CN102116028B - 一种木排桩支护开挖核心筒区域土方的方法及结构 - Google Patents
一种木排桩支护开挖核心筒区域土方的方法及结构 Download PDFInfo
- Publication number
- CN102116028B CN102116028B CN201110006802XA CN201110006802A CN102116028B CN 102116028 B CN102116028 B CN 102116028B CN 201110006802X A CN201110006802X A CN 201110006802XA CN 201110006802 A CN201110006802 A CN 201110006802A CN 102116028 B CN102116028 B CN 102116028B
- Authority
- CN
- China
- Prior art keywords
- raft
- stake
- layer
- foundation ditch
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明公开了一种木排桩支护开挖核心筒区域土方的方法及结构,本发明按基坑的长宽要求在基坑边缘一个挨一个的垂直打入第一层木排桩,在第一层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;在第一层木排桩外侧的地面垂直打入钢地锚;用拉筋将钢地锚与水平木桩拉紧;在第一层木排桩内侧开挖基坑;在基坑底部边缘垂直打入第二层木排桩;在第二层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;用拉桩将第一层木排桩与第二层木排桩经门型抓钉连接;在第二层木排桩内侧继续开挖基坑;再在基坑底部打入第三层木排桩;用木桩将第二层木排桩与第三层木排桩经抓钉连接;以此类推,直至挖到设计深度。本发明具有施工简单、快捷、经济的特点。
Description
技术领域
本发明涉及一种木排桩支护开挖核心筒区域土方的方法及结构,属于建筑施工技术领域。
背景技术
在建筑工程施工中,核心筒区域的土方开挖一般是在大面积土方开挖完成之后进行,在这个时期,地下水位丰富,如果正逢雨季施工,在场地狭小,淤泥较多的情况下,大型机械无法进入现场作业。在这种场地条件下如采用复杂的施工工艺将对施工工期带来不利影响。
发明内容
本发明的目的在于,提供一种可以在恶劣条件下提高施工速度、减少土方开挖面积、减小工人劳动量、同时也能大幅提高核心筒土方开挖工作效率的木排桩支护开挖核心筒区域土方的方法及结构,从而克服现有技术的不足。
本发明的技术方案:本发明的一种木排桩支护开挖核心筒区域土方的方法是按以下步骤操作:
A、按基坑的长宽要求在基坑边缘一个挨一个的垂直打入第一层木排桩,构成木排桩的木桩长度为3-4米;
B、在第一层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;
C、在第一层木排桩外侧2.5~3.5米处每间隔1.5~2.5米的地面垂直打入钢地锚,钢地锚的打入深度为2~3米;
D、用直径为10毫米以上的拉筋将钢地锚与水平木桩拉紧;
E、在第一层木排桩内侧开挖基坑,基坑的边缘为40~50°斜坡;
F、当基坑挖至1.5米深度时,再在基坑底部边缘一个挨一个的垂直打入第二层木排桩;
G、在第二层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;
H、用拉桩每间隔1.5~2.5米将第一层木排桩与第二层木排桩经门型抓钉连接;
I、在第二层木排桩内侧继续开挖基坑,基坑的边缘为40~50°斜坡;
J、当基坑挖至3米深度时,再在基坑底部边缘一个挨一个的垂直打入第三层木排桩;
K、用木桩每间隔1.5~2.5米将第二层木排桩与第三层木排桩经门型抓钉连接;
L、以此类推,每挖1.5米时,就打一层木排桩,并将两层木排桩用木桩连接,直至挖到设计深度;
M、最后在基坑底部的边缘砌一圈砖墙,在砖墙与边坡之间加填石粉,夯实。
前述木排桩支护开挖核心筒区域土方的方法中,所述木排桩、水平木桩和拉桩所用的材料均为直径为100~150毫米的圆木。
按照上述方法构建的一种木排桩支护开挖核心筒区域土方的结构,包括基坑,基坑的边缘为斜坡,沿基坑的边缘至少设有两层间隔设置的木排桩,每层木排桩的高度差为1.5米;每层木排桩的内侧均设有水平木桩,最外层木排桩的外侧间隔的设有钢地锚,钢地锚经拉筋与最外层木排桩的水平木桩连接;两层木排桩之间间隔的设有拉桩;基坑底部的边缘设有砖墙,在砖墙与基坑的边缘之间设有回填石粉。
前述的结构中,所述基坑的边缘为斜坡,其坡度为40~50°。
前述的结构中,所述木排桩、水平木桩和拉桩所用材料为圆木;木排桩的圆木长度为3-4米;拉桩的圆木长度根据两层木排桩的顶部距离确定。
前述的结构中,所述水平木桩与木排桩经门型抓钉连接;拉桩与木排桩经门型抓钉连接。
前述的结构中,所述钢地锚的间距为1.5~2.5米,钢地锚打入地下2~3米,露出地面0.3~0.5米。
由于采用了上述技术方案,本发明可以在恶劣条件下提高施工速度,减少土方开挖面积,减小工人劳动量,同时也能大幅提高核心筒土方开挖时的工作效率。因此,本发明与现有技术相比,本发明不仅具有施工简单、快捷、工作效率高的优点,而且还具有能有效减小工人劳动量、提高经济效益、同时提高恶劣条件下土方开挖的适用性等优点。
附图说明
图1是本发明的结构示意图;
图2是本发明的俯视平面图。
附图中的标记为:1-基坑,2-木排桩,3-水平木桩,4-钢地锚,5-拉筋,6-拉桩,7-砖墙,8-回填石粉,9-门型抓钉。
具体实施方式
下面结合附图和实施例对本发明作进一步的详细说明,但不作为对本发明进行任何限制的依据。
本发明的实施例:本发明的结构如图1和图2所示,在实施本发明的一种木排桩支护开挖核心筒区域土方的方法时,按以下步骤进行操作:
A、按基坑的长宽要求在基坑边缘一个挨一个的垂直打入第一层木排桩,构成木排桩的木桩长度为4米;
B、在第一层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;
C、在第一层木排桩外侧3米处每间隔2米的地面垂直打入钢地锚,钢地锚的打入深度为2.5米;
D、用直径为10毫米以上的拉筋将钢地锚与水平木桩拉紧;
E、在第一层木排桩内侧开挖基坑,基坑的边缘为45°斜坡;
F、当基坑挖至1.5米深度时,再在基坑底部边缘一个挨一个的垂直打入第二层木排桩;
G、在第二层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;
H、用拉桩每间隔2米将第一层木排桩与第二层木排桩经门型抓钉连接;
I、在第二层木排桩内侧继续开挖基坑,基坑的边缘为45°斜坡;
J、当基坑挖至3米深度时,再在基坑底部边缘一个挨一个的垂直打入第三层木排桩;
K、用木桩每间隔2米将第二层木排桩与第三层木排桩经门型抓钉连接;
L、以此类推,每挖1.5米时,就打一层木排桩,并将两层木排桩用木桩连接,直至挖到设计深度;
M、最后在基坑底部的边缘砌一圈砖墙,在砖墙与边坡之间加填石粉,夯实。
前述木排桩支护开挖核心筒区域土方的方法,所述木排桩、水平木桩和拉桩所用的材料均为直径为100~150毫米的圆木。
根据上述方法构建的本发明的一种木排桩支护开挖核心筒区域土方的结构为:该结构包括基坑1,基坑1的边缘为斜坡,其坡度为45°。沿基坑1的边缘至少设有两层间隔设置的木排桩2,每层木排桩2的高度差为1.5米;每层木排桩2的内侧均设有水平木桩3,最外层木排桩2的外侧间隔的设有钢地锚4,钢地锚4经拉筋5与最外层木排桩2的水平木桩3连接;两层木排桩2之间间隔的设有拉桩6;基坑1底部的边缘设有砖墙7,在砖墙7与基坑1的边缘之间设有回填石粉8。所述木排桩2、水平木桩3和拉桩6所用材料为圆木;木排桩2的圆木长度为3-4米;拉桩6的圆木长度根据两层木排桩2的顶部距离确定。所述水平木桩3与木排桩2经门型抓钉9连接;拉桩6与木排桩2经门型抓钉9连接。所述钢地锚4的间距为2米,钢地锚4打入地下2.5米,露出地面0.3米。
Claims (2)
1.一种木排桩支护开挖核心筒区域土方的方法,其特征在于:该方法按以下步骤操作:
A、按基坑的长宽要求在基坑边缘一个挨一个的垂直打入第一层木排桩,构成木排桩的木桩长度为3-4米;
B、在第一层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;
C、在第一层木排桩外侧2.5~3.5米处每间隔1.5~2.5米的地面垂直打入钢地锚,钢地锚的打入深度为2~3米;
D、用直径为10毫米以上的拉筋将钢地锚与水平木桩拉紧;
E、在第一层木排桩内侧开挖基坑,基坑的边缘为40~50°斜坡;
F、当基坑挖至1.5米深度时,再在基坑底部边缘一个挨一个的垂直打入第二层木排桩;
G、在第二层木排桩的基坑一侧用门型抓钉固定一圈水平木桩;
H、用拉桩每间隔1.5~2.5米将第一层木排桩与第二层木排桩经门型抓钉连接;
I、在第二层木排桩内侧继续开挖基坑,基坑的边缘为40~50°斜坡;
J、当基坑挖至3米深度时,再在基坑底部边缘一个挨一个的垂直打入第三层木排桩;
K、用拉桩每间隔1.5~2.5米将第二层木排桩与第三层木排桩经门型抓钉连接;
L、以此类推,每挖1.5米时,就打一层木排桩,并将两层木排桩用拉桩连接,直至挖到设计深度;
M、最后在基坑底部的边缘砌一圈砖墙,在砖墙与边坡之间加填石粉,夯实。
2.根据权利要求1所述木排桩支护开挖核心筒区域土方的方法,其特征在于:所述木排桩、水平木桩和拉桩所用的材料均为直径为100~150毫米的圆木。
3、一种木排桩支护开挖核心筒区域土方的结构,其特征在于:包括基坑(1),基坑(1)的边缘为斜坡,沿基坑(1)的边缘至少设有两层间隔设置的木排桩(2),每层木排桩(2)的高度差为1.5米;每层木排桩(2)的内侧均设有水平木桩(3),最外层木排桩(2)的外侧间隔的设有钢地锚(4),钢地锚(4)经拉筋(5)与最外层木排桩(2)的水平木桩(3)连接;两层木排桩(2)之间间隔的设有拉桩(6);基坑(1)底部的边缘设有砖墙(7),在砖墙(7)与基坑(1)的边缘之间设有回填石粉(8)。
4、根据权利要求3所述的木排桩支护开挖核心筒区域土方的结构,其特征在于:所述基坑(1)的边缘为斜坡,其坡度为40~50°。
5、根据权利要求3所述的木排桩支护开挖核心筒区域土方的结构,其特征在于:所述木排桩(2)、水平木桩(3)和拉桩(6)所用材料为圆木;木排桩(2)的圆木长度为3-4米;拉桩(6)的圆木长度根据两层木排桩(2)的顶部距离确定。
6、根据权利要求3所述的木排桩支护开挖核心筒区域土方的结构,其特征在于:所述水平木桩(3)与木排桩(2)经门型抓钉(9)连接;拉桩(6)与木排桩(2)经门型抓钉(9)连接。
7、根据权利要求3所述的木排桩支护开挖核心筒区域土方的结构,其特征在于:所述钢地锚(4)的间距为1.5~2.5米,钢地锚(4)打入地下2~3米,露出地面0.3~0.5米。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110006802XA CN102116028B (zh) | 2011-01-13 | 2011-01-13 | 一种木排桩支护开挖核心筒区域土方的方法及结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110006802XA CN102116028B (zh) | 2011-01-13 | 2011-01-13 | 一种木排桩支护开挖核心筒区域土方的方法及结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102116028A CN102116028A (zh) | 2011-07-06 |
CN102116028B true CN102116028B (zh) | 2012-05-23 |
Family
ID=44214941
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110006802XA Expired - Fee Related CN102116028B (zh) | 2011-01-13 | 2011-01-13 | 一种木排桩支护开挖核心筒区域土方的方法及结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102116028B (zh) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102383435B (zh) * | 2011-09-28 | 2015-06-10 | 中铁大桥局集团有限公司 | 一种高落差大堤双排桩 |
CN103243721B (zh) * | 2013-05-22 | 2016-02-17 | 中国建筑第八工程局有限公司 | 软弱地质条件下高层建筑筏板基础及核心筒开挖施工方法 |
CN105714846B (zh) * | 2014-12-02 | 2018-09-04 | 中国石油天然气股份有限公司 | 一种重力式挡土墙及其施工方法 |
CN104532851B (zh) * | 2014-12-17 | 2017-01-11 | 北京工业大学 | 一种回收装配式双排桩及其支护方法 |
CN105297750B (zh) * | 2015-11-17 | 2017-07-07 | 中国铁道科学研究院铁道建筑研究所 | 一种防护边坡构筑方法 |
CN108677967A (zh) * | 2018-05-28 | 2018-10-19 | 郑林 | 一种填土层中钢花管土钉组合地锚支护方法 |
CN109914425B (zh) * | 2019-03-26 | 2020-07-28 | 五冶集团上海有限公司 | 一种超高层核心筒区域砖胎膜的施工方法 |
CN112081114A (zh) * | 2020-09-07 | 2020-12-15 | 中国建筑第四工程局有限公司 | 一种加速深基坑坑中坑施工速度的微型桩结构 |
CN113529731B (zh) * | 2021-06-03 | 2022-10-25 | 浙江省建筑设计研究院 | 一种斜桩施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1481327A1 (ru) * | 1987-03-31 | 1989-05-23 | Московский Институт По Изысканиям И Проектированию Инженерных Сооружений | Устройство дл креплени ограждений подземных сооружений |
CN1693590A (zh) * | 2005-05-19 | 2005-11-09 | 劳道邦 | 一种治理膨胀土滑坡新技术 |
CN101280566A (zh) * | 2008-05-28 | 2008-10-08 | 浙江舜江建设集团有限公司 | 一种搅拌桩基坑支护结构 |
CN101418570A (zh) * | 2008-11-28 | 2009-04-29 | 天津大学 | 双排桩基坑支护方法 |
CN101649608A (zh) * | 2009-09-01 | 2010-02-17 | 同济大学 | 一种生态护坡结构 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4423115B2 (ja) * | 2004-06-04 | 2010-03-03 | 株式会社不動テトラ | 既設盛土直下の地盤沈下低減改良工法 |
JP4782648B2 (ja) * | 2006-09-22 | 2011-09-28 | 東京インキ株式会社 | 擁壁 |
-
2011
- 2011-01-13 CN CN201110006802XA patent/CN102116028B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1481327A1 (ru) * | 1987-03-31 | 1989-05-23 | Московский Институт По Изысканиям И Проектированию Инженерных Сооружений | Устройство дл креплени ограждений подземных сооружений |
CN1693590A (zh) * | 2005-05-19 | 2005-11-09 | 劳道邦 | 一种治理膨胀土滑坡新技术 |
CN101280566A (zh) * | 2008-05-28 | 2008-10-08 | 浙江舜江建设集团有限公司 | 一种搅拌桩基坑支护结构 |
CN101418570A (zh) * | 2008-11-28 | 2009-04-29 | 天津大学 | 双排桩基坑支护方法 |
CN101649608A (zh) * | 2009-09-01 | 2010-02-17 | 同济大学 | 一种生态护坡结构 |
Non-Patent Citations (4)
Title |
---|
JP特开2005-344412A 2005.12.15 |
JP特开2008-75389A 2008.04.03 |
卢继明.锚碇式双排桩治理滑坡的设计与应用.《铁道建筑技术》.2004,(第3期),全文. * |
蒋国权,沈泽丰.灌江国际大酒店核心筒支护设计与施工.《山西建筑》.2009,第35卷(第21期),全文. * |
Also Published As
Publication number | Publication date |
---|---|
CN102116028A (zh) | 2011-07-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102116028B (zh) | 一种木排桩支护开挖核心筒区域土方的方法及结构 | |
CN102124163B (zh) | 椅式自支撑挡土墙的施工方法 | |
US8974152B2 (en) | Polymer grouting method for constructing vertical supporting system | |
CN103321241B (zh) | 深水开敞式组合基础码头及其施工方法 | |
CN104612179B (zh) | 贯穿超厚粉砂层的地下连续墙的施工方法 | |
CN101597904B (zh) | 一种防水板桩围堰及其施工方法 | |
CN103924602B (zh) | 深厚软土基坑施工方法 | |
CN107059877A (zh) | 一种施工时底部带有链刀的基础及其施工法 | |
CN107142926B (zh) | 浅水河床厚漂石覆盖层上的钢栈桥钢管桩抗冲刷施工方法 | |
CN108532586A (zh) | 一种停车库用地下连续墙的施工方法 | |
CN102116030A (zh) | 一种组合基坑支护结构及其施工方法 | |
CN104895121B (zh) | 一种减小地下结构建设中地表沉降及建构筑物变形的横向隔断法 | |
CN108677925A (zh) | 半预制地下连续墙结构及其施工方法 | |
CN103243721B (zh) | 软弱地质条件下高层建筑筏板基础及核心筒开挖施工方法 | |
CN106948757A (zh) | 一种利用基坑区域进行的地埋管打井施工工艺 | |
CN203782778U (zh) | 逆作法施工地下土外运装置 | |
CN102425179B (zh) | 一种微型钢管灌注桩支撑加筋土渗沟结构 | |
CN209669900U (zh) | 水底强透水砂性土层中隧道建设围堰结构 | |
CN202273235U (zh) | 一种木排桩支护开挖核心筒区域土方的结构 | |
CN103410155B (zh) | 一种可回收前置装配式支撑围护结构及其应用方法 | |
RU121275U1 (ru) | Армированная грунтоцементная стена для защиты зданий и сооружений от откапываемого вблизи котлована | |
CN106337418A (zh) | 一种狭小区域深基坑的支护结构及支护方法 | |
CN104153356B (zh) | 混凝土桩的施工装置及其施工方法 | |
Spagnoli et al. | Support for offshore monopile installation through the trench cutter technology | |
CN201943076U (zh) | 一种组合基坑支护结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120523 Termination date: 20170113 |