CN102182499B - Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed - Google Patents

Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed Download PDF

Info

Publication number
CN102182499B
CN102182499B CN2011100997914A CN201110099791A CN102182499B CN 102182499 B CN102182499 B CN 102182499B CN 2011100997914 A CN2011100997914 A CN 2011100997914A CN 201110099791 A CN201110099791 A CN 201110099791A CN 102182499 B CN102182499 B CN 102182499B
Authority
CN
China
Prior art keywords
pressure
coal
sand
water
waterpower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2011100997914A
Other languages
Chinese (zh)
Other versions
CN102182499A (en
Inventor
黄炳香
程庆迎
付军辉
张统
管辉
刘江伟
薛伟超
王友壮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN2011100997914A priority Critical patent/CN102182499B/en
Publication of CN102182499A publication Critical patent/CN102182499A/en
Application granted granted Critical
Publication of CN102182499B publication Critical patent/CN102182499B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a hydrofracturing-based method and hydrofracturing-based equipment for diminishing dust and eliminating outburst of a coal bed. The method comprises the following steps of: firstly, drilling a long hole towards a working surface in a return airway of the coal-excavating working surface, sealing the hole with a hole sealer for hydrofracturing and forming a hydrofractured seam in the coal rock body; secondly, adding sand into a sand mixer and conveying the mixed fluid of water and sand into the hydrofractured seam by using a mud sand pump, wherein thin sand is added first and then thick sand is added; thirdly, connecting a mash gas extracting pipeline to the hydrofractured hole, draining water through negative pressure and extracting mash gas; and finally, removing the mash gas extracting pipeline from the hole sealer, and connecting a static-pressure water-injecting pipeline for performing static-pressure water injection into the coal bed after the hydrofracturing and the mash gas extraction and stopping water injection till the water flows to the position 3 to 5m ahead of the coal wall of the working surface. By employing the expansion of the main hydrofractured seam of the coal bed, the expansion of wing-shaped branched seams and the soaking effect of the absorbed water, the structure of the coal bed is changed, the strength of the coal bed is weakened and the permeability of the coal bed is improved, so the aims of weakening the strength of the coal bed, increasing the permeability of the coal bed, eliminating the outburst and diminishing the dust are achieved.

