CN101858150A - 一种钢结构组合节点安装方法 - Google Patents

一种钢结构组合节点安装方法 Download PDF

Info

Publication number
CN101858150A
CN101858150A CN201010100278A CN201010100278A CN101858150A CN 101858150 A CN101858150 A CN 101858150A CN 201010100278 A CN201010100278 A CN 201010100278A CN 201010100278 A CN201010100278 A CN 201010100278A CN 101858150 A CN101858150 A CN 101858150A
Authority
CN
China
Prior art keywords
steel
channel
truss
junction plate
section steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201010100278A
Other languages
English (en)
Other versions
CN101858150B (zh
Inventor
杨元
陶俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI LUBAN GROUP
Original Assignee
ANHUI LUBAN CONSTRUCTION MANAGEMENT GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI LUBAN CONSTRUCTION MANAGEMENT GROUP Co Ltd filed Critical ANHUI LUBAN CONSTRUCTION MANAGEMENT GROUP Co Ltd
Priority to CN2010101002788A priority Critical patent/CN101858150B/zh
Publication of CN101858150A publication Critical patent/CN101858150A/zh
Application granted granted Critical
Publication of CN101858150B publication Critical patent/CN101858150B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明提供一种钢结构组合节点安装方法,属于建筑施工技术领域,其安装步骤主要为:先在钢柱1上与桁架连接的位置加焊槽钢4,在桁架的上弦杆2和下弦杆3端部内侧80~150mm处均焊接内隔板5;再在每块内隔板5边缘加焊封头板6,在封头板6下部焊接连接板7,然后在连接板7与封头板6两侧再焊接垂直加劲肋8。安装时,直接将连接板7和槽钢4用高强度螺栓9连接。本发明采用内隔板5和垂直加劲肋8的组合节点方式,取消了传统节点所需的对穿孔,桁架上下弦与钢柱1壁不需要焊接,减少了制造工序和成本,传力更明确,增加了节点的强度,提高了钢结构的安全系数。

Description

一种钢结构组合节点安装方法
技术领域
本发明属于建筑施工领域,涉及一种钢结构安装方法。
背景技术
在大型的钢结构建筑中,钢管与钢管桁架的组合节点安装方法十分重要,直接影响到钢结构的安全性和实用性。一般采用对穿螺栓节点,即用高强度螺栓穿过钢管,安装到钢管桁架上。这种安装方法虽然简单,但对桁架长度的加工精度要求较高,施工累计误差不易消除,安装时对温度敏感,安装成本较大,而且节点区柱壁上要开孔,削弱了钢管截面,影响钢管的结构稳定性,造成安全隐患,不适合应用于对安全质量要求较高的钢结构建筑。
发明内容
本发明的目的是克服现有的对穿螺栓节点安装方法的缺陷,提供一种安全可靠、施工要求简便且成本低的钢结构安装方法。
本发明实现目的所采取的技术方案为:一种钢结构安装方法,其安装步骤主要为:先在钢柱(1)上与桁架连接的位置加焊两段槽钢(4),槽钢上预留高强度螺栓孔;在桁架的上弦杆(2)和下弦杆(3)端部内侧均焊接内隔板(5);再在每块内隔板(5)边缘加焊封头板(6);在封头板(6)下部焊接与槽钢(4)相匹配的连接板(7),连接板(7)上预留与槽钢(4)相同的高强度螺栓孔;然后在连接板(7)与封头板(6)两侧再焊接与槽钢(4)相匹配的垂直加劲肋(8);安装时,直接将连接板(7)和槽钢(4)用高强度螺栓(9)连接。
所使用的构件尺寸为:钢柱(1)直径为180mm;桁架上弦杆(2)和桁架下弦杆(3)之间距离为1500mm;槽钢长度为490mm,宽180mm,厚18mm;槽钢(4)与连接板(7)上所留螺栓孔直径为21.5mm,每个槽钢或连接板有8个孔;内隔板(5)根据需求调整大小,安装在桁架上弦杆(2)或下弦杆(3)端部内侧80~150mm处;封头板(6)长200mm,宽200mm,厚10mm;连接板(7)长160mm,宽140mm,厚10mm;垂直加劲肋(8)长160mm,宽140mm,厚10mm。
设置内隔板(5)和垂直加劲肋(8)可以使桁架截面局部增强,使桁架塑性铰外移,节点具有更好的抗震性能。垂直加劲肋(8)还可以将桁架上的拉、压力直接传给柱腹板,避免钢柱(1)壁平面外变形过大。
本发明采用冷成型方矩形钢柱,代替了传统的H型钢柱,提高了钢柱(1)截面抗弯模量,增强了钢结构抗腐蚀、耐火性能。采用内隔板(5)和垂直加劲肋(8)的组合节点方式,桁架上下弦与钢柱(1)壁不需要焊接,传力更明确,同时为垂直加劲肋(8)焊接垫板留下空间,而且不需要加工腹板过焊孔,减少了制造工序。传统钢结构节点安装方法需在钢柱(1)上加工对穿孔,由于管径较大,普通钻头加工长度不能满足要求,采取两边加工既降低效率又难以保证孔位同心,因此需定做加长钻头,增加安装成本。采用对穿孔连接桁架后,不能立即固定,若完全固定将会影响相邻一侧桁架的安装,因此只能临时固定,使安装过程中存在较大的安全隐患。本发明提供的一种更钢结构组合节点安装方法,在加工中取消了钢柱的对穿孔,并且选用的高强度螺栓均为标准件,无需定做,既减少加工工序,又节省了安装成本,桁架安装后可立即固定,减少了安全隐患。
附图说明
说明书附图为本发明所述的一种钢结构组合节点的结构示意图。
图中,1为钢柱,2为桁架上弦杆,3为桁架下弦杆,4为槽钢,5为内隔板,6为封头板,7为连接板,8为垂直加劲肋,9为高强度螺栓。
具体实施方式
以下根据附图说明对本发明的具体实施做进一步的详细描述。
本发明提供的一种钢结构组合节点安装方法,具体操作时可按以下步骤进行:
1、施工准备
按照施工标准检验所用原料钢材即冷成型方矩形钢材的质量,确保原材料的安全性,同时检查施工过程要使用的机械完好无损,清理施工场地,尽量减少安全隐患,然后根据结构要求按照标高将钢柱1埋设好,钢柱1直径为180mm,为施工做好准备。
2、构件制作
按照尺寸要求制作槽钢4、内隔板5、封头板6、连接板7和垂直加劲肋8,并且在槽钢4和连接板7上制作与标准高强度螺栓9相匹配的螺栓孔。槽钢长度为490mm,宽180mm,厚18mm;槽钢(4)与连接板(7)上所留螺栓孔直径为21.5mm,每个槽钢或连接板有8个孔;内隔板(5)根据需求调整大小,可制作为长250mm,宽200mm,厚10mm;封头板(6)长200mm,宽200mm,厚10mm;连接板(7)长160mm,宽140mm,厚10mm;垂直加劲肋(8)长160mm,宽140mm,厚10mm。
3、安装组合节点
先在钢柱1上与桁架连接的位置加焊槽钢4,在桁架的上弦杆2和下弦杆3端部内侧100mm处均焊接内隔板5;再在每块内隔板5边缘加焊封头板6,在封头板6下部焊接连接板7,然后在连接板7与封头板6两侧再焊接垂直加劲肋8。安装时,直接将连接板7和槽钢4用高强度螺栓9连接。

Claims (4)

1.一种钢结构组合节点安装方法,其特征是安装步骤主要为:先在钢柱(1)上与桁架连接的位置加焊两段槽钢(4),槽钢上预留高强度螺栓孔;在桁架的上弦杆(2)和下弦杆(3)端部内侧均焊接内隔板(5);再在每块内隔板(5)边缘加焊封头板(6);在封头板(6)下部焊接与槽钢(4)相匹配的连接板(7),连接板(7)上预留与槽钢(4)相同的高强度螺栓孔;然后在连接板(7)与封头板(6)两侧再焊接与槽钢(4)相匹配的垂直加劲肋(8);安装时,直接将连接板(7)和槽钢(4)用高强度螺栓(9)连接。
2.根据权利要求1所述的一种钢结构组合节点安装方法,其特征是所使用的构件尺寸为:钢柱(1)直径为180mm;桁架上弦杆(2)和桁架下弦杆(3)之间距离为1500mm;槽钢长度为490mm,宽180mm,厚18mm;槽钢(4)与连接板(7)上所留螺栓孔直径为21.5mm,每个槽钢或连接板有8个孔;内隔板(5)根据需求调整大小,安装在桁架上弦杆(2)或下弦杆(3)端部内侧80~150mm处;封头板(6)长200mm,宽200mm,厚10mm;连接板(7)长160mm,宽140mm,厚10mm;垂直加劲肋(8)长160mm,宽140mm,厚10mm。
3.根据权利要求1所述的一种钢结构组合节点安装方法,其特征是设置内隔板(5)和垂直加劲肋(8)可以使桁架截面局部增强,使桁架塑性铰外移,节点具有更好的抗震性能。
4.根据权利要求1所述的一种钢结构组合节点安装方法,其特征是垂直加劲肋(8)可以将桁架上的拉、压力直接传给柱腹板,避免钢柱(1)壁平面外变形过大。
CN2010101002788A 2010-01-25 2010-01-25 一种钢结构组合节点安装方法 Active CN101858150B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101002788A CN101858150B (zh) 2010-01-25 2010-01-25 一种钢结构组合节点安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101002788A CN101858150B (zh) 2010-01-25 2010-01-25 一种钢结构组合节点安装方法

Publications (2)

Publication Number Publication Date
CN101858150A true CN101858150A (zh) 2010-10-13
CN101858150B CN101858150B (zh) 2011-06-29

Family

ID=42944289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101002788A Active CN101858150B (zh) 2010-01-25 2010-01-25 一种钢结构组合节点安装方法

Country Status (1)

Country Link
CN (1) CN101858150B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493662A (zh) * 2011-11-28 2012-06-13 中建八局大连建设工程有限公司 一种两端节点固定的管件衬垫管的安装方法
CN102913742A (zh) * 2012-07-20 2013-02-06 上海交通大学 钢桁架领结式整体节点的结构构造和施工方法
CN111335486A (zh) * 2020-04-09 2020-06-26 钟建敏 一种钢桁架与框架柱侧向铰接连接装置

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1368397A1 (ru) * 1986-04-07 1988-01-23 Ростовское Отделение Центрального Научно-Исследовательского И Проектного Института Стальных Металлоконструкций Им.Н.П.Мельникова Каркас здани
CN201165725Y (zh) * 2007-12-18 2008-12-17 北京别一阁钢结构科技开发有限公司 冲压成型的金属连接板及桁架
CN101200965B (zh) * 2007-12-18 2011-12-07 北京别一阁钢结构科技开发有限公司 冲压成型的金属连接板及桁架
CN101397844B (zh) * 2008-09-25 2011-01-26 陕西省第三建筑工程公司 特殊型钢混凝土组合结构倾斜墙体模架工程施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493662A (zh) * 2011-11-28 2012-06-13 中建八局大连建设工程有限公司 一种两端节点固定的管件衬垫管的安装方法
CN102913742A (zh) * 2012-07-20 2013-02-06 上海交通大学 钢桁架领结式整体节点的结构构造和施工方法
CN102913742B (zh) * 2012-07-20 2015-05-20 上海交通大学 钢桁架领结式整体节点的施工方法
CN111335486A (zh) * 2020-04-09 2020-06-26 钟建敏 一种钢桁架与框架柱侧向铰接连接装置
CN111335486B (zh) * 2020-04-09 2021-07-06 钟建敏 一种钢桁架与框架柱侧向铰接连接装置

Also Published As

Publication number Publication date
CN101858150B (zh) 2011-06-29

Similar Documents

Publication Publication Date Title
CN202831235U (zh) 一种内置套管的矩形钢管柱与h型钢梁装配式节点
CN110593419B (zh) 一种装配式穿心螺栓不等高梁-方钢管混凝土柱节点构造及作法
CN106677336A (zh) 一种方钢管混凝土柱与工字形截面钢梁的连接节点构造及作法
CN101824908A (zh) 剪力墙大模板和剪力墙大模板体系
CN110863569B (zh) 滑动式复式钢管混凝土柱-梁节点及柱-柱连接体系
CN111962952A (zh) 一种钢管混凝土柱-H型钢梁-钢支撑-π形连接件组合式中柱底部节点及作法
CN101858150B (zh) 一种钢结构组合节点安装方法
CN112282121A (zh) 预制式内置波纹钢板增强混凝土组合剪力墙及施工工艺
CN201474096U (zh) 一种梁柱节点的减震连接结构
CN211257341U (zh) 一种圆钢管混凝土柱与工字形钢梁的刚性加强连接节点
CN103306376A (zh) 一种可拼装式钢管混凝土叠合柱-型钢混凝土梁节点
CN103510627A (zh) 方钢管混凝土柱与工字钢梁的套管式节点及其加工方法
CN113585456B (zh) 预制混凝土梁柱连接节点构造及施工方法
CN111851987B (zh) 一种附着式短肢工字钢花篮拉杆拉结式悬挑架施工方法
CN102031750B (zh) T-pbl形式钢桁腹杆与混凝土的节点构造
CN111962950A (zh) 一种钢管混凝土柱-H型钢梁-钢支撑-π形连接件组合式角柱中部节点及作法
CN201850654U (zh) 一种钢结构节点装置
CN201635386U (zh) 剪力墙大模板和剪力墙大模板体系
CN111962953B (zh) 一种钢管混凝土柱-H型钢梁-钢支撑-π形连接件组合式边柱中部节点及作法
CN106088398A (zh) 一种复合墙板
CN213897669U (zh) 预制式内置波纹钢板增强混凝土组合剪力墙
CN212927241U (zh) 一种钢管混凝土柱-H钢梁-支撑-π形组合式角柱中部节点
CN213539881U (zh) 一种钢管混凝土柱H型梁支撑π形组合式中柱底部节点
CN209891401U (zh) 一种方钢管混凝土柱与组合梁节点连接结构
CN107700824A (zh) 杆式附墙架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170822

Address after: 241300 Nanling Economic Development Zone, Wuhu, Anhui

Patentee after: ANHUI LUBAN STEEL STRUCTURE Co.,Ltd.

Address before: 241300 Anhui city of Wuhu province Nanling Nanxiang County Road No. 118

Patentee before: ANHUI LUBAN Group

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221214

Address after: No.118 Nanxiang Road, Nanling County, Wuhu City, Anhui Province

Patentee after: ANHUI LUBAN Group

Address before: 241300 Nanling County Economic Development Zone, Wuhu City, Anhui Province

Patentee before: ANHUI LUBAN STEEL STRUCTURE Co.,Ltd.