US8974152B2 - Polymer grouting method for constructing vertical supporting system - Google Patents
Polymer grouting method for constructing vertical supporting system Download PDFInfo
- Publication number
- US8974152B2 US8974152B2 US13/866,026 US201313866026A US8974152B2 US 8974152 B2 US8974152 B2 US 8974152B2 US 201313866026 A US201313866026 A US 201313866026A US 8974152 B2 US8974152 B2 US 8974152B2
- Authority
- US
- United States
- Prior art keywords
- polymer
- grouting
- supporting system
- constructing
- vertical supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/13—Foundation slots or slits; Implements for making these slots or slits
Definitions
- the present invention belongs to a side slope excavating supporting technology field of infrastructures of civil engineering, water conservancy, mining, municipality, etc., and particularly relates to a polymer grouting method for constructing vertical supporting system of excavating of foundation pit, side slope, municipal pipeline, etc.
- the water stopping method in the side slope supporting system is embodied as technologies, such as cement mixing piles, high-pressure jet grouting pile, and TRD method.
- technologies such as cement mixing piles, high-pressure jet grouting pile, and TRD method.
- the above supporting technologies played important roles in practical projects, but they also have some technical shortages. For example, it is difficult to use the soil nailing wall under the condition of soft soil, unbonded loose sandy soil and rich underground water. In addition, when the soil nailing wall is used as a permanent structure, the problem of durability, such as corrosion, should be considered.
- the design of the composite soil nailing wall is mostly borrowed from the design of soil nailing wall, and the role of advance supporting and water-stopping curtain are not considered in the design and calculation of the composite soil nailing wall.
- For the underground continuous wall sandy soil and mud dug out requires for the settlement equipment and the mechanical equipment, so the cost is high.
- the drainage tends to pollute the underground water, and excavating the slot tends to cause the settlement of the buildings.
- For the row pile supporting structure there is no mature design method at present, and there are few systematic and in-depth researches on the stress mechanism, the working properties and the applicable conditions of the row pile.
- the conventional side slope supporting technology mostly uses cement materials, so the water stopper constructed is a rigid solid having an elastic modulus greatly different from the elastic modulus of the soil, and is poor in impervious anti-cracking property.
- the materials and the soil are disassembled, when stopping the water, and the material grouted in is difficult to form a complete continuum.
- the water stopper is formed by the construction methods, such as excavating slots, mixing, spraying and vibrating, so the side slope structure is greatly damaged by turbulent motions.
- the construction period will be extended to 2 ⁇ 3 times, and the cost will increase by more than 1 time.
- the current situation is not suitable for the development requirement of the infrastructure building of civil engineering, water conservancy, mining, municipality, etc. of our country at present. Therefore, the research and development of the supporting system combining supporting structure and the water-blocking function is an important technological problem to be solved in the present in the side slope excavation process of civil engineering, water conservancy and municipality infrastructure constructions, such as foundation pit, side slope and municipal pipeline excavation.
- Polymer grouting technology is a rapid foundation reinforcement technology developing in the 1970s. This technology takes advantage of characteristic that the polymer materials expand rapidly and solidify after the chemical reaction to reinforce the foundation, fill the void, and raise the floor by injecting the polymer materials into the foundation.
- the polymer grouting technology is mainly applied in field of foundation reinforcement of industrial and civil building and road maintenance.
- the present invention provides a polymer grouting method for constructing a vertical supporting system combining water-blocking function and supporting reinforce function, and provides a new supporting technology to excavation of foundation pit, side slope and municipal pipeline. At present, there is no report related to the polymer grouting method for constructing vertical supporting system.
- An object of the present invention is to provide a polymer grouting method for constructing a vertical supporting system combining a water-blocking function and a supporting reinforce function to meet developing requirements of excavation supporting of foundation pit, side slope and municipal pipeline, and to make up for the shortage of the conventional supporting technology.
- the present invention is developed based on giving full play to the small permeability coefficient, good durability, and excellent expansion characteristics of the polymer materials, the earth pressure theory and the geotechnical anchoring theory.
- the slots of foundation pits, side slopes, municipal pipelines, etc. can be excavated vertically fast by adopting the present invention, which realizes advance water blocking and retaining for the side slopes in the process of excavation in the real sense, and greatly increases supporting speed of the side slopes.