Description

A kind of causing based on waterpower split the method and apparatus that the coal seam subtracts the dirt extinction
Technical field
The present invention relates to the method and apparatus of a kind of colliery extinction, especially a kind ofly make coal seam weakening strength, anti-reflection, extinction, subtract causing of dirt and split the method and apparatus that the coal seam subtracts the dirt extinction based on waterpower.
Background technology
Control, the reduction of hard top coal are pressed in the coal mine impact ore deposit, the coal containing methane gas layer is anti-reflection, coal and gas outburst prevention treatment and subtract the major issue that dirt is progress of coal mining always.For overcoming the above problems, existing method action effect is single, can not accomplish impulsion pressure control, the reduction of hard top coal, the coal containing methane gas layer is anti-reflection, coal and gas outburst prevention treatment and subtract the integrated control of dirt.For example traditional gas pumping method is just beaten intensive long drilled holes in coal rock layer, just direct then mash gas extraction, and it is dark and very close to hole, and causes construction loaded down with trivial details, and the extraction effect is very undesirable, effectively integrated control.Also had for example and adopt coal-bed flooding to prevent and treat the method that press in the coal mine impact ore deposit, the water injection pressure effect and not obvious that causes less than normal, it is poorer to subtract the dirt effect.
Summary of the invention
Technical problem: the objective of the invention is to the problem that exists in the prior art; Provide a kind of method simple, easy to operate, controlled good; Safe and reliable, control is pressed in effective coal mine impact ore deposit, the coal containing methane gas layer is anti-reflection, coal and gas outburst prevention treatment and subtract incorporate method and apparatus such as dirt.
Technical scheme: of the present invention causing based on waterpower split the method that the coal seam subtracts the dirt extinction, comprises the steps:
A. according to the required time of punching pressure break, mash gas extraction, the moistening softening process of coal body and the actual fltting speed of work plane, confirm to cause the distance of leading rib when splitting drilling construction;
B. the hole of in coal mining tailentry road, in the work plane coal body, drilling successively, the degree of depth of boring is no less than 1/2 of coal-getter's face length degree, in boring, places high-pressure rubber pipe then, and the installation hole packer carries out sealing of hole apart from hell 8~10 m places;
C. utilize high-pressure pump in boring, to carry out the pulsed high pressure water injection, coal body is carried out waterpower cause and split, make and produce a large amount of hydraulic fracture in the coal body through high-pressure rubber pipe;
D. after waterpower causes and splits completion, in puddle mixer, add fine sand earlier, after add coarse sand, utilize the water sand pump that sand water fluid-mixing is transported in the hydraulic fracture through sand delivering pipeline;
E. after annotating the sand completion, with after the aperture direction moves 2~3m, carrying out sealing of hole once more after the hole packer release, avoid waterpower to cause the influence in crack, the place connects the gas drainage under suction pipeline in the aperture, carries out draining and gas pumping;
F. after gas pumping is accomplished; Pull down the gas pumping pipeline from hole packer; Connect the static pressure water injecting pipeline to waterpower cause split with gas pumping after coal body carry out the static pressure water filling, the aperture water pressure that requires the static pressure water filling is more than or equal to critical pore water pressure and waterpower pad value sum;
G. when coal-face is advanced into distance first boring 3~5m place, stop water filling, accomplishes a waterpower and cause and split the coal seam and subtract the dirt extinction and circulate, repeating step b, c, d, e, f are until the exploitation of the whole coal-face of completion.
The pressure of said pulsed high pressure water injection is 20~30 MPa; Described static pressure water injection pressure is 2~3 MPa.
Cause the equipment that the coal seam subtracts the dirt extinction that splits based on waterpower; Comprise hole packer; Also comprise the high-pressure pump, water sand pump and the puddle mixer that are laid in the return aircourse, be connected with the high-pressure rubber pipe that inserts in the boring on the high-pressure pump, be connected to real-time display monitoring appearance of flow/pressure and pressure-relief valve on the high-pressure rubber pipe; Puddle mixer is provided with water inlet pipe and sand inlet, and puddle mixer is connected with the water sand pump through sand delivering pipeline, is connected to flow detector and pressure-relief valve on the sand delivering pipeline.
Beneficial effect: the present invention can effectively prevent and treat the coal mine impact ore deposit pressure accident in the fracturing scope; Through carrying out gas pumping after the pulsed high pressure water injection pressure break again; And then cause through waterpower and to carry out the static pressure water filling after splitting, compared with present technology, it is effective that coal-bed flooding subtracts dirt; Can remove numerous hidden danger of safety of coal mines in advance, the spontaneous combustion of prevention coal is got angry also has good effect in addition.For the ore deposit press control, the reduction of hard top coal, the coal containing methane gas layer is anti-reflection, aspects such as dirt are given prominence to, subtracted to control coal and gas, result of use is good, the gas pumping amount is remarkable, has the benefit of achieving many things at one stroke.Its technology is simple, and is controlled good, and easy construction is safe and reliable, effective, has practicality widely.
Description of drawings
Fig. 1 is that of the present invention causing based on waterpower split the coal seam and subtracted dirt extinction method sketch map.
Fig. 2 is that of the present invention causing based on waterpower split the device structure sketch map that the coal seam subtracts the dirt extinction.
Fig. 3 is that of the present invention causing based on waterpower split the principle schematic that the coal seam subtracts dirt extinction method.
Fig. 4 is a coal and rock pore water pressure curve map of the present invention.
