CN102226396B - Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling - Google Patents

Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling Download PDF

Info

Publication number
CN102226396B
CN102226396B CN 201110130801 CN201110130801A CN102226396B CN 102226396 B CN102226396 B CN 102226396B CN 201110130801 CN201110130801 CN 201110130801 CN 201110130801 A CN201110130801 A CN 201110130801A CN 102226396 B CN102226396 B CN 102226396B
Authority
CN
China
Prior art keywords
ore
artificial
filling
excavation
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110130801
Other languages
Chinese (zh)
Other versions
CN102226396A (en
Inventor
周科平
肖雄
邓红卫
李杰林
刘泽洲
刘朝晖
董国庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN 201110130801 priority Critical patent/CN102226396B/en
Publication of CN102226396A publication Critical patent/CN102226396A/en
Application granted granted Critical
Publication of CN102226396B publication Critical patent/CN102226396B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a non-explosive mining method by excavation, artificial group-column reconstruction, long-hole caving and subsequent filling, comprising the following steps of: excavating a certain quantity of column wells in a certain arrangement mode within the scope of ore pillars by the raise-boring machine well-drilling technology; placing steel reinforcement cages into the column wells after the excavation of the column wells, followed by filling concrete to form artificial group-columns, whose mechanical properties meet the requirement of stope stability and which are used to replace artificial pillars so as to form a relative stable restricted space around the ore mining areas; stoping by the major diameter long-hole caving mode, moving ore out by a scraper, and filling the goaf at a time after moving ore out. The mining method provided by the invention is suitable for the mining of underground metal loose and soft fragmental orebodies by adopting non-explosive technology to excavate column wells and filling the column wells to form artificial group-columns in order to replace artificial pillars, and has advantages of simple construction process, high construction efficiency, low production cost, high mining efficiency, and large production capacity of ore blocks and panels.

Description

Non-explosive excavation reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method
Technical field
The present invention relates to a kind of non-explosive excavation and reproduce artificial bundle pillar deep hole ore caving afterwards filling exploitation method, especially be applicable to the exploitation of underground metallic ore break and broken orebody.
Background technology
The soft broken metalliferous deposit is regarded as a kind of complicated uneasily mining orebody always, because the developmental joint fissure of ore body, ore deposit rock resistance to overturning is relatively poor, can allow exposed area little, and therefore the downdraft mode access back-filling methods that adopt carry out the back production of this type of ore body more.And in traditional downdraft mode access back-filling method, the method that its artificial bar post is constructed still is to construct to the route cemented-method under adopting, the work cycle of this method for constructing comprises driling explosion, ore removal, filling and protects top etc., after finishing a circulation, therefore change again the back production of another layering over to, exist complex process, safety condition is poor, operating efficiency is low, adopt and fill that cycle period is long, labour intensity is large, nugget production capacity is low and the shortcoming such as mining cost height.Therefore, traditional artificial bar post mode of constructing is restricting the back production efficient of downdraft mode Drift stoping method, also has influence on the production capacity in whole panel.
Summary of the invention
Technical problem to be solved by this invention provides a kind of in the break and broken orebody exploitation, the efficient of constructing is high, technique is simple, cost is lower and the stability of stope and bundle pillar is high, operating efficiency is high, and the non-explosive excavation that nugget production capacity is large reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method.
In order to solve the problems of the technologies described above, non-explosive excavation provided by the invention reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method, in bar post ore body scope, excavate the post well of some by certain arranged mode with the raise boring machine drilling technology, after the post well has excavated, put into reinforcing cage within it, reinforcing cage can be put in segmentation, then adopt concrete to carry out filling, form artificial bundle pillar with this, the mechanical property of bundle pillar satisfies the requirement of STOPE STABILITY, substitute artificial bar post, around the section of back production ore deposit, form a relatively firm restricted clearance.Use large diameter, deep borehole ore caving mode rooming, scraper ore removal, the complete rear one-time filling of ore removal goaf.
Construct the upper level of artificial bar columnar region and the chamber that lower horizontal is distinguished digging drill chamber, replacing reaming cutter at needs, in rig work chamber, creep into guide hole downwards, the guide hole diameter is 0.25m, and guide hole is given a farfetched interpretation to the chamber of changing reaming cutter, removes the guide hole drill bit, be replaced with reaming bit, and from bottom to top reaming, finish the excavation of post well, the diameter of post well is 2.0m.
Each post well excavates according to the mutual arranged mode of 1-2-1, and the diameter of post well is 2.0m, and post well spacing is 1.0m; Behind post well of every excavation, reinforcing cage is placed in segmentation in the post well, and the length that reinforcing cage is every section is 2m, and diameter is 1.6m, and the coupled columns well carries out concrete filling; Then carry out excavation and the filling of next post well, finish the construction of whole artificial bundle pillar.
Around the section of back production ore deposit, utilize the post group who manually constructs to form a relatively firm restricted clearance, the Drilling large resistancing line is lower to large diameter, deep borehole in drilling chamber, adopts deep hole ore caving mode to carry out back production; The ore of a large amount of avalanches is transported by scraper by drawhole, realizes strengthening ore removal; Ore removal is put casting resin, bashing by the filling down-hole in the artificial roof pillar after finishing.
The invention has the beneficial effects as follows, adopt non-blasting technique excavation post well, and the packed column well forms artificial bundle pillar, utilize bundle pillar to substitute artificial bar post, the efficient of constructing is high, technique is simple, cost is lower and the stability of stope and bundle pillar is high, operating efficiency is high, and nugget production capacity is large, has solved that artificial bar post is constructed inefficiency and the difficult problem that affects panel production capacity.
Description of drawings
Fig. 1 is the front view that non-explosive excavation reproduces artificial bundle pillar deep hole ore caving afterwards filling mining methods.
Fig. 2 is the left view that non-explosive excavation reproduces artificial bundle pillar deep hole ore caving afterwards filling mining methods.
Among the figure: 1. the horizontal haulage drift in stage casing, 2. mining filling route, 3. large diameter, deep borehole, 4. injected hole, 5. ventilation connecting taxiway, 6. filling connecting taxiway, 7. the filling route is 8. reserved the filling well, 9. discharging tunnel during the back production top board, 10. artificial roof pillar, 11. kerve drilling chambers, 12. the boundary line of ore body, 13. slot raises, 14. bottom lines that undercut, 15. dress ore deposit route, 16. discharging tunnels, the 17. rock drilling gallerys that undercut, 18. the filling service shaft, 19. post wells, 20. drop shafts;
Fig. 3 be along III-III among Fig. 1 to sectional view.
Fig. 4 is to sectional view along IV-IV among Fig. 1.
Among the figure, 20. drop shafts, 13. slot raises, 18. filling service shafts, 11. kerve drilling chambers, 8. reserve the filling well, 21. artificial post groups, 22. short connection roadways, 23. drilling chambers, 24. ore bodies, 25. inclined shaft, 26. filling ventilation connecting taxiways, 27. scraper chambers, 28. extracting drifts, 29. lower wall discharging tunnels;
Fig. 5 is to sectional view along V-V among Fig. 1.
Fig. 6 is to sectional view along VI-VI among Fig. 1.
Among the figure, 27. scraper chambers, 20. drop shafts, 30. scraper roads, 13. slot raises, 31. filling returnairshafts, the 17. rock drilling gallerys that undercut, 18. filling service shafts, 19. post wells, 32. ventilating shafts, 15. dress ore deposit routes;
Fig. 7 is the mutual arranged schematic diagram of bundle pillar 1-2-1.
Among the figure, 19. post wells, 33. artificial bar columnar region ore bodies
Fig. 8 is the restricted clearance schematic diagram that bundle pillar and artificial roof are constructed.
Among the figure, 34. bundle pillars, 10. artificial roof
The specific embodiment
The present invention is further described below in conjunction with drawings and Examples.
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7 and Fig. 8, the implementation of this scheme is:
(1) construct the upper level digging drill chamber of artificial bar columnar region at needs, rig chamber net section need satisfy the requirements such as inclination angle, azimuth and equipment convenient in carrying of post well; Change simultaneously the chamber of reaming cutter at the lower horizontal excavation of artificial bar post.
(2) in the rig chamber, creep into guide hole downwards, guide hole is given a farfetched interpretation to the chamber of the replacing reaming cutter of foot, in the chamber of changing reaming cutter, remove the guide hole drill bit, be replaced with reaming bit, and from bottom to top reaming, the diameter of guide hole is 0.25m, and the diameter of post well is 2.0m.
(3) the post well excavates according to the mutual arranged mode of 1-2-1, finishes the post well of some; Behind post well of every excavation, in the post well, place reinforcing cage, can transfer by segmentation, the length that reinforcing cage is every section is 2.0m, diameter is 1.6m, and the coupled columns well carries out concrete filling, then carries out excavation and the filling of next post well, finish the construction of whole artificial bundle pillar, thereby around the section of back production ore deposit, form a relatively firm restricted clearance.
(4) Drilling large resistancing line lower to large diameter, deep borehole in drilling chamber adopts deep hole ore caving mode to carry out back production.
(5) ore of a large amount of avalanches is transported by scraper by drawhole, realizes strengthening ore removal; Ore removal is put casting resin, bashing by the filling down-hole in the artificial roof pillar after finishing.

Claims (4)

1. a non-explosive excavation reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method, it is characterized in that: utilize the raise boring machine drilling technology in bar post ore body scope, to excavate the post well of some by certain assembled arrangement mode, after the post well has excavated, put into reinforcing cage within it, then adopt concrete to carry out filling, form artificial bundle pillar with this, the mechanical property of artificial bundle pillar satisfies the requirement of STOPE STABILITY, in order to substitute artificial bar post, around the section of back production ore deposit, form a relatively firm restricted clearance; Use large diameter, deep borehole ore caving mode rooming, scraper ore removal, the complete rear one-time filling of ore removal goaf.
2. non-explosive excavation according to claim 1 reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method, it is characterized in that: construct the upper level in artificial bundle pillar zone and the chamber that lower horizontal is distinguished digging drill work chamber, replacing reaming cutter at needs, in rig work chamber, creep into guide hole downwards, the guide hole diameter is 0.25m, guide hole is given a farfetched interpretation to the chamber of changing reaming cutter, remove the guide hole drill bit, be replaced with reaming bit, and from bottom to top reaming, finish the excavation of post well, the diameter of post well is 2.0m.
3. non-explosive excavation according to claim 1 and 2 reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method, it is characterized in that: each post well excavates according to mutual arranged mode of 2-1 rows of 1-1 row of 1 row, the diameter of post well is 2.0m, and post well spacing is 1.0m; Behind post well of every excavation, reinforcing cage is placed in segmentation in the post well, and the length that reinforcing cage is every section is 2m, and diameter is 1.6m, and the coupled columns well carries out concrete filling; Then carry out excavation and the filling of next post well, finish the construction of whole artificial bundle pillar.
4. non-explosive excavation according to claim 1 reproduces artificial bundle pillar deep hole ore caving afterwards filling mining method, it is characterized in that: around the section of back production ore deposit, utilize the bundle pillar of manually constructing to form a relatively firm restricted clearance, the Drilling large resistancing line is lower to large diameter, deep borehole in drilling chamber, adopts deep hole ore caving mode to carry out back production; The ore of a large amount of avalanches is transported by scraper by drawhole, realizes strengthening ore removal; Ore removal is put casting resin, bashing by the filling down-hole in the artificial roof pillar after finishing.
CN 201110130801 2011-05-19 2011-05-19 Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling Expired - Fee Related CN102226396B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110130801 CN102226396B (en) 2011-05-19 2011-05-19 Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110130801 CN102226396B (en) 2011-05-19 2011-05-19 Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling

Publications (2)

Publication Number Publication Date
CN102226396A CN102226396A (en) 2011-10-26
CN102226396B true CN102226396B (en) 2013-02-06

Family

ID=44807390

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110130801 Expired - Fee Related CN102226396B (en) 2011-05-19 2011-05-19 Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling

Country Status (1)

