CN206844135U - A kind of cofferdam - Google Patents
A kind of cofferdam Download PDFInfo
- Publication number
- CN206844135U CN206844135U CN201720671521.9U CN201720671521U CN206844135U CN 206844135 U CN206844135 U CN 206844135U CN 201720671521 U CN201720671521 U CN 201720671521U CN 206844135 U CN206844135 U CN 206844135U
- Authority
- CN
- China
- Prior art keywords
- layer
- cofferdam
- soil layer
- hillside
- blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The utility model discloses a kind of cofferdam, the cofferdam is included both sides and excavates the hillside soil layer of shaping, the pedestal set along hillside soil layer and be arranged on being blocked with horizontal made of gel sand gravel between two pedestals;It is in the riprap concrete layer and toe gear shield being distributed up and down that the pedestal, which includes being located at hillside soil layer surface, the part top layer of the hillside soil layer excavates to form ladder, the riprap concrete layer coordinates with ladder, and the vertical anchor pole for being provided with while being fixedly connected with riprap concrete and hillside on the ladder;Native stone is provided between the riprap concrete layer and toe gear shield and fills out slag blanket, has that structural stability is good, is not easy to separate with massif, the advantages of hydraulic pressure bearing strength is high.
Description
Technical field
Hydraulic engineering field is the utility model is related to, more particularly to a kind of cofferdam.
Background technology
Cofferdam refers in hydraulic engineering construction, to build permanent water conservancy projects, the provisional building enclosure built.Its
Effect is to prevent water and soil from entering building and building position, in cofferdam internal drainage, to excavate foundation ditch, build building.One
As be mainly used in waterwork, except as formal building a part in addition to, cofferdam is typically removed after being finished.Build harbour
When, to create the dry construction condition of small range, that is, need to make above-mentioned cofferdam structure.But compared to the lake of land, Jiang Dao
Interior current are increasingly complex, and impact is larger, change its course when especially Jiang Dao makes dam, it is necessary to intercept on a large scale, and
Dykes and dams build that the cycle is longer, i.e., cofferdam must also have very high lasting impact resistance, it is therefore desirable to design a kind of resistance to punching
The cofferdam structure that hitting property is more preferable, intensity is higher.
Utility model content
The purpose of this utility model is to provide a kind of cofferdam, and having can the lasting shock proof advantage of high intensity.
Above-mentioned technical purpose of the present utility model technical scheme is that:
A kind of cofferdam, including both sides excavate shaping hillside soil layer, along hillside soil layer set pedestal and be arranged on two bases
Being blocked with horizontal made of gel sand gravel between seat;It is in that the jackstone being distributed up and down mixes that the pedestal, which includes being located at hillside soil layer surface,
Solidifying soil layer and toe gear shield, the part top layer of the hillside soil layer are excavated to form ladder, and the riprap concrete layer is matched somebody with somebody with ladder
Close, and the vertical anchor pole for being provided with while being fixedly connected with riprap concrete layer and hillside soil layer on the ladder;The jackstone
Native stone, which is provided with, between concrete layer and toe gear shield fills out slag blanket.
Using such scheme, hillside soil layer can be carried out to excavate operation with less with stair-stepping fit system, avoided
Stability that is excessive and destroying massif itself is destroyed to massif, and riprap concrete layer is connected to after upward slope soil layer, it is unlikely
It is excessive in the lower outer local pressure because of abutting portion, and cause tiltedly to be finally resulted in the landing of riprap concrete layer by crush-cutting;
And anchor pole is even more that both are connected as a single entity, to increase resistance moment of torsion;In addition, toe gear shield is due to stable in toe position
Property it is preferable, native stone fills out the Undertaking effect that slag blanket is kept off shield by toe, and reinforced undertaking to riprap concrete layer is abutted, equally
Riprap concrete layer also native stone is filled out slag blanket play a part of compacting, with hillside soil layer is embedding is integrated;So as on the hillside of both sides
Surface forms stable wear surface;On this basis, horizontal the blocking of cement sand and gravel formation is poured between two wear surfaces
With good stability, it is not easy to separate with massif, remains that high intensity carries.
More preferably:The toe gear shield includes the blocks that multiple superimposions form, and the blocks includes
Reinforced gabion and gelling sandy gravel stratum, the gelling sandy gravel stratum are filled and wrap up reinforced gabion.
Using such scheme, reinforced gabion provides tension bearing capacity, and gelling sand stone layer provides measuring body ability, Liang Zhejie
Conjunction can form fabulous water pressure resistance;, and can be with advance comprising and blocks can be with rapid shaping, and the wetting for reducing water is done
Disturb.
More preferably:It is described horizontal to block including multiple blocks being formed by stacking and the metamorphosis for being wrapped in blocks surrounding
Concrete layer.
Using such scheme, a kind of concrete between normality and between rolling, it is set to possess shaking for normal concrete
Smash performance, while but also with the advantage such as grinding concrete construction is fast, intensity is high, blocks that can be with fabulous reinforcement after compound
Between structural strength, to resist stiffness hydraulic pressure.
More preferably:The toe gear shield is provided with five on the vertical vertical section along the solum horizontal of hillside
Individual blocks, five blocks (361) are distributed as two, upper strata and lower floor three, and five blocks (361) shapes
Into breach towards hillside.
Using such scheme, slag blanket formation can be filled out when slag blanket is formed and abutted to native stone towards massif being filled out with native stone
Support holding power, keep force stability.
More preferably:The reinforced gabion includes lid and cage body, and the lid and cage body are included around composition
The framework of steel reinforcement of cuboid and in the distribution bar in the netted square face for being filled in framework of steel reinforcement and being divided into.
Using such scheme, framework of steel reinforcement is main load-carrying construction, and helical pitch is longer, it is necessary to from thicker reinforcing bar, and
The local load-carrying construction of distribution bar, is local pressure train of thought after the completion of pouring, and the stress of stiffener and gelling sandstone joins
System.
More preferably:Four top margins of the cage body are provided with suspension ring.
Using such scheme, suspension ring can carry out suspension hook and put in order to apparatus.
More preferably:The native stone fills out slag blanket surface and is provided with slope protection concrete layer.
Using such scheme, avoid filling out the situations such as slag blanket forms Rolling Stone or punching falls, and fill out slag blanket as after internal layer, due to it
Locally variable, but and can carries out fine motion, can be with fabulous formation anti-seismic structure so that filling out between slag blanket and each layer.
More preferably:The top of the riprap concrete layer, which is set, fills out slag formation roadbed, is provided with the roadbed
With cofferdam road made of normal concrete.
Using such scheme, passage of the cofferdam road as the conveying of blocks or other materials, filling out slag blanket can weaken
Caused vibrations in course of conveying.
In summary, the utility model has the advantages that:
The composition complementary structure that slag blanket and toe gear shield are filled out with riprap concrete layer, native stone is formed on the hillside surface of both sides
Stable wear surface;On this basis, horizontal the blocking of cement sand and gravel formation is poured between two wear surfaces, is had fine
Stability, be not easy to separate with massif, remain high intensity carry.
Brief description of the drawings
Fig. 1 is the structural representation in the cofferdam of embodiment 1;
Fig. 2 is the structural representation of the cage body of embodiment 1;
Fig. 3 is the structural representation of the lid of embodiment 1.
In figure, 1, horizontal block;2nd, hillside soil layer;3rd, pedestal;4th, cage body;5th, lid;31st, cofferdam road;32nd, roadbed;33、
Riprap concrete layer;34th, anchor pole;35th, native stone fills out slag blanket;36th, toe gear shield;361st, blocks;37th, slope protection concrete layer;41、
Distribution bar;42nd, framework of steel reinforcement;43rd, suspension ring.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model
Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but
As long as all protected in the scope of protection of the utility model by Patent Law.
Embodiment 1:A kind of cofferdam, as shown in figure 1, excavating the hillside soil layer 2 of shaping including both sides, being set along hillside soil layer 2
The pedestal 3 put and be arranged between two pedestals 3 horizontal block 1.
It is in that riprap concrete layer 33, the native stone being distributed up and down fill out slag blanket 35 and slope that pedestal 3, which includes being located at the surface of hillside soil layer 2,
Pin gear shield 36.The part top layer of hillside soil layer 2 excavates to form ladder, and riprap concrete layer 33 coordinates with ladder, and is hung down on ladder
To the anchor pole 34 for being provided with while being fixedly connected with riprap concrete layer 33 and hillside soil layer 2.The top of riprap concrete layer 33
Setting fills out slag and forms roadbed 32, is provided with roadbed 32 with cofferdam road 31 made of normal concrete;To provide material conveying
Passage.
It is located at before toe gear shield 36 on the toe of hillside soil layer 2, native stone fills out slag blanket 35 and is arranged on the He of riprap concrete layer 33
Between toe gear shield 36, native stone fills out the surface of slag blanket 35 and is provided with slope protection concrete layer 37.
Toe gear shield 36 and horizontal block include the blocks 361 that forms of multiple superimposions, toe gear shield 36 it is vertical in
Five blocks 361 are provided with vertical section along the level of hillside soil layer 2, five blocks 361 are distributed as two, upper strata
Lower floor three, and the breach on upper strata is towards hillside soil layer 2, to strengthen support ability.
It is horizontal to block the 1 abnormal concrete layer for being also wrapped in the surrounding of blocks 361, to strengthen bearing capacity.Blocks 361
Including reinforced gabion and gelling sandy gravel stratum, gelling sandy gravel stratum is filled and wraps up reinforced gabion.
Reference picture 2 and Fig. 3, reinforced gabion include lid 5 and cage body 4, and lid 5 and cage body 4 include rectangular around forming
The framework of steel reinforcement 42 of body and in the distribution bar 41 in the netted square face for being filled in framework of steel reinforcement 42 and being divided into.Four of cage body 4
Top margin is provided with suspension ring 43, in order to hang operation.
Claims (8)
1. a kind of cofferdam, it is characterized in that:Hillside soil layer (2), the pedestal set along hillside soil layer (2) of shaping are excavated including both sides
(3) and it is arranged on being blocked (1) with horizontal made of gel sand gravel between two pedestals (3);The pedestal (3) includes being located at hillside soil
In riprap concrete layer (33) and toe the gear shield (36) being distributed up and down, the part table of the hillside soil layer (2) on layer (2) surface
Layer excavates to form ladder, and the riprap concrete layer (33) and ladder coordinate, and on the ladder it is vertical be provided with and meanwhile with throwing
The anchor pole (34) that stone concrete layer (33) is fixedly connected with hillside soil layer (2);The riprap concrete layer (33) and toe gear shield
(36) native stone is provided between and fills out slag blanket (35).
2. a kind of cofferdam according to claim 1, it is characterized in that:Toe gear shield (36) include multiple superimposions and
Into blocks (361), the blocks (361) include reinforced gabion and gelling sandy gravel stratum, it is described gelling sandy gravel stratum filling simultaneously
Wrap up reinforced gabion.
3. a kind of cofferdam according to claim 2, it is characterized in that:Described horizontal block (1) includes multiple bulks being formed by stacking
Body (361) and the abnormal concrete layer for being wrapped in blocks (361) surrounding.
4. a kind of cofferdam according to claim 2, it is characterized in that:The toe gear shield (36) is vertical in hillside soil layer
(2) five blocks (361) are provided with the vertical section along level, five blocks (361) are distributed as upper strata two
Individual and lower floor three, and the breach that is formed of five blocks (361) is towards hillside.
5. a kind of cofferdam according to claim 4, it is characterized in that:The reinforced gabion includes lid (5) and cage body (4),
The lid (5) and cage body (4) include around the framework of steel reinforcement (42) for forming cuboid and are filled in framework of steel reinforcement in netted
(42) distribution bar (41) in the square face being divided into.
6. a kind of cofferdam according to claim 5, it is characterized in that:Four top margins of the cage body (4) are provided with suspension ring
(43)。
7. a kind of cofferdam according to claim 1, it is characterized in that:The native stone fills out slag blanket (35) surface and is provided with bank protection and mixes
Solidifying soil layer (37).
8. a kind of cofferdam according to claim 1, it is characterized in that:The top of the riprap concrete layer (33) sets and fills out slag
Roadbed (32) is formed, is provided with the roadbed (32) with cofferdam road (31) made of normal concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720671521.9U CN206844135U (en) | 2017-06-10 | 2017-06-10 | A kind of cofferdam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720671521.9U CN206844135U (en) | 2017-06-10 | 2017-06-10 | A kind of cofferdam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206844135U true CN206844135U (en) | 2018-01-05 |
Family
ID=60799531
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720671521.9U Active CN206844135U (en) | 2017-06-10 | 2017-06-10 | A kind of cofferdam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206844135U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112030878A (en) * | 2020-09-03 | 2020-12-04 | 四川省公路规划勘察设计研究院有限公司 | Rapid rush-to-pass construction method along river subgrade water damage |
CN113529521A (en) * | 2021-07-10 | 2021-10-22 | 南京华宇建设股份有限公司 | Soft soil roadbed reinforced structure |
-
2017
- 2017-06-10 CN CN201720671521.9U patent/CN206844135U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112030878A (en) * | 2020-09-03 | 2020-12-04 | 四川省公路规划勘察设计研究院有限公司 | Rapid rush-to-pass construction method along river subgrade water damage |
CN113529521A (en) * | 2021-07-10 | 2021-10-22 | 南京华宇建设股份有限公司 | Soft soil roadbed reinforced structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107419630A (en) | A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction | |
CN103758113B (en) | A kind of grid encloses the anti-liquefied foundation reinforcement means of hoop | |
CN101270579B (en) | Foundation pit guard method for expansion construction from deep foundation pit to shallow foundation pit | |
CN206902488U (en) | A kind of soft soil foundation high-filled embankment of effectively control settlement after construction | |
CN211200423U (en) | Civil engineering side slope protection reinforced structure | |
CN106400744B (en) | A kind of side slope comprehensive treatment structure and its construction method for preventing river channel erosion | |
CN110485313A (en) | Bridge pier stream dead zone reinforcement means | |
CN103437370A (en) | Method and supporting structure for slip resisting and soil retaining of abrupt slope | |
CN206844135U (en) | A kind of cofferdam | |
CN107503323B (en) | A kind of method of construction of ecological slope protection | |
CN108867552A (en) | A kind of riverbank peg board revetment structure and revetment method | |
CN107816050A (en) | A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method | |
CN111270698A (en) | Protective structure for exposed diseases of bridge pile foundation in sand-mining river channel in mountainous area and construction method of protective structure | |
CN208934006U (en) | The double-deck barrier wall structure | |
CN207582477U (en) | A kind of concrete cofferdam and earth rock cofferdam combined cofferdam | |
CN113818402A (en) | Reinforcing and reinforcing structure of clay core rockfill dam and construction method thereof | |
CN203729309U (en) | Support system with combined double-row piles combined with vertical prestressed anchor bolts | |
KR20160025670A (en) | Repair-reinforcement method of the reservoir | |
CN106567365A (en) | Earth and rockfill dam longitudinal reinforcement construction method | |
CN110295573A (en) | Adapt to the channel revetment project post-evaluation structure of construction time severe hydrometeorological condition | |
CN108104113A (en) | Exceeded ruggedized construction and construction method are deformed for friction pile in work progress | |
CN108930253B (en) | Ecological flexible slope protection structure for river channel and construction method | |
CN211872840U (en) | Face combination retaining wall structure forever among urban hydraulic engineering | |
CN102767159A (en) | Strengthening method for existing revetments of urban river | |
CN211735258U (en) | Pile type rock-fill angle bead |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |