CN102493662A CN2011103846598A CN201110384659A CN102493662A CN 102493662 A CN102493662 A CN 102493662A CN 2011103846598 A CN2011103846598 A CN 2011103846598A CN 201110384659 A CN201110384659 A CN 201110384659A CN 102493662 A CN102493662 A CN 102493662A
Authority
CN
China
Prior art keywords
node
pipe
arc
shaped lining
pipe fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103846598A
Other languages
English (en)
Inventor
周光毅
仇春慧
张强
毛立贤
刘旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
China Construction Eighth Engineering Division Co Ltd Dalian Branch
Original Assignee
China Construction Eighth Engineering Division Co Ltd Dalian Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd Dalian Branch filed Critical China Construction Eighth Engineering Division Co Ltd Dalian Branch
Priority to CN2011103846598A priority Critical patent/CN102493662A/zh
Publication of CN102493662A publication Critical patent/CN102493662A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明涉及建筑钢结构施工领域。一种两端节点固定的管件衬垫管的安装方法,第一步:在一端节点处将整体衬垫管在安装前与节点焊接完成,再将管件与节点对接;第二步另一端节点采用下述施工方法,将衬垫管三等分为三等分弧形衬板,在每段弧形衬板上焊接上把手,将弧形衬板塞进节点与直管的缝隙里面,塞进去后,用把手旋转使弧形衬板与对接口贴紧,将弧形衬板与直管焊接后,刨掉把手,其他两段弧形衬板按照此方法安装,形成整体衬垫管。本发明施工方法简单,由于操作间隙小的一端节点,采用分体式衬垫管即弧形衬板,易于插入直管与节点的间隙中,插入后形成衬垫管,既便于安装施工,提高了生产效率,又满足了管件的性能要求,保证了产品质量。

Description

一种两端节点固定的管件衬垫管的安装方法
技术领域
本发明涉及建筑钢结构施工领域,特别是两端节点固定的管件衬垫管的安装方法。
背景技术
在建筑领域中,管桁架施工过程中常常出现弦杆两端节点已定位,弦杆需塞入两个节点之间的情况出现。通常将一端管口对接位置的衬垫管先固定在节点上,另一端的衬垫管加长先行放入弦杆内,弦杆定位后,慢慢将放入弦杆的衬垫管移到管口对接处,实现对接焊缝衬垫管的定位。由于弦杆定位后,对接口空间狭小,衬垫管移动难度很大,很难保证衬垫管是否移至对接口处,不仅费时费力,影响工期而且质量无法保证,给施工带来了很大的难度。
发明内容
本发明的目的是克服上述不足问题,提供一种两端节点固定的管件衬垫管的安装方法,方法简单,易于安装,施工质量好,施工效率高。
本发明为实现上述目的所采用的技术方案是:一种两端节点固定的管件衬垫管的安装方法,涉及两端节点、直管和衬垫管, 
第一步:在一端节点处将整体衬垫管在安装前与节点焊接完成,再将管件与节点对接;
第二步另一端节点采用下述施工方法,将衬垫管三等分为三等分弧形衬板,在每段弧形衬板上焊接上把手,将弧形衬板塞进节点与直管的缝隙里面,塞进去后,用把手旋转使弧形衬板与对接口贴紧,将弧形衬板与直管焊接后,刨掉把手,其他两段弧形衬板按照此方法安装,形成整体衬垫管。
所述把手采用焊条或粗铁丝等。
本发明施工方法简单,两端节点固定的管件,一端采用整体式衬垫管,先行安装,易于施工,另一端由于操作间隙小,采用分体式衬垫管即弧形衬板,由于分体弧形衬板易于插入直管与节点的间隙中,而且插入后形成衬垫管,既便于安装施工,提高了生产效率,又满足了管件的性能要求,保证了产品质量。
附图说明:
图1是本发明管件外观图。
图2是本发明分体式衬垫管结构示意图。
图3是本发明分体式衬垫管安装把手结构示意图。
图4是本发明分体式衬垫管插装时状态图。
图5是本发明分体式衬垫管插入后状态图。
具体实施方式:
一种两端节点固定的管件衬垫管的安装方法,涉及如图1所示的两端节点固定的管件,两端节点1、6、直管2和衬垫管3,
第一步:在一端节点1处将整体衬垫管3在安装前与节点焊接完成,再将管件与节点对接;
第二步:另一端节点6采用下述施工方法,将衬垫管三等分为三等分弧形衬板4(如图2),在每段弧形衬板上焊接上把手5(如图3),把手采用焊条或粗铁丝等,将弧形衬板塞进节点与直管的缝隙里面(如图4),塞进去后,用焊条或粗铁丝旋转使弧形衬板与对接口贴紧(如图5),将弧形衬板与直管焊接后,刨掉把手,其他两段弧形衬板按照此方法安装,形成整体衬垫管。

Claims (2)

1.一种两端节点固定的管件衬垫管的安装方法,涉及两端节点和直管,其特征是:
第一步:在一端节点处将整体衬垫管在安装前与节点焊接完成,再将管件与节点对接;
第二步另一端节点采用下述施工方法,将衬垫管三等分为三等分弧形衬板,在每段弧形衬板上焊接上把手,将弧形衬板塞进节点与直管的缝隙里面,塞进去后,用焊条或粗铁丝旋转使弧形衬板与对接口贴紧,将弧形衬板与直管焊接后,刨掉把手,其他两段弧形衬板按照此方法安装,形成整体衬垫管。
2.根据权利要求1所述的一种两端节点固定的管件衬垫管的安装方法,其特征是:所述把手采用焊条或粗铁丝。
CN2011103846598A 2011-11-28 2011-11-28 一种两端节点固定的管件衬垫管的安装方法 Pending CN102493662A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103846598A CN102493662A (zh) 2011-11-28 2011-11-28 一种两端节点固定的管件衬垫管的安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103846598A CN102493662A (zh) 2011-11-28 2011-11-28 一种两端节点固定的管件衬垫管的安装方法

Publications (1)

Publication Number Publication Date
CN102493662A true CN102493662A (zh) 2012-06-13

Family

ID=46185516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103846598A Pending CN102493662A (zh) 2011-11-28 2011-11-28 一种两端节点固定的管件衬垫管的安装方法

Country Status (1)

Country Link
CN (1) CN102493662A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104951177A (zh) * 2014-03-24 2015-09-30 联想(北京)有限公司 一种信息处理方法及电子设备
CN112872697A (zh) * 2019-11-29 2021-06-01 中冶(上海)钢结构科技有限公司 一种圆管对接口焊接衬垫板管内滑动安装的方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29812547U1 (de) * 1998-07-14 1998-10-15 Klee Klamp Ltd Anschlußvorrichtung
CN2823382Y (zh) * 2005-07-12 2006-10-04 徐国彬 支承节点
CN101691797A (zh) * 2009-09-14 2010-04-07 江苏沪宁钢机股份有限公司 一种屋面桁架的制作方法
CN101858150A (zh) * 2010-01-25 2010-10-13 安徽鲁班建设投资集团有限公司 一种钢结构组合节点安装方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29812547U1 (de) * 1998-07-14 1998-10-15 Klee Klamp Ltd Anschlußvorrichtung
CN2823382Y (zh) * 2005-07-12 2006-10-04 徐国彬 支承节点
CN101691797A (zh) * 2009-09-14 2010-04-07 江苏沪宁钢机股份有限公司 一种屋面桁架的制作方法
CN101858150A (zh) * 2010-01-25 2010-10-13 安徽鲁班建设投资集团有限公司 一种钢结构组合节点安装方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周光毅等: "大连国际会议中心管桁架屋盖施工技术", 《施工技术》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104951177A (zh) * 2014-03-24 2015-09-30 联想(北京)有限公司 一种信息处理方法及电子设备
CN104951177B (zh) * 2014-03-24 2018-02-27 联想(北京)有限公司 一种信息处理方法及电子设备
CN112872697A (zh) * 2019-11-29 2021-06-01 中冶(上海)钢结构科技有限公司 一种圆管对接口焊接衬垫板管内滑动安装的方法

Similar Documents

Publication Publication Date Title
CN202780252U (zh) 钢管对接焊缝处的滑动衬垫环连接结构
CN104533433A (zh) 小半径曲线隧道的始发方法
CN104314584A (zh) 一种拼装式顶管管片结构及其拼装方法
CN101949213A (zh) 建筑结构变形缝模板专用支撑系统
CN103953353A (zh) 盾构始发反力架及其安装使用方法
CN102493662A (zh) 一种两端节点固定的管件衬垫管的安装方法
CN105234568A (zh) 一种圆管相贯节点全板厚熔透焊接方法
CN204312088U (zh) 一种拼装式顶管管片结构
CN203238696U (zh) 一种挖掘机斗齿
CN201688028U (zh) 地埋管道滚动隔热支架
CN204626453U (zh) 城市地下综合管廊中管道的支承机构
CN201460220U (zh) 地下连续墙内衬墙支模用单头对拉螺栓
CN202493039U (zh) 一种两端节点固定的管件
CN202280152U (zh) 一种在钢筋混凝土板底设置预埋件的结构
CN103758387B (zh) 液化天然气储罐壁板的安装方法
CN103243773B (zh) 一种挖掘机斗齿
CN202850489U (zh) 预埋线管定位连接件
CN104832708B (zh) 一种管道预装架
CN206608506U (zh) 光伏t型线夹
CN205077629U (zh) 中空夹层钢管混凝土柱与钢梁连接装置
CN202255037U (zh) 一种边板及换热器
CN106229913A (zh) 一种可拆卸电缆保护管结构
CN202768552U (zh) 一种钢管桁架拼接结构
CN206550566U (zh) 一种塔机标准节主弦杆连接套的定位焊接工装
CN201605715U (zh) 地下管沟的管沟梁

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION CO.

Effective date: 20130306

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130306

Address after: 116000. 235 and 237 Gorky Road, Shahekou District, Liaoning, Dalian

Applicant after: Dalian Branch China Construction Eineering Division Corp. Ltd.

Applicant after: China Construction Eighth Engineering Division Co., Ltd.

Address before: 116000. 235 and 237 Gorky Road, Shahekou District, Liaoning, Dalian

Applicant before: Dalian Branch China Construction Eineering Division Corp. Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)