Country Link
CN (1) CN102226396B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587973B (en) * 2011-12-01 2014-04-16 中南大学 Method for protecting high-stress ore pillars by aid of pressure relief precrack
CN102518438B (en) * 2012-01-06 2013-11-06 中南大学 Roof regeneration medium-length hole ore blast backfill mining method
CN102587915A (en) * 2012-03-21 2012-07-18 西安建筑科技大学 Induction caving mining method under artificial false roof
CN102704933B (en) * 2012-05-25 2014-10-29 中国矿业大学 Isolated-section grouting filling coal-mining method for mining overburden rock
CN102865080A (en) * 2012-10-08 2013-01-09 中南大学 Induced fracture engineering arrangement and non-blasting mining process for high-geostress hard rock
CN103061767B (en) * 2013-01-17 2015-08-05 云南临沧鑫圆锗业股份有限公司 Lower to horizontal slice Dry-placed fill mining
CN103306719B (en) * 2013-06-07 2015-05-20 中国矿业大学 Coal mine underground drilled hole filling and reinforcing device and method
CN103835661B (en) * 2013-11-06 2016-03-16 北京中煤矿山工程有限公司 A kind of local excavation pre support mine shaft rising boring technique
CN104481539B (en) * 2014-12-05 2016-06-29 西安建筑科技大学 From kerve tight-face blasting caved stopes
CN104763423B (en) * 2015-03-04 2017-01-25 鞍钢集团矿业公司有限公司 Technology for mining powder ore by inverse well rock drilling
CN105041316A (en) * 2015-06-29 2015-11-11 徐庆余 Pillar mining method
CN106761858B (en) * 2017-01-09 2019-03-19 广东安元矿业勘察设计有限公司 The supporting back production of stull open-stope method and filling new process
CN113202473B (en) * 2021-05-21 2023-12-08 中煤第七十一工程处有限责任公司 Underground mine broken rock downward mining method
CN114439477A (en) * 2022-04-12 2022-05-06 北京科技大学 Non-explosive mining method for filling by using 3D printed mesh-shaped member and waste rock

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4135450A (en) * 1975-07-11 1979-01-23 Canadian Industries Limited Method of underground mining
ZA80816B (en) * 1980-02-13 1981-01-28 H Vidal Method for working a mine in accordance with the bord-and-pillar method
CN1260460C (en) * 2003-06-06 2006-06-21 中南大学 Continuous mining process with deep hole dropping and top-bottom pillars mining in advance
CN101105129B (en) * 2007-07-16 2010-05-19 中南大学 Mining environment reconstructed continuous mining afterwards filling mining method
CN101871347B (en) * 2010-07-08 2011-12-14 中南大学 Mining environment reconstruction layering and striping medium-length hole ore removal mining method

Also Published As

Publication number Publication date
CN102226396A (en) 2011-10-26

Similar Documents

Publication Publication Date Title
CN102226396B (en) Non-explosive mining method of excavation, artificial group-column reconstruction, long-hole caving and subsequent filling
CN105587318B (en) A kind of method of mining by the way of filling of the parallel middle thickness orebody group continuous stoping of low-angle dip
CN101105129B (en) Mining environment reconstructed continuous mining afterwards filling mining method
CN103557002B (en) A kind of mechanized concentrates drop shaft filling-up method
CN103437769B (en) Combination is reproduced structure medium-length hole ore blast and is worked in coordination with cable bolting afterwards filling mining method
CN103615250B (en) The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes
CN102251773B (en) Route type upward horizontal layered filling mining method suitable for extremely complex ore body mining
CN105178961B (en) A kind of roomy stope borehole drilling stage open stope afterwards filling mining method
CN109252862A (en) Ultra-large stope large diameter, deep borehole high-stage open stope afterwards filling mining method
CN104989404A (en) Diagonal ore-break-down medium-length hole mining method for steeply-inclined thin vein ore body
CN107905834A (en) A kind of hypotonic high prominent coal seam architecture gas production method
CN101737052A (en) Sublevel fill-mining method
CN105952450B (en) A kind of new method of the double stope collaboration exploitations in underground mine underground
CN102953732A (en) Room-and-pillar major-diameter longhole inverted-step-like segmented lateral caving subsequent filling mining method
CN102168579A (en) Rib-pillar-free continuous sublevel filling method for mining preparation in medium-thickness slope crushed ore body vein
CN107687341A (en) A kind of Upward slicing point pillar filling mining method of extremely thick big unstable ore body
CN105649631A (en) Efficient mechanical mining method for gently-inclined thin ore bodies
CN102518438A (en) Roof regeneration medium-length hole ore blast backfill mining method
CN106761912A (en) It is a kind of be suitable for unstable formation efficiently on to route slicing and filling mining methods
MX2012009756A (en) Underground mining.
AU2021101512A4 (en) Panel area and panel area column collaborative mining method for an inclined thick and large ore body
CN103206215A (en) Precontrol top upward access cut-and-filling stopping method
CN104481543A (en) Sub-level shrinkage caving method
CN106223956A (en) Medium-length hole courtyard mining afterwards filling method
CN105673014A (en) Method for controlling rock burst of hard roof jump mining working face

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130206