- the present invention provides a new method to the excavation and supporting of the foundation pits, the side slopes, the municipal pipelines, etc., which is advanced, efficient, economic and practical.
- the present invention provides a polymer grouting method for constructing a vertical supporting system, comprising following steps of:
- step 3 and step 4 excavating vertically by layer in turn, wherein step 3 and step 4 is repeated until a construction of the polymer vertical supporting system reaches a projected depth, and then the construction of the polymer vertical supporting system is completed.
- the present invention has following advantages of:
- construction without water i.e. adopting construction method without water, wherein non-water reacted type polymer materials don't shrink in air, have good tractility, anti-vibrating property and anti-cracking property;
- the coping and anchor grouting can be constructed continuously without intervals, so the construction is fast and convenient, about 90% of the strength can be formed 15 minutes after the materials react, so leaving to firm is not required, compared to conventional supporting structure system, more than 80% of the construction period can be saved;
- the polymer vertical supporting system is mainly characteristic in realizing blocking water function while keeping the side slope stable, and saving a large quantity of construction period.
- the polymer grouting material has a stable performance, no pollution, a good flexibility, the polymer supporting system constructed bonds with the soil tightly, has a compatible deformation with the soil, a low permeability coefficient, and a preservative effect on the reinforcement as a water-resisting layer.
- the polymer grouting method for constructing the vertical supporting system according to the present invention has obvious advantages in construction process of excavation project of foundation pit, side slope, municipal pipeline, etc. Compared to conventional supporting technologies, the polymer grouting method for constructing the vertical supporting system is a wholly new technology, which is embodied in following aspects.
- the water-blocking panel and the anchors in the polymer vertical supporting system is embodied as a new non-water reacted typed high-molecular polymer grouting material according to an idea of flexible supporting, which has characteristics, such as safety, environmental protection, lightness, durableness, high expansion rate, good permeability resistance and early strength.
- the polymer water-blocking panel constructed is a flexible anti-seepage element, which bonds with the soil tightly, has a compatible deformation with the soil, has good anti-cracking and anti-seepage properties, and realizes advance supporting.
- the polymer vertical supporting system makes full use of the high expansion characteristic of the polymer materials.
- the polymer anchors after expanding bond tightly with the surrounding soil, and are able to provide a larger withdrawal resistance, to help keeping the polymer water-blocking panel stable and to save slope-setting unload space. All of the anchor rods work, because of being constructing connected together.
- the anchor rods are stressed synergistically, and the withdrawal resistances generated by all of the anchor rods are able to balance out a lateral soil pressure, in order to ensure a stability of the supporting system.
- the polymer grouting method for constructing the vertical supporting system makes use of self-expansibility and rheological property of the polymer material to form the ultrathin polymer water-blocking panel, and to construct the coping and the anchors, which fully shows a technical advantage of fast and convenient construction.
- the present invention is obviously different from the conventional supporting technologies in aspects of the supporting materials, the supporting ideas, the force mechanism, the construction method, etc.
- the present invention has the advantages of fastness and convenience, lightness, high tenacity, economy, durableness, etc., and is successfully applied in foundation pit supporting engineering, so the present invention has a good prospect in development and application.
- FIG. 1 is a sketch view of a polymer water-blocking panel according to a preferred embodiment of the present invention.
- FIG. 2 is a top view of FIG. 1 .
- FIG. 3 is a sketch view of a coping of a polymer vertical supporting system according to the preferred embodiment of the present invention.
- FIG. 4 is a sketch view of polymer anchors according to the preferred embodiment of the present invention.
- FIG. 5 is a connecting sketch view of polymer anchor rods according to the preferred embodiment of the present invention.
- FIG. 6 is a front sketch view of a whole impression of the polymer vertical supporting system according to the preferred embodiment of the present invention.
- FIG. 7 is a sectional view of the whole impression of the polymer vertical supporting system according to the preferred embodiment of the present invention.
- a polymer grouting method for constructing a vertical supporting system comprises following steps of:
- step 3 and step 4 excavating vertically by layer in turn, wherein step 3 and step 4 is repeated until a construction of the polymer vertical supporting system reaches a projected depth 20 , and then the construction of the polymer vertical supporting system is completed, as referred to FIG. 6 and FIG. 7 .
