CN102352626A - Fill side slope supporting composite anchor rod and construction method thereof - Google Patents
Fill side slope supporting composite anchor rod and construction method thereof Download PDFInfo
- Publication number
- CN102352626A CN102352626A CN2011103379196A CN201110337919A CN102352626A CN 102352626 A CN102352626 A CN 102352626A CN 2011103379196 A CN2011103379196 A CN 2011103379196A CN 201110337919 A CN201110337919 A CN 201110337919A CN 102352626 A CN102352626 A CN 102352626A
- Authority
- CN
- China
- Prior art keywords
- banketing
- fill
- construction
- anchor pole
- slope retaining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention relates to a fill side slope supporting composite anchor rod and a construction method thereof, belonging to the field of the fill side slope support. The fill side slope supporting composite anchor rod comprises a fill power transmission belt (1) and a fill anchor rod; the fill power transmission belt (1) directly contacts fill; the fill anchor rod comprises a rod body (2) and an anchoring body (3); the rod body (2) is arranged in the anchoring body (3); and the fill power transmission belt (1) is connected with the anchoring body (3). In construction, the anchor rod can be constructed in undisturbed soil and connected with the rod body (2) arranged in the fill, after the damage factors of the fill construction to the anchor rod are eliminated, the anchoring body (3) is constructed. The problem of the use restriction of the fill side slope support against an anchor rod retaining wall is solved successfully, and the anchor rod buried in the fill can be effectively protected from being damaged during fill construction. The fill side slope supporting composite anchor rod is convenient to construct, has a short construction period, low manufacturing cost and high bearing capacity and can be widely applied to the field of the fill side slope supporting engineering.
Description
Technical field
The present invention relates to field of civil engineering, particularly relate to the slope support engineering field of banketing.
Background technology
Fast development along with engineering construction; Utilize embankment construction house, the projects such as highway, railway of building to get more and more; A large amount of embankment slope retainings is the important component part of embankment engineering; Because of the pore-forming difficulty of banketing, filler are formed complicated, inhomogeneous; The slope retaining that bankets is a great problem of geotechnical slope supporting always; Particularly when side slope is steep, embankment slope retaining mode commonly used at present is the gravity barricade, hold up the slope retaining form of banketing such as arm-type barricade, and cost is high, long in time limit.
The content of invention
First purpose of the present invention is to provide a kind of slope retaining Composite Bolt of banketing; This slope retaining Composite Bolt of banketing can be given full play to the potentiality of geotechnical body; Huge anchored force is provided; And huge anchored force can be passed to by the object of anchoring reliably; Enlarged the range of application of anchor pole; Can reduce the cost and the duration of embankment slope retaining significantly, safe and reliable, cost is low.
This slope retaining Composite Bolt of banketing comprises the load transfering strip that bankets, the anchor pole two parts that banket are formed; The load transfering strip that bankets wherein directly contacts with banketing; The anchor pole that bankets comprises the body of rod and anchoring body two parts composition, and the body of rod is positioned at anchoring body, and the load transfering strip that bankets is connected with anchoring body.
In the above-mentioned slope retaining Composite Bolt of banketing, the above-mentioned load transfering strip that bankets is a kind of and force structure that bankets and directly contact that when fill construction, is arranged in banketing.
In the above-mentioned slope retaining Composite Bolt of banketing, the above-mentioned load transfering strip that bankets is arranged at a kind of in mortar, concrete or the cement paste in banketing when being fill construction.
In the above-mentioned slope retaining Composite Bolt of banketing, the above-mentioned load transfering strip that bankets is a kind of tubular structure that when fill construction, is arranged in banketing.
In the above-mentioned slope retaining Composite Bolt of banketing, the above-mentioned load transfering strip that bankets is a kind of combination that when fill construction, is arranged in tubular structure and mortar in banketing, concrete, the cement paste.
In the above-mentioned slope retaining Composite Bolt of banketing, the above-mentioned load transfering strip that bankets comprises the one or more block structures that are arranged in banketing.
In the above-mentioned slope retaining Composite Bolt of banketing; The above-mentioned anchor pole that bankets comprises the undisturbed soil anchoring section and bankets and pass through anchor pole section two parts composition; Undisturbed soil anchoring section wherein for the construction with the undisturbed soil that links to each other that bankets in anchor pole, banket and be placed in the anchor pole in banketing when passing through the anchor pole section for fill construction.
Second purpose of the present invention is to provide a kind of slope retaining Composite Bolt job practices of banketing; This slope retaining Composite Bolt job practices of banketing can realize the construction of the above-mentioned slope retaining Composite Bolt of banketing smoothly; And very big anti-pulling capacity can be provided, easy construction, reliable in quality.
This slope retaining Composite Bolt job practices of banketing may further comprise the steps:
A) confirm the anchor pole position;
B) construction undisturbed soil anchoring section;
C) bottom-up backfill successively to the banketing of slope retaining Composite Bolt of banketing passed through anchor pole section top; And setting the banket interior side slope consistent with the slope retaining Composite Bolt direction of banketing; Slot grooving the banketing of slope retaining Composite Bolt of banketing passed through the banket load transfering strip and the body of rod of anchor pole section on the side slope in banketing, and the body of rod that passes through the anchor pole section that will banket is connected with the undisturbed soil anchoring section;
D) one deck soil under the backfill, repeating step c);
E) treat that fill construction thickness is enough, after fill construction was eliminated the destructive factor of the slope retaining Composite Bolt of banketing, construction was banketed and is passed through the anchoring body of anchor pole section, locks the slope retaining Composite Bolt of banketing, and construction is accomplished.
Banket slope retaining Composite Bolt and job practices easy construction thereof of the present invention; Cost is low; The anchor pole bearing capacity is big; Successfully solved the restriction that the slope retaining that bankets uses anchored bolt retaining wall; Can in the fill construction process, effectively protect the anchor pole that is embedded in banketing not to be destroyed; Construction period is short, extensively the model engineering fields such as slope retaining that are applied to banket.
Description of drawings
Fig. 1 is the used slope retaining Composite Bolt structure construction sketch map that bankets of one embodiment of the present of invention.
Fig. 2 is the used slope retaining Composite Bolt construction first step sketch map that bankets of one embodiment of the present of invention.
Fig. 3 is used second step of the slope retaining Composite Bolt construction sketch map that bankets of one embodiment of the present of invention.
Fig. 4 for the used slope retaining Composite Bolt of banketing of one embodiment of the present of invention construct the 3rd the step sketch map.
Fig. 5 for the used slope retaining Composite Bolt of banketing of one embodiment of the present of invention construct the 4th the step sketch map.
Fig. 6 for the used slope retaining Composite Bolt of banketing of one embodiment of the present of invention construct the 5th the step sketch map.
The specific embodiment
As one embodiment of the present of invention, introduce slope retaining Composite Bolt structure construction, operating principle and the job practices of banketing of the present invention in conjunction with Fig. 1 to Fig. 6.At first combine Fig. 1, Fig. 6 to introduce the slope retaining Composite Bolt structure construction that bankets of the present invention.As shown in Figure 1; The slope retaining Composite Bolt of banketing comprises the load transfering strip that bankets (1); The anchor pole two parts that banket are formed; The load transfering strip that bankets (1) wherein directly contacts with banketing; The anchor pole that bankets is connected with the load transfering strip that bankets (1); The anchor pole that bankets comprises the body of rod (2) and anchoring body (3) two parts composition; The body of rod (2) is positioned at anchoring body (3); The load transfering strip that bankets (1) in Fig. 1 can be a concrete; It also can be mortar; It can also be cement paste; The shape of load transfering strip (1) of banketing can be a tubulose; Bar shaped; Or a blocks, the load transfering strip that bankets (1) can also be the combination of a plurality of blocks.The body of rod (2) can be a reinforcing bar, also can be steel strand, can also be tension members such as steel pipe.Anchoring body (3) can be materials such as cement mortar, cement paste, epoxy resin; Be positioned at anchoring body (3) in order to ensure the body of rod (2); Can between the anchoring body (3) and the body of rod (2), locator (4) be set; The available reinforcement fabrication of locator (4), locator (4) can guarantee that the body of rod (2) has enough protective layer thickness.In the embankment slope retaining; Bigger at the width that bankets; Under the situation that the body itself that bankets is not enough to keep stable; The part of the anchor pole that bankets can be arranged in the undisturbed soil that links to each other with the zone of banketing; As shown in Figure 6; The anchor pole that bankets in undisturbed soil partly is undisturbed soil anchoring section (6), and the structure construction of undisturbed soil anchoring section (6) also comprises the body of rod (2) and anchoring body (3) two parts composition, can implement with reference to existing anchor pole technology.Present embodiment mainly combines Fig. 2 to Fig. 6 with the lower part, introduces the job practices of the slope retaining Composite Bolt of banketing.As shown in Figure 2; The first step in job practices; After the on-the-spot undisturbed soil removing surface; The gradient of the line of slope (9) of mensuration undisturbed soil as shown in Figure 2; Status requirement in conjunction with the slope retaining Composite Bolt of banketing in line of slope (9) and the design drawing; The first step is accomplished in the anchor pole of confirming undisturbed soil anchoring section (6) mouthful position (5) of burying, and gets into for the 2nd step.In this step; It mainly is the construction of before banketing, accomplishing relevant position undisturbed soil anchoring section (6); Can adopt existing anchor rod construction method to accomplish; In this step; As shown in Figure 3; Can be as required; Before fill construction, accomplish the construction of whole undisturbed soil anchoring sections (6); Also can combine with the layered backfill construction sequence; The bottom-up undisturbed soil anchoring section (6) of before the covering of banketing, successively constructing, the body of rod (2) of undisturbed soil anchoring section (6) can adopt the reinforcement fabrication of 1 diameter 32, and anchoring body (3) is optional to be made with cement paste or cement mortar; Thereby accomplished for second step, got into for the 3rd step.In this step; As shown in Figure 4; Bottom-up backfill soil is successively passed through the top of anchor pole section (7) to the banketing of slope retaining Composite Bolt of banketing; And setting the banket interior side slope (8) consistent with the slope retaining Composite Bolt direction of banketing; Can on the interior side slope (8) of banketing, open the groove of 300mm * 300mm; The thick mortar of first backfill 50mm in groove; Then the steel pipe (10) of diameter 73mm, thickness 4mm is positioned over the top of mortar; And the body of rod (2) that the reinforcing bar conduct of a diameter 32mm of placement is banketed and passed through anchor pole section (7) in steel pipe (10); And locator (4) is set on the body of rod (2); To guarantee that the body of rod (2) is positioned at the center of steel pipe (10); The reinforcing bar of the undisturbed soil anchoring section (6) of having constructed is connected as one as the body of rod (2) with the reinforcing bar that passes through anchor pole section (7) that bankets; The mortar of the thick 150mm of backfill covers steel pipe (10) in groove afterwards, then fluting is filled and led up.Embedding steel pipe (10) has been formed the load transfering strip that bankets (1) of the slope retaining Composite Bolt of banketing of the present invention with the mortar that is covered in steel pipe (10) in this step; For improve the load transfering strip that bankets (1) and banket between bonding strength, can one or more block mortars or concrete structure be set along steel pipe (10) diverse location.The load transfering strip (1) that bankets can increase the stability of the body that bankets in the fill construction process.In this step; Between invar pipe (10) and the body of rod (2) be not set firm the connection; Therefore; In the fill construction process; Even bigger banket sedimentation and horizontal movement occur; Be positioned at the inner body of rod (2) of steel pipe (10) and under the protection of steel pipe (10), can be damaged, steel pipe (10) can also protect the body of rod (2) not to be compacted work progress factor affecting such as machinery in the fill compaction process, has guaranteed that simultaneously undisturbed soil anchoring section (6) is not destroyed in the fill construction process.Thereby accomplished for the 3rd step, got into for the 4th step.Mainly be according to one deck soil under the fill construction requirement backfill in this step, repeated for the 3rd step, as shown in Figure 5.Thereby got into for the 5th step.In this step; As shown in Figure 6; Treat that fill construction thickness is enough; After fill construction is eliminated the destructive factor of the slope retaining Composite Bolt of banketing; In steel pipe (10), inject cement paste or cement mortar; Treat the anchoring body (3) that just having formed after cement paste or cement mortar are solidified bankets passes through anchor pole section (7), the body of rod (2) of the slope retaining Composite Bolt of banketing accomplished of will constructing then with by anchoring body (11) locking, form the side slope anchored bolt retaining wall supporting of banketing.By anchoring body (11) can be to spray the steel concrete barricade, also can be soil-baffling structures such as antislide pile, lattice girder.Thereby accomplish the slope retaining Composite Bolt construction of banketing of the present invention.
This patent includes but not limited to other job practicess of the alternative use of professional person in this area.
Claims (8)
1. slope retaining Composite Bolt of banketing; It is characterized in that this slope retaining Composite Bolt of banketing comprises the load transfering strip that bankets (1), the anchor pole two parts that banket are formed; The load transfering strip that bankets (1) wherein directly contacts with banketing; The anchor pole that bankets comprises the body of rod (2) and anchoring body (3) two parts composition; The body of rod (2) is positioned at anchoring body (3), and the load transfering strip that bankets (1) is connected with anchoring body (3).
2. the slope retaining Composite Bolt of banketing according to claim 1, the load transfering strip (1) that it is characterized in that banketing are a kind of and force structures that bankets and directly contact that when fill construction, is arranged in banketing.
3. the slope retaining Composite Bolt of banketing according to claim 1, the load transfering strip (1) that it is characterized in that banketing are arranged at a kind of in mortar, concrete or the cement paste in banketing when being fill construction.
4. the slope retaining Composite Bolt of banketing according to claim 1, the load transfering strip (1) that it is characterized in that banketing is a kind of tubular structure that when fill construction, is arranged in banketing.
5. the slope retaining Composite Bolt of banketing according to claim 1, the load transfering strip (1) that it is characterized in that banketing are a kind of combinations that when fill construction, is arranged in tubular structure and mortar in banketing, concrete, the cement paste.
6. the slope retaining Composite Bolt of banketing according to claim 1, the load transfering strip (1) that it is characterized in that banketing comprises the one or more block structures that are arranged in banketing.
7. the slope retaining Composite Bolt of banketing according to claim 1; The anchor pole that it is characterized in that banketing comprises undisturbed soil anchoring section (6) and bankets and pass through anchor pole section (7) two parts composition; Undisturbed soil anchoring section (6) wherein for the construction with the undisturbed soil that links to each other that bankets in anchor pole, banket and be placed in the anchor pole in banketing when passing through anchor pole section (7) for fill construction.
8. slope retaining Composite Bolt job practices of banketing may further comprise the steps:
A) confirm the anchor pole position;
B) construction undisturbed soil anchoring section (6);
C) bottom-up backfill successively to the banketing of slope retaining Composite Bolt of banketing passed through anchor pole section (7) top; And setting the banket interior side slope (8) consistent with the slope retaining Composite Bolt direction of banketing; Go up slot grooving the banketing of slope retaining Composite Bolt of banketing in the interior side slope (8) of banketing and pass through the load transfering strip that bankets (1) and the body of rod (2) of anchor pole section (7), and the body of rod (2) that passes through anchor pole section (7) that will banket is connected with undisturbed soil anchoring section (6);
D) one deck soil under the backfill, repeating step c);
E) treat that fill construction thickness is enough, after fill construction was eliminated the destructive factor of the slope retaining Composite Bolt of banketing, the anchoring body (3) that construction is banketed and passed through anchor pole section (7) locked the slope retaining Composite Bolt of banketing, and construction is accomplished.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103379196A CN102352626A (en) | 2011-10-31 | 2011-10-31 | Fill side slope supporting composite anchor rod and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103379196A CN102352626A (en) | 2011-10-31 | 2011-10-31 | Fill side slope supporting composite anchor rod and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102352626A true CN102352626A (en) | 2012-02-15 |
Family
ID=45576257
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011103379196A Pending CN102352626A (en) | 2011-10-31 | 2011-10-31 | Fill side slope supporting composite anchor rod and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102352626A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102605780A (en) * | 2012-04-17 | 2012-07-25 | 周治国 | Recyclable anchor rod for foundation pit support and construction method thereof |
CN103541369A (en) * | 2013-10-31 | 2014-01-29 | 张胜文 | Anchor axis flat inclined type anchorage cable (rod) retaining wall structure and construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04319117A (en) * | 1991-04-19 | 1992-11-10 | Taisei Corp | Banking structure |
CN101298780A (en) * | 2008-06-23 | 2008-11-05 | 云南省公路规划勘察设计院 | High and light anchorage cable pile panel wall and construction method thereof |
CN201224890Y (en) * | 2008-06-20 | 2009-04-22 | 云南省公路规划勘察设计院 | High and light type anchorage cable pile panel wall in high filling branch block engineering |
KR20100123339A (en) * | 2009-05-15 | 2010-11-24 | 주식회사 건화 | Ground retaining wall having air penetration pipes applied for road construction and village development, and its construction method |
CN202280058U (en) * | 2011-10-31 | 2012-06-20 | 张继红 | Compound anchor rod for filling side-slope shore |
-
2011
- 2011-10-31 CN CN2011103379196A patent/CN102352626A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04319117A (en) * | 1991-04-19 | 1992-11-10 | Taisei Corp | Banking structure |
CN201224890Y (en) * | 2008-06-20 | 2009-04-22 | 云南省公路规划勘察设计院 | High and light type anchorage cable pile panel wall in high filling branch block engineering |
CN101298780A (en) * | 2008-06-23 | 2008-11-05 | 云南省公路规划勘察设计院 | High and light anchorage cable pile panel wall and construction method thereof |
KR20100123339A (en) * | 2009-05-15 | 2010-11-24 | 주식회사 건화 | Ground retaining wall having air penetration pipes applied for road construction and village development, and its construction method |
CN202280058U (en) * | 2011-10-31 | 2012-06-20 | 张继红 | Compound anchor rod for filling side-slope shore |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102605780A (en) * | 2012-04-17 | 2012-07-25 | 周治国 | Recyclable anchor rod for foundation pit support and construction method thereof |
CN102605780B (en) * | 2012-04-17 | 2015-01-28 | 周治国 | Recyclable anchor rod for foundation pit support and construction method thereof |
CN103541369A (en) * | 2013-10-31 | 2014-01-29 | 张胜文 | Anchor axis flat inclined type anchorage cable (rod) retaining wall structure and construction method |
CN103541369B (en) * | 2013-10-31 | 2015-12-30 | 张胜文 | The flat inclined of anchor pulling shaft line is anchored rope or is anchored pole spacing wall construction and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106638673B (en) | A kind of construction method of compound retaining structure | |
CN103469814A (en) | Novel barricade supporting structure for road or river bank dam and construction method thereof | |
CN106968260A (en) | The device and method come down for Strengthening Tunnel mountain body entrance | |
CN109505229A (en) | Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method | |
KR20140075767A (en) | Retaining wall construction using site compaction and excavation | |
CN110374111B (en) | Slope releasing and steel pipe pile anchor cooperative supporting system | |
CN104863162B (en) | Foundation pit support system applied to expansive soil regions and construction method thereof | |
CN104790429A (en) | Integral prestress reinforced earth retaining wall construction method | |
CN103352477A (en) | Vertical pres-stressed anchor rod gravity-type composite retaining wall and method for designing and constructing retaining wall | |
CN103603369A (en) | Construction method of anchor pile counterfort retaining wall | |
CN1067453C (en) | Supporting and protecting method for base pit, side slope, flat anchor and spray net | |
CN111962533A (en) | Energy dissipation type pile anchor structure in strong seismic region and construction method thereof | |
CN110629770B (en) | Reservoir side slope hydro-fluctuation belt seepage-proofing slope protection structure and construction method thereof | |
CN112030878A (en) | Rapid rush-to-pass construction method along river subgrade water damage | |
CN103603379A (en) | Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system | |
CN206599785U (en) | A kind of campshed anchor draws cement earth pile diaphragm wall supporting construction | |
CN111910630A (en) | Anchor cable structure and anchor cable frame beam construction method | |
CN206902734U (en) | A kind of earth construction of soft foundation zone | |
CN102352626A (en) | Fill side slope supporting composite anchor rod and construction method thereof | |
CN113417300A (en) | Slope support system and construction method thereof | |
CN202280058U (en) | Compound anchor rod for filling side-slope shore | |
CN209211459U (en) | Skirt piles are gone along with sb. to guard him in a kind of buried subway station PBA | |
CN206070564U (en) | A kind of NEW TYPE OF COMPOSITE retaining structure | |
CN114411761A (en) | Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method | |
CN113982002A (en) | Construction method of light side slope framework structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120215 |
|
WD01 | Invention patent application deemed withdrawn after publication |