CN102330567A - 公路采空区注浆处治方法 - Google Patents

公路采空区注浆处治方法 Download PDF

Info

Publication number
CN102330567A
CN102330567A CN201110239404A CN201110239404A CN102330567A CN 102330567 A CN102330567 A CN 102330567A CN 201110239404 A CN201110239404 A CN 201110239404A CN 201110239404 A CN201110239404 A CN 201110239404A CN 102330567 A CN102330567 A CN 102330567A
Authority
CN
China
Prior art keywords
slip casting
goaf
hole
slurries
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201110239404A
Other languages
English (en)
Inventor
田志忠
孙雅洁
窦随兵
张明欣
王亚伟
崔兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Traffic Planning Survey Design Institute Co Ltd
Original Assignee
Shanxi Traffic Planning Survey Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Traffic Planning Survey Design Institute Co Ltd filed Critical Shanxi Traffic Planning Survey Design Institute Co Ltd
Priority to CN201110239404A priority Critical patent/CN102330567A/zh
Publication of CN102330567A publication Critical patent/CN102330567A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明涉及一种公路采空区注浆处治方法,其步骤如下:(1)确定注浆孔位置;(2)钻孔及下套管;(3)浇筑孔口管;(4)拌制浆液;(5)注浆;(6)终止注浆。注浆法适用于矿层开采后覆岩发生了较严重的垮塌、滑落或经稳定性评价处于欠稳定或不稳定的采空塌陷区。

Description

公路采空区注浆处治方法
  
技术领域
    本发明属于一种采空区处治方法,具体涉及一种公路采空区注浆处治方法。 
背景技术
    目前,国内外关于采空区常用的处治方法有布置监测网监测,钻探、物探、开挖检测、孔内电视。(1)监测网监测,通过布置适宜的监测网,对采空区处治后变形进行监测,可定量评价采空区处治效果。该方法能够直观的、定量评价采空区稳定状态,为采空区勘察及处治设计提供基础数据;但是周期较长,实施较困难,应用不普遍。(2)钻探,采空区处治6个月后,选择一定能够数量的点,采用钻探、取芯观测方法检测注浆效果。该方法是直接取得注浆效果数据最有效的方法,通过钻探过程、岩芯采取观测等,直接获得采空区处治后处治范围内的地层数据,对处治效果进行评价,该方法应用广泛,效果很好。(3)物探,物探是采空区检测的辅助方法,可分为地面物探和孔内物探。地面物探是注浆结束后在地表布设测线,采用瞬变电磁法和高密度电法进行注浆前后波形及参数对比,一般用于工程时间要求紧,但是定性判断,人为因素较多;孔内物探是在检查孔中做波速测井或孔间CT等进行检测,可测带钻孔周边地层波速指标,根据合格标准判断采空区处治效果。(4) 孔内电视检测,在检查孔中,利用数字式摄像可以直接观察孔壁岩体的空洞、裂隙及地下水的分布情况,较直观地观察到岩体的完整程度,评价采空区的处治效果。但孔内摄像运用的是光学原理,要求孔内为清水或干孔,采空区检查孔孔内大多赋存有水,受成孔条件的制约,在泥浆护壁孔内由于水质浑浊,运用效果欠佳(5) 开挖检测,开挖检测方法是在空洞地基处治上方开挖探井、探坑至处治段底部,观测处治段充填体厚度及充填情况,观测有无空洞,测试充填物强度,得出充填率,必要时进行现场试验,确定承载力。开挖检测方法施工简单、直观,且比较经济,适用于浅埋空洞处治效果的检验。 
发明内容
本发明所要解决的技术问题是提供一种公路采空区处治方法,该方法步骤简单,处治效果较好。 
本发明的技术方案:一种公路采空区注浆处治方法,它的步骤如下: 
(1)定点
注浆孔用经纬仪、皮尺进行实地测量放样,钻孔实际位置原则误差不超过0.5m,因受地形影响,钻孔不能放在设计位置时,可视具体情况在设计代表和工程监理的认可下予以调整;
(2)钻孔及下套管
钻孔均在地表施工
① 用φ127mm钻头开孔,钻至完整基岩6m后,下入φ114mm套管或焊管护壁,然后变径为φ91mm,在第四系卵、砾石层的钻探过程中采用跟管钻进;
② 用φ89mm钻头,钻至煤层采空区中的塌陷冒落带或煤层底板以下1m;
(3)浇筑孔口管
浇筑孔口管的操作按准备工作、下注浆管及托盘、 搅拌水泥、浇筑注浆管及托盘和保护管口的流程进行;
(4)拌制浆液
① 浆液配制按设计浆液配合比进行,并随机抽查浆液的各项指标;
② 原材料:水用水表或定量容器计量;水泥按袋或按定量容器即散装水泥计量,注浆材料宜采用水泥、粉煤灰、粘土;当采空区空洞和裂隙发育,地下水流速大于200m/h时,宜先灌注砂、砾石、石屑、矿渣骨料后注浆;注浆过程中,可根据需要加入水玻璃、三乙醇胺添加剂改变浆液性能,缩短凝结时间;
③ 制浆工艺如说明书附图所示
④ 搅拌过程:每次搅拌时间不少于3分钟;
(5)注浆
① 施工顺序:按采空区的倾斜方向,先施工采空区底板标高较低位置的注浆孔及构造物工点处的注浆孔,再沿倾斜方向由低向高、由边部向中心展开施工;
② 注浆
注浆采用浆液浓度先稀后稠的方法,注浆开始后,要定时观测泵的吸浆量和泵压,记录注浆过程中发生的各种现象,收集原始数据,并根据实际情况及时调整注浆量和浆液浓度;稀浆灌注量取单孔注浆量的30%;
注浆时,避免在短时间内注入大量水泥浆,当注浆量大时,采用间歇式注浆法施工,或在孔口加一漏斗状的投砂器,用浆液将砂或石屑带入孔内,或在浆液中加入水泥重量2%的速凝剂;
注浆孔口管为114mm焊管,骨料为直径小于3mm的砂或石屑;
③注浆过程中若出现地表裂隙大量跑浆时,应采用间歇式注浆或减小泵量及地表充填裂隙的措施,阻止浆液从地面大量流失;
④注浆及间歇注浆前必须用清水洗孔,压水时间不小于10分钟;
(6)终止注浆
在注浆孔的注浆末期,泵压逐渐升高,当泵量小于70L/min时,根据结构物类型和采空区特征,孔口压力在1.0~3.0MPa,稳定15分钟,结束该孔的注浆施工。
附图说明
图1为本发明的制浆工艺图。 
具体实施方式
(1)定点 
注浆孔应用经纬仪、皮尺进行实地测量放样,钻孔实际位置原则误差不应超过0.5m。因受地形影响,钻孔不能放在设计位置时,可视具体情况在设计代表和工程监理的认可下予以调整。
(2)钻孔及下套管 
钻孔均在地表施工。
① 用φ127mm钻头开孔,钻至完整基岩6m后,下入φ114mm套管或焊管护壁,然后变径为φ91mm。在第四系卵、砾石层的钻探过程中采用跟管钻进。 
② 用φ89mm钻头,钻至煤层采空区中的塌陷冒落带或煤层底板以下1m。 
(3)浇筑孔口管 
浇筑孔口管的操作应按准备工作、下注浆管及托盘、 搅拌水泥、浇筑注浆管及托盘和保护管口的流程进行。
(4)拌制浆液 
① 浆液配制应按设计浆液配合比进行,并随机抽查浆液的各项指标。
② 原材料:水用水表或定量容器计量;水泥按袋或按定量容器(散装水泥)计量。注浆材料宜采用水泥、粉煤灰、粘土等。当采空区空洞和裂隙发育,地下水流速大于200m/h时,宜先灌注砂、砾石、石屑、矿渣等骨料后注浆。注浆过程中,可根据需要加入一定量的水玻璃、三乙醇胺等添加剂改变浆液性能,缩短凝结时间。 
③制浆工艺如说明书附图所示 
④ 搅拌过程:每次搅拌时间不得少于3分钟。
(5)注浆 
① 施工顺序:按采空区的倾斜方向,先施工采空区底板标高较低位置的注浆孔及构造物工点处的注浆孔,再沿倾斜方向由低向高、由边部向中心展开施工。
② 注浆 
注浆采用浆液浓度先稀后稠的方法,注浆开始后,要定时观测泵的吸浆量和泵压,记录注浆过程中发生的各种现象,收集原始数据,并根据实际情况及时调整注浆量和浆液浓度。稀浆灌注量取单孔注浆量的30%为宜。
注浆时,应避免在短时间内注入大量水泥浆,当注浆量较大时,应采用间歇式注浆法施工,或在孔口加一漏斗状的投砂器,用浆液将砂或石屑带入孔内,或在浆液中加入水泥重量2%的速凝剂。 
注浆孔口管为114mm焊管,骨料为直径小于3mm的砂或石屑。 
③注浆过程中若出现地表裂隙大量跑浆时,应采用间歇式注浆,或减小泵量及地表充填裂隙的措施,阻止浆液从地面大量流失。 
④注浆及间歇注浆前必须用清水洗孔,压水时间不得小于10分钟。 
(6)终止注浆 
在注浆孔的注浆末期,泵压逐渐升高,当泵量小于70L/min时,根据结构物类型和采空区特征,孔口压力在1.0~3.0MPa,稳定15分钟,可结束该孔的注浆施工。
  

Claims (1)

1.一种公路采空区注浆处治方法,其特征是它的步骤如下:
(1)定点
注浆孔用经纬仪、皮尺进行实地测量放样,钻孔实际位置原则误差不超过0.5m,因受地形影响,钻孔不能放在设计位置时,可视具体情况在设计代表和工程监理的认可下予以调整;
(2)钻孔及下套管
钻孔均在地表施工
① 用φ127mm钻头开孔,钻至完整基岩6m后,下入φ114mm套管或焊管护壁,然后变径为φ91mm,在第四系卵、砾石层的钻探过程中采用跟管钻进;
② 用φ89mm钻头,钻至煤层采空区中的塌陷冒落带或煤层底板以下1m;
(3)浇筑孔口管
浇筑孔口管的操作按准备工作、下注浆管及托盘、 搅拌水泥、浇筑注浆管及托盘和保护管口的流程进行;
(4)拌制浆液
① 浆液配制按设计浆液配合比进行,并随机抽查浆液的各项指标;
② 原材料:水用水表或定量容器计量;水泥按袋或按定量容器即散装水泥计量,注浆材料宜采用水泥、粉煤灰、粘土;当采空区空洞和裂隙发育,地下水流速大于200m/h时,宜先灌注砂、砾石、石屑、矿渣骨料后注浆;注浆过程中,可根据需要加入水玻璃、三乙醇胺添加剂改变浆液性能,缩短凝结时间;
③ 制浆工艺如说明书附图所示
④ 搅拌过程:每次搅拌时间不少于3分钟;
(5)注浆
① 施工顺序:按采空区的倾斜方向,先施工采空区底板标高较低位置的注浆孔及构造物工点处的注浆孔,再沿倾斜方向由低向高、由边部向中心展开施工;
② 注浆
注浆采用浆液浓度先稀后稠的方法,注浆开始后,要定时观测泵的吸浆量和泵压,记录注浆过程中发生的各种现象,收集原始数据,并根据实际情况及时调整注浆量和浆液浓度;稀浆灌注量取单孔注浆量的30%;
注浆时,避免在短时间内注入大量水泥浆,当注浆量大时,采用间歇式注浆法施工,或在孔口加一漏斗状的投砂器,用浆液将砂或石屑带入孔内,或在浆液中加入水泥重量2%的速凝剂;
注浆孔口管为114mm焊管,骨料为直径小于3mm的砂或石屑;
③注浆过程中若出现地表裂隙大量跑浆时,应采用间歇式注浆或减小泵量及地表充填裂隙的措施,阻止浆液从地面大量流失;
④注浆及间歇注浆前必须用清水洗孔,压水时间不小于10分钟;
(6)终止注浆
在注浆孔的注浆末期,泵压逐渐升高,当泵量小于70L/min时,根据结构物类型和采空区特征,孔口压力在1.0~3.0MPa,稳定15分钟,结束该孔的注浆施工。
CN201110239404A 2011-08-19 2011-08-19 公路采空区注浆处治方法 Pending CN102330567A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110239404A CN102330567A (zh) 2011-08-19 2011-08-19 公路采空区注浆处治方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110239404A CN102330567A (zh) 2011-08-19 2011-08-19 公路采空区注浆处治方法

Publications (1)

Publication Number Publication Date
CN102330567A true CN102330567A (zh) 2012-01-25

Family

ID=45482502

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110239404A Pending CN102330567A (zh) 2011-08-19 2011-08-19 公路采空区注浆处治方法

Country Status (1)

Country Link
CN (1) CN102330567A (zh)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244149A (zh) * 2013-05-16 2013-08-14 中国十七冶集团有限公司 插管注浆修复隧道塌陷的施工方法
CN103628912A (zh) * 2013-11-04 2014-03-12 葛洲坝集团基础工程有限公司 一种采空区处理充填灌浆的施工方法
CN104833389A (zh) * 2015-05-19 2015-08-12 长沙理工大学 灌浆封孔止浆可视化实验装置及实验方法
CN105240047A (zh) * 2015-09-16 2016-01-13 鞍钢集团矿业公司 一种治理露天矿地下采空区的充填加固方法
CN106368731A (zh) * 2016-11-16 2017-02-01 中国神华能源股份有限公司 采空区处理方法
CN106761543A (zh) * 2016-12-02 2017-05-31 淮北矿业股份有限公司 一种钻孔通过采空区漏失段的方法
CN106837411A (zh) * 2017-02-04 2017-06-13 长江勘测规划设计研究有限责任公司 一种深埋盾构隧道充填注浆的布置结构及方法
CN107313788A (zh) * 2017-08-17 2017-11-03 新疆龟兹矿业有限公司 强水力联系下注浆堵水的方法及装置
CN108240234A (zh) * 2017-12-28 2018-07-03 辽宁工程技术大学 一种铁路沿线下伏煤矿采空区注浆处治方法
CN109137883A (zh) * 2018-08-25 2019-01-04 大同煤矿集团有限责任公司 采空区灌注黄土固结剂防止自燃系统及其注浆方法
CN111997685A (zh) * 2020-09-03 2020-11-27 中铁八局集团第三工程有限公司 一种高速公路穿越煤层采空区段施工方法
CN114233377A (zh) * 2021-12-17 2022-03-25 中国十七冶集团有限公司 一种过程控制采空区注浆量的装置及施工方法
CN114233378A (zh) * 2021-12-17 2022-03-25 中国十七冶集团有限公司 一种采空区自行走钻孔注浆一体化设备及安装使用方法
WO2022117124A1 (zh) * 2021-04-26 2022-06-09 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
CN114876359A (zh) * 2022-04-07 2022-08-09 山西省交通科技研发有限公司 一种基于斜孔注浆的公路采空区处治方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3933236A1 (de) * 1989-10-05 1991-04-18 Werner Berwald Verfahren und vorrichtung zur herstellung eines streckendammen/stuetzpfeilers im untertaegigen grubenbetrieb
CN101598032A (zh) * 2009-06-30 2009-12-09 北京国电华北电力工程有限公司 一种建设特高压杆塔的采空区注浆方法
CN101797771A (zh) * 2010-04-02 2010-08-11 中铁二局股份有限公司 高速公路下伏采空区注浆投沙时浆液的制备方法
CN101806059A (zh) * 2010-04-02 2010-08-18 中铁二局股份有限公司 高速公路下伏采空区地表钻孔注浆投沙工艺
CN201635765U (zh) * 2010-04-02 2010-11-17 中铁二局股份有限公司 用于高速公路下伏采空区的投沙器
CN101906991A (zh) * 2010-07-19 2010-12-08 刘清洁 一种治理地下采空区或空洞的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3933236A1 (de) * 1989-10-05 1991-04-18 Werner Berwald Verfahren und vorrichtung zur herstellung eines streckendammen/stuetzpfeilers im untertaegigen grubenbetrieb
CN101598032A (zh) * 2009-06-30 2009-12-09 北京国电华北电力工程有限公司 一种建设特高压杆塔的采空区注浆方法
CN101797771A (zh) * 2010-04-02 2010-08-11 中铁二局股份有限公司 高速公路下伏采空区注浆投沙时浆液的制备方法
CN101806059A (zh) * 2010-04-02 2010-08-18 中铁二局股份有限公司 高速公路下伏采空区地表钻孔注浆投沙工艺
CN201635765U (zh) * 2010-04-02 2010-11-17 中铁二局股份有限公司 用于高速公路下伏采空区的投沙器
CN101906991A (zh) * 2010-07-19 2010-12-08 刘清洁 一种治理地下采空区或空洞的施工方法

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244149B (zh) * 2013-05-16 2015-05-20 中国十七冶集团有限公司 插管注浆修复隧道塌陷的施工方法
CN103244149A (zh) * 2013-05-16 2013-08-14 中国十七冶集团有限公司 插管注浆修复隧道塌陷的施工方法
CN103628912A (zh) * 2013-11-04 2014-03-12 葛洲坝集团基础工程有限公司 一种采空区处理充填灌浆的施工方法
CN103628912B (zh) * 2013-11-04 2016-05-11 中国葛洲坝集团基础工程有限公司 一种采空区处理充填灌浆的施工方法
CN104833389A (zh) * 2015-05-19 2015-08-12 长沙理工大学 灌浆封孔止浆可视化实验装置及实验方法
CN105240047A (zh) * 2015-09-16 2016-01-13 鞍钢集团矿业公司 一种治理露天矿地下采空区的充填加固方法
CN106368731A (zh) * 2016-11-16 2017-02-01 中国神华能源股份有限公司 采空区处理方法
CN106761543B (zh) * 2016-12-02 2019-07-19 淮北矿业股份有限公司 一种钻孔通过采空区漏失段的方法
CN106761543A (zh) * 2016-12-02 2017-05-31 淮北矿业股份有限公司 一种钻孔通过采空区漏失段的方法
CN106837411B (zh) * 2017-02-04 2020-04-03 长江勘测规划设计研究有限责任公司 一种深埋盾构隧道充填注浆的布置结构及方法
CN106837411A (zh) * 2017-02-04 2017-06-13 长江勘测规划设计研究有限责任公司 一种深埋盾构隧道充填注浆的布置结构及方法
CN107313788B (zh) * 2017-08-17 2019-05-10 新疆龟兹矿业有限公司 强水力联系下注浆堵水的方法及装置
CN107313788A (zh) * 2017-08-17 2017-11-03 新疆龟兹矿业有限公司 强水力联系下注浆堵水的方法及装置
CN108240234A (zh) * 2017-12-28 2018-07-03 辽宁工程技术大学 一种铁路沿线下伏煤矿采空区注浆处治方法
CN108240234B (zh) * 2017-12-28 2019-06-28 辽宁工程技术大学 一种铁路沿线下伏煤矿采空区注浆处治方法
CN109137883A (zh) * 2018-08-25 2019-01-04 大同煤矿集团有限责任公司 采空区灌注黄土固结剂防止自燃系统及其注浆方法
CN111997685A (zh) * 2020-09-03 2020-11-27 中铁八局集团第三工程有限公司 一种高速公路穿越煤层采空区段施工方法
WO2022117124A1 (zh) * 2021-04-26 2022-06-09 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
CN114233377A (zh) * 2021-12-17 2022-03-25 中国十七冶集团有限公司 一种过程控制采空区注浆量的装置及施工方法
CN114233378A (zh) * 2021-12-17 2022-03-25 中国十七冶集团有限公司 一种采空区自行走钻孔注浆一体化设备及安装使用方法
CN114233378B (zh) * 2021-12-17 2023-11-10 中国十七冶集团有限公司 一种采空区自行走钻孔注浆一体化设备及安装使用方法
CN114876359A (zh) * 2022-04-07 2022-08-09 山西省交通科技研发有限公司 一种基于斜孔注浆的公路采空区处治方法

Similar Documents

Publication Publication Date Title
CN102330567A (zh) 公路采空区注浆处治方法
CN108240234B (zh) 一种铁路沿线下伏煤矿采空区注浆处治方法
CN109630137B (zh) 一种隧道高位穿越巨型溶腔的回填处理施工方法
CN103603689B (zh) 一种采空区处理帷幕灌浆的施工方法
CN102071940B (zh) 煤矿井筒穿越多层采空区的施工方法
CN111997685A (zh) 一种高速公路穿越煤层采空区段施工方法
CN113186924A (zh) 一种地铁基坑深埋溶洞处理方法
CN103899351B (zh) 一种处理复杂采空区的充填加固方法
CN110106868B (zh) 一种岩溶地质大直径桩基成孔工艺方法
CN107842374B (zh) 用于上软下硬富水地层的盾构新型惰性浆液及组合注浆工艺
CN103628912A (zh) 一种采空区处理充填灌浆的施工方法
CN105155563A (zh) 一种基坑软流塑地层涌水加固治理方法
CN106437796B (zh) 一种岩石地层盾构隧道端头加固结构及加固方法
CN107795303A (zh) 水合物开采井管内砾石充填仿真系统及方法
CN113279687B (zh) 一种临河煤矿老空区水害查治一体化治理方法
CN107246007B (zh) 一种cfg桩的施工方法
CN112814737B (zh) 基于叠层多分支水平井的陷落柱超前治理方法及系统
CN104929146A (zh) 一种多层岩溶发育带桩基础工程施工方法
CN107938649A (zh) 一种溶洞地基加固方法
CN101413396A (zh) 一种张拉锚杆的注装方法
CN102011591A (zh) 深井工作面注浆工艺
CN115539121A (zh) 一种采空区注浆施工工艺
CN113309565A (zh) 一种大空间大倾角采空区帷幕注浆方法
CN106522981A (zh) 穿越采空区隧道的支护方法
CN106223961B (zh) 一种煤矿回风大巷过断层掘进施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120125