Among the figure: the 1-hole packer; The 2-pressure-relief valve; The real-time display monitoring appearance of 3-flow/pressure; The 4-high-pressure rubber pipe; The 5-pressure meter; 6-water sand pump; The 7-flow detector; The 8-puddle mixer; The 8-1-agitator; The 8-2-sand inlet; 9-boring; The 10-coal body; The 11-water inlet pipe; 12-puddle mixer motor; The 13-high-pressure pump; The 14-sand delivering pipeline; 15-water sand pump motor; A-air intake lane; The b-return aircourse; C-tunnel relaxation zone radius; Sealed borehole length when d-gas pumping or static pressure water filling; E-hole packer displacement; The f-sealed borehole length; The g-hydraulic fracture; The h-drilling depth; P-critical pore water pressure; X-causes the distance of leading rib when splitting drilling construction; W-waterpower causes splits hole sealing depth; The v-spacing of wells.
The specific embodiment
As shown in Figure 1, the average thickness of certain pit coal layer is 15m, and the hardness in coal seam is 3, and seam inclination is 11 °, and the coal seam buried depth is 550m, and active length is 168m, adopts the top coal caving method to mine, and taking and placing are than 1:2.5, and top board is a sandstone, and the hardness of sandstone is 6.According to the required time of the moistening operation such as softening of punching pressure break, mash gas extraction, coal body and the actual fltting speed of work plane, what confirm to cause leading rib when splitting drilling construction is 20m apart from x; In the tailentry road b apart from base plate 1.5m place along coal body 10 tendencies play the boring 9 that length is 130m; The degree of depth of boring 9 is no less than 1/2 of coal-getter's face length degree; Bore diameter is 75mm; Spacing of wells v is 16m, and the place couples together high-pressure rubber pipe 4 and the real-time display monitoring appearance 3 of flow/pressure in the aperture, carries out flow/pressure and shows monitoring in real time; Waterpower causes that sealing of hole segment length d+ hole packer displacement e+ waterpower causes the sealing of hole degree f when splitting water filling when splitting hole sealing depth=roadway surrounding rock relaxation zone radius c+ mash gas extraction or static pressure water filling; Drawing the hole sealing depth that waterpower causes when splitting is 8~10m; Put into high-pressure rubber pipe 4 in 9 approximately to 1/2 place of hole depth to boring then; And apart from hell 8~10 m places hole packer 1 is installed and is carried out conventional sealing of hole; Inject water under high pressure with high-pressure pump 13 through high-pressure rubber pipe 4 pulsed in boring 9 afterwards, the pressure of pulsed high pressure water injection is 20~30 MPa, when the real-time display monitoring appearance 3 demonstration flows of flow/pressure increase considerably, when pressure reduces significantly; The real-time display monitoring appearance 3 of flow/pressure can feed back to high-pressure pump 13 to order according to the parameter of flow, pressure setting, and high-pressure pump 13 stops water filling.Through high pressure water injection coal and rock 10 is carried out waterpower and cause and split, make and produce a large amount of hydraulic fracture g in the coal and rock 10; After waterpower causes and splits completion; Remove high-pressure rubber pipe 4 from hole packer 1, in boring 9, put into sand delivering pipeline 14 then, through adding fine sand in the puddle mixer 8 earlier; After add coarse sand; Utilize water sand pump 6 that sand water fluid-mixing is transported among the hydraulic fracture g through sand delivering pipeline 14, when the pressure value of pressure meter 5 demonstrations rises sharply, stop to annotate sand.Accomplish and annotate after the sand; Hole packer 1 release, the aperture direction is carried out sealing of hole once more after moving 2~3m; The sealing of hole segment length f of hole packer 1 should be greater than the extension length (extension length universal experience value be 1.5m) of hydraulic fracture in the sealing of hole section, avoids waterpower to cause the influence in crack, and is as shown in Figure 3.The place connects the gas drainage under suction pipeline in the aperture, carries out draining and gas pumping; After gas pumping is accomplished; Pull down the gas pumping pipeline from hole packer 1; Connect the static pressure water injecting pipeline to waterpower cause split with gas pumping after coal body 10 carry out the static pressure water filling, as shown in Figure 4, confirm critical pore water pressure p according to the peak value flex point of coal and rock pore water pressure force curve; Owing in boring, there is the water pressure decay; So need satisfy the static pressure water filling in the water pressure in aperture more than or equal to critical pore water pressure p and waterpower pad value sum, thereby when confirming the static pressure water filling in the water pressure value in aperture, the water pressure value in the aperture during static pressure water filling is generally 2~3 MPa.When coal-face is advanced into the distance boring 3~5m of 9 places, stop water filling, accomplishes a waterpower and cause and split the coal seam and subtract the dirt extinction and circulate.Next boring 9 is played in continuation in work plane coal body 10; Repeat said process, accomplish next waterpower and cause and split the coal seam and subtract dirt extinction circulation, along with the continuous propelling of work plane; The waterpower of accomplishing whole coal-face causes to be split the coal seam and subtracts dirt extinction circulation, finishes until the coal mining of coal-face.Water sand pump 6 is connected with sand delivering pipeline 14 passes hole packer 1 and deliver to boring and annotate sand in 9; After accomplishing notes sand hole packer 1 release is carried out sealing of hole once more after the aperture direction moves 2~3m, connection gas drainage under suction pipeline carries out draining and draws out methane; After gas pumping is accomplished, pull down the gas pumping pipeline from hole packer 1, connect the static pressure water injecting pipeline to waterpower cause split with gas pumping after coal body 10 carry out the static pressure water filling and when coal-face is advanced into the distance boring 3~5m of 9 places, stop water filling.
As shown in Figure 2; The present invention is based on waterpower and cause the equipment that the coal seam subtracts the dirt extinction that splits; Mainly constitute by hole packer 1, the high-pressure pump 13, water sand pump 6 and the puddle mixer 8 that are laid in the b of return aircourse; Be connected with the high-pressure rubber pipe 4 that inserts in the boring 9 on the high-pressure pump 13, be connected to real-time display monitoring appearance 3 of flow/pressure and pressure-relief valve 2 on the high-pressure rubber pipe 4; Puddle mixer 8 mainly is made up of the puddle mixer motor 12 of agitator 8-1, control agitator 8-1, and puddle mixer 8 is provided with water inlet pipe 11 and sand inlet 8-2, on the water inlet pipe 11 by-pass valve control is arranged.Puddle mixer 8 is connected with water sand pump 6 through sand delivering pipeline 14, is connected to flow detector 7 and pressure-relief valve on the sand delivering pipeline 14.Be furnished with water sand pump motor 15 and water sand pump pressure table 5 on the water sand pump 6.

Claims (1)

1. one kind causes based on waterpower and to split the method that the coal seam subtracts the dirt extinction, it is characterized in that comprising the steps:
A. according to the required time of punching pressure break, mash gas extraction, the moistening softening process of coal body and the actual fltting speed of work plane, confirm to cause the distance (x) of leading rib when splitting drilling construction;
B. the hole (9) of in coal mining tailentry road (b), in work plane coal body (10), drilling successively; The degree of depth of boring is no less than 1/2 of coal-face length; In boring, place high-pressure rubber pipe (4) then, and apart from hell 8~10 m places hole packer (1) is installed and is carried out sealing of hole;
C. utilize high-pressure pump (13) to carry out the pulsed high pressure water injection to boring in (9), coal body (10) is carried out waterpower cause and split, make and produce a large amount of hydraulic fracture in the coal body (10) through high-pressure rubber pipe (4);
D. after waterpower causes and splits completion, in puddle mixer (8), add fine sand earlier, after add coarse sand, utilize water sand pump (6) that sand water fluid-mixing is transported in the hydraulic fracture (g) through sand delivering pipeline (14);
E. after annotating the sand completion, with after the aperture direction moves 2~3m, carrying out sealing of hole once more after hole packer (1) release, avoid waterpower to cause the influence in crack, the place connects the gas drainage under suction pipeline in the aperture, carries out draining and gas pumping;
F. after gas pumping is accomplished; Pull down the gas pumping pipeline from hole packer (1); Connect the static pressure water injecting pipeline to waterpower cause split with gas pumping after coal body (10) carry out the static pressure water filling, the aperture water pressure that requires the static pressure water filling is more than or equal to critical pore water pressure (p) and waterpower pad value sum;
G. when coal-face is advanced into distance first boring (9) 3~5m places, stop water filling, accomplishes a waterpower and cause and split the coal seam and subtract the dirt extinction and circulate, repeating step b, c, d, e, f are until the exploitation of the whole coal-face of completion.
2. according to claim 1 causing based on waterpower split the method that the coal seam subtracts the dirt extinction, and it is characterized in that: the pressure of said pulsed high pressure water injection is 20~30 MPa.
3. according to claim 1 causing based on waterpower split the method that the coal seam subtracts the dirt extinction, and it is characterized in that: described static pressure water injection pressure is 2~3 MPa.
One kind realize claim 1,2 or 3 said methods cause the equipment that the coal seam subtracts the dirt extinction that splits based on waterpower; Comprise hole packer (1); It is characterized in that: also comprise the high-pressure pump (13), water sand pump (6) and the puddle mixer (8) that are laid in the return aircourse (b); Be connected with the high-pressure rubber pipe (4) that inserts in the boring (9) on the high-pressure pump (13), be connected to real-time display monitoring appearance of flow/pressure (3) and pressure-relief valve (2) on the high-pressure rubber pipe (4); Puddle mixer (8) is provided with water inlet pipe (11) and sand inlet (8-2), and puddle mixer (8) is connected with water sand pump (6) through sand delivering pipeline (14), is connected to flow detector (7) and pressure-relief valve (2) on the sand delivering pipeline (14).
CN2011100997914A 2011-04-21 2011-04-21 Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed Active CN102182499B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100997914A CN102182499B (en) 2011-04-21 2011-04-21 Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100997914A CN102182499B (en) 2011-04-21 2011-04-21 Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed

Publications (2)

Publication Number Publication Date
CN102182499A CN102182499A (en) 2011-09-14
CN102182499B true CN102182499B (en) 2012-11-14

Family

ID=44568777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100997914A Active CN102182499B (en) 2011-04-21 2011-04-21 Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed

Country Status (1)

Country Link
CN (1) CN102182499B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2547873C1 (en) * 2013-12-10 2015-04-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Method of stimulation of coal bed through wells drilled from excavations

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2520669C1 (en) * 2013-03-12 2014-06-27 Федеральное государственное бюджетное учреждение науки Институт горного дела им. Н.А. Чинакала Сибирского отделения Российской академии наук Coal seam degassing
CN103541711B (en) * 2013-10-21 2016-04-13 中国矿业大学 Xuan Ding small-bore, coal-face termination hydraulic fracture control method
RU2540709C1 (en) * 2013-12-10 2015-02-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Method of shock wave destruction of coal seam through wells drilled from excavation
CN104594901B (en) * 2014-12-08 2016-05-25 太原理工大学 A kind of working face is invaded the method in district by igneous rock
CN105003294B (en) * 2015-07-30 2017-09-29 山东科技大学 One kind is based on hydrothermal reaction coupling pressure break coal body coal uncovering method
CN105422164B (en) * 2015-12-14 2018-03-06 河南理工大学 Hydrofracturing is anti-reflection to aid in coal seam efficient water injection method and apparatus
CN105649625B (en) * 2016-01-15 2017-11-21 山东科技大学 A kind of high-low pressure subregion fracturing anatonosis formula coal-bed flooding method
CN106703871B (en) * 2017-02-06 2019-03-01 华北科技学院 A kind of method of high pressure water injection prevention and treatment gas and coal dust
CN106907175B (en) * 2017-05-02 2019-06-04 中国矿业大学 The efficient extraction coal roadway stripe gas of bottom plate concordant long drilled holes staged fracturing and region outburst elimination method
CN108266222A (en) * 2018-01-10 2018-07-10 中国矿业大学 A kind of solvent extraction, moistening reversion, pulsation pressure break Trinity coal body anti-reflection method
CN109098750B (en) * 2018-09-20 2023-12-15 中国矿业大学 Device for underground gas extraction hole to be used as coal seam water injection hole and construction method
CN109538198B (en) * 2018-11-12 2022-06-14 辽宁大学 Experimental device for preventing and treating coal seam disaster gas injection bubble water and punching integration and application
CN109989783B (en) * 2019-05-14 2023-08-15 河南理工大学 Supercritical carbon dioxide positive and negative pressure interaction combined gas extraction system and gas extraction method
CN110130826A (en) * 2019-07-01 2019-08-16 中煤新集能源股份有限公司 A kind of complete method of underground mine Driving Face in Coal Tunnel synthesis dust prevention
CN110617102A (en) * 2019-10-08 2019-12-27 刘云山 Method for quickly releasing gas in coal mine underground high-pressure water injection fracturing coal seam
CN110646584B (en) * 2019-10-09 2021-09-24 中煤科工集团重庆研究院有限公司 Similar simulation method and device for coal seam water injection hole sealing test
CN111197497B (en) * 2020-03-04 2022-03-11 淮南矿业(集团)有限责任公司 Rock cross-cut coal uncovering high-pressure hydraulic punching comprehensive permeability increasing method
CN111794798B (en) * 2020-07-13 2022-04-19 安徽理工大学 Working face dynamic pressure water injection dust fall method for layered fully-mechanized mining of slowly-inclined thick coal seam
CN114046148B (en) * 2021-11-10 2023-02-21 中国矿业大学 Liquid CO 2 Method for improving coal seam water injection effect by fracturing and permeability increasing
CN114151124B (en) * 2021-11-30 2023-03-24 中国矿业大学 Water injection dust reduction method for intelligent liquid carbon-water circulating injection fracturing and moistening coal seam
CN114109382B (en) * 2021-11-30 2023-02-24 中国矿业大学 Coal bed liquid CO 2 Water intelligent circulating filling, cracking, moistening and dust reducing system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575983A (en) * 2009-02-27 2009-11-11 河南省煤层气开发利用有限公司 Directional fracturing permeability improvement outburst elimination method in coal mine and device thereof.
CN101718191A (en) * 2009-08-27 2010-06-02 中国矿业大学 Directional cracking method for waterpower slotting
CN101824982A (en) * 2010-04-19 2010-09-08 中国矿业大学 Coal bed gas drainage effective radius measuring method
CN101956546A (en) * 2010-09-14 2011-01-26 中国矿业大学 Method for improving crossing-hole gas extraction concentration

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8424599B2 (en) * 2007-03-29 2013-04-23 Fracmaster, Llc Automated closed loop flowback and separation system
US20110030963A1 (en) * 2009-08-04 2011-02-10 Karl Demong Multiple well treatment fluid distribution and control system and method
US8171993B2 (en) * 2009-09-18 2012-05-08 Heat On-The-Fly, Llc Water heating apparatus for continuous heated water flow and method for use in hydraulic fracturing

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575983A (en) * 2009-02-27 2009-11-11 河南省煤层气开发利用有限公司 Directional fracturing permeability improvement outburst elimination method in coal mine and device thereof.
CN101718191A (en) * 2009-08-27 2010-06-02 中国矿业大学 Directional cracking method for waterpower slotting
CN101824982A (en) * 2010-04-19 2010-09-08 中国矿业大学 Coal bed gas drainage effective radius measuring method
CN101956546A (en) * 2010-09-14 2011-01-26 中国矿业大学 Method for improving crossing-hole gas extraction concentration

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2547873C1 (en) * 2013-12-10 2015-04-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Method of stimulation of coal bed through wells drilled from excavations

Also Published As

Publication number Publication date
CN102182499A (en) 2011-09-14

Similar Documents

Publication Publication Date Title
CN102182499B (en) Hydrofracturing-based method and equipment for diminishing dust and eliminating outburst of coal bed
CN101575983B (en) Directional fracturing permeability improvement outburst elimination method in coal mine and device thereof.
CN110145233B (en) Rock burst coal seam drilling-cutting-pressing-pumping-injecting multi-disaster cooperative prevention and control method
CN102383828B (en) Refection reducing and outburst eliminating method for deep-hole hydraulic fracture driving gas shallow hole extraction
CN105971663B (en) A kind of the drilling arrangement and anti-reflection method of coal seam high-pressure hydraulic slot pressure break
CN104747075B (en) Anti-collapsing drilling method for grout spraying of soft coal seam
CN101666241B (en) Integrated drilling-blasting-pressurizing-drawing protrusion preventing method for regional gas control
CN110552671B (en) CO auxiliary by dimethyl ether 2 Method for realizing high-efficiency development of heavy oil reservoir by flooding
CN104879159B (en) A kind of devices and methods therefor of weak seam stope anti-reflection mash gas extraction
CN101608552A (en) The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process
CN102937011A (en) Secondary grouting and plugging device and method of regional crack field of gas extraction and drilling group
RU2419723C1 (en) Degasation method of developed coal beds
CN108397227A (en) A kind of progressive extinction roadway layout method of tendency
CN103195467A (en) Hydraulic fracturing and grouting solidification combined rock cross-cut coal uncovering method
CN102678092A (en) Method for commonly extracting coal and coal bed gas by up-hole and down-hole joint construction
CN102518412A (en) Method for mining coal and gas by hydraulic jet grouting washout
CN113503150B (en) Bauxite in-situ leaching exploitation method
CN113216962B (en) Synergistic anti-reflection desorption promotion experimental system and method for ultrasonic activated fracturing fluid
CN105089493A (en) Ground vertical well and underground cross drilling combined pressure-released coal-bed gas extraction method
CN108915690B (en) Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling
CN106437737A (en) Pipe jacking type coal mine small section roadway tunneling method
CN113217043A (en) Efficient and rapid plugging method and construction method for water source with water inrush fault water guide zone
CN103032059B (en) A kind of directed hydraulic pressure burst communicatin exploitation method
CN109113701A (en) Using air as the anti-reflection technology of pulsating pressure-air creep pressure break and device of medium
RU2511329C1 (en) Method of action on coal bed

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant