction of uplift pile 4, smooth construction site, And ram packing reality;
Step 2-2: the setting-out of stake position carries out setting-out to stake position, and confirms stake top absolute altitude;Two rows of uplift piles 4 are laid in subway Outside 3 two sides protective wire of tunnel, the distance of protective wire 31 is not less than 3m, and the drilling position of uplift pile 4 need to construct on the outside of protective wire Process is forbidden to cross the operation of protective wire 31, to prevent from having an impact tunnel 3 in pore forming process;With mortar or concrete to stake Position carries out reinforcement protection, in case testing in drilling process to stake position;Stake position is carried out to check to ensure that fender pile must not be displaced;
Step 2-3: full circle swinging host is in place, hangs full circle swinging chassis, and center chassis is overlapped with pile center's point, then hangs Host is mounted on chassis, finally installs counter-force fork;
Step 2-4: steel pile casting is placed in lifting, after host is in place, hangs installation steel sleeve, carries out rotary drilling, and revolution is driven Casing is pushed while dynamic casing, realizes that casing quickly pierces stratum;
Step 2-5: measurement adjustment verticality, before steel sleeve is crept into, with 2 laser transits in XY both direction or use Plumb bob adjusts casing verticality;
Step 2-6: steel pile casting drilling takes soil to designed elevation, after correcting casing verticality, with pressing sleeve under full-rotating drill Pipe;Start to take soil out of casing with punching grab bucket as casing compression distance 3m, grab soil on one side, continues to push casing on one side;According to Different Strata using punching grab bucket, block stamp, takes mud bucket to be used interchangeably;Remain casing bottom be ahead of excavation face depth it is not small In 2.5m, cannula tip cannot be below 50cm beyond drilling machine platform;When being bored into rock stratum, Spiral digging machine can be cooperated to construct;Root According to field geology situation, different drill bits is selected;When rotary drilling rig is crept into, such as rock depth, hole termination depth are confirmed in time and is hung Muscle length.Moment records in drilling process hydralic pressure gauge torque data in Different Strata, when changing on drop-down propose the casing drop that shakes up Low-frictional force is lost to prevent casing and drill bit;
Step 2-7: pore-forming inspection, when drilling depth reaches design requirement, to hole location, aperture, hole depth and gradient etc. It is checked, using ultrasonic wave measuring for verticality;
Step 2-8: first time borehole cleaning after pore-forming, fishes for sediment with Spiral digging machine or punching grab bucket in time;Bottom hole sediment thickness is not Greater than 5cm, after borehole cleaning, clear supervising engineer is reported to check and accept by quality personnel after depth of pore forming and sediment thickness acceptance(check);
Step 2-9: fabrication of reinforcing cage installation, pile foundation steel bar cage are concentrated in reinforcing bar field and are made;Steel reinforcement cage is every 2m along pile body Surrounding is evenly arranged 4 chucking lug muscle, and the pile crown reinforcing bar for protruding into cushion cap part is wrapped up using pearl cotton casing, in order to rear Phase carries out pile crown and cuts;Steel reinforcement cage is transported to scene storage after processing is completed, uses bracket support pad below, is covered above with colour bar cloth; Connecting sleeve or welded reinforcement cage are used according to on-site actual situations;Steel reinforcement cage installation uses crawler crane, is captured by single machine Steel reinforcement cage is hung, and is transferred section by section, is fixed on the positioning after the completion of decentralization in aperture, avoids occurring during concrete perfusion floating Cage phenomenon, it is ensured that steel reinforcement cage is overlapped with hole location center, and hangs muscle length is accurate;The welding of main reinforcement uses single welding, fusion length 10d;The 50% of main reinforcement sum is not to be exceeded in splice in same section, and the spacing of two connectors is not less than 500mm;
Step 2-10: secondary pile hole cleaning, pipe inner wall is smooth, smoother, and internal diameter is consistent, and interface is tight;Conduit diameter uses 30cm carries out examination and spells and pressure testing test before use;Conduit assembling posterior axis deviation is no more than the 0.5% of drilling depth and is not larger than 10cm;1.5 times of pressure testing power position bottom hole hydrostatic pressure;When conduit hangs load hole, rubber ring or Rubber washer are placed straight, tight It is close, it is ensured that good seal;Sediment thickness is checked again for before pouring underwater concrete;Secondary pile hole cleaning is carried out using gas lift reverse circulation, Iterative cycles are until bottom hole sediment thickness reaches code requirement;
Step 2-11: pouring underwater concrete checks and pours underwater coagulation immediately after sediment thickness after borehole cleaning, borehole cleaning are qualified Soil;Pile foundation concrete all uses concrete mixing station centralized mixing, and concrete tank car is transported to scene;By experimenter couple before perfusion The concrete progress field test shown up, slump, divergence, gassiness figureofmerit have to comply with mix-design requirement;Conduit Lower mouth is buried in concrete not less than 1m, and 3m is not more than;Underwater gliders guarantee is carried out continuously, and conduit exists in filling process Buried depth control is between 2-6m in concrete;Underwater concrete pours top surface by design of pile top elevation 1m control is higher by, to protect Demonstrate,prove the quality of stake top concrete;Before telephone-moving, concrete is measured again and sets depth;
Step 2-12: extracting conduit and steel pile casting, when pouring underwater concrete, by casing merogenesis situation, pulls out when pouring Conduit, then pull out conduit;Vertical tremor when above mentioning conduit, makes concrete compaction;After underwater gliders, pass through full circle swinging Drilling machine extracts at a slow speed remaining conduit and steel pile casting, recycling, and is covered stake holes with steel plate, carries out next operation;
In the construction of uplift pile 4, the stake diameter of uplift pile 4, pilespacing, stake is long, the arrangement of reinforcement that enters rock depth and pile body, mixed Solidifying soil intensity is designed must satisfy the requirement of the anti-floating in excavation of foundation pit tunnel according to live physical condition;Generally, resistance to plucking The stake diameter 1000mm-1200mm of stake 4, stake spacing are not more than 1.5m;Stake grows into that middle decomposed rock is no less than 3m or decomposed rock is not in a subtle way Less than 2m.
Referring to Fig. 3, step 3: base, 2 excavation constructions carry out 2 excavation construction of foundation pit by the way of excavation section by section;
Step 3-1: 2 excavation construction of foundation pit prepares;
Step 3-2: 2 digging measure setting-out of foundation pit;
Step 3-3: section gap excavates the soil body;
Step 3-4: deburring and clear bottom;
3 top foundation pit 2 of tunnel needs section gap to excavate when excavating, and separates excavation pit according to the principle for digging one every one, opens When digging pit earthwork, every section of excavation length is no more than 8m.
Referring in particular to Fig. 9, Figure 10, in excavation pit, excavated backward according to sequence 1., 2., 3., 4., tunnel upper It needs section gap to excavate when excavation of foundation pit, according to the principle excavation pit of " digging one every one ", reduces unload produced by soil to greatest extent Big buoyancy, with guarantee construction period bottom of foundation ditch will not due to top off-load is excessive there is a phenomenon where bottom heaves;The earthwork is opened The anti-floating plate construction at hole bottom is carried out after digging, immediately to prevent upper load long duration of action from leading to the protuberance of bottom of foundation ditch.To anti- Kickboard intensity reaches the 80% of design strength, can carry out next section of earth excavation.
Referring to Fig. 4, Fig. 7, Fig. 8, Fig. 9, step 4: anti-floating plate 5 is constructed, and is carried out anti-floating plate 5 by the way of section construction and is applied Work;
Step 4-1: anti-floating, 5 surveying setting-outs;
Step 4-2: 5 reinforcement fabrication of anti-floating plate installation;
Step 4-3: anti-floating plate 5 is bound;
Step 4-4: 5 concreting of anti-floating plate;
In the construction of anti-floating plate 5, with soil body sequential segment construction reinforced bar agent on crack resistance of concrete kickboard is excavated, anti-floating plate 5 is thick Degree, width, length, using concrete grade, reinforced steel bar strength view field condition determine;Anti-floating plate 5 uses section construction, is being segmented When construction, the reserved steel bar lap of splice and anchorage length, carried out at once after excavating the soil body arrangement of anti-floating slab muscle and with it is anti- 4 reserved steel bars are pulled out to be bound and welded;It designs and common considers or by anti-floating in combination with base plate of foundation pit when anti-floating plate 5 designs Plate is designed as a part of base plate of foundation pit;Generally, anti-floating plate is situ Concrete Slabs, and plate thickness is not less than 1000mm, main reinforcement arrangement of reinforcement are not less than HRB400, and concrete strength is not less than C30.
When anti-floating plate 5 is constructed, pressed with soil body sequential segment construction reinforced bar agent on crack resistance of concrete kickboard is excavated referring in particular to Fig. 7 According to the construction of sequential segment backward of 51,52,53,54 corresponding regions, 51,52,53,54 corresponding regions are what anti-floating plate 5 was constructed Sequence backward;In section construction, enough lapped length of steel bar and anchorage length are reserved, carries out anti-floating at once after excavating the soil body The arrangement of slab muscle is simultaneously bound and is welded with the reserved steel bar of uplift pile, and bar splicing area should meet related specifications;Make Anti-floating plate considers when designing in combination with back-plane design jointly, or is designed anti-floating plate as a part of bottom plate, to save Engineering spending;After constructing to one section of anti-floating plate, it is same that next section of excavation of foundation pit and the construction of anti-floating plate, step are carried out at once On, until the construction of all sheet pile float Structures finishes.
The step 3 and step 4 recurrence interval are carried out up to complete design boundary of works area.
Referring in particular to Fig. 5-10, anti-floating construction method is excavated based on the above-mentioned shallow earthing subway tunnel pit earthwork in hole bottom, Anti-floating constructing structure is excavated the present invention also provides a kind of shallow earthing subway tunnel pit earthwork in hole bottom, including uplift pile 4 and anti- Kickboard 5, the uplift pile 4 are arranged in rows in 3 two sides of tunnel, two rows of uplift piles 4 be arranged at the safety line 31 of 3 two sides of tunnel with Outside, the anti-floating plate 5 is cast in the upper end of uplift pile 4 and across two rows of uplift pile 4, and anti-floating plate 5 is located at the portion of two rows of uplift piles Quartile is in 3 top of tunnel.
As an improvement of the above technical solution, the safety line 31 is greater than 3m, the uplift pile at a distance from 3 side wall of tunnel The stake spacing of 4 stake diameter 1000mm-1200mm, uplift pile 4 are not more than 1.5m, and the stake of uplift pile 4 grows into middle decomposed rock and is no less than 3m or decomposed rock is no less than 2m in a subtle way;
The anti-floating plate 5 is situ Concrete Slabs, and the plate thickness of anti-floating plate 5 is not less than 1000mm, the main reinforcement of anti-floating plate 5 Arrangement of reinforcement is not less than HRB400, and the concrete strength of anti-floating plate 5 is not less than C30, and anti-floating plate 5 is poured in such a way that section gap pours It builds, the distance of each section of anti-floating plate 5 is 4-8mm.
It as a further improvement of the above technical scheme, further include supporting construction 1, the supporting construction 1 includes being parallel to The bored concrete pile or hole-drilling interlocking pile of the diameter 1000mm-1200mm of tunnel trend and setting in foundation pit surrounding and use diameter 600mm deep-mixed pile or the water-stop curtain of high-pressure rotary jet grouting pile setting.
In one embodiment, referring in particular to Figure 11-13, it is made of foundation pit east side foundation pit, west side foundation pit, east side foundation pit Perimeter 300m, area 5581m2,22.65~25.85m of cutting depth, support form be " ground-connecting-wall+inner support (four be abound with+ Part the is five) ".The shallow Foundation Pit bottom in west side is located at about 4m above subway tunnel line, and east side and Dong Keng are close to foundation pit is about 50m, wide about 25m, area about 1302m2, place elevation are about 4.5m, and base pit elevation -2.0m, foundation depth is about 6.5m, Support form be " bored concrete pile+reinforced concrete angle brace+stirring pile water stopping curtain ", south and north flanks along subway direction using " slope excavate+ Slip casting perforated soil nail ", slope top use cement mixing method sealing.
The project west side foundation pit lower part there are two subway tunnels, tunnel top away from ground about 10m, away from foundation pit bottom 3.2m~ 4m.It is right using the peg board soil combined type anti-floating construction technology of the invention patent to prevent tunnel top bottom of foundation ditch from swelling Subway tunnel carries out anti-floating safeguard protection.
1, supporting construction is made using 1800 rotary digging stake of D1000 in the west side project Xi Keng, and stake 600 single shaft of long 10.4m, D850 stirs It mixes stake and makees water sealing structure;North side and southern side are excavated using slope, and slope is excavated top and carried out using the uniaxial mixing pile of D850@600 Reinforce sealing, the long 7.5m of stake;East side carries out cell wall pre-reinforcement to east hole ground-connecting-wall using 600 three axes agitating pile of D850@, and stake is long 15.8m。
2, subway protection linear distance subway tunnel sideline is 3m.
3, uplift pile totally 18, are embedded rock pile, and using " a full set of cylinder full circle swinging bored concrete pile " construction technology, sleeve is with proceeding to Scar.Pile body uses underwater C45 filling concrete;Stake is long to be determined by bearing course at pile end, wherein 16 decomposed rock > in a subtle way 500mm, 2 enter middle weathering lower section > 500mm, a length of 14~32m of stake, and stake diameter is 1.2~1.6m, and spacing 5m, is arranged between stake On the outside of subway tunnel protective wire, away from protective wire apart from outer average distance 3.6m.
4, it being segmented and carries out when tunnel upper excavation of foundation pit, excavation of foundation pit depth is about 6.5m, every section of excavation length 4m~5m, Excavation pit is carried out according to the principle of " digging one every three ", excavates gradient 1:1, slope surface hangs steel mesh, and injection C20 concrete 10cm is thick.
5, two tunnel tops are laid with one block of armored concrete anti-floating plate respectively, and confrontation kickboard makees back-plane design, thickness 1000mm, area 950m2, board bottom is away from 3.9~4.2m of subway tunnel top.
6, due to the project east side foundation pit diaphram wall and west side subway tunnel distance it is very close, diaphram wall with Construct again row's uplift pile between subway tunnel without extra position, thus hole bottom anti-floating Board position to the diaphram wall at this into Row bar planting is connected, to provide more stable withdrawal resistance with anti-floating plate using diaphram wall body.
It is to be illustrated to preferable implementation of the invention, but the invention is not limited to the implementation above Example, those skilled in the art can also make various equivalent variations on the premise of without prejudice to spirit of the invention or replace It changes, these equivalent deformations or replacement are all included in the scope defined by the claims of the present application.

Claims (10)

1. cheating the shallow earthing subway tunnel pit earthwork in bottom excavates anti-floating construction method, it is characterised in that: walked including construction below It is rapid:
Step 1: support construction carries out supporting construction by Foundation Pit Support Design requirement;
Step 2: resistance to plucking pile driving construction lays row's uplift principle respectively on the outside of safeguard protection line;
Step 3: excavation carries out excavation by the way of excavation section by section;
Step 4: the construction of anti-floating plate carries out anti-floating plate construction by the way of section construction;
The step 3 and step 4 recurrence interval are carried out up to complete design boundary of works area.
2. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 1 excavates anti-floating construction method, feature exists In: in support construction, construction procedure includes:
Step 1-1: carrying out advance support construction by Foundation Pit Support Design requirement, and the two sides pattern foundation pit supporting structure for being parallel to tunnel trend can Using the bored concrete pile or hole-drilling interlocking pile of diameter 1000mm-1200mm, the two sides foundation pit of Vertical tunnel trend is using classification slope It excavates;
Step 1-2: implementing water-stop curtain construction by Foundation Pit Support Design requirement, is stirred in foundation pit surrounding using diameter 600mm deep layer It mixes stake or high-pressure rotary jet grouting pile sets water-stop curtain;
3m must be met apart from tunnel top or side in the two collateral shields and water-stop curtain of Vertical tunnel trend;
Before carrying out advance support construction, according to field condition can Dewatering well and inverted well in advance, in excavation of foundation pit and make With in the process, implementation can be needed to cheat interior precipitation or recharge according to anti-floating.
3. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 1 excavates anti-floating construction method, feature exists In: the resistance to plucking pile driving construction takes full-sleeve full-rotation construction technology, including construction procedure:
Step 2-1: uplift pile preparation of construction verifies buried pipeline situation, smooth construction site, and ram before resistance to plucking pile driving construction Packing is real;
Step 2-2: the setting-out of stake position carries out setting-out to stake position, and confirms stake top absolute altitude;
Step 2-3: full circle swinging host is in place, hangs full circle swinging chassis, and center chassis is overlapped with pile center's point, then hangs master Machine is mounted on chassis, finally installs counter-force fork;
Step 2-4: steel pile casting is placed in lifting, after host is in place, is hung installation steel sleeve, is carried out rotary drilling, revolution driving set Casing is pushed while pipe, realizes that casing quickly pierces stratum;
Step 2-5: measurement adjustment verticality before steel sleeve is crept into, in XY both direction or uses plumb bob with 2 laser transits Adjust casing verticality;
Step 2-6: steel pile casting drilling takes soil to designed elevation, after correcting casing verticality, pushes casing with full-rotating drill;
Step 2-7: pore-forming inspection carries out hole location, aperture, hole depth and gradient etc. when drilling depth reaches design requirement It checks, using ultrasonic wave measuring for verticality;
Step 2-8: first time borehole cleaning after pore-forming, fishes for sediment with Spiral digging machine or punching grab bucket in time;
Step 2-9: fabrication of reinforcing cage installation, pile foundation steel bar cage are concentrated in reinforcing bar field and are made;
Step 2-10: secondary pile hole cleaning, pipe inner wall is smooth, smoother, and internal diameter is consistent, and interface is tight;
Step 2-11: pouring underwater concrete checks and pours underwater concrete immediately after sediment thickness after borehole cleaning, borehole cleaning are qualified;
Step 2-12: extracting conduit and steel pile casting, and when pouring underwater concrete, by casing merogenesis situation, conduit is pulled out when pouring, Conduit is pulled out again.
4. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 3 excavates anti-floating construction method, feature exists In:
In step 2-2, two rows of uplift piles are laid in outside the protective wire of subway tunnel two sides, and the distance of protective wire is not less than 3m, are resisted The drilling position of pile pulling need to be on the outside of protective wire, and work progress is forbidden to cross protective wire operation, right in pore forming process to prevent Tunnel has an impact;Reinforcement protection is carried out to stake position with mortar or concrete, in case testing in drilling process to stake position;It is right Stake position carries out checking to ensure that fender pile must not be displaced;
In step 2-6, starts to take soil out of casing with punching grab bucket as casing compression distance 3m, grab soil on one side, continue on one side Push casing;According to Different Strata, using punching grab bucket, block stamp, mud bucket is taken to be used interchangeably;Remain that casing bottom is ahead of excavation The depth in face is not less than 2.5m, and cannula tip cannot be below 50cm beyond drilling machine platform;When being bored into rock stratum, Spiral digging machine can be cooperated It constructs;According to field geology situation, different drill bits is selected;When rotary drilling rig is crept into, confirmation such as rock depth in time, whole hole Depth and hangs muscle length;Record in drilling process hydralic pressure gauge torque data in Different Strata, when changing on drop-down mention and shaking up Casing reduces frictional force, is lost to prevent casing and drill bit;
In step 2-8, bottom hole sediment thickness is not more than 5cm, after borehole cleaning, after depth of pore forming and sediment thickness acceptance(check) Clear supervising engineer is reported to check and accept by quality personnel;
In step 2-9, steel reinforcement cage is evenly arranged 4 chucking lug muscle along pile body surrounding every 2m, protrudes into the pile crown of cushion cap part Reinforcing bar is wrapped up using pearl cotton casing, is cut in order to which the later period carries out pile crown;Steel reinforcement cage is transported to scene after processing is completed and deposits It puts, uses bracket support pad below, covered above with colour bar cloth;Connecting sleeve or welded reinforcement are used according to on-site actual situations Cage;Steel reinforcement cage installation uses crawler crane, is captured by single machine and hangs steel reinforcement cage, and transferred section by section, carries out after the completion of decentralization in aperture Positioning is fixed, and avoids that floating cage phenomenon occurs during concrete perfusion, it is ensured that steel reinforcement cage is overlapped with hole location center, hangs muscle length Accurately;The welding of main reinforcement uses single welding, fusion length 10d;Main reinforcement sum is not to be exceeded in splice in same section 50%, the spacing of two connectors is not less than 500mm;
In step 2-10, conduit diameter uses 30cm, and examination is carried out before use and is spelled and pressure testing test;Conduit assembles posterior axis deviation No more than 0.5% not larger than 10cm of drilling depth;1.5 times of pressure testing power position bottom hole hydrostatic pressure;When conduit hangs load hole, Rubber ring or Rubber washer are placed straight, tight, it is ensured that good seal;Sediment thickness is checked again for before pouring underwater concrete; Secondary pile hole cleaning is carried out using gas lift reverse circulation, iterative cycles are until bottom hole sediment thickness reaches code requirement;
In step 2-11, pile foundation concrete all uses concrete mixing station centralized mixing, and concrete tank car is transported to scene;Before perfusion Concrete progress field test by experimenter to showing up, slump, divergence, gassiness figureofmerit have to comply with match ratio and set Meter requires;Mouth is buried in concrete not less than 1m under conduit, is not more than 3m;Underwater gliders guarantee is carried out continuously, and is perfused Conduit is in buried depth control in concrete between 2-6m in the process;Underwater concrete pours top surface by being higher by design of pile top elevation 1m control, to guarantee the quality of stake top concrete;Before telephone-moving, concrete is measured again and sets depth;
In step 2-12, vertical tremor when above mentioning conduit makes concrete compaction;After underwater gliders, by complete Slewing drilling machine extracts at a slow speed remaining conduit and steel pile casting, recycling, and is covered stake holes with steel plate, carries out next operation.
5. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 4 excavates anti-floating construction method, feature exists In: in the construction of uplift pile, the stake diameter of uplift pile, pilespacing, stake is long, the arrangement of reinforcement, the concrete strength that enter rock depth and pile body It is designed according to live physical condition must satisfy the requirement of the anti-floating in excavation of foundation pit tunnel;The stake diameter 1000mm- of uplift pile 1200mm, stake spacing are not more than 1.5m;Stake grows into that middle decomposed rock is no less than 3m or decomposed rock is no less than 2m in a subtle way.
6. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 1 excavates anti-floating construction method, feature exists In: the excavation includes construction procedure below: step 3-1: excavation prepares;
Step 3-2: excavation of foundation pit surveying and locating;
Step 3-3: section gap excavates the soil body;
Step 3-4: deburring and clear bottom;
It needs section gap to excavate when tunnel upper excavation of foundation pit, separates excavation pit, excavation pit according to the principle for digging one every one When the earthwork, every section of excavation length is no more than 8m.
7. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 1 excavates anti-floating construction method, feature exists In: the anti-floating plate construction includes construction procedure below: step 4-1: anti-floating plate surveying setting-out;
Step 4-2: anti-floating slab muscle fabrication and installation;
Step 4-3: anti-floating plate binding;
Step 4-4: anti-floating board concrete pours;
In the anti-floating plate construction, with excavation soil body sequential segment construction reinforced bar agent on crack resistance of concrete kickboard, anti-floating plate thickness, width Degree, length are determined using concrete grade, reinforced steel bar strength view field condition;Anti-floating plate uses section construction, in section construction When, the reserved steel bar lap of splice and anchorage length carry out the arrangement of anti-floating slab muscle and and uplift pile at once after excavating the soil body Reserved steel bar bound and welded;When anti-floating plate designs in combination with base plate of foundation pit design it is common consider or using anti-floating plate as A part of base plate of foundation pit is designed;Anti-floating plate is situ Concrete Slabs, and plate thickness is not less than 1000mm, and main reinforcement arrangement of reinforcement is not Less than HRB400, concrete strength is not less than C30.
8. cheating the shallow earthing subway tunnel pit earthwork in bottom excavates anti-floating constructing structure, it is characterised in that: including uplift pile and anti-floating Plate, the uplift pile are arranged in rows in tunnel two sides, and two rows of uplift piles are arranged at other than the safety line of tunnel two sides, described anti- Kickboard is cast in the upper end of uplift pile and across two rows of uplift pile, and the part that anti-floating plate is located at two rows of uplift piles is located on tunnel Portion.
9. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 8 excavates anti-floating constructing structure, feature exists In: the safety line is greater than 3m, the stake diameter 1000mm-1200mm of the uplift pile, the stake of uplift pile at a distance from tunnel-side Spacing is not more than 1.5m, and the stake of uplift pile grows into that middle decomposed rock is no less than 3m or decomposed rock is no less than 2m in a subtle way;
The anti-floating plate is situ Concrete Slabs, and the plate thickness of anti-floating plate is not less than 1000mm, and the main reinforcement arrangement of reinforcement of anti-floating plate is not Less than HRB400, the concrete strength of anti-floating plate is not less than C30, and anti-floating plate is poured in such a way that section gap pours, each The distance of section anti-floating plate is 4-8mm.
10. the shallow earthing subway tunnel pit earthwork in hole bottom according to claim 8 excavates anti-floating constructing structure, feature exists In: further include supporting construction, the supporting construction include be parallel to tunnel trend diameter 1000mm-1200mm bored concrete pile or Hole-drilling interlocking pile and the sealing curtain that foundation pit surrounding is set and is arranged using diameter 600mm deep-mixed pile or high-pressure rotary jet grouting pile Curtain.
CN201910407566.9A 2019-05-16 2019-05-16 It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure Pending CN110080237A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910407566.9A CN110080237A (en) 2019-05-16 2019-05-16 It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910407566.9A CN110080237A (en) 2019-05-16 2019-05-16 It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure

Publications (1)

Publication Number Publication Date
CN110080237A true CN110080237A (en) 2019-08-02

Family

ID=67420432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910407566.9A Pending CN110080237A (en) 2019-05-16 2019-05-16 It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure

Country Status (1)

Country Link
CN (1) CN110080237A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397044A (en) * 2019-07-22 2019-11-01 中铁第四勘察设计院集团有限公司 The prominent foundation ditch construction method and foundation pit structure gushed of anti-artesian water
CN110593267A (en) * 2019-09-18 2019-12-20 中国建筑第八工程局有限公司 Construction method of foundation pit above tunnel
CN111305282A (en) * 2020-04-06 2020-06-19 福建工程学院 Subway station anti-floating system in weak water-rich stratum and construction method thereof
CN111395347A (en) * 2020-02-21 2020-07-10 湖南大学 Method for controlling upward floating of existing tunnel striding on foundation pit by adopting prestressed uplift pile
CN111622209A (en) * 2020-05-27 2020-09-04 中国一冶集团有限公司 Composite roadbed drainage pipe network anti-floating structure
CN112664203A (en) * 2020-12-25 2021-04-16 北京市政路桥股份有限公司 Reinforcing system for controlling deformation of shield tunnel by dredging river above shield tunnel and construction method
CN113186989A (en) * 2021-04-20 2021-07-30 广州地铁设计研究院股份有限公司 Anti-floating construction method for tunnel
CN113235341A (en) * 2021-05-31 2021-08-10 中铁第六勘察设计院集团有限公司 Construction method for adding high-speed railway subgrade to existing high-speed railway in parallel
CN114457850A (en) * 2022-03-11 2022-05-10 浙江交工集团股份有限公司 Construction method of anti-floating system for crossing existing subway intersection section on open trench tunnel
CN114482071A (en) * 2022-02-28 2022-05-13 中国建筑第五工程局有限公司 Device for improving rock-socketed depth of large-diameter cast-in-place pile
CN115419074A (en) * 2022-09-28 2022-12-02 中建八局第三建设有限公司 Crawler-type earth-conveying and excavating method for ultra-deep foundation pit
CN115467339A (en) * 2022-09-17 2022-12-13 中建五局土木工程有限公司 Construction method of abutment foundation of river under soft soil condition of near tunnel shallow covering layer
CN116657675A (en) * 2023-07-31 2023-08-29 中国建筑第六工程局有限公司 Construction method for anti-floating reinforcement of thin bottom plate of subway station foundation pit in high water level area
CN117211289A (en) * 2023-11-08 2023-12-12 中国建筑第六工程局有限公司 Construction method of multiple systems of foundation in complex environment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1641114A (en) * 2004-01-17 2005-07-20 上海市城市建设设计研究院 Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre
CN205742299U (en) * 2016-06-15 2016-11-30 中国电建集团铁路建设有限公司 A kind of an ultra shallow buries the float Structure of shield tunnel
CN207003499U (en) * 2017-07-25 2018-02-13 广州大学 A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN108005129A (en) * 2017-09-28 2018-05-08 中国矿业大学(北京) A kind of safeguard structure system and method for controlling tunnel vertical deformation
CN108978645A (en) * 2018-08-21 2018-12-11 中铁九局集团第四工程有限公司 Rich water sandy gravel shallow embedding riverbed uplift pile anti-floating plate reinforced construction method is worn under shield
CN210263062U (en) * 2019-05-16 2020-04-07 深圳市工勘岩土集团有限公司 Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1641114A (en) * 2004-01-17 2005-07-20 上海市城市建设设计研究院 Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre
CN205742299U (en) * 2016-06-15 2016-11-30 中国电建集团铁路建设有限公司 A kind of an ultra shallow buries the float Structure of shield tunnel
CN207003499U (en) * 2017-07-25 2018-02-13 广州大学 A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN108005129A (en) * 2017-09-28 2018-05-08 中国矿业大学(北京) A kind of safeguard structure system and method for controlling tunnel vertical deformation
CN108978645A (en) * 2018-08-21 2018-12-11 中铁九局集团第四工程有限公司 Rich water sandy gravel shallow embedding riverbed uplift pile anti-floating plate reinforced construction method is worn under shield
CN210263062U (en) * 2019-05-16 2020-04-07 深圳市工勘岩土集团有限公司 Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
赵炜等: "上跨盾构隧道近距离基坑施工技术", 河南科技, no. 6, pages 60 - 61 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397044A (en) * 2019-07-22 2019-11-01 中铁第四勘察设计院集团有限公司 The prominent foundation ditch construction method and foundation pit structure gushed of anti-artesian water
CN110593267A (en) * 2019-09-18 2019-12-20 中国建筑第八工程局有限公司 Construction method of foundation pit above tunnel
CN111395347A (en) * 2020-02-21 2020-07-10 湖南大学 Method for controlling upward floating of existing tunnel striding on foundation pit by adopting prestressed uplift pile
CN111305282A (en) * 2020-04-06 2020-06-19 福建工程学院 Subway station anti-floating system in weak water-rich stratum and construction method thereof
CN111622209A (en) * 2020-05-27 2020-09-04 中国一冶集团有限公司 Composite roadbed drainage pipe network anti-floating structure
CN112664203A (en) * 2020-12-25 2021-04-16 北京市政路桥股份有限公司 Reinforcing system for controlling deformation of shield tunnel by dredging river above shield tunnel and construction method
CN113186989A (en) * 2021-04-20 2021-07-30 广州地铁设计研究院股份有限公司 Anti-floating construction method for tunnel
CN113235341A (en) * 2021-05-31 2021-08-10 中铁第六勘察设计院集团有限公司 Construction method for adding high-speed railway subgrade to existing high-speed railway in parallel
CN114482071A (en) * 2022-02-28 2022-05-13 中国建筑第五工程局有限公司 Device for improving rock-socketed depth of large-diameter cast-in-place pile
CN114457850A (en) * 2022-03-11 2022-05-10 浙江交工集团股份有限公司 Construction method of anti-floating system for crossing existing subway intersection section on open trench tunnel
CN115467339A (en) * 2022-09-17 2022-12-13 中建五局土木工程有限公司 Construction method of abutment foundation of river under soft soil condition of near tunnel shallow covering layer
CN115419074A (en) * 2022-09-28 2022-12-02 中建八局第三建设有限公司 Crawler-type earth-conveying and excavating method for ultra-deep foundation pit
CN115419074B (en) * 2022-09-28 2023-09-08 中建八局第三建设有限公司 Crawler-type soil conveying and excavating method for ultra-deep foundation pit
CN116657675A (en) * 2023-07-31 2023-08-29 中国建筑第六工程局有限公司 Construction method for anti-floating reinforcement of thin bottom plate of subway station foundation pit in high water level area
CN116657675B (en) * 2023-07-31 2023-11-14 中国建筑第六工程局有限公司 Construction method for anti-floating reinforcement of thin bottom plate of subway station foundation pit in high water level area
CN117211289A (en) * 2023-11-08 2023-12-12 中国建筑第六工程局有限公司 Construction method of multiple systems of foundation in complex environment

Similar Documents

Publication Publication Date Title
CN110080237A (en) It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN100464055C (en) Construction method of shallow buried underground excavating tunnel super large section using PBA method
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN102322064A (en) Construction method for underground diaphragm wall of deep foundation pit for subway station in collapsible loess areas
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN103031839B (en) Construction method of hand-dug piles
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN102943466A (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN107447778A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN110512593A (en) Reclaimation area ultra-deep ground-connecting-wall structure and its construction method
CN110359540A (en) A kind of shallow earthing Large Diameter Pipeline high water level wears the artificial jacking construction engineering method of existing road
CN109113746A (en) The construction method of shield inspection-pit
CN107489164A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN110424460A (en) A kind of tunnel open excavation construction technology
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN104695458A (en) Construction method of deep stirring and jet grouting compound pile waterproof curtain
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination