CN107816050A - A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method - Google Patents

A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method Download PDF

Info

Publication number
CN107816050A
CN107816050A CN201711288950.9A CN201711288950A CN107816050A CN 107816050 A CN107816050 A CN 107816050A CN 201711288950 A CN201711288950 A CN 201711288950A CN 107816050 A CN107816050 A CN 107816050A
Authority
CN
China
Prior art keywords
cofferdam
vertical
laid
built
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711288950.9A
Other languages
Chinese (zh)
Other versions
CN107816050B (en
Inventor
宋成年
惠建伟
皇新波
李新亮
欧甫
郝龙
李涛
马熊
谢勇
李重元
董珂
张禄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority to CN201711288950.9A priority Critical patent/CN107816050B/en
Publication of CN107816050A publication Critical patent/CN107816050A/en
Application granted granted Critical
Publication of CN107816050B publication Critical patent/CN107816050B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes
    • E02B3/108Temporary dykes with a filling, e.g. filled by water or sand
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of concrete cofferdam and earth rock cofferdam combined cofferdam, the combined cofferdam includes the vertical concrete cofferdam being laid in river course and two horizontal earth rock cofferdams being laid in respectively between vertical concrete cofferdam both ends and riverbank.Horizontal earth-rock cofferdam structure stabilization in the combined cofferdam, ability to resist splash erosion are strong, and itself earth flow can be avoided to lose polluted-water and foundation ditch.The invention also discloses a kind of construction method in combinations thereof cofferdam, the construction method includes:Step 1: Temporary Cofferdam is built;Step 2: vertical concrete cofferdam is built;Step 3: horizontal earth rock cofferdam is built.In the construction method, when horizontal earth rock cofferdam is built, by first building rockfill, interior heap body and outer heap body are built again, avoid during interior heap body and outer heap body build, a large amount of earth and stone materials that tumble cause later stage water pollution into water body and foundation ditch, and once directly construct bottom plugging structure and vertical waterproof construction, improve efficiency of construction.

