CN112030878A - Construction method of rapid rush-through construction of subgrade water damaged along the river - Google Patents

Construction method of rapid rush-through construction of subgrade water damaged along the river Download PDF

Info

Publication number
CN112030878A
CN112030878A CN202010914652.1A CN202010914652A CN112030878A CN 112030878 A CN112030878 A CN 112030878A CN 202010914652 A CN202010914652 A CN 202010914652A CN 112030878 A CN112030878 A CN 112030878A
Authority
CN
China
Prior art keywords
slope
construction method
river
layer
embankment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010914652.1A
Other languages
Chinese (zh)
Inventor
邬凯
马洪生
唐国汉
张建永
周海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute
Original Assignee
Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute filed Critical Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute
Priority to CN202010914652.1A priority Critical patent/CN112030878A/en
Publication of CN112030878A publication Critical patent/CN112030878A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)

Abstract

The invention relates to the technical field of highway subgrade engineering, in particular to a rapid rush-to-pass construction method along river subgrade water damage, which comprises the following steps: s1, prefabricating a reinforcement gabion on site; s2, stacking the reinforcement gabions at the toe to form a toe retaining wall; s3, building stones between the toe retaining wall and the highway layer by layer and compacting the stones layer by layer to form a stone-filled embankment; and S4, mounting a slope protection protective net for protecting the rockfill embankment on the slope surface of the rockfill embankment. The construction method has the advantages of convenient and fast integral construction, economy, applicability and low safety risk, takes the water-damaged roadbed section with the length of 50 meters as an example, and has the construction period of 5-7 days, thereby greatly shortening the construction period compared with the prior art. The roadbed along the river constructed by the construction method can form a whole, the capability of resisting erosion and erosion caused by flushing of flood is improved, the disaster resistance of the roadbed along the river is further enhanced, even if the roadbed meets over-standard flood, serious roadbed damage such as broken roads and the like can not occur, and the long-term smoothness of the road along the river is ensured.

Description

沿河路基水毁快速抢通施工方法Construction method of rapid rush-through construction of subgrade water damaged along the river

技术领域technical field

本发明涉及公路路基工程技术领域,尤其是一种沿河路基水毁快速抢通的施工方法。The invention relates to the technical field of highway subgrade engineering, in particular to a construction method for fast rushing through the flooded subgrade along a river.

背景技术Background technique

我国山区公路大部分与河道并行,一面傍山,一面临河,许多沿河路基为半挖半填或全为填方筑成。由于部分道路修建年限较长,公路等级和设计标准低,在汛期超标准洪水冲刷、下渗、浸泡、渗流、软化等作用影响下,路基结构极易造成水毁失稳,进而使交通中断。特别是凹岸路基,更是水毁集中发育的路段,路基水毁多形成路基整体结构的渐进性破坏,造成路基冲失、路面板悬空、路基沉陷等灾害。路基失稳后横坡较陡,坡脚水流湍急,冲失及悬空高度超过10余米,这就造成路基水毁后的抢通难度极大。Most of the mountain roads in my country are parallel to the river, one side is near the mountain and the other is facing the river. Many roadbeds along the river are half excavated, half filled or fully filled. Due to the long construction years of some roads and low road grades and design standards, under the influence of excessive flooding, infiltration, soaking, seepage, softening and other effects during the flood season, the subgrade structure is very likely to cause water damage and instability, thereby causing traffic interruption. In particular, the concave bank subgrade is the road section with concentrated development of water damage. Subgrade water damage often causes progressive damage to the overall structure of the subgrade, resulting in subgrade erosion, suspension of pavement, subsidence and other disasters. After the subgrade is destabilized, the transverse slope is steep, the water flow at the foot of the slope is turbulent, and the washout and overhang height exceeds 10 meters, which makes it extremely difficult to rush through after the subgrade is destroyed by water.

目前,沿河路基水毁后的抢通方法主要有两种。第一种方法是施工挡土墙结构来保护路堤;挡土墙主要依靠自身重量来满足其抗滑移和抗倾覆安全,沿河挡土墙基础必须保障足够的埋深来防止冲刷引起的失稳。一般挡土墙基础埋深需1~3米,但由于汛期水毁路基坡脚水流湍急,临河挡土墙基础施工需形成临时围堰,且易出现涌水透水事故,安全风险和施工难度极大。高大挡土墙的混凝土浇筑还需要关模施工,由于横坡高陡,模板搭设较困难,施工周期也较长;以50米长的水毁路基段为例,采用挡土墙进行处治的施工周期至少需要20天。At present, there are two main ways to get through after the subgrade along the river is destroyed by water. The first method is to construct a retaining wall structure to protect the embankment; the retaining wall mainly relies on its own weight to meet its anti-slip and anti-overturning safety, and the retaining wall foundation along the river must ensure sufficient depth to prevent loss caused by erosion stable. Generally, the depth of the retaining wall foundation needs to be 1 to 3 meters. However, due to the rapid water flow at the foot of the subgrade and the slope in the flood season, the construction of the retaining wall foundation near the river needs to form a temporary cofferdam, and it is prone to water inrush and water leakage accidents, and the safety risks and construction difficulties are extremely high. . The concrete pouring of the tall retaining wall also needs to close the formwork. Due to the high and steep cross slope, the formwork is difficult to set up, and the construction period is also long. Taking the 50-meter-long water-damaged subgrade section as an example, the retaining wall is used for treatment construction. The cycle takes at least 20 days.

第二种方法是施工浆砌片石护坡来保护路堤;浆砌片石作为迎水面,来抵抗水流冲刷和淘蚀。浆砌片石护坡在施工时,需要先码砌片石,再采用水泥砂浆进行勾缝和砌筑,人工施工周期较长,以50米长的水毁路基段为例,采用挡墙进行处治的施工周期大于15天。由于护坡坡脚处水流湍急,需多次抛填大块石才能形成护脚基础,且在长期冲刷淘蚀作用下易脱空,整体抗灾能力较弱。The second method is to construct the rubble rubble slope protection to protect the embankment; the rubble rubble acts as the upstream surface to resist the erosion and erosion of the water flow. During the construction of the rubble rubble slope protection, it is necessary to lay the rubble first, and then use cement mortar for jointing and masonry. The manual construction period is long. Taking the 50-meter-long water-damaged subgrade section as an example, the construction of the treatment is carried out with a retaining wall. The period is greater than 15 days. Due to the turbulent water flow at the foot of the slope protection, large stones need to be thrown and filled many times to form the foundation of the foot protection, and it is easy to be emptied under the action of long-term erosion and erosion, and the overall disaster resistance is weak.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题是提供一种施工周期短的沿河路基水毁快速抢通施工方法。The technical problem to be solved by the present invention is to provide a construction method for rapid rush-through of water-damaged subgrade along the river with short construction period.

本发明解决其技术问题所采用的技术方案是:沿河路基水毁快速抢通施工方法,包括以下步骤:S1、现场预制钢筋石笼;S2、将钢筋石笼堆叠在坡脚处以形成坡脚挡墙;S3、在坡脚挡墙与公路之间逐层填筑石料并分层压实以形成填石路堤;S4、在填石路堤的坡面安装对其进行保护的护坡防护网。The technical solution adopted by the present invention to solve the technical problem is: a construction method for rapid rush through the water damage of subgrade along the river, comprising the following steps: S1, prefabricating reinforced gabions on site; S2, stacking reinforced gabions at the toe of the slope to form the toe of the slope Retaining wall; S3. Fill stone material layer by layer between the retaining wall at the foot of the slope and the road and compact it in layers to form a stone-filled embankment; S4. Install a slope protection net to protect it on the slope of the stone-filled embankment.

进一步的,步骤S2中,相邻的两层钢筋石笼之间错缝堆垛以形成马牙搓;相邻的钢筋石笼之间采用焊接的方式相连接。Further, in step S2, two adjacent layers of reinforced gabions are stacked at staggered seams to form a horse tooth rub; adjacent reinforced gabions are connected by welding.

进一步的,步骤S3中,所述填石路堤中石料的粒径大于40mm且小于或等于500mm;填石路堤中每层的厚度大于或等于该层中石料粒径的1.5倍。Further, in step S3, the particle size of the stone in the rock-filled embankment is greater than 40 mm and less than or equal to 500 mm; the thickness of each layer in the rock-filled embankment is greater than or equal to 1.5 times the particle size of the stone in the layer.

进一步的,步骤S4中,护坡防护网的安装方法,包括以下步骤:Further, in step S4, the installation method of the slope protection net includes the following steps:

S4.1、在填石路堤的坡面上钻凿若干个锚杆孔;在每个锚杆孔中注入水泥砂浆并插入锚杆;所述锚杆的上端位于锚杆孔的外部;S4.1. Drill several bolt holes on the slope of the rock-filled embankment; inject cement mortar into each bolt hole and insert the bolt; the upper end of the bolt is located outside the bolt hole;

S4.2、在填石路堤的坡面上沿横向布置若干根纵向支撑绳,每根纵向支撑绳从相应位置处的锚杆上端的环套中穿过,且纵向支撑绳的两端与锚杆上端的环套固定连接;S4.2. Several longitudinal support ropes are arranged laterally on the slope of the rock-filled embankment. The ring sleeve on the upper end of the rod is fixedly connected;

在填石路堤的坡面上沿纵向布置若干根横向支撑绳,每根横向支撑绳从相应位置处的锚杆上端的环套中穿过,且横向支撑绳的两端与锚杆上端的环套固定连接;Several transverse support ropes are arranged longitudinally on the slope of the rock-filled embankment. Set of fixed connections;

S4.3、在填石路堤的坡面上铺挂一层格栅网,并用铁丝将格栅网与纵向支撑绳和横向支撑绳连接;S4.3. Hang a layer of grid net on the slope of the rock-filled embankment, and connect the grid net to the longitudinal support rope and the transverse support rope with iron wires;

在格栅网的上方铺设一层钢绳网,并用缝合绳将钢绳网与纵向支撑绳和横向支撑绳连接。A layer of steel rope net is laid on the top of the grille net, and the steel rope net is connected with the longitudinal support rope and the transverse support rope with a suture rope.

进一步的,步骤S4.1中,所述锚杆孔的孔径大于或等于42mm;所述锚杆的长度为L,所述锚杆孔的深度为H;其中,H>L+200mm。Further, in step S4.1, the diameter of the bolt hole is greater than or equal to 42 mm; the length of the bolt is L, and the depth of the bolt hole is H; wherein, H>L+200mm.

进一步的,步骤S4.2中,所述纵向支撑绳和横向支撑绳的直径均为16mm。Further, in step S4.2, the diameters of the longitudinal support rope and the transverse support rope are both 16 mm.

进一步的,步骤S4.3中,所述格栅网的数量为多个,相邻格栅网之间重叠、且重叠宽度大于或等于50mm,相邻格栅网之间采用铁丝连接。Further, in step S4.3, the number of the grids is multiple, the adjacent grids overlap, and the overlapping width is greater than or equal to 50 mm, and the adjacent grids are connected by iron wires.

进一步的,所述格栅网的型号为S0/2.2/50;所述钢绳网的型号为D0/08/300。Further, the model of the grille mesh is S0/2.2/50; the model of the steel wire mesh is D0/08/300.

本发明的有益效果是:本发明实施例的沿河路基水毁快速抢通施工方法,整体施工便捷,经济适用,安全风险低,以50米长的水毁路基段为例,施工周期为5-7天,与现有技术相比,大大缩短了施工周期。采用本发明实施例的施工方法施工的沿河路基可形成一个整体,提高了其抵抗洪水冲刷淘蚀的能力,进而增强了沿河路基的抗灾能力,即使遇到超标准洪水,也不会出现断道等严重的路基毁坏,保证了沿河公路长期畅通。The beneficial effects of the present invention are as follows: the construction method of the water-damaged subgrade along the river in the embodiment of the present invention is convenient for overall construction, economical and applicable, and has low safety risk. -7 days, compared with the existing technology, the construction period is greatly shortened. The subgrade along the river constructed by the construction method of the embodiment of the present invention can form a whole, which improves its ability to resist flood erosion and erosion, thereby enhancing the disaster resistance capacity of the subgrade along the river. Even if it encounters excessive floods, it will not occur Serious damage to roadbeds such as broken roads ensures long-term smooth flow of highways along the river.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍;显而易见地,下面描述中的附图仅仅是本发明中记载的一些实施例,对于本领域普通技术人员来说,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that are used in the description of the embodiments or the prior art; obviously, the accompanying drawings in the following description are only These are some embodiments described in the present invention. For those of ordinary skill in the art, other drawings can also be obtained according to these drawings without creative efforts.

图1是采用本发明实施例的沿河路基水毁快速抢通施工方法施工的沿河路基的结构示意图;Fig. 1 is the structural representation of the subgrade along the river constructed by the construction method of the water-damaged and fast rush-through construction method of the subgrade along the river according to the embodiment of the present invention;

图2是将钢筋石笼堆叠在坡脚处形成的坡脚挡墙的结构示意图;Figure 2 is a schematic structural diagram of a toe retaining wall formed by stacking reinforced gabions at the slope toe;

图3是在填石路堤的坡面安装的护坡防护网的结构示意图。Figure 3 is a schematic structural diagram of a slope protection net installed on the slope of a rock-filled embankment.

图中附图标记为:1-钢筋石笼,2-坡脚挡墙,3-公路,4-填石路堤,5-护坡防护网,6- 锚杆,7-纵向支撑绳,8-横向支撑绳,9-格栅网,10-钢绳网,11-缝合绳。The reference signs in the figure are: 1- reinforced gabion, 2- retaining wall at the foot of the slope, 3- highway, 4- rock embankment, 5- slope protection net, 6- anchor rod, 7- longitudinal support rope, 8- transverse Support rope, 9-grid mesh, 10-steel wire mesh, 11-suture rope.

具体实施方式Detailed ways

为了使本领域的人员更好地理解本发明,下面结合附图和实施例对本发明进一步说明。需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互结合。In order to make those skilled in the art better understand the present invention, the present invention will be further described below with reference to the accompanying drawings and embodiments. It should be noted that the embodiments of the present invention and the features of the embodiments may be combined with each other under the condition of no conflict.

本发明实施例的沿河路基水毁快速抢通施工方法,包括以下步骤:S1、现场预制钢筋石笼1;S2、将钢筋石笼1堆叠在坡脚处以形成坡脚挡墙2;S3、在坡脚挡墙2与公路3之间逐层填筑石料并分层压实以形成填石路堤4;S4、在填石路堤4的坡面安装对其进行保护的护坡防护网5。The construction method for quickly rushing through the flooded subgrade along the river according to the embodiment of the present invention includes the following steps: S1, prefabricating reinforced gabions 1 on site; S2, stacking the reinforced gabions 1 at the foot of the slope to form a retaining wall 2 at the foot of the slope; S3, Fill stone material layer by layer between the toe retaining wall 2 and the highway 3 and compact it in layers to form a stone filled embankment 4; S4, install a slope protection net 5 on the slope of the stone filled embankment 4 to protect it.

步骤S1,现场预制钢筋石笼1。Step S1, prefabricating the reinforced gabion 1 on site.

所述钢筋石笼1为钢筋包裹片漂石的长方体结构,其包括由钢筋焊接而成的钢筋笼,以及充填在钢筋笼内的片漂石。所述钢筋石笼1可在现场宽敞地带集中预制。The reinforced gabion 1 is a rectangular parallelepiped structure in which reinforced steel wraps a piece of boulder, which includes a reinforced cage welded by reinforced steel, and a piece of boulder filled in the reinforced cage. The reinforced gabion 1 can be centrally prefabricated in a spacious area on site.

钢筋石笼1的预制方法,包括以下步骤:The prefabrication method of the reinforced gabion 1 includes the following steps:

S1.1、根据钢筋笼的设计尺寸对钢筋进行切割下料,将下料后的钢筋弯折并焊接形成顶部开口的笼身以及用于盖合在笼身顶部的笼盖。所述笼身和笼盖中的钢筋均包括龙骨钢筋和网格钢筋,其中龙骨钢筋的直径大于网格钢筋的直径。笼身与笼盖在制造时,每两根钢筋的交叉点应焊接牢固。S1.1. Cut the steel bar according to the design size of the steel bar cage, bend and weld the steel bar after cutting to form a cage body with an open top and a cover for covering the top of the cage body. The reinforcement bars in the cage body and the cage cover both include keel reinforcement bars and grid reinforcement bars, wherein the diameter of the keel reinforcement bars is larger than the diameter of the grid reinforcement bars. When the cage body and the cage cover are manufactured, the intersection of each two steel bars should be welded firmly.

S1.2、在笼身内充填片漂石,然后再将笼盖与笼身焊接在一起。所述片漂石采用饱和单轴抗压强度大于或等于30MPa的石块,并且石块的最短轴大于或等于150mm。片漂石在钢筋笼内的布置方式为,外圈充填尺寸较大的片漂石,且该部分片漂石的粒径大于钢筋笼上网孔的孔径,内圈充填尺寸较小的片漂石,且片漂石之间应夯实。S1.2. Fill the cage body with boulders, and then weld the cage cover and the cage body together. The boulder is made of stones with a saturated uniaxial compressive strength greater than or equal to 30 MPa, and the shortest axis of the stones is greater than or equal to 150 mm. The arrangement of boulders in the steel cage is that the outer ring is filled with larger boulders, and the particle size of this part of boulders is larger than the diameter of the mesh holes of the steel cage, and the inner ring is filled with smaller boulders , and the boulders should be compacted.

步骤S2、将钢筋石笼1堆叠在坡脚处以形成坡脚挡墙2。Step S2, stacking the reinforced gabions 1 at the toe of the slope to form the retaining wall 2 at the toe of the slope.

本发明实施例中,采用的是边预制钢筋石笼1,边将钢筋石笼1堆叠在坡脚处以形成坡脚挡墙2的施工方式;也就就是说,当一个钢筋石笼1预制完成后,就采用汽车吊将钢筋石笼1安放在坡脚处;这样就可提高施工效率,节约施工周期。In the embodiment of the present invention, the construction method of prefabricating the reinforced gabion 1 while stacking the reinforced gabion 1 at the toe of the slope to form the retaining wall 2 at the toe of the slope is adopted; that is, when the prefabrication of a reinforced gabion 1 is completed After that, the reinforced gabion 1 is placed at the foot of the slope by using a truck crane; in this way, the construction efficiency can be improved and the construction period can be saved.

由于钢筋石笼1对基础承载力要求不高,且变形适应能力较强,因此,不需要在坡脚处开挖基础进行埋置,直接将钢筋石笼1安放在坡脚处即可。通过若干个钢筋石笼1堆叠在坡脚处以形成坡脚挡墙2,这样不仅对填石路堤4的下端进行防护,能起到稳固坡脚的作用,而且还能起到防冲刷、淘蚀的作用。Since the reinforced gabion 1 does not have high requirements on the bearing capacity of the foundation and has strong deformation adaptability, it is not necessary to excavate the foundation at the toe of the slope for embedding, and the reinforced gabion 1 can be placed directly at the toe of the slope. A number of reinforced gabions 1 are stacked at the toe of the slope to form a retaining wall 2 at the toe of the slope, which not only protects the lower end of the rock-filled embankment 4, but also stabilizes the toe of the slope, and can also prevent erosion and erosion. effect.

为了提高坡脚挡墙2的整体性和稳定性,步骤S2中,相邻的两层钢筋石笼1之间错缝堆垛以形成马牙搓;相邻的钢筋石笼1之间采用焊接的方式相连接。In order to improve the integrity and stability of the retaining wall 2 at the foot of the slope, in step S2, two adjacent layers of reinforced gabions 1 are stacked with staggered joints to form a horse tooth rub; adjacent reinforced gabions 1 are welded by welding. way to connect.

将平行于河道的方向定为横向,将垂直于横向的方向定为纵向;参见图1、图2,任意上下两层钢筋石笼1之间在沿横向和纵向的方向上均应错缝堆垛以形成马牙搓,以避免出现上下贯通的直缝,提高了坡脚挡墙2的整体性和稳定性。进一步的,任意相邻的钢筋石笼1之间采用焊接的方式相连接,这样就使得坡脚挡墙2连接为整体,进而提高了坡脚挡墙2的整体性和稳定性,增强了坡脚挡墙2的抗灾能力,即使遇到超标准洪水,也不会毁坏坡脚挡墙 2。The direction parallel to the river channel is designated as the horizontal direction, and the direction perpendicular to the horizontal direction is designated as the vertical direction; refer to Figure 1 and Figure 2, between any upper and lower layers of reinforced stone cages 1 should be staggered in the horizontal and vertical directions. It is stacked to form a horse tooth rub, so as to avoid straight seams running up and down, and improve the integrity and stability of the retaining wall 2 at the foot of the slope. Further, any adjacent reinforced gabions 1 are connected by welding, so that the retaining wall 2 at the foot of the slope is connected as a whole, thereby improving the integrity and stability of the retaining wall 2 at the foot of the slope, and enhancing the slope. The anti-disaster ability of the foot retaining wall 2 will not destroy the foot retaining wall 2 even if it encounters a flood that exceeds the standard.

步骤S3、在坡脚挡墙2与公路3之间逐层填筑石料并分层压实以形成填石路堤4。Step S3 , filling stone material layer by layer between the retaining wall 2 at the foot of the slope and the highway 3 and compacting the layers to form the stone-filled road embankment 4 .

填石路堤4是形成路基的承载结构,其可直接利用山区的硬质岩石或中硬岩石进行填筑,施工便捷。步骤S3中,所述填石路堤4中石料的粒径大于40mm且小于或等于500mm;填石路堤4中每层的厚度大于或等于该层中石料粒径的1.5倍。The rock-filled embankment 4 is a bearing structure for forming a roadbed, which can be directly filled with hard rocks or medium-hard rocks in mountainous areas, and the construction is convenient. In step S3, the particle size of the stone in the rock-filled road embankment 4 is greater than 40 mm and less than or equal to 500 mm; the thickness of each layer in the rock-filled road embankment 4 is greater than or equal to 1.5 times the particle size of the stone in the layer.

本发明实施例中,所述填石路堤4采用的是逐层填筑石料并分层压实的施工方式。施工时,当铺填粒径为250mm以上的石料时,应先铺填大块石料,大面向下,小面向上,摆平放稳,再用小石块找平,石屑塞填,最后压实;当铺填粒径为250mm以下的石料时,可直接分层摊铺,分层压实。In the embodiment of the present invention, the stone-filled road embankment 4 adopts a construction method of filling stone material layer by layer and layer-by-layer compaction. During construction, when laying and filling stones with a particle size of more than 250mm, large stones should be laid and filled first, with the large side facing down and the small side facing up. When paving and filling stones with a particle size of less than 250mm, it can be directly paved in layers and compacted by layers.

步骤S4、在填石路堤4的坡面安装对其进行保护的护坡防护网5。Step S4 , installing a slope protection net 5 to protect the slope of the rock-filled embankment 4 .

本发明实施例中,填石路提4应沿横向的方向分段施工,当一段填石路堤4施工完成后,就在该段填石路堤4的坡面上安装护坡防护网5,并确保护坡防护网5紧贴填石路堤4的坡面。所述护坡防护网5主要由锚杆6、纵向支撑绳7、横向支撑绳8、格栅网9和钢绳网10构成。通过设置护坡防护网5,不仅对填石路堤4进行保护,提高了填石路堤4的整体性和稳定性,还使填石路堤4具有良好的透水性和抗冲刷能力,并且缩短了施工周期,避免了人工勾缝砌筑的周期长的问题。In the embodiment of the present invention, the rock-filled road lift 4 should be constructed in sections along the lateral direction. After the construction of a section of the rock-filled road embankment 4 is completed, the slope protection net 5 is installed on the slope of the rock-filled road embankment 4 to ensure that The slope protection net 5 is in close contact with the slope of the stone-filled embankment 4 . The slope protection net 5 is mainly composed of an anchor rod 6 , a longitudinal support rope 7 , a lateral support rope 8 , a grid net 9 and a steel rope net 10 . The provision of the slope protection net 5 not only protects the rock-filled embankment 4, improves the integrity and stability of the rock-filled embankment 4, but also enables the rock-filled embankment 4 to have good water permeability and anti-scour capability, and shortens the construction period , to avoid the problem of long period of artificial jointing and masonry.

参见图1、图3,步骤S4中,护坡防护网5的安装方法,包括以下步骤:Referring to FIG. 1 and FIG. 3, in step S4, the installation method of the slope protection net 5 includes the following steps:

S4.1、在填石路堤4的坡面上钻凿若干个锚杆孔;在每个锚杆孔中注入水泥砂浆并插入锚杆6;所述锚杆6的上端位于锚杆孔的外部;S4.1. Drill several bolt holes on the slope of the rock-filled embankment 4; inject cement mortar into each bolt hole and insert the bolt 6; the upper end of the bolt 6 is located outside the bolt hole ;

S4.2、在填石路堤4的坡面上沿横向布置若干根纵向支撑绳7,每根纵向支撑绳7从相应位置处的锚杆6上端的环套中穿过,且纵向支撑绳7的两端与锚杆6上端的环套固定连接;S4.2. Several longitudinal support ropes 7 are arranged laterally on the slope of the rock-filled embankment 4. Each longitudinal support rope 7 passes through the loop on the upper end of the anchor rod 6 at the corresponding position, and the longitudinal support rope The two ends of the bolt are fixedly connected with the ring sleeve on the upper end of the anchor rod 6;

在填石路堤4的坡面上沿纵向布置若干根横向支撑绳8,每根横向支撑绳8从相应位置处的锚杆6上端的环套中穿过,且横向支撑绳8的两端与锚杆6上端的环套固定连接;Several transverse support ropes 8 are arranged longitudinally on the slope of the rock-filled embankment 4, each transverse support rope 8 passes through the loop at the upper end of the anchor rod 6 at the corresponding position, and the two ends of the transverse support rope 8 are connected to The ring sleeve at the upper end of the anchor rod 6 is fixedly connected;

S4.3、在填石路堤4的坡面上铺挂一层格栅网9,并用铁丝将格栅网9与纵向支撑绳7 和横向支撑绳8连接;S4.3, lay a layer of grid net 9 on the slope of the rock-filled embankment 4, and connect the grid net 9 with the longitudinal support rope 7 and the lateral support rope 8 with iron wires;

在格栅网9的上方铺设一层钢绳网10,并用缝合绳11将钢绳网10与纵向支撑绳7和横向支撑绳8连接。A layer of steel wire mesh 10 is laid above the grid net 9 , and the wire mesh 10 is connected with the longitudinal support rope 7 and the transverse support rope 8 by sewing ropes 11 .

步骤S4.1中,应根据锚杆6的设计位置在填石路堤4的坡面上钻凿锚杆孔,并以高压气清孔。所述锚杆孔的孔径大于或等于42mm;所述锚杆6的长度为L,所述锚杆孔的深度为H;其中,H>L+200mm。在每个锚杆孔中注入不低于M30的水泥砂浆并插入锚杆6,检查并确保锚杆孔内浆液饱满。当填石路堤4的坡面起伏高差较大时,应适当增加锚杆6的数量,以确保后续安装的格栅网9和钢绳网10紧贴坡面。In step S4.1, according to the design position of the bolt 6, the bolt hole should be drilled on the slope of the rock-filled embankment 4, and the hole should be cleared with high pressure air. The diameter of the bolt hole is greater than or equal to 42 mm; the length of the bolt 6 is L, and the depth of the bolt hole is H; wherein, H>L+200mm. Inject cement mortar no less than M30 into each bolt hole and insert bolt 6, check and ensure that the grout in the bolt hole is full. When the slope surface of the rock-filled embankment 4 has a large undulation and height difference, the number of anchor rods 6 should be appropriately increased to ensure that the grid mesh 9 and the wire rope mesh 10 installed subsequently adhere to the slope surface.

步骤S4.2中,所述纵向支撑绳7指的是该支撑绳的长度方向沿纵向延伸,所述横向支撑绳8指的是该支撑绳的长度方向沿横向延伸。在填石路堤4的坡面上沿横向的方向布置若干根纵向支撑绳7,沿纵向的方向布置若干根横向支撑绳8,每根纵向支撑绳7和横向支撑绳8 从相对应位置的锚杆6上端的环套中穿过,且在张紧后的两端通过绳卡与锚杆6上端的环套固定连接。In step S4.2, the longitudinal support rope 7 means that the length direction of the support rope extends longitudinally, and the lateral support rope 8 means that the length direction of the support rope extends laterally. Several longitudinal support ropes 7 are arranged in the lateral direction on the slope of the rock-filled embankment 4, and several transverse support ropes 8 are arranged in the longitudinal direction. The upper end of the rod 6 passes through the loop, and the two ends after tensioning are fixedly connected to the loop at the upper end of the anchor rod 6 through rope clips.

例如,所述纵向支撑绳7和横向支撑绳8的直径均为16mm。当支撑绳的长度小于15米时,每根支撑绳的端部通过两个绳卡与锚杆6上端的环套固定连接;当支撑绳的长度大于15 米且小于30米时,每根支撑绳的端部通过三个绳卡与锚杆6上端的环套固定连接;当支撑绳的长度大于30米时,每根支撑绳的端部通过四个绳卡与锚杆6上端的环套固定连接。For example, the diameters of the longitudinal support ropes 7 and the transverse support ropes 8 are both 16 mm. When the length of the support rope is less than 15 meters, the end of each support rope is fixedly connected to the ring sleeve on the upper end of the anchor rod 6 through two rope clips; when the length of the support rope is greater than 15 meters and less than 30 meters, each support The end of the rope is fixedly connected with the loop on the upper end of the anchor rod 6 through three rope clips; when the length of the support rope is greater than 30 meters, the end of each support rope is connected with the loop on the upper end of the anchor rod 6 through four rope clips. Fixed connection.

步骤S4.3中,先在填石路堤4的坡面上从上向下铺挂一层格栅网9,所述格栅网9可以位于支撑绳的上方,也可以位于支撑绳的下方。例如,所述格栅网9的型号为S0/2.2/50。所述格栅网9与纵横向支撑绳之间采用直径为1.2mm的铁丝按1米的间距进行扎结。进一步的,所述格栅网9的数量为多个,相邻格栅网9之间重叠、且重叠宽度大于或等于50mm,相邻格栅网9之间采用铁丝连接。具体的,相邻的格栅网9之间采用直径为1.2mm的铁丝按1 米的间距进行扎结。In step S4.3, a layer of grid nets 9 are firstly laid on the slope of the rock-filled embankment 4 from top to bottom. The grid nets 9 may be located above the support ropes or below the support ropes. For example, the model of the grille mesh 9 is S0/2.2/50. Between the grid net 9 and the vertical and horizontal support ropes, iron wires with a diameter of 1.2 mm are used for tying at a distance of 1 meter. Further, the number of the grids 9 is multiple, the adjacent grids 9 overlap, and the overlapping width is greater than or equal to 50 mm, and the adjacent grids 9 are connected by iron wires. Specifically, an iron wire with a diameter of 1.2 mm is used to bind the adjacent grids 9 at a distance of 1 meter.

格栅网9铺挂完成后,再在格栅网9的上方从上向下铺设一层钢绳网10。例如,所述钢绳网10的型号为D0/08/300。所述钢绳网10与纵横向支撑绳之间采用一根直径为8mm的缝合绳11进行缝合并预张拉,缝合绳11的两端各用两个绳卡与支撑绳进行固定连接。After the grid net 9 is laid and hung, a layer of steel rope net 10 is laid on the top of the grid net 9 from top to bottom. For example, the model of the wire mesh 10 is D0/08/300. A sewing cord 11 with a diameter of 8 mm is used for sewing and pretensioning between the steel cord net 10 and the vertical and horizontal support cords.

本发明实施例的沿河路基水毁快速抢通施工方法,整体施工便捷,经济适用,安全风险低,以50米长的水毁路基段为例,施工周期为5-7天,与现有技术相比,大大缩短了施工周期。采用本发明实施例的施工方法施工的沿河路基可形成一个整体,在快速形成路基承载结构的同时,提高了沿河路基的抗冲刷淘蚀能力,进而增强了沿河路基的抗灾能力,即使遇到超标准洪水,也不会出现断道等严重的路基毁坏,可作为永久性路基防护工程,保证了沿河公路长期畅通,解决了传统抢通施工方法存在的施工周期长,安全风险大、抗灾能力低的问题。The construction method of the water-damaged subgrade along the river in the embodiment of the present invention is convenient for overall construction, economical and applicable, and has low safety risk. Taking a 50-meter-long subgrade section with water damage as an example, the construction period is 5-7 days, which is similar to the existing construction period. Compared with the technology, the construction period is greatly shortened. The subgrade along the river constructed by the construction method of the embodiment of the present invention can be formed as a whole, and the bearing structure of the subgrade can be quickly formed, and the erosion resistance of the subgrade along the river is improved, and the disaster resistance capacity of the subgrade along the river is further enhanced. In case of excessive floods, there will be no serious subgrade damage such as road breakage. It can be used as a permanent subgrade protection project to ensure long-term smooth flow of roads along the river, and solve the long construction period and high safety risks of traditional emergency construction methods. , The problem of low disaster resistance.

实施例一:Example 1:

某山区公路,水毁路基段的长度为50米,冲失及悬空高度为15米。On a mountain road, the length of the subgrade section destroyed by water is 50 meters, and the washout and overhang height is 15 meters.

采用本发明的沿河路基水毁快速抢通施工方法对上述水毁路基段进行施工,包括以下步骤:The above-mentioned water-damaged roadbed section is constructed by using the construction method of the present invention for rapid rush-through of water-damaged roadbed along the river, comprising the following steps:

S1、现场预制钢筋石笼1。钢筋石笼1的长×宽×高为2000×2000×1000mm;钢筋笼中的龙骨钢筋的直径为16mm,网格钢筋的直径为8mm;钢筋笼上的网格尺寸为150×150mm;钢筋笼内的片漂石为饱和单轴抗压强度大于30MPa的石块,且其最短轴大于150mm。S1. Prefabricated reinforced gabion 1 on site. The length × width × height of the reinforced gabion 1 is 2000 × 2000 × 1000 mm; the diameter of the keel reinforcement in the reinforcement cage is 16 mm, and the diameter of the mesh reinforcement is 8 mm; the mesh size on the reinforcement cage is 150 × 150 mm; the reinforcement cage The boulders inside are stones with saturated uniaxial compressive strength greater than 30MPa, and their shortest axis is greater than 150mm.

S2、采用吊车将钢筋石笼1安放在坡脚处,以叠放三层以形成坡脚挡墙2。任意上下两层钢筋石笼1之间在沿横向和纵向的方向上均错缝堆垛以形成马牙搓,且任意相邻的钢筋石笼1之间采用焊接的方式相连接。S2. Use a crane to place the reinforced gabion 1 at the foot of the slope to stack three layers to form the retaining wall 2 at the foot of the slope. Any two upper and lower layers of reinforced gabions 1 are stacked with staggered seams in the transverse and longitudinal directions to form a horse tooth rub, and any adjacent reinforced gabions 1 are connected by welding.

S3、在坡脚挡墙2与公路3之间逐层填筑石料并分层压实以形成填石路堤4。所述填石路堤4中石料的粒径大于40mm且小于或等于500mm;填石路堤4中每层的厚度大于或等于该层中石料粒径的1.5倍。S3 , filling stone material layer by layer between the retaining wall 2 at the foot of the slope and the highway 3 and compacting the layers to form the stone filling embankment 4 . The particle size of the stone in the rock-filled road embankment 4 is greater than 40 mm and less than or equal to 500 mm; the thickness of each layer in the rock-filled road embankment 4 is greater than or equal to 1.5 times the particle size of the stone in the layer.

S4、在填石路堤4的坡面安装对其进行保护的护坡防护网5。S4. Install a slope protection net 5 on the slope of the rock-filled embankment 4 to protect it.

S4.1、在填石路堤4的坡面沿横向和纵向以4500mm的间距钻凿若干个锚杆孔,每个锚杆孔的直径为42mm,深度为3200mm;在每个锚杆孔中注入M30的水泥砂浆并插入3米长的锚杆 6。S4.1. Drill a number of bolt holes on the slope of the rock-filled embankment 4 with a spacing of 4500mm in the horizontal and vertical directions, each bolt hole has a diameter of 42mm and a depth of 3200mm; inject injection into each bolt hole M30 cement mortar and insert 3 meter long anchor rod 6.

S4.2、在填石路堤4的坡面上沿横向以4500mm的间距布置若干个纵向支撑绳7,每根纵向支撑绳7从相应位置处的锚杆6上端的环套中穿过,纵向支撑绳7张紧后的两端采用绳卡与锚杆6上端的环套固定连接。S4.2. On the slope of the rock-filled embankment 4, arrange a number of longitudinal support ropes 7 with a spacing of 4500mm in the transverse direction. The two ends of the tensioned support rope 7 are fixedly connected to the ring sleeve on the upper end of the anchor rod 6 by rope clips.

在填石路堤4的坡面上沿纵向以4500mm的间距布置若干个横向支撑绳8,每根横向支撑绳8从相应位置处的锚杆6上端的环套中穿过,横向支撑绳8张紧后的两端采用绳卡与锚杆 6上端的环套固定连接。On the slope of the rock-filled embankment 4, a number of transverse support ropes 8 are arranged longitudinally at intervals of 4500 mm. Each transverse support rope 8 passes through the loop at the upper end of the anchor rod 6 at the corresponding position. The two ends after tightening are fixedly connected with the ring sleeve on the upper end of the anchor rod 6 by rope clips.

S4.3、在填石路堤4的坡面上从上向下铺挂一层型号为S0/2.2/50的格栅网9,相邻的格栅网9之间重叠、且重叠的宽度为60mm,相邻的格栅网9之间的缝合以及格栅网9与纵横支撑绳之间用直径为1.2mm的铁丝按照1米的间距进行扎结。S4.3. Lay a layer of grid nets 9 of type S0/2.2/50 from top to bottom on the slope of the rock-filled embankment 4, and the adjacent grid nets 9 overlap and overlap with a width of 60mm, the stitching between adjacent grids 9 and the grids 9 and the vertical and horizontal support ropes are tied with iron wires with a diameter of 1.2mm at a distance of 1 meter.

然后在格栅网9的上方从上向下铺设一层型号为D0/08/300的钢绳网10,每张钢绳网10 通过一根直径为8mm的缝合绳11与纵横支撑绳进行缝合并预张拉,缝合绳11的两端各用两个绳卡与支撑绳或锚杆6上端的环套进行固定连接。Then, a layer of steel wire mesh 10 with a model of D0/08/300 is laid on top of the grille net 9 from top to bottom, and each steel wire mesh 10 is stitched with the vertical and horizontal support ropes by a stitching rope 11 with a diameter of 8 mm. And pre-tensioning, the two ends of the suture rope 11 are fixedly connected with the support rope or the loop on the upper end of the anchor rod 6 by two rope clips.

采用本发明实施例的沿河路基水毁快速抢通施工方法对上述50米长的水毁路基段进行抢通施工,其施工周期为5天。The above-mentioned 50-meter-long water-damaged subgrade section was constructed by using the construction method for rapid rush-through of water-damaged subgrade along the river according to the embodiment of the present invention, and the construction period was 5 days.

采用现有的挡土墙结构的施工方法对上述50米长的水毁路基段进行抢通施工,其施工周期为25天。The construction of the 50-meter-long subgrade section damaged by water is carried out by using the existing construction method of the retaining wall structure, and the construction period is 25 days.

采用现有的浆砌片石护坡的施工方法对上述50米长的水毁路基段进行抢通施工,其施工周期为17天。The 50-meter-long water-damaged subgrade section was constructed by using the existing construction method of screed rubble slope protection, and the construction period was 17 days.

由上可知,本发明实施例的沿河路基水毁快速抢通施工方法,整体施工便捷,安全风险低,施工周期短。采用本发明实施例的施工方法施工的沿河路基可形成一个整体,提高了其抵抗洪水冲刷淘蚀的能力,进而增强了沿河路基的抗灾能力,即使遇到超标准洪水,也不会出现断道等严重的路基毁坏,保证了沿河公路长期畅通。It can be seen from the above that the construction method for rapid rush-through of subgrade water damage along the river according to the embodiment of the present invention has the advantages of convenient overall construction, low safety risk and short construction period. The subgrade along the river constructed by the construction method of the embodiment of the present invention can form a whole, which improves its ability to resist flood erosion and erosion, thereby enhancing the disaster resistance capacity of the subgrade along the river. Even if it encounters excessive floods, it will not occur Serious damage to roadbeds such as broken roads ensures long-term smooth flow of highways along the river.

以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (8)

1.沿河路基水毁快速抢通施工方法,其特征在于,包括以下步骤:S1、现场预制钢筋石笼(1);S2、将钢筋石笼(1)堆叠在坡脚处以形成坡脚挡墙(2);S3、在坡脚挡墙(2)与公路(3)之间逐层填筑石料并分层压实以形成填石路堤(4);S4、在填石路堤(4)的坡面安装对其进行保护的护坡防护网(5)。1. The construction method of rapid rush through the water damage of subgrade along the river, is characterized in that, comprises the following steps: S1, prefabricated reinforced gabions (1) on site; S2, stacking reinforced gabions (1) at the toe of the slope to form a toe block Wall (2); S3. Fill stone material layer by layer between the retaining wall at the foot of the slope (2) and the road (3) and compact it in layers to form a stone-filled embankment (4); S4. In the stone-filled embankment (4) A slope protection net (5) for protecting the slope surface is installed. 2.根据权利要求1所述的沿河路基水毁快速抢通施工方法,其特征在于,步骤S2中,相邻的两层钢筋石笼(1)之间错缝堆垛以形成马牙搓;相邻的钢筋石笼(1)之间采用焊接的方式相连接。2. The construction method for fast rushing through the water damage of roadbed along the river according to claim 1, is characterized in that, in step S2, staggered stacking between adjacent two-layer reinforced stone cages (1) to form a horse tooth rubbing ; Adjacent reinforced gabions (1) are connected by welding. 3.根据权利要求1所述的沿河路基水毁快速抢通施工方法,其特征在于,步骤S3中,所述填石路堤(4)中石料的粒径大于40mm且小于或等于500mm;填石路堤(4)中每层的厚度大于或等于该层中石料粒径的1.5倍。3. The construction method according to claim 1, characterized in that, in step S3, the particle size of the stone in the rock-filled embankment (4) is greater than 40mm and less than or equal to 500mm; The thickness of each layer in the stone embankment (4) is greater than or equal to 1.5 times the particle size of the stone in the layer. 4.根据权利要求1所述的沿河路基水毁快速抢通施工方法,其特征在于,步骤S4中,护坡防护网(5)的安装方法,包括以下步骤:4. The construction method for fast rushing through the water damage of roadbed along the river according to claim 1, is characterized in that, in step S4, the installation method of slope protection net (5), comprises the following steps: S4.1、在填石路堤(4)的坡面上钻凿若干个锚杆孔;在每个锚杆孔中注入水泥砂浆并插入锚杆(6);所述锚杆(6)的上端位于锚杆孔的外部;S4.1. Drill several bolt holes on the slope of the rock-filled embankment (4); inject cement mortar into each bolt hole and insert the bolt (6); the upper end of the bolt (6) outside the bolt hole; S4.2、在填石路堤(4)的坡面上沿横向布置若干根纵向支撑绳(7),每根纵向支撑绳(7)从相应位置处的锚杆(6)上端的环套中穿过,且纵向支撑绳(7)的两端与锚杆(6)上端的环套固定连接;S4.2. Several longitudinal support ropes (7) are arranged laterally on the slope of the rock-filled embankment (4). Pass through, and the two ends of the longitudinal support rope (7) are fixedly connected with the loop on the upper end of the anchor rod (6); 在填石路堤(4)的坡面上沿纵向布置若干根横向支撑绳(8),每根横向支撑绳(8)从相应位置处的锚杆(6)上端的环套中穿过,且横向支撑绳(8)的两端与锚杆(6)上端的环套固定连接;Several transverse support ropes (8) are arranged longitudinally on the slope of the rock-filled embankment (4), and each transverse support rope (8) passes through the loop at the upper end of the anchor rod (6) at the corresponding position, and Both ends of the lateral support rope (8) are fixedly connected with the ring sleeve at the upper end of the anchor rod (6); S4.3、在填石路堤(4)的坡面上铺挂一层格栅网(9),并用铁丝将格栅网(9)与纵向支撑绳(7)和横向支撑绳(8)连接;S4.3. Lay a layer of grid net (9) on the slope of the rock-filled embankment (4), and connect the grid net (9) with the longitudinal support rope (7) and the lateral support rope (8) with iron wires ; 在格栅网(9)的上方铺设一层钢绳网(10),并用缝合绳(11)将钢绳网(10)与纵向支撑绳(7)和横向支撑绳(8)连接。A layer of steel rope net (10) is laid on the grid net (9), and the steel rope net (10) is connected with the longitudinal support rope (7) and the transverse support rope (8) by sewing ropes (11). 5.根据权利要求4所述的沿河路基水毁快速抢通施工方法,其特征在于,步骤S4.1中,所述锚杆孔的孔径大于或等于42mm;所述锚杆(6)的长度为L,所述锚杆孔的深度为H;其中,H>L+200mm。5. The construction method for rapid rushing through of water damaged roadbed along the river according to claim 4, characterized in that, in step S4.1, the diameter of the bolt hole is greater than or equal to 42mm; the diameter of the bolt (6) The length is L, and the depth of the bolt hole is H; wherein, H>L+200mm. 6.根据权利要求4所述的沿河路基水毁快速抢通施工方法,其特征在于,步骤S4.2中,所述纵向支撑绳(7)和横向支撑绳(8)的直径均为16mm。6. The construction method for rapid rush to clear water damage of subgrade along the river according to claim 4, characterized in that, in step S4.2, the diameters of the longitudinal support rope (7) and the lateral support rope (8) are both 16mm . 7.根据权利要求4所述的沿河路基水毁快速抢通施工方法,其特征在于,步骤S4.3中,所述格栅网(9)的数量为多个,相邻格栅网(9)之间重叠、且重叠宽度大于或等于50mm,相邻格栅网(9)之间采用铁丝连接。7. The construction method for rapid rush to clear water damage of roadbed along the river according to claim 4, is characterized in that, in step S4.3, the quantity of described grid net (9) is multiple, adjacent grid net (9) 9) The overlap between them, and the overlap width is greater than or equal to 50mm, and the adjacent grids (9) are connected by iron wires. 8.根据权利要求4所述的沿河路基水毁快速抢通施工方法,其特征在于,所述格栅网(9)的型号为S0/2.2/50;所述钢绳网(10)的型号为D0/08/300。8. The construction method for rapid rush to clear water damage of roadbed along the river according to claim 4, wherein the model of the grille net (9) is S0/2.2/50; The model number is D0/08/300.
CN202010914652.1A 2020-09-03 2020-09-03 Construction method of rapid rush-through construction of subgrade water damaged along the river Pending CN112030878A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010914652.1A CN112030878A (en) 2020-09-03 2020-09-03 Construction method of rapid rush-through construction of subgrade water damaged along the river

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010914652.1A CN112030878A (en) 2020-09-03 2020-09-03 Construction method of rapid rush-through construction of subgrade water damaged along the river

Publications (1)

Publication Number Publication Date
CN112030878A true CN112030878A (en) 2020-12-04

Family

ID=73591325

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010914652.1A Pending CN112030878A (en) 2020-09-03 2020-09-03 Construction method of rapid rush-through construction of subgrade water damaged along the river

Country Status (1)

Country Link
CN (1) CN112030878A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112609522A (en) * 2020-12-23 2021-04-06 四川省交通勘察设计研究院有限公司 Quick embankment
CN112681045A (en) * 2020-12-22 2021-04-20 湖北省路桥集团有限公司 Ramp way back-pressure embankment deformation control structure and construction method
CN113897832A (en) * 2021-11-22 2022-01-07 长沙理工大学 Repairing structure and repairing method for water damage of geogrid reverse-wrapping embankment
CN113944117A (en) * 2021-10-29 2022-01-18 成都未来智隧科技有限公司 Slope protection structure
CN113981750A (en) * 2021-11-17 2022-01-28 中铁七局集团郑州工程有限公司 Construction method for rapid first-aid repair after water damage of embankment of existing railway riverside vehicle station
CN115354621A (en) * 2022-06-27 2022-11-18 四川省公路规划勘察设计研究院有限公司 Ecological slope protection block and slope protection structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061225A (en) * 2011-10-21 2013-04-24 中铁二十一局集团有限公司 Rock salt railroad bed structure of section parallel to existing line and construction method of structure
CN206844135U (en) * 2017-06-10 2018-01-05 浙江华东工程咨询有限公司 A kind of cofferdam
CN109056439A (en) * 2018-09-20 2018-12-21 杭州市交通规划设计研究院 It is close to the multilayered structure and construction method of mountain high-fill roadbed
CN210975567U (en) * 2019-09-12 2020-07-10 中交投资南京有限公司 Side slope surface protection structure applied to bridge construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061225A (en) * 2011-10-21 2013-04-24 中铁二十一局集团有限公司 Rock salt railroad bed structure of section parallel to existing line and construction method of structure
CN206844135U (en) * 2017-06-10 2018-01-05 浙江华东工程咨询有限公司 A kind of cofferdam
CN109056439A (en) * 2018-09-20 2018-12-21 杭州市交通规划设计研究院 It is close to the multilayered structure and construction method of mountain high-fill roadbed
CN210975567U (en) * 2019-09-12 2020-07-10 中交投资南京有限公司 Side slope surface protection structure applied to bridge construction

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112681045A (en) * 2020-12-22 2021-04-20 湖北省路桥集团有限公司 Ramp way back-pressure embankment deformation control structure and construction method
CN112681045B (en) * 2020-12-22 2022-06-07 湖北省路桥集团有限公司 Ramp way back-pressure embankment deformation control structure and construction method
CN112609522A (en) * 2020-12-23 2021-04-06 四川省交通勘察设计研究院有限公司 Quick embankment
CN113944117A (en) * 2021-10-29 2022-01-18 成都未来智隧科技有限公司 Slope protection structure
CN113981750A (en) * 2021-11-17 2022-01-28 中铁七局集团郑州工程有限公司 Construction method for rapid first-aid repair after water damage of embankment of existing railway riverside vehicle station
CN113981750B (en) * 2021-11-17 2024-10-01 中铁七局集团郑州工程有限公司 Construction method for quick rush repair after water destruction of embankment of existing railway side-stream station
CN113897832A (en) * 2021-11-22 2022-01-07 长沙理工大学 Repairing structure and repairing method for water damage of geogrid reverse-wrapping embankment
CN115354621A (en) * 2022-06-27 2022-11-18 四川省公路规划勘察设计研究院有限公司 Ecological slope protection block and slope protection structure
CN115354621B (en) * 2022-06-27 2023-11-24 四川省公路规划勘察设计研究院有限公司 Ecological slope protection blocks and slope protection structures

Similar Documents

Publication Publication Date Title
CN112030878A (en) Construction method of rapid rush-through construction of subgrade water damaged along the river
CN107250460B (en) Precast block retaining wall method for preventing landslide
CN104452784B (en) Composite bolt pile used for slope strengthening and construction technique of composite bolt pile
CN105002927B (en) A construction method of anti-filtering layer for retaining wall of excavated slope
CN210315102U (en) Slope protection reinforced roadbed structure of composite ecological decoration panel
CN101899839A (en) A kind of prestressed cantilever opposite tension retaining wall with reinforcement
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN111778793A (en) A cavity collapse prevention structure and construction method
CN102966072B (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN106836244A (en) Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall
CN111455831A (en) Ultra-high composite reinforced soil abutment combined with prestressed anchor cable and its construction method
CN116537221A (en) Highway tunnel portal section collapse sliding body slope protection reinforcing structure and construction method
CN103643686A (en) Retaining structure of water-saturated landslide with gradual slope ratio and construction method
CN109736156A (en) A highway guardrail and a sound barrier share an integrated steel anchor pipe foundation structure and construction method
CN211228180U (en) A culvert structure capable of protecting the embankment
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
JP6676462B2 (en) Embankment reinforcement method
CN219410355U (en) Flexible side-width structure of high-fill embankment of existing railway
CN208293630U (en) A kind of structural system of the antiseismic liquefaction uplifting in subway station
CN103343541B (en) Pile-plate combined type foundation pit excavation protective structure and construction method thereof
CN108505547A (en) A kind of structural system and method for the antiseismic liquefaction uplifting in subway station
CN111893829B (en) A roadbed protection structure
CN115506305A (en) Foot protection slope protection structure along river road and construction method thereof
CN210315650U (en) Anchor rod reinforced composite retaining wall
CN115012947A (en) Reverse method prefabricated shaft and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201204

RJ01 Rejection of invention patent application after publication