CN102493434A - Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile - Google Patents
Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile Download PDFInfo
- Publication number
- CN102493434A CN102493434A CN201110384951XA CN201110384951A CN102493434A CN 102493434 A CN102493434 A CN 102493434A CN 201110384951X A CN201110384951X A CN 201110384951XA CN 201110384951 A CN201110384951 A CN 201110384951A CN 102493434 A CN102493434 A CN 102493434A
- Authority
- CN
- China
- Prior art keywords
- pile
- reinforcement
- concrete
- pile head
- pile crown
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110384951.XA CN102493434B (en) | 2011-11-28 | 2011-11-28 | Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110384951.XA CN102493434B (en) | 2011-11-28 | 2011-11-28 | Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102493434A true CN102493434A (en) | 2012-06-13 |
CN102493434B CN102493434B (en) | 2014-04-16 |
Family
ID=46185290
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110384951.XA Active CN102493434B (en) | 2011-11-28 | 2011-11-28 | Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102493434B (en) |
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102926380A (en) * | 2012-11-20 | 2013-02-13 | 中铁十九局集团第三工程有限公司 | Bridge cast-in-place pile chiseling-free pile head and construction method thereof |
CN103266612A (en) * | 2013-06-06 | 2013-08-28 | 大连大金马基础建设有限公司 | Pile splicing anchor bar protecting frame |
CN104234038A (en) * | 2014-03-03 | 2014-12-24 | 王磊 | Bored concrete pile construction technology without breaking of pile head |
CN104343115A (en) * | 2014-11-13 | 2015-02-11 | 中交隧道工程局有限公司 | Structure and method for integrally breaking pile head of pile foundation |
CN104727306A (en) * | 2015-03-19 | 2015-06-24 | 中交二航局第三工程有限公司 | Cast-in place pile pouring and pile head cutting-off method |
CN105178318A (en) * | 2014-05-30 | 2015-12-23 | 中国二十冶集团有限公司 | Method for removing steel pipe downcomer well |
CN105297729A (en) * | 2015-11-23 | 2016-02-03 | 中国葛洲坝集团第六工程有限公司 | Bridge pile foundation pile head breaking device and method |
CN105350524A (en) * | 2015-12-04 | 2016-02-24 | 中交隧道工程局有限公司 | Steel reinforcement cage structure, concrete filling pile structure and construction method of concrete filling pile structure |
CN106120792A (en) * | 2016-08-11 | 2016-11-16 | 北京城建七建设工程有限公司 | A kind of pile foundation pile crown concrete prestripping assembly and construction method |
CN106400802A (en) * | 2016-08-24 | 2017-02-15 | 中交公局厦门工程有限公司 | Integral quick lifting method for pile head of drilled pile during pre-embedding and drilling-free ring-cutting |
CN106400803A (en) * | 2016-10-31 | 2017-02-15 | 中国葛洲坝集团第六工程有限公司 | Integral cast-in-situ bored pile head breaking process |
CN106400804A (en) * | 2016-11-17 | 2017-02-15 | 宁波市政工程建设集团股份有限公司 | Obstructing pulling method pile digging construction device and method |
CN106759336A (en) * | 2016-12-19 | 2017-05-31 | 中交路桥建设有限公司 | A kind of cast-in-situ bored pile quickly abolishes pile crown construction method |
CN106958245A (en) * | 2017-04-07 | 2017-07-18 | 中交二公局第工程有限公司 | The quick structure and method for abolishing concrete pile head |
CN106968251A (en) * | 2017-05-26 | 2017-07-21 | 中交第二航务工程局有限公司 | A kind of concrete filling pile head abolishes device and its construction method |
CN107034887A (en) * | 2017-03-30 | 2017-08-11 | 河南大建桥梁钢构股份有限公司 | Bored piles headring cuts construction method |
CN107542092A (en) * | 2017-08-18 | 2018-01-05 | 广州市公路工程公司 | High efficiency honeycomb method broken pile head construction technology |
CN108104116A (en) * | 2018-01-19 | 2018-06-01 | 中建筑港集团有限公司 | A kind of filling pile head processing method and Quick Release pile crown bored concrete pile |
CN108487238A (en) * | 2018-05-24 | 2018-09-04 | 北京良乡蓝鑫水利工程设计有限公司 | A kind of filling pile head processing unit and its construction method |
CN110468842A (en) * | 2019-08-14 | 2019-11-19 | 中交第二公路工程局有限公司 | A kind of concrete pile head abolishes structure and its restructuring bankrupt |
CN112030960A (en) * | 2020-07-22 | 2020-12-04 | 中铁十局集团第一工程有限公司 | Construction method of separable fulcrum pile |
CN113622427A (en) * | 2021-07-06 | 2021-11-09 | 中国二十冶集团有限公司 | Auxiliary device for chiseling pile head and construction method for chiseling pile head |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03107017A (en) * | 1989-09-21 | 1991-05-07 | Nitto Kensetsu Kk | Pile head treatment method for cast-in-place concrete pile |
JPH05287734A (en) * | 1992-04-02 | 1993-11-02 | Taisei Corp | Pile head processing method |
JPH08105041A (en) * | 1994-10-04 | 1996-04-23 | Jdc Corp | Pile top treating method of cast-in-place foundation pillar and tool for this treatment |
JP2003055962A (en) * | 2001-08-17 | 2003-02-26 | Achilles Corp | Head edge treatment sheet for cast-in-place pile and head edge cutting treatment method |
JP2005325607A (en) * | 2004-05-14 | 2005-11-24 | Takenaka Komuten Co Ltd | Pile head treating method of cast-in-place concrete pile |
JP2006037492A (en) * | 2004-07-27 | 2006-02-09 | Takenaka Komuten Co Ltd | Pile head processing construction method of cast-in-place concrete pile |
CN101333811A (en) * | 2008-08-05 | 2008-12-31 | 中国建筑材料科学研究总院 | Concrete filling pile head static cutting and crushing method |
JP2010007397A (en) * | 2008-06-28 | 2010-01-14 | 索郎 ▲廣▼▲瀬▼ | Pile head treating method and pile head treating apparatus |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5287734B2 (en) * | 2010-01-07 | 2013-09-11 | トヨタ自動車株式会社 | Parking assistance device |
-
2011
- 2011-11-28 CN CN201110384951.XA patent/CN102493434B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03107017A (en) * | 1989-09-21 | 1991-05-07 | Nitto Kensetsu Kk | Pile head treatment method for cast-in-place concrete pile |
JPH05287734A (en) * | 1992-04-02 | 1993-11-02 | Taisei Corp | Pile head processing method |
JPH08105041A (en) * | 1994-10-04 | 1996-04-23 | Jdc Corp | Pile top treating method of cast-in-place foundation pillar and tool for this treatment |
JP2003055962A (en) * | 2001-08-17 | 2003-02-26 | Achilles Corp | Head edge treatment sheet for cast-in-place pile and head edge cutting treatment method |
JP2005325607A (en) * | 2004-05-14 | 2005-11-24 | Takenaka Komuten Co Ltd | Pile head treating method of cast-in-place concrete pile |
JP2006037492A (en) * | 2004-07-27 | 2006-02-09 | Takenaka Komuten Co Ltd | Pile head processing construction method of cast-in-place concrete pile |
JP2010007397A (en) * | 2008-06-28 | 2010-01-14 | 索郎 ▲廣▼▲瀬▼ | Pile head treating method and pile head treating apparatus |
CN101333811A (en) * | 2008-08-05 | 2008-12-31 | 中国建筑材料科学研究总院 | Concrete filling pile head static cutting and crushing method |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102926380A (en) * | 2012-11-20 | 2013-02-13 | 中铁十九局集团第三工程有限公司 | Bridge cast-in-place pile chiseling-free pile head and construction method thereof |
CN103266612A (en) * | 2013-06-06 | 2013-08-28 | 大连大金马基础建设有限公司 | Pile splicing anchor bar protecting frame |
CN104234038A (en) * | 2014-03-03 | 2014-12-24 | 王磊 | Bored concrete pile construction technology without breaking of pile head |
CN105178318B (en) * | 2014-05-30 | 2017-06-30 | 中国二十冶集团有限公司 | A kind of steel pipe downcast pipe well removal method |
CN105178318A (en) * | 2014-05-30 | 2015-12-23 | 中国二十冶集团有限公司 | Method for removing steel pipe downcomer well |
CN104343115A (en) * | 2014-11-13 | 2015-02-11 | 中交隧道工程局有限公司 | Structure and method for integrally breaking pile head of pile foundation |
CN104727306A (en) * | 2015-03-19 | 2015-06-24 | 中交二航局第三工程有限公司 | Cast-in place pile pouring and pile head cutting-off method |
CN105297729A (en) * | 2015-11-23 | 2016-02-03 | 中国葛洲坝集团第六工程有限公司 | Bridge pile foundation pile head breaking device and method |
CN105350524A (en) * | 2015-12-04 | 2016-02-24 | 中交隧道工程局有限公司 | Steel reinforcement cage structure, concrete filling pile structure and construction method of concrete filling pile structure |
CN106120792A (en) * | 2016-08-11 | 2016-11-16 | 北京城建七建设工程有限公司 | A kind of pile foundation pile crown concrete prestripping assembly and construction method |
CN106400802A (en) * | 2016-08-24 | 2017-02-15 | 中交公局厦门工程有限公司 | Integral quick lifting method for pile head of drilled pile during pre-embedding and drilling-free ring-cutting |
CN106400803A (en) * | 2016-10-31 | 2017-02-15 | 中国葛洲坝集团第六工程有限公司 | Integral cast-in-situ bored pile head breaking process |
CN106400804A (en) * | 2016-11-17 | 2017-02-15 | 宁波市政工程建设集团股份有限公司 | Obstructing pulling method pile digging construction device and method |
CN106759336A (en) * | 2016-12-19 | 2017-05-31 | 中交路桥建设有限公司 | A kind of cast-in-situ bored pile quickly abolishes pile crown construction method |
CN107034887A (en) * | 2017-03-30 | 2017-08-11 | 河南大建桥梁钢构股份有限公司 | Bored piles headring cuts construction method |
CN106958245A (en) * | 2017-04-07 | 2017-07-18 | 中交二公局第工程有限公司 | The quick structure and method for abolishing concrete pile head |
CN106968251A (en) * | 2017-05-26 | 2017-07-21 | 中交第二航务工程局有限公司 | A kind of concrete filling pile head abolishes device and its construction method |
CN107542092A (en) * | 2017-08-18 | 2018-01-05 | 广州市公路工程公司 | High efficiency honeycomb method broken pile head construction technology |
CN108104116A (en) * | 2018-01-19 | 2018-06-01 | 中建筑港集团有限公司 | A kind of filling pile head processing method and Quick Release pile crown bored concrete pile |
CN108487238A (en) * | 2018-05-24 | 2018-09-04 | 北京良乡蓝鑫水利工程设计有限公司 | A kind of filling pile head processing unit and its construction method |
CN110468842A (en) * | 2019-08-14 | 2019-11-19 | 中交第二公路工程局有限公司 | A kind of concrete pile head abolishes structure and its restructuring bankrupt |
CN112030960A (en) * | 2020-07-22 | 2020-12-04 | 中铁十局集团第一工程有限公司 | Construction method of separable fulcrum pile |
CN113622427A (en) * | 2021-07-06 | 2021-11-09 | 中国二十冶集团有限公司 | Auxiliary device for chiseling pile head and construction method for chiseling pile head |
Also Published As
Publication number | Publication date |
---|---|
CN102493434B (en) | 2014-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102493434A (en) | Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile | |
CN106759336A (en) | A kind of cast-in-situ bored pile quickly abolishes pile crown construction method | |
CN102312429B (en) | Rapid separation and integral hoisting method for pile head of cast-in-place concrete pile | |
CN105297729B (en) | Bridge pile foundation pile head breaking device and method | |
CN106958245A (en) | The quick structure and method for abolishing concrete pile head | |
CN103243745B (en) | A kind of method of pile tube deviation rectification | |
CN207739259U (en) | A kind of filling pile head cuts device | |
CN103485343A (en) | Pile head processing method of filling pile | |
CN107604920A (en) | A kind of quick construction method for abolishing filling pile head | |
CN108612109A (en) | The carrierless method for dismounting of concrete support beam | |
CN106836213A (en) | Grouting behind shaft or drift lining pre-stress hollow square pile and its construction technology | |
CN110863498A (en) | Deep foundation pit combined supporting construction method next to subway station | |
CN102425184A (en) | Cap preserved hole construction method for deep-water soft soil foundation reverse low pile cap composite foundation | |
CN104631460A (en) | Girdling splitting type integral pile breaking method | |
CN206859222U (en) | The quick structure for abolishing concrete pile head | |
CN206408630U (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body | |
CN206941586U (en) | A kind of device for improving pile crown and abolishing efficiency | |
CN101929159B (en) | Protective method of pipelines in natural gas pipeline full-section excavation construction | |
CN206110122U (en) | Bridge drilled pile convenient to get rid of pile head | |
CN109944246A (en) | A kind of construction method of broken pile head | |
CN206667233U (en) | A kind of steel wire rope, steel pipe, buckle combine detachable hangs muscle | |
CN206385532U (en) | It is a kind of to be used for the piling template of CFG | |
CN206144569U (en) | Confined is advance in advance and is protected tunnel structure | |
CN113373922A (en) | Geothermal energy pile construction equipment and construction method thereof | |
CN106759435A (en) | A kind of steel structure base ring of mountain region wind driven generator base |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD. Effective date: 20150302 Owner name: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU Free format text: FORMER OWNER: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU GROUP GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU Effective date: 20150302 |
|
C41 | Transfer of patent application or patent right or utility model | ||
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE |
|
TR01 | Transfer of patent right |
Effective date of registration: 20150302 Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No. Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau Patentee after: No.1 Engineering Co., Ltd., Zhongtie Bridge Bureau Group Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd. Patentee before: No.1 Engineering Co., Ltd., Zhongtie Bridge Bureau Group Patentee before: Group Co., Ltd., Zhongtie Daqiao Bureau |