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
-
- 1) locating the integrated polymer water-blocking panel and forming slots, comprising locating the integrated polymer water-blocking panel in an area of a side slope required to be excavated vertically according to a design, and forming slots continuously with a three-cone slot-forming plate and a direct pushing machine for slot-forming.
- 2) grouting into a slot hole, comprising putting a grouting pipe into the slot hole, wherein the grouting pipe extends to a bottom of the slot hole, injecting two-component expansive polymer grouting materials into the slot hole through the grouting pipe with a polymer grouting equipment, and lifting the grouting pipe with a lifting grouting control equipment at a same time, in such a manner that a polymer material fills the slot hole from bottom to top to form a polymer water-blocking panel, which is schistose; and
- 3) structuring the integrated polymer water-blocking panel by connecting the polymer water-blocking panels, comprising repeating the above step 2), wherein the polymer water-blocking panels in adjacent slot holes bond together tightly to form the integrated polymer water-blocking panel, which is continuous, even and regular;
-
- 1) construction of mesh reinforcements, wherein vertical mesh reinforcements are constructed by a hammer method and the horizontal mesh reinforcements are constructed by a binding method;
- 2) excavating vertically downwards in a side where a supporting system is constructed, to obtain a shallow slot having a depth of 280˜320 mm, and to interlock surface structure reinforcements and the mesh reinforcements in a coping; and
- 3) locating and installing a coping shaping steel die above the shallow slot, and processing a polymer grouting through a grouting hole preset on a top of the coping shaping steel die, to form the polymer coping of the supporting system;
-
- 1) excavating vertically by layer at a vertical spacing of 1.2-2 m, wherein a protecting soil having a thickness of 150-200 mm is reserved at a position of the integrated polymer water-blocking panel for being cleared by a manual method; and
- 2) processing polymer anchoring construction on the integrated polymer water-blocking panel cleared, comprising steps of:
- a) producing anchor rods, comprising aligning rods and removing rust from the rods, cutting welding materials, welding centring supports, and binding a hole-sealing capsule and a hole-sealing grouting pipe on an end portion of each rod, wherein the hole-sealing capsule is at a join of an anchor section and a free section when being bound, a detachable inlet valve is provided at a polymer inlet of an anchoring grouting pipe, a connecting join between the grouting pipes and a grouting gun is fixed and sealed by a hose clamp, the grouting pipes comprise two grouting pipes, a first grouting pipe is the hole-sealing grouting pipe, an outlet of which is provided in the hole-sealing capsule, and a second grouting pipe is the anchoring grouting pipe, an outlet of which is provided in a bottom of an anchoring hole;
- b) anchoring holes construction, comprising constructing anchoring holes at a spacing of 1.2-2 m;
- c) implanting the anchor rods, comprising implanting the anchor rods made before into the anchoring holes, and ensuring that each of the rods are in a central position; and
- d) polymer grouting, comprising processing hole-sealing grouting firstly, i.e. injecting the two-component expansive polymer grouting material into the hole-sealing capsule with a grouting equipment, and then processing anchoring grouting, i.e. injecting the two-component expansive polymer grouting materials into the anchoring grouting pipe with the grouting equipment, wherein the polymer material fill the anchoring holes from the bottom of the anchoring holes progressively, and the two-component expansive polymer grouting material expands and pressurizes soil of a hole wall tightly to have a close contact with the surrounding soil, in such a manner that polymer anchors are formed;
-
- 1) locating the integrated polymer water-blocking
panel 3 and forming slots, comprising locating the integrated polymer water-blockingpanel 3 in an area of a side slope required to be excavated vertically according to a design, and forming slots continuously on aground 1 with a three-cone slotting board and a static slotting machine. - 2) grouting into a
slot hole 2, comprising putting a grouting pipe into theslot hole 2, wherein the grouting pipe extends to a bottom of theslot hole 2, injecting two-component expansive polymer grouting materials into theslot hole 2 through the grouting pipe with a polymer grouting equipment, and lifting the grouting pipe with a lifting grouting control equipment at a same time, in such a manner that a polymer material fills theslot hole 2 from bottom to top to form a polymer water-blocking panel; and - 3) structuring the integrated polymer water-blocking
panel 3 by connecting the polymer water-blocking panels, comprising repeating the above step 2), wherein the polymer water-blocking panels in adjacent slot holes bond together tightly to form the integrated polymer water-blockingpanel 3, which is continuous, even and regular, as referred toFIG. 1 andFIG. 2 ;
- 1) locating the integrated polymer water-blocking
-
- 1) construction of mesh reinforcements, wherein
vertical mesh reinforcements 5 are constructed by a hammer method and thehorizontal mesh reinforcements 6 are constructed by a binding method; - 2) excavating vertically downwards in a side where a supporting system is constructed, to obtain a shallow slot having a depth of 280˜320 mm, to form a ground with the
shallow slot 4, and interlockingsurface structure reinforcements 7 and the mesh reinforcements in a coping; and - 3) locating and installing a coping shaping steel die 8 above the shallow slot, and processing a polymer grouting through a
grouting hole 9 preset on a top of the coping shapingsteel die 8, to form the polymer coping 10 of the supporting system, as referred toFIG. 3 ;
- 1) construction of mesh reinforcements, wherein
-
- 1) excavating vertically by layer at a vertical spacing of 1.2-2 m, wherein a protecting soil having a thickness of 150-200 mm is reserved at a position of the integrated polymer water-blocking
panel 3 for being cleared by a manual method; and - 2) processing polymer anchoring construction on the integrated polymer water-blocking
panel 3 cleared, comprising steps of:- a) producing anchor rods, wherein
rods 12 can be made of reinforcing bars or steel strand according to designing requirements, comprising aligning therods 12 and removing rust from the rods, cutting welding materials, welding centring supports 13, and binding a hole-sealingcapsule 15 and a hole-sealinggrouting pipe 14 on an end portion of eachrod 15, wherein the hole-sealingcapsule 15 is at a join of an anchor section and a free section when being bound, a detachable inlet valve is provided at a polymer inlet of an anchoringgrouting pipe 16, a connecting join between the grouting pipes and a grouting gun is fixed and sealed by a hose clamp, the grouting pipes comprise two grouting pipes, a first grouting pipe is the hole-sealinggrouting pipe 14, an outlet of which is provided in the hole-sealingcapsule 15, and a second grouting pipe is the anchoringgrouting pipe 16, an outlet of which is provided in a bottom of an anchoringhole 17; - b) anchoring
holes 17 construction, comprisingconstructing anchoring holes 17 at a spacing of 1.2-2 m; - c) implanting the anchor rods, comprising implanting the anchor rods made before into the anchoring holes 17 and ensuring that each of the
rods 12 is in a central position; and - d) polymer grouting, comprising processing hole-sealing grouting firstly, i.e. injecting the two-component expansive polymer grouting material into the hole-sealing
capsule 15 with a grouting equipment, and then processing anchoring grouting, i.e. injecting the two-component expansive polymer grouting material into the anchoringgrouting pipe 16 with the grouting equipment, wherein the polymer materials fill the anchoring holes 17 from the bottom of the anchoring holes 17 progressively, and the two-component expansive polymer grouting material expands and pressurizes soil of a hole wall tightly to have a close contact with the surrounding soil, in such a manner that polymer anchors 11 are formed, as referred toFIG. 4 ;
- a) producing anchor rods, wherein
