CN106759336A - A kind of cast-in-situ bored pile quickly abolishes pile crown construction method - Google Patents

A kind of cast-in-situ bored pile quickly abolishes pile crown construction method Download PDF

Info

Publication number
CN106759336A
CN106759336A CN201611181114.6A CN201611181114A CN106759336A CN 106759336 A CN106759336 A CN 106759336A CN 201611181114 A CN201611181114 A CN 201611181114A CN 106759336 A CN106759336 A CN 106759336A
Authority
CN
China
Prior art keywords
pile
pile crown
ring
concrete
wire rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611181114.6A
Other languages
Chinese (zh)
Inventor
刘大勇
张瑞平
揭庆芳
吴海海
林振来
朱丹丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201611181114.6A priority Critical patent/CN106759336A/en
Publication of CN106759336A publication Critical patent/CN106759336A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention provides a kind of cast-in-situ bored pile and quickly abolishes pile crown construction method, during pile foundation steel bar cage processing and fabricating, cage bar is located at stake top absolute altitude above section keeping parallelism state, and be inserted in soft sponge protection pipe;When steel reinforcement cage is installed, at design stake top absolute altitude, a steel wire rope for being cased with plastic flexible pipe is surround and fixed;When carrying out pile foundation filling concrete, the pile crown concrete embedded set more than stake top absolute altitude meets the reinforcing bar suspension ring of pile crown integral hoisting force request, and the upper end of suspension ring is exposed on pile crown top of concrete;When cutting pile crown, ring peels off steel wire rope, steel wire rope is carried out ring cutting to pile crown;Along ring cutting position, symmetrical horizontal inserting piling gad block makes pile crown be separated with pile body;Pile crown is integrally vertically sling and removed by suspension ring.

Description

A kind of cast-in-situ bored pile quickly abolishes pile crown construction method
Technical field
The present invention relates to highway bridge construction technology of cast-in-place bored field, and in particular to a kind of cast-in-situ bored pile quickly breaks Except pile crown construction method.
Background technology
During cast bored concrete pile, in process of vibrating, cement mortar carries bubble and returns upwards concrete, so stake top strong concrete Degree is relatively low, and to ensure pile foundation concrete strength, in perfusion, pile crown highly should be higher than that design stake top absolute altitude 0.5-1.0m, and in pile foundation After the completion of pouring, the pile crown part that will be above design of pile top absolute altitude is cut, and exposes reinforcing bar, and then held with bar connecting upper strata The reinforcing bar of platform structure, carries out pouring for superstructure.The work for cutting this part pile crown concrete is called " broken pile head ".Conventional at present Pile crown cuts method:Manually it is aided with small machine to cut, or ring cutting is carried out using abrasive machine to pile crown in designed elevation position, Then artificial chisel is except the cover concrete of super envelope pile crown, and cage bar peeled off into concrete from lateral, then by pile crown concrete piecemeal Cleaning.Existing these pile crowns cut method and have the following disadvantages:
1st, cutting pile crown can cause bending to damage to reinforcing bar;
2nd, binder following pile body cover to reinforcement cracking is easily caused when pile crown cuts or is peeled off, bury the disease of cage bar corrosion And be difficult to check and make up;
3rd, pile crown cuts low construction efficiency, influences duration progress.
The content of the invention
It is an object of the invention to provide a kind of construction method that can quickly abolish pile crown, in effective solution work progress Damage to reinforcing bar and pile body, improves efficiency of construction, it is ensured that construction quality.
Technical scheme is as follows:
A kind of cast-in-situ bored pile quickly abolishes pile crown construction method, it is characterised in that comprise the following steps:
(1) steel reinforcement cage processing:During steel reinforcement cage processing and fabricating, cage bar is not bent positioned at stake top absolute altitude above section, Keeping parallelism state;Every cage bar is inserted in soft sponge protection pipe positioned at stake top absolute altitude above section, and sponge is protected Pipe two ends tighten;
(2) steel reinforcement cage is installed:When steel reinforcement cage is installed, at design stake top absolute altitude, around and fix one and be cased with plastics The ring steel wire rope of flexible pipe, and the fag end of ring steel wire rope is located at outside pile foundation concrete to be poured;
(3) poured pile base concrete and pre-buried suspension ring:Pile foundation filling concrete is carried out, the pile crown more than stake top absolute altitude is mixed Solidifying soil embedded set meets the reinforcing bar suspension ring of pile crown integral hoisting force request, the upper end of suspension ring expose pile crown top of concrete it On;
(4) after pile foundation concrete reaches design strength requirement, cushion cap foundation ditch is excavated;
(5) after the completion of cushion cap excavation of foundation pit, the fag end of ring steel wire rope is connected with excavator or loop wheel machine, and ring peels off steel Cord, makes concrete of the steel wire rope during being stripped at ring cutting stake top absolute altitude, and realization carries out ring cutting to pile crown;
(6) along ring cutting position, symmetrical horizontal inserting piling gad block makes pile crown be separated with pile body;
(7) integrally vertically sling by suspension ring with excavator or loop wheel machine and remove pile crown.
The invention has the advantages that:
1st, overall vertical lifting upwards departs from pile body, is prevented effectively from during Stake head handling the damage to reinforcing bar, makes cage bar It is parallel, do not bend, and realize the soap-free emulsion polymeization and between the concrete that need to remove.
2nd, pile crown is integrally hung out upwards, and reduction is impacted or damaged to pile concrete, it is ensured that between pile foundation and cushion cap Connection.
3rd, operation is simple, and efficiency of construction is high.
4th, the input of construction equipment is reduced, flexible pipe used in the present invention, steel wire rope are repeatable to be utilized, foam sleeve etc. Material can gather materials on the spot, and substitute is more, can effective reduces cost.
5th, construction noise and dust are substantially reduced, and construction environment improves, effectively the health of protection workmen.
Brief description of the drawings
Fig. 1 is reinforcement cage structure schematic diagram of the invention;
Fig. 2 is the view after steel reinforcement cage of the present invention is installed;
Fig. 3 is the view after the completion of pile foundation concreting of the present invention;
Fig. 4 is the view after pile crown of the present invention is removed.
Specific embodiment
The cage bar of common steel reinforcement cage pile crown part bends in advance, so as to cushion cap bar connecting.
As shown in figure 1, the present invention is in steel reinforcement cage processing and fabricating, cage bar 1 is not carried out positioned at stake top absolute altitude above section Bending, keeping parallelism state;Every cage bar is located at stake top absolute altitude (in Fig. 1 at horizontal line) above section and is inserted in soft sponge guarantor Pillar 2, and the two ends of sponge protection pipe 2 are tightened.Sponge protects tube thickness about 10mm, and its effect makes pile crown reinforcing bar with perfusion It is non-caked between concrete.
As shown in Fig. 2 the present invention is when steel reinforcement cage is installed, at design stake top absolute altitude, it surround and fixes one and be cased with modeling Expect the ring steel wire rope 3 of flexible pipe, and the fag end 4 of ring steel wire rope is located at outside pile foundation concrete to be poured.Ring steel wire Rope can simply be fixed using adhesive tape or the nonmetallic cotton rope easily broken by external force etc with steel reinforcement cage.
As shown in figure 3, when carrying out pile foundation filling concrete, the main part of ring steel wire rope 3 is poured into concrete, but Its fag end 4 is located at outside pile foundation concrete.When being poured at stake top absolute altitude, buried in the pile crown concrete more than stake top absolute altitude The reinforcing bar suspension ring 5 for meeting pile crown integral hoisting force request are put, the upper end of suspension ring 5 is exposed on pile crown top of concrete.Suspension ring It is used as hanger (suspension centre) when being removed for pile crown.
After pile foundation concrete reaches design strength requirement, cushion cap foundation ditch is excavated.After the completion of cushion cap excavation of foundation pit, excavator is used Or loop wheel machine connects the fag end of ring steel wire rope, and ring peels off steel wire rope, and by steel wire rope, ring cuts during being stripped Concrete at stake top absolute altitude, realization carries out ring cutting to pile crown.
Along ring cutting position, symmetrical horizontal inserting piling gad block, due to the extremely low characteristic of concrete tensile strength, by symmetrical water Plug flat beats gad block, pile crown is separated with pile body.
Pile crown is vertically sling and removed with excavator or the entirety of loop wheel machine connection suspension ring 5.State such as Fig. 4 institutes after pile crown removal Show.After manual amendment being carried out to pile crown top surface, you can enter next procedure construction.

Claims (1)

1. a kind of cast-in-situ bored pile quickly abolishes pile crown construction method, it is characterised in that comprise the following steps:
(1) steel reinforcement cage processing:During steel reinforcement cage processing and fabricating, cage bar is not bent positioned at stake top absolute altitude above section, kept Parastate;Every cage bar is inserted in soft sponge protection pipe positioned at stake top absolute altitude above section, and by sponge protection pipe two End tightens;
(2) steel reinforcement cage is installed:When steel reinforcement cage is installed, at design stake top absolute altitude, around and fix one and be cased with plastic flexible pipe Ring steel wire rope, and make ring steel wire rope fag end be located at pile foundation concrete to be poured outside;
(3) poured pile base concrete and pre-buried suspension ring:Pile foundation filling concrete is carried out, the pile crown concrete more than stake top absolute altitude Embedded set meets the reinforcing bar suspension ring of pile crown integral hoisting force request, and the upper end of suspension ring is exposed on pile crown top of concrete;
(4) after pile foundation concrete reaches design strength requirement, cushion cap foundation ditch is excavated;
(5) after the completion of cushion cap excavation of foundation pit, the fag end of ring steel wire rope is connected with excavator or loop wheel machine, and ring peels off steel wire Rope, makes concrete of the steel wire rope during being stripped at ring cutting stake top absolute altitude, and realization carries out ring cutting to pile crown;
(6) along ring cutting position, symmetrical horizontal inserting piling gad block makes pile crown be separated with pile body;
(7) integrally vertically sling by suspension ring with excavator or loop wheel machine and remove pile crown.
CN201611181114.6A 2016-12-19 2016-12-19 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method Pending CN106759336A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611181114.6A CN106759336A (en) 2016-12-19 2016-12-19 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611181114.6A CN106759336A (en) 2016-12-19 2016-12-19 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method

Publications (1)

Publication Number Publication Date
CN106759336A true CN106759336A (en) 2017-05-31

Family

ID=58891009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611181114.6A Pending CN106759336A (en) 2016-12-19 2016-12-19 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method

Country Status (1)

Country Link
CN (1) CN106759336A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107604920A (en) * 2017-09-14 2018-01-19 云南建投第五建设有限公司 A kind of quick construction method for abolishing filling pile head
CN108203979A (en) * 2018-02-27 2018-06-26 中建路桥集团有限公司 A kind of pile crown breaking system and restructuring bankrupt using the method for abolishing that disappears
CN108547304A (en) * 2018-05-17 2018-09-18 山东电力建设第三工程有限公司 The invalid pile crown of deposited reinforced concrete pile integrally abolishes construction technology
CN109083148A (en) * 2018-08-24 2018-12-25 中铁十四局集团第三工程有限公司 A kind of drilling pile pile crown constructing device and its construction method
CN109969934A (en) * 2019-04-11 2019-07-05 中国十七冶集团有限公司 It is a kind of quickly to abolish cast-in-situ bored pile pile crown hanging hook and its construction method
CN110453685A (en) * 2019-09-16 2019-11-15 腾达建设集团股份有限公司 A chisel-free pile head device and its application method
CN113373926A (en) * 2021-06-06 2021-09-10 中交路桥建设有限公司 Separation device for pile head breaking and construction method
CN113622427A (en) * 2021-07-06 2021-11-09 中国二十冶集团有限公司 Auxiliary device for chiseling pile head and construction method for chiseling pile head
CN114086555A (en) * 2021-11-25 2022-02-25 中铁三局集团有限公司 Combined device for breaking pile head of bored pile foundation and pile head breaking construction method
CN114718070A (en) * 2022-05-06 2022-07-08 中铁广州工程局集团第三工程有限公司 Construction method for breaking soil between piles and pile heads of super-irrigation cast-in-place pile
CN114922182A (en) * 2022-06-27 2022-08-19 中国十七冶集团有限公司 Method for quickly separating embedded part from pile head of cast-in-place pile
CN114960648A (en) * 2022-06-14 2022-08-30 重庆建工集团股份有限公司 Concrete pile head line cutting device
CN115613573A (en) * 2022-11-11 2023-01-17 中国建筑第八工程局有限公司 A high-efficiency cutting system for pile heads of cast-in-place piles
CN115613572A (en) * 2022-10-18 2023-01-17 中国十九冶集团有限公司 A kind of bored pile structure and construction method that can quickly peel off the pile head
CN116378032A (en) * 2023-05-12 2023-07-04 中建八局第四建设有限公司 A pile head cutting process

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03107017A (en) * 1989-09-21 1991-05-07 Nitto Kensetsu Kk Pile head treatment method for cast-in-place concrete pile
JP4388413B2 (en) * 2004-05-14 2009-12-24 株式会社竹中工務店 Pile head treatment method for cast-in-place concrete piles
CN102493434A (en) * 2011-11-28 2012-06-13 中铁大桥局股份有限公司 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile
CN102425159B (en) * 2011-08-31 2013-12-18 浙江大学城市学院 Pile cutting construction method of bored concrete pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03107017A (en) * 1989-09-21 1991-05-07 Nitto Kensetsu Kk Pile head treatment method for cast-in-place concrete pile
JP4388413B2 (en) * 2004-05-14 2009-12-24 株式会社竹中工務店 Pile head treatment method for cast-in-place concrete piles
CN102425159B (en) * 2011-08-31 2013-12-18 浙江大学城市学院 Pile cutting construction method of bored concrete pile
CN102493434A (en) * 2011-11-28 2012-06-13 中铁大桥局股份有限公司 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107604920A (en) * 2017-09-14 2018-01-19 云南建投第五建设有限公司 A kind of quick construction method for abolishing filling pile head
CN108203979A (en) * 2018-02-27 2018-06-26 中建路桥集团有限公司 A kind of pile crown breaking system and restructuring bankrupt using the method for abolishing that disappears
CN108547304A (en) * 2018-05-17 2018-09-18 山东电力建设第三工程有限公司 The invalid pile crown of deposited reinforced concrete pile integrally abolishes construction technology
CN109083148A (en) * 2018-08-24 2018-12-25 中铁十四局集团第三工程有限公司 A kind of drilling pile pile crown constructing device and its construction method
CN109083148B (en) * 2018-08-24 2021-06-22 中铁十四局集团第三工程有限公司 Pile head construction device for drilling and filling pile and construction method thereof
CN109969934A (en) * 2019-04-11 2019-07-05 中国十七冶集团有限公司 It is a kind of quickly to abolish cast-in-situ bored pile pile crown hanging hook and its construction method
CN110453685A (en) * 2019-09-16 2019-11-15 腾达建设集团股份有限公司 A chisel-free pile head device and its application method
CN113373926B (en) * 2021-06-06 2024-05-07 中交路桥建设有限公司 Separating device for pile head breaking and construction method
CN113373926A (en) * 2021-06-06 2021-09-10 中交路桥建设有限公司 Separation device for pile head breaking and construction method
CN113622427A (en) * 2021-07-06 2021-11-09 中国二十冶集团有限公司 Auxiliary device for chiseling pile head and construction method for chiseling pile head
CN114086555A (en) * 2021-11-25 2022-02-25 中铁三局集团有限公司 Combined device for breaking pile head of bored pile foundation and pile head breaking construction method
CN114718070A (en) * 2022-05-06 2022-07-08 中铁广州工程局集团第三工程有限公司 Construction method for breaking soil between piles and pile heads of super-irrigation cast-in-place pile
CN114960648A (en) * 2022-06-14 2022-08-30 重庆建工集团股份有限公司 Concrete pile head line cutting device
CN114960648B (en) * 2022-06-14 2023-11-14 重庆建工集团股份有限公司 Concrete pile head line cutting device
CN114922182A (en) * 2022-06-27 2022-08-19 中国十七冶集团有限公司 Method for quickly separating embedded part from pile head of cast-in-place pile
CN115613572A (en) * 2022-10-18 2023-01-17 中国十九冶集团有限公司 A kind of bored pile structure and construction method that can quickly peel off the pile head
CN115613573A (en) * 2022-11-11 2023-01-17 中国建筑第八工程局有限公司 A high-efficiency cutting system for pile heads of cast-in-place piles
CN116378032A (en) * 2023-05-12 2023-07-04 中建八局第四建设有限公司 A pile head cutting process

Similar Documents

Publication Publication Date Title
CN106759336A (en) A kind of cast-in-situ bored pile quickly abolishes pile crown construction method
CN105297729B (en) Bridge pile foundation pile head breaking device and method
CN104294819B (en) A kind of construction method of castinplace pile
CN110528511A (en) A kind of the impact drilling pile construction method
CN107604920A (en) A kind of quick construction method for abolishing filling pile head
CN106400802A (en) Integral quick lifting method for pile head of drilled pile during pre-embedding and drilling-free ring-cutting
CN102493434A (en) Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile
WO1996018001A1 (en) Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method
CN108951431B (en) Construction technology of precast concrete cofferdam and pier for bridge
CN106958245A (en) The quick structure and method for abolishing concrete pile head
CN110106889A (en) A kind of deep basal pit perfusion slope protection pile adds cable bolting construction
CN110820742A (en) Construction method for breaking underwater cast-in-place pile head
CN108286268A (en) Deep foundation pit monitoring inclinometer pipe protection device and method
CN101718098B (en) A kind of micro-pile combined excavation and excavation composite foundation and its construction method
CN105862862B (en) A kind of large diameter pile buries hammer Refloatation method
CN205224036U (en) Device is abolished to bridge pile foundation pile head
CN207739259U (en) A kind of filling pile head cuts device
CN206859222U (en) The quick structure for abolishing concrete pile head
CN106968252B (en) Pile pulling recharging method and pile pulling recharging system
CN106978809A (en) A kind of construction method of casing off concrete protective reserved steel bar
CN109944246A (en) A kind of construction method of broken pile head
CN114232628A (en) Cutting hoop for integrally breaking pile head of cast-in-situ bored pile and construction method
CN218813700U (en) Drilled pile structure capable of quickly stripping pile head
CN206902712U (en) Pile pulling recharge system
CN112195915B (en) Method for conveniently breaking pile head of large-diameter secant pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170531