Description

A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method
Technical field
The invention belongs to construction of hydro project technical field, more particularly to a kind of concrete cofferdam and earth rock cofferdam combination to enclose Weir and its construction method.
Background technology
Earth rock cofferdam is to build the cofferdam that weir forms by native stone.Earth rock cofferdam can be combined with dam of closure, be abandoned using excavation Slag, and directly can excavate carrier loader using major project and carry out mechanization rapid construction, it is the most widely used cofferdam in China Form.But earth rock cofferdam erosion resistibility is relatively low, and floor space is big, is typically used for transverse cofferdam.Concrete cofferdam is commonly used It is dash head height in the characteristics of water-control project built in batholith soil, this cofferdam, bottom width is small, and impact resistance is big, weir Top can overflow, especially in segmentation cofferdam method water conservancy diversion construction, with the longitudinal cofferdam of concreting can with two sides dash, and A part as dam body or lock chamber body can be combined with permanent building, but concrete cofferdam cost is high.So occur one The combined cofferdam with concrete cofferdam combination earth rock cofferdam is planted, concrete cofferdam is as longitudinal cofferdam, native stone in the combined cofferdam Cofferdam is as transverse cofferdam.
In the prior art to being had the following disadvantages in the construction method for the combined cofferdam:
1. the earth rock cofferdam weir body in the combined cofferdam fills, earth and stone material, which largely tumbles, causes later stage water pollution.
2. the vertical waterproof construction of the earth rock cofferdam in the combined cofferdam is to use the bottom-up construction party built paragraph by paragraph Method is built, and often builds one section of vertical waterproof construction, it is necessary in the vertical waterproof construction both sides constructing soil stone of the section, treat native stone Fill to the vertical waterproof construction height of the section, next section of vertical waterproof construction could be built, the construction method has construction speed The problem of degree is slow, construction is inconvenient.
The combined cofferdam configuration aspects have the following disadvantages in the prior art:
1. the earth rock cofferdam upstream face water resistant stream scouring capability in the combined cofferdam is weak.
2. earth rock cofferdam side slope in the combined cofferdam by rainwater and current scour can cause mud pollution construction foundation pit and Water body.
The content of the invention
In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is that provide a kind of coagulation fortifield village Weir and earth rock cofferdam combined cofferdam, gabion mask and stone armour layer are set by the upstream face in horizontal earth rock cofferdam, improved Earth rock cofferdam upstream face water resistant stream scouring capability, avoids and is caused mud pollution water body by rainwater and current scour, by The domatic laying turf of interior heap body of horizontal earth rock cofferdam, avoids and is caused mud pollution foundation ditch by rainwater and current scour, pass through Rockfill is set at the weir body toe of horizontal earth rock cofferdam, strengthens the toe of horizontal earth rock cofferdam, avoids laterally native stone Earth flow at the toe in cofferdam loses, and improves the stability of horizontal earth rock cofferdam.Present invention also offers a kind of combinations thereof The construction method in cofferdam, the construction method by when horizontal earth rock cofferdam is built, first building rockfill, then build interior heap body and Outer heap body, during avoiding interior heap body and the build of outer heap body, largely tumble earth and stone material and cause later stage water into water body and foundation ditch Pollution, by when horizontal earth rock cofferdam is built, once directly constructing bottom plugging structure and vertical waterproof construction, Ran Houzai The weir body for carrying out horizontal earth rock cofferdam fills, and improves efficiency of construction.
In order to solve the above technical problems, the technical solution adopted by the present invention is:A kind of concrete cofferdam and earth rock cofferdam group Surround weir, it is characterised in that:Vertical concrete is laid in respectively including the vertical concrete cofferdam being laid in river course and two Horizontal earth rock cofferdam between cofferdam both ends and riverbank, the vertical concrete cofferdam is parallel with the river course, the transverse direction Earth rock cofferdam and the river course are perpendicular;The horizontal earth rock cofferdam includes being embedded in bottom plugging structure in riverbed, vertical Waterproof construction and weir body;The bottom plugging structure and vertical waterproof construction be laid in vertical concrete cofferdam end with Between riverbank and vertical concrete cofferdam is each perpendicular to, the vertical waterproof construction is laid on the bottom plugging structure vertically Side, the bottom of the vertical waterproof construction are stretched to inside the bottom plugging structure, and the weir body includes being laid in vertically anti- Interior heap body and outer heap body inside and outside water-bound;The interior heap body and outer heap body are native clitter body;The native clitter body Upper surface is gradually outward-dipping domatic from top to bottom, and the height of the vertical waterproof construction is not less than the native clitter body Highly;
Rockfill is laid with the domatic toe of the native clitter body, the rockfill is by vertical reinforcement cage and is filled in Stone composition in the vertical reinforcement cage, the vertical reinforcement cage be laid in vertical concrete cofferdam end and riverbank it Between and be transversely to the machine direction concrete cofferdam;
The domatic of the outer heap body is upstream face, and the domatic bottom of the outer heap body is laid with gabion mask, the gabion Ordinary water level of the height of mask not less than river in the river course;The gabion mask is by the oblique steel along the outer domatic laying of heap body Muscle cage and the stone composition being filled in the oblique reinforcing bar cage, the top of the vertical reinforcement cage and the oblique reinforcing bar cage Bottom connects;
The top of the gabion mask and stone armour layer is laid with along outer heap body is domatic, the stone armour layer is by laying The outer heap body it is domatic on multiple mask stones composition;
Between the gap of the two neighboring mask stone and the interior heap body it is domatic on be all covered with turf.
A kind of above-mentioned concrete cofferdam and earth rock cofferdam combined cofferdam, it is characterised in that:The vertical waterproof construction bag Include the geomembrane laid vertically and the protector protected geomembrane;The protector includes being laid in geomembrane two Two row's vertical rods of side, often arrange and backplate are laid between the vertical rod and geomembrane, and two backplates are clamped in geomembrane Both sides and it is clamped between vertical rod described in two rows;The size of the backplate plate face is not less than the size of geomembrane;The vertical rod, shield The bottom of plate and geomembrane is stretched to inside the plugging structure of the bottom.
A kind of above-mentioned concrete cofferdam and earth rock cofferdam combined cofferdam, it is characterised in that:The bottom plugging structure bag Two cut-pff walls for being laid in vertical waterproof construction both sides and being embedded in the riverbed are included, the outside edge of each cut-pff wall The polylith slabstone that the length direction of cut-pff wall is in a row laid, slabstone described in polylith are in parallel laying with cut-pff wall, same antiseepage Dryness argillic horizon is laid with described in polylith on the outside of wall between the outside of slabstone and the riverbed.
A kind of above-mentioned concrete cofferdam and earth rock cofferdam combined cofferdam, it is characterised in that:The native clitter body includes cloth The argillic horizon of vertical waterproof construction side and the native rock layers being laid on the outside of argillic horizon are located at, between the argillic horizon and native rock layers Loaded filter is laid with, is embedded in the middle part of the vertical rod in the argillic horizon.
A kind of above-mentioned concrete cofferdam and earth rock cofferdam combined cofferdam, it is characterised in that:The vertical concrete cofferdam Vertically offer vertical groove on two end faces, the leading edge of the geomembrane and two backplates is embedded in In the vertical groove.
Present invention also offers a kind of construction method in combinations thereof cofferdam, it is characterised in that:Comprise the following steps:
Step 1: Temporary Cofferdam is built:Construction Temporary Cofferdam on the outside of along combined cofferdam construction location of constructing, and by described in Water on the inside of Temporary Cofferdam is drained;
Step 2: vertical concrete cofferdam is built:Routinely concrete cofferdam process for constructing builds vertical concrete cofferdam;
Step 3: horizontal earth rock cofferdam is built:An institute is respectively built between the both ends in vertical concrete cofferdam and riverbank State horizontal earth rock cofferdam;Each horizontal earth rock cofferdam, which is built, to be comprised the following steps:
Step 301, surveying setting-out:According to constructed horizontal earth rock cofferdam design drawing, surveyed in Temporary Cofferdam on riverbed Amount setting-out goes out profile outside line, profile interior lines and the cofferdam center line of horizontal earth rock cofferdam, the cofferdam center line be located at profile outside line with Between profile interior lines, the distance between the profile outside line and cofferdam center line and the distance between profile interior lines and cofferdam center line phase Together;
Step 302, bottom plugging structure and vertical waterproof construction are built:Shuting is excavated along cofferdam center line, at described section Bottom plugging structure is built in tank;Vertical waterproof construction is built along vertical plane residing for the center line of cofferdam;
Step 303, rockfill are built:Rockfill is built along the inner side of the inner side of profile outside line and profile interior lines;
Step 304, weir body fill:Interior heap body and outer heap are built respectively in the inner side and outer side of the vertical waterproof construction Body;
Step 305, upstream face side slope gabion mask are built:Gabion mask is built in the lower slope of the outer heap body;
Step 306, ecological safeguard structure are built:Above gabion mask stone is formed along the domatic laying stone of outer heap body Armour layer, then in stone armour layer between the gap of stone and interior heap body domatic laying turf.
Combinations of the above cofferdam construction method, it is characterised in that:In step 302, the bottom plugging structure includes laying In vertical waterproof construction both sides and two cut-pff walls being embedded in the riverbed, the outside of each cut-pff wall is along cut-pff wall The polylith slabstone in a row laid of length direction, slabstone described in polylith is in parallel laying with cut-pff wall, on the outside of same cut-pff wall Polylith described in slabstone outside and the riverbed between be laid with dryness argillic horizon;
Comprise the following steps when being constructed to the bottom plugging structure:
Step 3021, lay multiple slabstones, front and rear two adjacent stones from the front to the back along the side wall of the shuting Dryness clay has been filled at gap between plate;Reserved 0.5m between each slabstone and the side wall of the shuting~ 0.7m gaps;
Step 3022, fill up between each slabstone and the side wall of the shuting dryness clay and form dryness and glue Soil layer
Step 3023, vertical waterproof construction of being constructed along cofferdam center line, the bottom of vertical waterproof construction are laid in described intercept water The bottom of groove;
Step 3024, the casting concrete between vertical waterproof construction and each slabstone, the shape after concrete final set Into two cut-pff walls, the front end of the cut-pff wall pours with vertical concrete cofferdam to be integrated.
Combinations of the above cofferdam construction method, it is characterised in that:Riverbed residing for horizontal earth rock cofferdam of constructing is karst Landforms riverbed, when shuting described in step 302 excavates, riverbed basement rock is broken into pieces by quartering hammer first, then dig out by digging machine Quartering hammer breaks the particle that riverbed basement rock is formed into pieces, forms the shuting.
Combinations of the above cofferdam construction method, it is characterised in that:In step 2, the vertical concrete after the completion of build encloses The middle part of weir Liang Ge end faces vertically opens up vertical groove;In step 302, the vertical waterproof construction includes vertical cloth If geomembrane and the protector that is protected geomembrane;The protector includes being laid in two rows of geomembrane both sides Vertical rod, often arrange and backplate is laid between the vertical rod and geomembrane, two backplates are clamped in both sides and the card of geomembrane Tightly between vertical rod described in two rows;The size of the backplate plate face is not less than the size of geomembrane;The vertical rod, backplate and geotechnique The bottom of film is stretched to inside the bottom plugging structure;In step 302, when building vertical waterproof construction, by the geotechnique The leading edge of film and two backplates is embedded in the vertical groove.
Combinations of the above cofferdam construction method, it is characterised in that:Rockfill is built in step 303 to comprise the following steps:
Step 3031:Packing sedimentation by throwing stones construction is carried out to rockfill construction area, forms the ground that rockfill is built;
Step 3032:On the ground that step 3031 is built, vertical reinforcement cage described in colligation, then to the vertical reinforcement cage Inside fill full stone and form rockfill.
The present invention has advantages below compared with prior art:
1st, the present invention sets gabion mask and stone armour layer by horizontal earth rock cofferdam in upstream face, improves native stone and encloses Weir upstream face water resistant stream scouring capability, avoids and is caused mud pollution water body by rainwater and current scour.
2nd, the present invention avoids interior heap body by rainwater and water by the domatic laying turf of interior heap body in horizontal earth rock cofferdam Stream, which washes away, causes mud pollution foundation ditch.
3rd, the present invention strengthens the toe of horizontal earth rock cofferdam by setting rockfill at horizontal earth rock cofferdam toe, Avoid the earth flow at the toe of horizontal earth rock cofferdam to lose, improve the stability of horizontal earth rock cofferdam.
4th, when horizontal earth rock cofferdam of the present invention is built, by first building rockfill, then interior heap body and outer heap body are built, During avoiding interior heap body and the build of outer heap body, largely tumble earth and stone material and cause later stage water pollution into water body and foundation ditch.
5th, when horizontal earth rock cofferdam of the present invention is built, bottom plugging structure and vertical waterproof knot are once directly constructed Structure, weir body is then carried out again and is filled, improves efficiency of construction.
In summary, in combined cofferdam of the present invention, gabion mask is set by the upstream face in horizontal earth rock cofferdam With stone armour layer, improve earth rock cofferdam upstream face water resistant stream scouring capability, avoid earth rock cofferdam upstream face by rainwater and Current scour causes mud pollution water body, by the domatic laying turf of interior heap body in horizontal earth rock cofferdam, avoids interior heap body It is domatic to be caused mud pollution foundation ditch by rainwater and current scour, by setting enrockment at the weir body toe of horizontal earth rock cofferdam Body, the toe of horizontal earth rock cofferdam is strengthened, avoid the earth flow at the toe of horizontal earth rock cofferdam and lose, improve horizontal soil The stability in stone cofferdam.In combined cofferdam construction method of the present invention, by when horizontal earth rock cofferdam is built, first building heap Shi Ti, then interior heap body and outer heap body are built, during avoiding interior heap body and the build of outer heap body, largely tumble earth and stone material and enter water Body and foundation ditch cause later stage water pollution, by when horizontal earth rock cofferdam is built, once directly construct bottom plugging structure and Vertical waterproof construction, the weir body for then carrying out horizontal earth rock cofferdam again fill, and improve efficiency of construction.
Below by drawings and examples, technical scheme is described in further detail.
Brief description of the drawings
Fig. 1 is the structural representation of combined cofferdam of the present invention.
Fig. 2 is the cross-sectional structure schematic diagram of horizontal earth rock cofferdam in the present invention.
Fig. 3 is enlarged drawing at Fig. 2 A.
Fig. 4 is the structural representation that geomembrane and backplate are embedded in vertical concrete cofferdam in the present invention.
Fig. 5 is the layout position illustration of vertical rod in the present invention.
Fig. 6 is the structural representation of stone armour layer in the present invention.
Fig. 7 is the construction method flow chart of combined cofferdam in the present invention.
Fig. 8 is the full-size drawing that horizontal earth rock cofferdam builds front profile outside line, profile interior lines and cofferdam center line in the present invention.
Description of reference numerals:
1-Temporary Cofferdam;The outside line of 2-profile;3-profile interior lines;
4-cofferdam center line;5-cut-pff wall;6-rockfill;
7-vertical waterproof construction;7-1-geomembrane;7-2-backplate;
8-interior heap body;9-outer heap body;10-argillic horizon;
11-loaded filter;12-native rock layers;13-slabstone;
14-dryness argillic horizon;15-vertical rod;16-gabion mask;
17-stone armour layer;18-vertical concrete cofferdam;19-turf.
Embodiment
As shown in figure 1, a kind of concrete cofferdam and earth rock cofferdam combined cofferdam, including the longitudinal coagulation being laid in river course Earth cofferdam 18 and two horizontal earth rock cofferdams being laid in respectively between the both ends of vertical concrete cofferdam 18 and riverbank, the longitudinal direction Concrete cofferdam 18 is parallel with the river course, and the horizontal earth rock cofferdam and the river course are perpendicular;
As shown in Fig. 2 the horizontal earth rock cofferdam includes bottom plugging structure, the vertical waterproof construction being embedded in riverbed 7 and weir body;The bottom plugging structure and vertical waterproof construction 7 are laid in the end of vertical concrete cofferdam 18 and riverbank Between and be each perpendicular to vertical concrete cofferdam 18, the vertical waterproof construction 7 is laid on the bottom plugging structure vertically Side, the bottom of the vertical waterproof construction 7 are stretched to inside the bottom plugging structure, and the weir body includes being laid in vertically anti- Interior heap body 8 and outer heap body 9 inside and outside water-bound 7;The interior heap body 8 and outer heap body 9 are native clitter body;The native clitter To be gradually outward-dipping domatic from top to bottom, the height of the vertical waterproof construction 7 is not less than the native stone for the upper surface of body The height of heap body;
It should be noted that bottom plugging structure and vertical waterproof construction 7 constitute the waterproof of the horizontal earth rock cofferdam Vertical waterproof construction 7 is clamped in centre by structure, interior heap body 8 and outer heap body 9, ensure that the stabilization of vertical waterproof construction 7.Bottom Plugging structure, vertical waterproof construction 7 and weir body three synergy, have been effectively ensured the dash of the whole horizontal earth rock cofferdam Effect;
As shown in Fig. 2 being laid with rockfill 6 at the domatic toe of the native clitter body, the rockfill 6 is by vertical steel Muscle cage and the stone composition being filled in the vertical reinforcement cage, the vertical reinforcement cage are laid in the vertical concrete cofferdam Between 18 ends and riverbank and it is transversely to the machine direction concrete cofferdam 18;
It should be noted that the shape of cross section of the rockfill 6 is trapezoid cross section;Because of the soil at the toe of native clitter body Body is easily lost in, so forming rockfill 6 to native stone using vertical reinforcement cage and the stone being filled in the vertical reinforcement cage Corner protector is carried out at the toe of heap body, can effectively reduce the loss of the soil body;The vertical reinforcement cage makes stone firmly banding Stone is difficult to be moved, and ensure that the stability of itself of rockfill 6.
As shown in Fig. 2 the domatic of the outer heap body 9 is upstream face, the domatic bottom of the outer heap body 9 is laid with gabion shield Face 16, the height of the gabion mask 16 are not less than the ordinary water level in river in the river course;The gabion mask 16 is by along outer heap The oblique reinforcing bar cage of 9 domatic laying of body and the stone composition being filled in the oblique reinforcing bar cage, the top of the vertical reinforcement cage Portion is connected with the bottom of the oblique reinforcing bar cage;
It should be noted that the oblique reinforcing bar cage, by the firmly banding of the stone in it, it is difficult to be moved to make stone, Stone is set not to be lost in when by current scour with current;Gabion mask 16 is laid in the outer lower slope of heap body 9, makes current Will not directly be flushed on outer heap body 9, and gabion mask 16 using deadweight be firmly compacted outer heap body 9 it is domatic on, make The ability of the domatic anti-current scour of outer heap body 9 is greatly improved;
As shown in Fig. 2 the top of the gabion mask 16 and it is laid with stone armour layer 17 along outer heap body 9 is domatic, it is described Stone armour layer 17 by be laid on the outer heap body 9 it is domatic on multiple mask stones form;
It should be noted that stone armour layer 17 makes the rainwater extraneous factor such as blow not to be applied directly to the outer slope of heap body 9 Face, and multiple mask stones of stone armour layer 17 have been compacted the domatic soil body of outer heap body 9, make the domatic anti-rainwater of outer heap body 9 The ability washed away is greatly improved;
As shown in Figure 2 and Figure 6, between the gap of the two neighboring mask stone and the interior heap body 8 it is domatic on It is all covered with turf 19;The turf 19 covered between the gap of the two neighboring mask stone, can prevent erosion The mask stone is caused to tumble, and the turf 19 covered can purify air, can improve the air quality of job site.
It should be noted that setting gabion mask 16 and stone armour layer 17 by the outer upstream face of heap body 9, improve and meet water Face water resistant stream scouring capability, the native stone for avoiding outer heap body 9 is caused mud pollution water body by rainwater and current scour, by inside The domatic laying turf 19 of heap body 8, the native stone for avoiding interior heap body 8 are caused in mud pollution combined cofferdam by rainwater and current scour Foundation ditch, by the toe of outer heap body 9 and interior heap body 8 set rockfill 6 strengthen toe, avoid outer heap body 9 and interior heap Earth flow at the toe of body 8 loses, and improves the stability of horizontal earth rock cofferdam.
As shown in Figure 3 and Figure 5, the vertical waterproof construction 7 includes the geomembrane 7-1 laid vertically and to geomembrane 7-1 The protector protected;The protector includes being laid in two row's vertical rods 15 of geomembrane 7-1 both sides, often arranges described vertical Backplate 7-2, two backplate 7-2 are laid between bar 15 and geomembrane 7-1 and is clamped in geomembrane 7-1 both sides and clamping Between vertical rod 15 described in two rows;The size of the backplate 7-2 plate faces is not less than geomembrane 7-1 size;The vertical rod 15, shield Plate 7-2 and geomembrane 7-1 bottom are stretched to inside the plugging structure of the bottom.
It should be noted that by laying two row's vertical rods 15 and two backplate 7-2, maintain geomembrane 7-1 perpendicular Straight state, and two backplate 7-2 are protected to geomembrane 7-1, avoid outer heap body 9 and the interior soil body of heap body 8 directly connects Touch geomembrane 7-1, it is therefore prevented that the grit pad that the insect in the soil body breaks by the teeth in geomembrane 7-1 or the soil body breaks geomembrane 7-1, finally Geomembrane 7-1 waterproof is caused to fail.
As shown in figure 3, the bottom plugging structure includes being laid in the vertical both sides of waterproof construction 7 and is embedded in the riverbed Two interior cut-pff walls 5, the polylith slabstone 13 that each length direction of the outside of the cut-pff wall 5 along cut-pff wall 5 is in a row laid, Slabstone 13 described in polylith is in parallel laying with cut-pff wall 5, the outside of slabstone 13 and institute described in the polylith in the same outside of cut-pff wall 5 State and be laid with dryness argillic horizon 14 between riverbed.
It should be noted that the cut-pff wall 5 is concrete walls, the lower end of vertical rod 15 is inserted into two respectively described in two rows In the cut-pff wall 5, two the backplate 7-2 and geomembrane 7-1 bottom are clamped between two cut-pff walls 5;By by institute The bottom for stating vertical waterproof construction 7 is stretched in the bottom plugging structure, not only realizes vertical waterproof construction 7 and the bottom Portion's plugging structure collaboration carries out waterproof work, and secures vertical waterproof construction 7 using the bottom plugging structure, improves The stability of vertical waterproof construction 7.
As shown in Fig. 2 the native clitter body includes being laid in the argillic horizon 10 of the vertical side of waterproof construction 7 and is laid in viscous The native rock layers 12 in the outside of soil layer 10, are laid with loaded filter 11, in the vertical rod 15 between the argillic horizon 10 and native rock layers 12 Portion is embedded in the argillic horizon 10.
It should be noted that the middle part of the vertical rod 15 is embedded in the argillic horizon 10, vertical rod 15 serves anchoring institute The effect of the soil body of argillic horizon 10 is stated, improves the stability of the weir body.
As shown in figure 4, vertical groove is vertically offered on described 18 two end faces in vertical concrete cofferdam, institute The leading edge for stating geomembrane 7-1 and two backplate 7-2 is embedded in the vertical groove.
It is it should be noted that described by the way that the geomembrane 7-1 and two backplate 7-2 leading edge are embedded in In vertical groove, it is therefore prevented that vertical concrete cofferdam 18 and the infiltration of horizontal earth rock cofferdam seam crossing.
As shown in fig. 7, a kind of combinations of the above cofferdam construction method, comprises the following steps:
Step 1: Temporary Cofferdam is built:As shown in figure 8, enclosed temporarily along construction on the outside of constructed combined cofferdam construction location Weir 1, and the water of the inner side of Temporary Cofferdam 1 is drained;
Routinely Temporary Cofferdam construction method construction Temporary Cofferdam 1, Temporary Cofferdam 1 can be steel sheet-pile cofferdam, can also The water-retaining structure formed for jackstone;
Step 2: vertical concrete cofferdam is built:Routinely concrete cofferdam process for constructing builds vertical concrete cofferdam 18;And vertically open up a vertical groove at the middle part of 18 two end faces in vertical concrete cofferdam
Step 3: horizontal earth rock cofferdam is built:It is each between the both ends in vertical concrete cofferdam 18 and riverbank to build one The horizontal earth rock cofferdam;Each horizontal earth rock cofferdam, which is built, to be comprised the following steps:
Step 301, surveying setting-out:As shown in figure 8, according to constructed horizontal earth rock cofferdam design drawing, in Temporary Cofferdam 1 Surveying and locating goes out profile outside line 2, profile interior lines 3 and the cofferdam center line 4 of horizontal earth rock cofferdam, the cofferdam center line 4 on interior riverbed Between profile outside line 2 and profile interior lines 3, the distance between the profile outside line 2 and cofferdam center line 4 and profile interior lines 3 with The distance between cofferdam center line 4 is identical;
Step 302, bottom plugging structure and vertical waterproof construction are built:Shuting is excavated along cofferdam center line 4, at described section Bottom plugging structure is built in tank;Vertical waterproof construction 7 is built along vertical plane residing for cofferdam center line 4;
Step 303, rockfill are built:Rockfill 6 is built along the inner side of the inner side of profile outside line 2 and profile interior lines 3;
Step 304, weir body fill:Interior heap body 8 and outer heap are built respectively in the inner side and outer side of the vertical waterproof construction 7 Body 9;
Step 305, upstream face side slope gabion mask are built:Gabion mask 16 is built in the lower slope of the outer heap body 9;
Step 306, ecological safeguard structure are built:Formed above gabion mask 16 along the domatic laying stone of outer heap body 9 Stone armour layer 17, then in stone armour layer 17 between the gap of stone and interior heap body 8 domatic laying turf 19.
It should be noted that by when horizontal earth rock cofferdam is built, rockfill 6 is first built, then builds interior heap body 8 and outer The earth and stone material that heap body 9, interior heap body 8 and outer heap body 9 largely tumble during building is stopped by rockfill 6, it is therefore prevented that largely tumbles Earth and stone material enters water body and foundation ditch causes later stage water pollution, by when horizontal earth rock cofferdam is built, once directly constructing bottom Portion's plugging structure and vertical waterproof construction 7, the weir body for then carrying out horizontal earth rock cofferdam again fill, and improve efficiency of construction. After the completion of vertical waterproof construction 7 is built, the native clitter body is built simultaneously in the vertical both sides of waterproof construction 7, makes the native clitter Body directly can once fill completion from bottom to top, need not stop halfway, can greatly improve efficiency of construction.
In the present embodiment, comprise the following steps when being constructed to the bottom plugging structure:
Step 3021, multiple slabstones 13 are laid from the front to the back along the side wall of the shuting, described in front and rear adjacent two Dryness clay has been filled at gap between slabstone 13;It is reserved between each slabstone 13 and the side wall of the shuting 0.5m~0.7m gaps;
Step 3022, dryness clay formation dryness is filled up between each slabstone 13 and the side wall of the shuting Argillic horizon 14
Step 3023, vertical waterproof construction 7 of being constructed along perpendicular residing for cofferdam center line 4, the bottom of vertical waterproof construction 7 It is laid in the bottom of the shuting;
Vertical waterproof construction 7 is built to comprise the following steps:
Step A, as shown in figure 5, each vertical laying row's vertical rod 15, the bottom position of vertical rod 15 along the both sides of cofferdam center line 4 In the bottom of the shuting, in the soil body for the bottom that the bottom of vertical rod 15 can also be inserted to the shuting;
Step B, and then by the geomembrane 7-1 and two backplate 7-2 between being inserted into vertical rod 15 described in two rows, and The geomembrane 7-1 and two backplate 7-2 leading edge be embedded in the end face of vertical concrete cofferdam 18 open up it is vertical In groove;The geomembrane 7-1 is to be clamped in advance between two backplate 7-2;
Step 3024, the casting concrete between two backplate 7-2 and each slabstone 13, treat concrete final set Two cut-pff walls 5 are formed afterwards, and the front end of the cut-pff wall 5 pours with vertical concrete cofferdam 18 to be integrated, vertical rod described in two rows 15 bottom is cast in two cut-pff walls 5 respectively.
It should be noted that pass through the multiple slabstones 13 and dryness argillic horizon 14 of first constructing, it is therefore prevented that the mud flow on riverbed Enter into the shuting, avoid and cause the later stage that Concrete contamination and the bottom of cut-pff wall 5 poured out occurs when pouring cut-pff wall 5 The problem of portion is unstable.By first constructing, vertical waterproof construction 7 pours two cut-pff walls 5 again, makes the bottom of vertical waterproof construction 7 It can be securely fixed by two cut-pff walls 5.
It should be noted that by laying two row's vertical rods 15 and two backplate 7-2, maintain geomembrane 7-1 perpendicular Straight state, make vertical waterproof construction 7 does not fill piecewise build in needs with weir body, can directly will before weir body is filled Vertical waterproof construction 7, which is built, to be completed, and filling for weir body is not influenceed by vertical waterproof construction 7 build progress, is made weir body Fill and can once complete, effectively raise efficiency of construction.
In the present embodiment, riverbed residing for horizontal earth rock cofferdam of constructing is karst landform riverbed, is cut described in step 302 When tank excavates, riverbed basement rock is broken into pieces by quartering hammer first, then quartering hammer is dug out by digging machine and breaks what riverbed basement rock was formed into pieces Particle, form the shuting.
It should be noted that breaking riverbed basement rock into pieces by quartering hammer, then quartering hammer is dug out by digging machine and breaks riverbed basement rock into pieces The method of the particle of formation, end to form the shuting, the disturbance to riverbed rock mass can be reduced, because being karst landform river Bed, according to the method for original Blasting Excavation shuting, easily causes riverbed large area and bursts apart, therefore breaks riverbed into pieces using quartering hammer Basement rock, then the method that quartering hammer breaks the particle that riverbed basement rock is formed into pieces is dug out by digging machine, end to form the shuting.
Rockfill 6 is built in the present embodiment, in step 303 to comprise the following steps:
Step 3031:Packing sedimentation by throwing stones construction is carried out to the construction area of rockfill 6, forms the subgrade of rockfill 6;
Step 3032:On the ground that step 3031 is built, vertical reinforcement cage described in colligation, then to the vertical reinforcement cage Inside fill full stone and form rockfill 6.
It should be noted that by carrying out packing sedimentation by throwing stones construction, stone has been compacted riverbed and has formed the subgrade of rockfill 6, The stability for the rockfill 6 for making to construct improves.
It is described above, only it is presently preferred embodiments of the present invention, not the present invention is imposed any restrictions, it is every according to the present invention Any simple modification, change and the equivalent structure change that technical spirit is made to above example, still fall within skill of the present invention In the protection domain of art scheme.

Claims (10)

1. a kind of concrete cofferdam and earth rock cofferdam combined cofferdam, it is characterised in that:Including the longitudinal coagulation being laid in river course Earth cofferdam (18) and two are laid in horizontal earth rock cofferdam of the vertical concrete cofferdam (18) between both ends and riverbank respectively, described Vertical concrete cofferdam (18) is parallel with the river course, and the horizontal earth rock cofferdam and the river course are perpendicular;The transverse direction Earth rock cofferdam includes bottom plugging structure, vertical waterproof construction (7) and the weir body being embedded in riverbed;The bottom plugging structure And vertical waterproof construction (7) is laid in the vertical concrete cofferdam (18) between end and riverbank and is each perpendicular to longitudinal direction and mixes Solidifying earth cofferdam (18), the vertical waterproof construction (7) are laid in above the bottom plugging structure vertically, the vertical waterproof knot The bottom of structure (7) is stretched to inside the bottom plugging structure, and the weir body includes being laid in two inside and outside vertical waterproof construction (7) The interior heap body (8) of side and outer heap body (9);The interior heap body (8) and outer heap body (9) are native clitter body;The native clitter body To be gradually outward-dipping domatic from top to bottom, the height of the vertical waterproof construction (7) is not less than the native clitter for upper surface The height of body;
Rockfill (6) is laid with the domatic toe of the native clitter body, the rockfill (6) is by vertical reinforcement cage and filling In the vertical reinforcement cage stone composition, the vertical reinforcement cage be laid in vertical concrete cofferdam (18) end with Between riverbank and it is transversely to the machine direction concrete cofferdam (18);
The domatic of the outer heap body (9) is upstream face, and the domatic bottom of the outer heap body (9) is laid with gabion mask (16), institute State ordinary water level of the height not less than river in the river course of gabion mask (16);The gabion mask (16) is by along outer heap body (9) the oblique reinforcing bar cage of domatic laying and the stone composition being filled in the oblique reinforcing bar cage, the top of the vertical reinforcement cage Portion is connected with the bottom of the oblique reinforcing bar cage;
The top of the gabion mask (16) and it is laid with stone armour layer (17), the stone mask along outer heap body (9) is domatic Layer (17) by be laid on the outer heap body (9) it is domatic on multiple mask stones form;
Between the gap of the two neighboring mask stone and the interior heap body (8) it is domatic on be all covered with turf (19).
2. according to a kind of concrete cofferdam and earth rock cofferdam combined cofferdam described in claim 1, it is characterised in that:It is described vertical Waterproof construction (7) includes the geomembrane (7-1) laid vertically and the protector protected geomembrane (7-1);It is described anti- Protection unit includes being laid in two row's vertical rods (15) of geomembrane (7-1) both sides, often arrange the vertical rod (15) and geomembrane (7-1) it Between be laid with backplate (7-2), two backplates (7-2) are clamped in the both sides of geomembrane (7-1) and are clamped on described in two rows Between vertical rod (15);The size of backplate (7-2) plate face is not less than the size of geomembrane (7-1);The vertical rod (15), backplate The bottom of (7-2) and geomembrane (7-1) is stretched to inside the bottom plugging structure.
3. according to a kind of concrete cofferdam and earth rock cofferdam combined cofferdam described in claim 1 or 2, it is characterised in that:It is described Bottom plugging structure includes two cut-pff walls (5) for being laid in vertical waterproof construction (7) both sides and being embedded in the riverbed, often The polylith slabstone (13) that length direction of the outside of the individual cut-pff wall (5) along cut-pff wall (5) is in a row laid, slabstone described in polylith (13) it is in parallel laying with cut-pff wall (5), the outside of slabstone (13) described in the polylith on the outside of same cut-pff wall (5) and the river Dryness argillic horizon (14) is laid between bed.
4. according to a kind of concrete cofferdam and earth rock cofferdam combined cofferdam described in claim 2, it is characterised in that:The native stone Heap body includes the native rock layers for being laid in the argillic horizon (10) of vertical waterproof construction (7) side and being laid on the outside of argillic horizon (10) (12) loaded filter (11), is laid between the argillic horizon (10) and native rock layers (12), is embedded in the middle part of the vertical rod (15) In the argillic horizon (10).
5. according to a kind of concrete cofferdam and earth rock cofferdam combined cofferdam described in claim 2, it is characterised in that:The longitudinal direction Vertical groove is vertically offered on (18) two end faces of concrete cofferdam, described in the geomembrane (7-1) and two The leading edge of backplate (7-2) is embedded in the vertical groove.
A kind of 6. combined cofferdam construction method as claimed in claim 1, it is characterised in that:Comprise the following steps:
Step 1: Temporary Cofferdam is built:Construction Temporary Cofferdam (1) on the outside of along combined cofferdam construction location of constructing, and by described in Water on the inside of Temporary Cofferdam (1) is drained;
Step 2: vertical concrete cofferdam is built:Routinely concrete cofferdam process for constructing builds vertical concrete cofferdam (18);
Step 3: horizontal earth rock cofferdam is built:An institute is respectively built between the both ends and riverbank of vertical concrete cofferdam (18) State horizontal earth rock cofferdam;Each horizontal earth rock cofferdam, which is built, to be comprised the following steps:
Step 301, surveying setting-out:According to constructed horizontal earth rock cofferdam design drawing, measured on Temporary Cofferdam (1) interior riverbed Setting-out goes out profile outside line (2), profile interior lines (3) and the cofferdam center line (4) of horizontal earth rock cofferdam, and the cofferdam center line (4) is located at Between profile outside line (2) and profile interior lines (3), the distance between the profile outside line (2) and cofferdam center line (4) and profile interior lines (3) it is identical with the distance between cofferdam center line (4);
Step 302, bottom plugging structure and vertical waterproof construction are built:Shuting is excavated along cofferdam center line (4), is intercepted water described Bottom plugging structure is built in groove;Vertical waterproof construction (7) is built along vertical plane residing for cofferdam center line (4);
Step 303, rockfill are built:Rockfill (6) is built along the inner side of the inner side of profile outside line (2) and profile interior lines (3);
Step 304, weir body fill:Interior heap body (8) and outer heap are built respectively in the inner side and outer side of the vertical waterproof construction (7) Body (9);
Step 305, upstream face side slope gabion mask are built:Gabion mask (16) is built in the lower slope of the outer heap body (9);
Step 306, ecological safeguard structure are built:Formed above gabion mask (16) along the domatic laying stone of outer heap body (9) Stone armour layer (17), then in stone armour layer (17) between the gap of stone and interior heap body (8) domatic laying turf (19)。
7. according to the combined cofferdam construction method described in claim 6, it is characterised in that:In step 302, the bottom closure knot Structure includes two cut-pff walls (5) for being laid in vertical waterproof construction (7) both sides and being embedded in the riverbed, each antiseepage The polylith slabstone (13) that length direction of the outside of wall (5) along cut-pff wall (5) is in a row laid, slabstone (13) described in polylith is with preventing It is in parallel laying to ooze wall (5), is laid described in the polylith on the outside of same cut-pff wall (5) between the outside of slabstone (13) and the riverbed There is dryness argillic horizon (14);
Comprise the following steps when being constructed to the bottom plugging structure:
Step 3021, lay multiple slabstones (13), front and rear two adjacent stones from the front to the back along the side wall of the shuting Dryness clay has been filled at gap between plate (13);It is pre- between each slabstone (13) and the side wall of the shuting Stay 0.5m~0.7m gaps;
Step 3022, fill up between each slabstone (13) and the side wall of the shuting dryness clay and form dryness and glue Soil layer (14)
Step 3023, the vertical waterproof construction (7) constructed along cofferdam center line (4), the bottom of vertical waterproof construction (7) are laid in described The bottom of shuting;
Step 3024, the casting concrete between vertical waterproof construction (7) and each slabstone (13), after concrete final set Two cut-pff walls (5) are formed, the front end of the cut-pff wall (5) pours with vertical concrete cofferdam (18) to be integrated.
8. according to the combined cofferdam construction method described in claim 6 or 7, it is characterised in that:Construct horizontal earth rock cofferdam institute Place riverbed is karst landform riverbed, when shuting described in step 302 excavates, breaks riverbed basement rock into pieces by quartering hammer first, The particle that quartering hammer breaks riverbed basement rock into pieces and formed is dug out by digging machine again, forms the shuting.
9. according to the combined cofferdam construction method described in claim 6 or 7, it is characterised in that:In step 2, after the completion of build The middle parts of (18) two end faces in vertical concrete cofferdam vertically open up vertical groove;It is described vertical in step 302 Waterproof construction (7) includes the geomembrane (7-1) laid vertically and the protector protected geomembrane (7-1);It is described anti- Protection unit includes being laid in two row's vertical rods (15) of geomembrane (7-1) both sides, often arrange the vertical rod (15) and geomembrane (7-1) it Between be laid with backplate (7-2), two backplates (7-2) are clamped in the both sides of geomembrane (7-1) and are clamped on described in two rows Between vertical rod (15);The size of backplate (7-2) plate face is not less than the size of geomembrane (7-1);The vertical rod (15), backplate The bottom of (7-2) and geomembrane (7-1) is stretched to inside the bottom plugging structure;In step 302, vertical waterproof knot is built During structure (7), the leading edge of the geomembrane (7-1) and two backplates (7-2) is embedded in the vertical groove.
10. according to the combined cofferdam construction method described in claim 6 or 7, it is characterised in that:Rockfill is built in step 303 (6) comprise the following steps:
Step 3031:Packing sedimentation by throwing stones construction is carried out to rockfill (6) construction area, forms the ground that rockfill (6) is built;
Step 3032:On the ground that step 3031 is built, vertical reinforcement cage described in colligation, then filled out into the vertical reinforcement cage Build full stone and form rockfill (6).
CN201711288950.9A 2017-12-07 2017-12-07 Concrete cofferdam and earth-rock cofferdam combined cofferdam and construction method thereof Active CN107816050B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711288950.9A CN107816050B (en) 2017-12-07 2017-12-07 Concrete cofferdam and earth-rock cofferdam combined cofferdam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711288950.9A CN107816050B (en) 2017-12-07 2017-12-07 Concrete cofferdam and earth-rock cofferdam combined cofferdam and construction method thereof

Publications (2)

Publication Number Publication Date
CN107816050A true CN107816050A (en) 2018-03-20
CN107816050B CN107816050B (en) 2023-03-03

Family

ID=61605460

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711288950.9A Active CN107816050B (en) 2017-12-07 2017-12-07 Concrete cofferdam and earth-rock cofferdam combined cofferdam and construction method thereof

Country Status (1)

Country Link
CN (1) CN107816050B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411865A (en) * 2018-04-02 2018-08-17 中国电建集团中南勘测设计研究院有限公司 A kind of construction method of water conservancy diversion discharge structure
CN110258469A (en) * 2019-06-05 2019-09-20 中国电建集团成都勘测设计研究院有限公司 The flat system in synthesis field for high-mountain gorge areas construction of hydropower plant
CN111926838A (en) * 2020-08-31 2020-11-13 河南传衡建设工程有限公司 River channel multi-span arch-connected slope supporting gallery type quick dismounting combined cofferdam
CN115450236A (en) * 2022-09-15 2022-12-09 中国葛洲坝集团国际工程有限公司 Cofferdam anti-seepage structure and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070280784A1 (en) * 2004-04-02 2007-12-06 Aquavilla Ab Floating Structure In The Shape Of A Concrete Cofferdam And A Method For Moulding The Concrete Cofferdam
CN102587397A (en) * 2012-03-13 2012-07-18 中建五局土木工程有限公司 Steel bearing plate soil-and-stone combined coffer structure and construction method thereof
CN105951857A (en) * 2016-06-27 2016-09-21 中国电建集团成都勘测设计研究院有限公司 Composite anti-seepage wall used in hydraulic cofferdam engineering and construction method thereof
CN207582477U (en) * 2017-12-07 2018-07-06 中铁二十局集团第六工程有限公司 A kind of concrete cofferdam and earth rock cofferdam combined cofferdam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070280784A1 (en) * 2004-04-02 2007-12-06 Aquavilla Ab Floating Structure In The Shape Of A Concrete Cofferdam And A Method For Moulding The Concrete Cofferdam
CN102587397A (en) * 2012-03-13 2012-07-18 中建五局土木工程有限公司 Steel bearing plate soil-and-stone combined coffer structure and construction method thereof
CN105951857A (en) * 2016-06-27 2016-09-21 中国电建集团成都勘测设计研究院有限公司 Composite anti-seepage wall used in hydraulic cofferdam engineering and construction method thereof
CN207582477U (en) * 2017-12-07 2018-07-06 中铁二十局集团第六工程有限公司 A kind of concrete cofferdam and earth rock cofferdam combined cofferdam

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
仵海强等: "三道湾水电站枢纽一期工程围堰防渗形式的优化", 《四川水利》 *
姚安华等: "景洪水电站二期围堰设计及施工", 《水力发电》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411865A (en) * 2018-04-02 2018-08-17 中国电建集团中南勘测设计研究院有限公司 A kind of construction method of water conservancy diversion discharge structure
CN110258469A (en) * 2019-06-05 2019-09-20 中国电建集团成都勘测设计研究院有限公司 The flat system in synthesis field for high-mountain gorge areas construction of hydropower plant
CN111926838A (en) * 2020-08-31 2020-11-13 河南传衡建设工程有限公司 River channel multi-span arch-connected slope supporting gallery type quick dismounting combined cofferdam
CN111926838B (en) * 2020-08-31 2024-04-26 河南传衡建设工程有限公司 River channel multi-span joint arch slope supporting corridor type rapid dismounting combined cofferdam
CN115450236A (en) * 2022-09-15 2022-12-09 中国葛洲坝集团国际工程有限公司 Cofferdam anti-seepage structure and construction method thereof

Also Published As

Publication number Publication date
CN107816050B (en) 2023-03-03

Similar Documents

Publication Publication Date Title
CN109629585B (en) Novel cofferdam structure under weak covering layer and construction method
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN107816050A (en) A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method
CN203668885U (en) Novel hydraulic reclamation mould bag
CN107881987A (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN207582477U (en) A kind of concrete cofferdam and earth rock cofferdam combined cofferdam
CN106498959A (en) Gutter for deep overburden
CN111270698A (en) Protective structure for exposed diseases of bridge pile foundation in sand-mining river channel in mountainous area and construction method of protective structure
CN104594297B (en) A kind of double face slab rock-fill dams and construction method thereof
CN111733842A (en) Cofferdam construction method and cofferdam structure
CN108277815A (en) The cofferdam structure and its construction method constructed for water intaking header structure in river
CN110804994B (en) Reservoir dam construction method
CN102425179B (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN108035368B (en) A kind of mud riverbed combined cofferdam and its construction method
CN107190709A (en) Recently dredging markets hydraulic reclamation Cheng Lu encloses the method in interior construction river course
CN217922839U (en) High-speed railway buried high embankment structure in deep and thick miscellaneous fill-up area
CN106522170A (en) Novel dam type adopting concrete anti-seepage wall as dam body anti-seepage body
CN211872840U (en) Yonglin combined retaining wall structure in urban water conservancy projects
CN108867225A (en) The processing method of sinkhole within the scope of karst landform road foundation
CN212223936U (en) A protective structure that is used for mountain area to adopt sand river course inner bridge pile foundation to expose disease
CN103343541A (en) Pile-plate combined type foundation pit excavation protective structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant