CN102383613A - 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置 - Google Patents

发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置 Download PDF

Info

Publication number
CN102383613A
CN102383613A CN2011103565132A CN201110356513A CN102383613A CN 102383613 A CN102383613 A CN 102383613A CN 2011103565132 A CN2011103565132 A CN 2011103565132A CN 201110356513 A CN201110356513 A CN 201110356513A CN 102383613 A CN102383613 A CN 102383613A
Authority
CN
China
Prior art keywords
roof truss
steel roof
lifting
main building
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103565132A
Other languages
English (en)
Other versions
CN102383613B (zh
Inventor
唐跃俊
周高峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN ELECTRIC POWER ENGINEERING SUPERVISION Co Ltd
State Grid Corp of China SGCC
Original Assignee
TIANJIN ELECTRIC POWER ENGINEERING SUPERVISION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN ELECTRIC POWER ENGINEERING SUPERVISION Co Ltd filed Critical TIANJIN ELECTRIC POWER ENGINEERING SUPERVISION Co Ltd
Priority to CN201110356513.2A priority Critical patent/CN102383613B/zh
Publication of CN102383613A publication Critical patent/CN102383613A/zh
Application granted granted Critical
Publication of CN102383613B publication Critical patent/CN102383613B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置,利用锅炉大型吊装设备将专用吊装起重装置以及钢屋架吊装到主厂房桥吊上,将钢屋架挂在已经安装完成的专用吊装起重装置的倒链上,移动主厂房桥吊至钢屋架需要的就位点处,利用倒链对钢屋架进行微调就位安装。本发明是一种操作简单、设计科学的发电厂主厂房钢屋架吊装施工方法及其专用吊装起重装置,本吊装方法借助主厂房桥吊的稳定性及来回的灵活性进行主厂房钢屋架的吊装工作,为吊装工作带来了极大的方便、减少了火电施工现场施工机械设备的再次投入以及来回周转、确保了钢屋架就位过程的安全性、提高了施工速度、节约了施工成本。

Description

发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置
技术领域
本发明涉及火电工程施工中的钢屋架吊装领域,尤其是一种发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置。
背景技术
在以往的火电项目施工中,由于主厂房钢屋架的安装高度一般在20多米,吊装钢屋架时需要全部采用大型的起重设备进行,而大型起重设备比较笨重,因此现有的这种吊装方法不但增加了大型设备转移的难度,而且操作麻烦、安全性差,给吊装工作带来极大的不便,延长了吊装的时间。
发明内容
本发明的目的是克服现有技术的不足,提供一种能够保障吊装安全、降低吊装难度、加快吊装速度并减少施工成本的发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置。
本发明的目的是通过以下技术手段实现的:
一种发电厂主厂房钢屋架吊装施工方法,其特征在于:包括以下步骤:
(1)将主厂房桥吊开到离锅炉大型吊装设备最近的位置;
(2)组装专用吊装起重装置,利用锅炉大型吊装设备将专用吊装起重装置吊装到主厂房桥吊上,将专用吊装起重装置安装在主厂房桥吊上;
(3)借助锅炉大型吊装设备将地面上的钢屋架吊装到桥吊梁上,将钢屋架挂在已经安装完成的专用吊装起重装置的倒链上,使钢屋架固定在吊装设备上;
(4)移动主厂房桥吊至钢屋架需要的就位点处,利用倒链对钢屋架进行微调,使钢屋架就位安装完毕。
而且,所述的专用吊装起重装置在地面上进行组装,或者在主厂房桥吊上进行组装。
而且,所述的主厂房桥吊上安装一个或者多个专用吊装起重装置。
而且,所述倒链的一端固定在钢屋架上,另一端固定在专用吊装起重装置的吊钩上。
一种发电厂主厂房钢屋架吊装施工的专用吊装起重装置,其特征在于:包括横梁、竖梁以及支撑梁,竖梁竖直安装在横梁上,支撑梁倾斜设置且支撑梁的两端分别安装在横梁和竖梁上形成三角架结构。
而且,所述的竖梁上端水平安装一连接梁,该连接梁上安装一用于连接倒链的吊钩。
而且,所述的横梁、竖梁、支撑梁、连接梁均为型钢,横梁、竖梁、支撑梁以及连接梁采用焊接或者螺栓连接方式安装在一起。
本发明的优点和积极效果是:
1、本吊装施工方法采用专用吊装起重装置,借助锅炉的大型吊装设备对钢屋架进行吊装,从而解决了二次使用大型吊装设备进出场的问题、减少了施工机械设备的再次投入以及频繁转移、降低了施工的难度、加快了钢屋架的吊装速度。
2、本吊装施工方法中所使用的专用吊装起重装置可以在现场进行组装,也可以在主厂房桥吊上进行组装。该专用吊装起重装置的架体采用型钢加工而成,不但组装方便、使用简单,而且可以根据每个工程的特点采用不同的型钢结构,增强施工的针对性,改善施工效果。
3、本专用吊装起重装置为三角架体系,在三角架的顶部还安装了一个满足吊装使用的可以人工调整钢屋架高度的起重设施,此结构满足强度需要,确保了吊装过程的稳定性和安全性。
4、主厂房钢屋架的吊装过程全部在施工人员的视线内进行,安全性能比使用以往的大型吊装设备更有保障,而且还为工程节约了大量的人力、物力和资金。
5、本吊装施工方法操作方便、灵活性好,吊装工作可以穿插在其它大型设备吊装期间进行。
6、本发明是一种操作简单、设计科学的发电厂主厂房钢屋架吊装施工方法及其专用吊装起重装置,本吊装方法借助主厂房桥吊的稳定性及来回的灵活性进行主厂房钢屋架的吊装工作,为吊装工作带来了极大的方便、减少了火电施工现场主厂房施工机械设备的再次投入以及来回周转、确保了钢屋架就位过程的安全性、提高了施工速度、节约了施工成本。
附图说明
图1是专用吊装起重装置的主视图;
图2是本发明的吊装示意图;
图3是图2的俯视图。
具体实施方式
下面结合附图详细叙述本发明的实施例;需要说明的是,本实施例是叙述性的,不是限定性的,不能以此限定本发明的保护范围。
本发电厂主厂房钢屋架吊装施工专用吊装起重装置,包括横梁5、竖梁4以及支撑梁3,竖梁竖直安装在横梁上,横梁安装在桥吊6上,支撑梁倾斜设置,且支撑梁的两端分别安装在横梁和竖梁上,横梁、竖梁以及支撑梁形成一个三角架结构。
竖梁上端水平安装一个连接梁1,该连接梁上安装一个吊钩2,该吊钩用于挂装倒链。本实施例中的横梁、竖梁、支撑梁以及连接梁均为型钢,其采用焊接方式或者螺栓连接方式安装在一起。
本发电厂主厂房钢屋架吊装施工方法,包括以下步骤:
(1)将主厂房桥吊开到离锅炉大型吊装设备最近的位置。
(2)组装专用吊装起重装置,其可以在地面上进行组装,也可以在主厂房桥吊上进行组装。利用锅炉大型吊装设备将专用吊装起重装置吊装到主厂房桥吊上,使用卡具将专用吊装起重装置安装在主厂房桥吊上。安装在主厂房桥吊上的专用吊装起重装置可以是一个,也可以是间隔设置的多个。
(3)借助锅炉大型吊装设备将地面上的钢屋架吊装到桥吊梁上,将钢屋架挂在已经安装完成的专用吊装起重装置的倒链上,使钢屋架固定在吊装设备上,该倒链的一端固定在钢屋架上,另一端固定在专用吊装起重装置的吊钩上。
(4)移动主厂房桥吊至钢屋架需要的就位点处,使用倒链对钢屋架的高度进行微调,使钢屋架就位安装完毕。

Claims (7)

1.一种发电厂主厂房钢屋架吊装施工方法,其特征在于:包括以下步骤:
(1)将主厂房桥吊开到离锅炉大型吊装设备最近的位置;
(2)组装专用吊装起重装置,利用锅炉大型吊装设备将专用吊装起重装置吊装到主厂房桥吊上,将专用吊装起重装置安装在主厂房桥吊上;
(3)借助锅炉大型吊装设备将地面上的钢屋架吊装到桥吊梁上,将钢屋架挂在已经安装完成的专用吊装起重装置的倒链上,使钢屋架固定在吊装设备上;
(4)移动主厂房桥吊至钢屋架需要的就位点处,利用倒链对钢屋架进行微调,使钢屋架就位安装完毕。
2.根据权利要求1所述的发电厂主厂房钢屋架吊装施工方法,其特征在于:所述的专用吊装起重装置在地面上进行组装,或者在主厂房桥吊上进行组装。
3.根据权利要求1所述的发电厂主厂房钢屋架吊装施工方法,其特征在于:所述的主厂房桥吊上安装一个或者多个专用吊装起重装置。
4.根据权利要求1所述的发电厂主厂房钢屋架吊装施工方法,其特征在于:所述倒链的一端固定在钢屋架上,另一端固定在专用吊装起重装置的吊钩上。
5.一种发电厂主厂房钢屋架吊装施工的专用吊装起重装置,其特征在于:包括横梁、竖梁以及支撑梁,竖梁竖直安装在横梁上,支撑梁倾斜设置且支撑梁的两端分别安装在横梁和竖梁上形成三角架结构。
6.根据权利要求5所述的发电厂主厂房钢屋架吊装施工的专用吊装起重装置,其特征在于:所述的竖梁上端水平安装一连接梁,该连接梁上安装一用于连接倒链的吊钩。
7.根据权利要求5所述的发电厂主厂房钢屋架吊装施工的专用吊装起重装置,其特征在于:所述的横梁、竖梁、支撑梁、连接梁均为型钢,横梁、竖梁、支撑梁以及连接梁采用焊接或者螺栓连接方式安装在一起。
CN201110356513.2A 2011-11-11 2011-11-11 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置 Expired - Fee Related CN102383613B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110356513.2A CN102383613B (zh) 2011-11-11 2011-11-11 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110356513.2A CN102383613B (zh) 2011-11-11 2011-11-11 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置

Publications (2)

Publication Number Publication Date
CN102383613A true CN102383613A (zh) 2012-03-21
CN102383613B CN102383613B (zh) 2014-09-17

Family

ID=45823413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110356513.2A Expired - Fee Related CN102383613B (zh) 2011-11-11 2011-11-11 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置

Country Status (1)

Country Link
CN (1) CN102383613B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103470057A (zh) * 2013-08-22 2013-12-25 安徽鸿路钢结构(集团)股份有限公司 一种高空构件起吊施工方法
CN103669882A (zh) * 2013-10-31 2014-03-26 中冶天工集团有限公司 工业厂房内利用钢丝绳做轨道进行构件安装的方法
CN107448924A (zh) * 2017-08-22 2017-12-08 山东电力工程咨询院有限公司 一种锅炉分层吊装的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0445187A1 (fr) * 1988-11-25 1991-09-11 DUEZ, Alain Procede et dispositif pour la construction et/ou l'execution de travaux sur des parois de batiments
JP2007032005A (ja) * 2005-07-25 2007-02-08 Tekken Constr Co Ltd スライド支承の摩擦係数低減機構
CN201411926Y (zh) * 2009-06-10 2010-02-24 中冶实久建设有限公司 弧形梁起重结构
CN101858149A (zh) * 2009-04-08 2010-10-13 上海市机械施工有限公司 一种大型钢结构整体平移和提升组合施工工艺
CN202467221U (zh) * 2011-11-11 2012-10-03 天津电力工程监理有限公司 发电厂主厂房钢屋架吊装起重装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0445187A1 (fr) * 1988-11-25 1991-09-11 DUEZ, Alain Procede et dispositif pour la construction et/ou l'execution de travaux sur des parois de batiments
JP2007032005A (ja) * 2005-07-25 2007-02-08 Tekken Constr Co Ltd スライド支承の摩擦係数低減機構
CN101858149A (zh) * 2009-04-08 2010-10-13 上海市机械施工有限公司 一种大型钢结构整体平移和提升组合施工工艺
CN201411926Y (zh) * 2009-06-10 2010-02-24 中冶实久建设有限公司 弧形梁起重结构
CN202467221U (zh) * 2011-11-11 2012-10-03 天津电力工程监理有限公司 发电厂主厂房钢屋架吊装起重装置

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103470057A (zh) * 2013-08-22 2013-12-25 安徽鸿路钢结构(集团)股份有限公司 一种高空构件起吊施工方法
CN103470057B (zh) * 2013-08-22 2016-03-23 安徽鸿路钢结构(集团)股份有限公司 一种高空构件起吊施工方法
CN103669882A (zh) * 2013-10-31 2014-03-26 中冶天工集团有限公司 工业厂房内利用钢丝绳做轨道进行构件安装的方法
CN103669882B (zh) * 2013-10-31 2016-02-03 中冶天工集团有限公司 工业厂房内利用钢丝绳做轨道进行构件安装的方法
CN107448924A (zh) * 2017-08-22 2017-12-08 山东电力工程咨询院有限公司 一种锅炉分层吊装的施工方法

Also Published As

Publication number Publication date
CN102383613B (zh) 2014-09-17

Similar Documents

Publication Publication Date Title
CN205387439U (zh) 一种桅杆起吊装置
CN201943007U (zh) 活动支架不变幅架梁吊机
CN205772984U (zh) 一种单片钢桁架的吊装装置
CN204899238U (zh) 一种单元式幕墙板块吊装装置
CN104032967B (zh) 预制装配式框架结构构件吊装施工方法
CN102328881A (zh) 超大型钢筋笼整体一次性吊装装置及其方法
CN103266779A (zh) 一种越过水平障碍物的提升滑移施工设备及其方法
CN104192735A (zh) 一种小型起重机
CN205077878U (zh) 一种单元式幕墙板块吊装装置
CN102493666A (zh) 一种超大超重构件高空平移安装施工方法
CN204434116U (zh) 一种用于内天井管道吊装的吊装设备
CN102383613B (zh) 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置
CN104291222A (zh) 一种超高层建筑核心筒内部硬质防护与行吊集成系统
CN201506692U (zh) 屋面钢结构简易提升装置及其安装结构
CN202324662U (zh) 太空板安装装置
CN202467221U (zh) 发电厂主厂房钢屋架吊装起重装置
CN204265208U (zh) 一种管片吊具
CN103434933A (zh) 一种大型构件吊装就位装置及就位方法
CN203794505U (zh) 一种内爬动臂塔式起重机的内爬钢梁倒运装置
CN202744961U (zh) 防落梁挡块的吊装机构
CN201825635U (zh) 电站锅炉吊装结构
CN201722937U (zh) 网架安装滑移平台
CN205132926U (zh) 水轮发电机组尾水肘管的专用井字吊具
CN106276599A (zh) 具备高亮照明功能的塔吊
CN204530506U (zh) 边跨合拢装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121204

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121204

Address after: 300143 No. 153 Xiang Xiang Road, Hebei District, Tianjin

Applicant after: Tianjin Electric Power Engineering Supervision Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 300143 No. 153 Xiang Xiang Road, Hebei District, Tianjin

Applicant before: Tianjin Electric Power Engineering Supervision Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140917

Termination date: 20201111