- 1) excavating vertically by layer at a vertical spacing of 1.2-2 m, wherein a protecting soil having a thickness of 150-200 mm is reserved at a position of the integrated polymer water-blocking
Claims (3)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310123667.6A CN103215960B (en) | 2013-04-11 | 2013-04-11 | Grouting method for high polymer vertical support system |
CN201310123667 | 2013-04-11 |
Publications (2)
Publication Number | Publication Date |
---|---|
US20140314494A1 US20140314494A1 (en) | 2014-10-23 |
US8974152B2 true US8974152B2 (en) | 2015-03-10 |
Family
ID=48814085
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US13/866,026 Active US8974152B2 (en) | 2013-04-11 | 2013-04-19 | Polymer grouting method for constructing vertical supporting system |
Country Status (2)
Country | Link |
---|---|
US (1) | US8974152B2 (en) |
CN (1) | CN103215960B (en) |
Families Citing this family (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102660955B (en) * | 2012-05-17 | 2015-05-13 | 上海强劲地基工程股份有限公司 | Quick construction method for foundation pit slope support |
CN104234057A (en) * | 2013-10-22 | 2014-12-24 | 王磊 | Polymer grouting curtain and prestressed pipe pile combined foundation pit supporting structure |
CN105464074B (en) * | 2015-11-22 | 2017-04-05 | 合肥工业大学 | A kind of artificial digging pile high polymer grouting safeguard structure and its construction method |
CN105672327B (en) * | 2016-02-04 | 2017-10-17 | 郑州安源工程技术有限公司 | A kind of design and construction method of minor diameter vertical shaft high polymer grouting excavation supporting structure |
CN105735322B (en) * | 2016-02-04 | 2017-12-22 | 郑州安源工程技术有限公司 | A kind of design and construction method of the recyclable supporting construction of combination of rigidity and flexibility antiseepage |
US10227749B2 (en) * | 2017-04-28 | 2019-03-12 | R&B Leasing | Landfill liner system |
CN108005097B (en) * | 2017-12-15 | 2024-02-23 | 兰州理工大学 | High-steep slope top construction/building anchor raft foundation structure and construction method |
CN108959752B (en) * | 2018-06-26 | 2023-10-13 | 湘潭大学 | Calculation method suitable for calculating displacement and internal force of pile body of three rows of steel pipes |
CN109487780A (en) * | 2019-01-13 | 2019-03-19 | 中国石油大学(华东) | A kind of steel pipe combination skeleton slip casting solution cavity interstitital texture with holes and construction method |
CN109653212A (en) * | 2019-01-31 | 2019-04-19 | 长江勘测规划设计研究有限责任公司 | Close on the irregular deep basal pit group comprehensive support structure and construction method of high-speed railway |
CN110499766B (en) * | 2019-08-30 | 2022-03-11 | 郑州安源工程技术有限公司 | Thin type grooving lifting synchronous grouting device and using method thereof |
CN111794209B (en) * | 2020-02-14 | 2022-04-01 | 宁波大学 | Embedded precast concrete column isolation pile and construction method thereof |
CN111648377A (en) * | 2020-06-16 | 2020-09-11 | 深圳市勘察测绘院(集团)有限公司 | Vertical and inclined pile combined foundation pit supporting method |
CN112922044A (en) * | 2021-02-01 | 2021-06-08 | 浙江工业大学 | Anchor rod combined anti-floating system |
CN113202109B (en) * | 2021-04-11 | 2022-11-15 | 中铁六局集团有限公司 | High-water-level jacking construction method for railway passenger underpass with multiple underpass railways |
CN113152491A (en) * | 2021-04-25 | 2021-07-23 | 福建省地质工程勘察院 | Construction method for emergency rescue disposal of soil landslide through high polymer grouting |
CN113529753B (en) * | 2021-07-09 | 2022-07-15 | 福建省地质工程勘察院 | Construction method for quickly treating hillock by grouting quick-setting high polymer |
CN113863342A (en) * | 2021-09-22 | 2021-12-31 | 中国化学工程第六建设有限公司 | Deep foundation pit construction method adopting pipe well and light well point dewatering |
CN113914321A (en) * | 2021-09-29 | 2022-01-11 | 温州市渣土利用开发股份有限公司 | Advanced integral curing method for ultra-soft site foundation pit |
CN114318982A (en) * | 2021-11-30 | 2022-04-12 | 中南大学 | Foam light soil supporting structure for building large-area terrace |
CN114542147A (en) * | 2022-04-02 | 2022-05-27 | 湖南科技大学 | Anchor net spraying-steel wire rope oblique crossing coupling supporting method |
CN115492118B (en) * | 2022-07-01 | 2024-03-01 | 中建八局第三建设有限公司 | Anti-drifting construction method for anchor rod of water-rich sand layer of oversized foundation pit |
CN115198769B (en) * | 2022-08-25 | 2023-06-02 | 湖北理工学院 | Adjustable foundation pit supporting device with automatic monitoring function |
CN116289967A (en) * | 2023-01-28 | 2023-06-23 | 中国十七冶集团有限公司 | Over-excavation collapse-prevention elevator foundation pit slope construction process |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1394718A (en) * | 1918-09-19 | 1921-10-25 | Walter E Emery | Process for sealing shafts or wells |
US3416322A (en) * | 1966-11-14 | 1968-12-17 | Albert G. Bodine | Sonic method and apparatus for implanting underground concrete walls |
US6299386B1 (en) * | 1999-06-09 | 2001-10-09 | R. John Byrne | Method and apparatus for a shoring wall |
US6799924B1 (en) * | 2003-03-14 | 2004-10-05 | Precision Piling Systems, Llc | Segmented concrete piling assembly with steel connecting rods |
US20110103898A1 (en) * | 2009-11-02 | 2011-05-05 | Zhengzhou Uretek Technology Ltd. | Directional fracture grouting method with polymer for seepage control of dikes and dams |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102051869B (en) * | 2009-11-02 | 2012-05-09 | 郑州优特基础工程维修有限公司 | High polymer heavy curtain grouting technology |
CN102108873B (en) * | 2009-12-29 | 2013-11-06 | 河南博特工程防护有限公司 | High-polymer grouting method for rapidly disposing percolating water in tunnel |
KR101242583B1 (en) * | 2011-05-23 | 2013-03-19 | 주식회사씨앤에프 | Method for manufacturing high temperature fiber grid of high strength |
CN102444128B (en) * | 2011-09-26 | 2013-11-13 | 郑州优特基础工程维修有限公司 | Grouting method for ultrathin high polymer cutoff wall |
-
2013
- 2013-04-11 CN CN201310123667.6A patent/CN103215960B/en active Active
- 2013-04-19 US US13/866,026 patent/US8974152B2/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1394718A (en) * | 1918-09-19 | 1921-10-25 | Walter E Emery | Process for sealing shafts or wells |
US3416322A (en) * | 1966-11-14 | 1968-12-17 | Albert G. Bodine | Sonic method and apparatus for implanting underground concrete walls |
US6299386B1 (en) * | 1999-06-09 | 2001-10-09 | R. John Byrne | Method and apparatus for a shoring wall |
US6799924B1 (en) * | 2003-03-14 | 2004-10-05 | Precision Piling Systems, Llc | Segmented concrete piling assembly with steel connecting rods |
US20110103898A1 (en) * | 2009-11-02 | 2011-05-05 | Zhengzhou Uretek Technology Ltd. | Directional fracture grouting method with polymer for seepage control of dikes and dams |
Also Published As
Publication number | Publication date |
---|---|
US20140314494A1 (en) | 2014-10-23 |
CN103215960B (en) | 2015-06-24 |
CN103215960A (en) | 2013-07-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8974152B2 (en) | Polymer grouting method for constructing vertical supporting system | |
US9777881B2 (en) | Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines | |
CN102900089B (en) | With the combination piling bar cofferdam of hydro-expansive rubber waterproof fore shaft | |
US20140314497A1 (en) | Polymer grouting method for constructing gravel pile | |
CN101597904B (en) | Waterproof sheet pile cofferdam and construction method thereof | |
CN105735322B (en) | A kind of design and construction method of the recyclable supporting construction of combination of rigidity and flexibility antiseepage | |
CN203034467U (en) | Combined steel pile cofferdam with water-proof fore shafts | |
JP6166264B2 (en) | How to build a retaining wall | |
CN204491626U (en) | The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine | |
CN102767180A (en) | Construction method for strengthening base of static-pressure anchor rod pile | |
CN106948340B (en) | A kind of construction method of the Manual excavated pile structure of high polymer grouting protection | |
CN110965595B (en) | Raft foundation building lifting reinforcement structure and method under corrosive geological environment | |
CN106884433A (en) | Control vibrations pile pulling causes the structure of underground structure depression and control depression method | |
CN105804007B (en) | A kind of reinforced earth quaywall structure based on the soft base of beach | |
CN113186903A (en) | Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure | |
CN102359112A (en) | Method for bracing foundation pit by using steel box piles | |
CN101586341B (en) | Water sealing method for civil engineering groundwork | |
KR101380782B1 (en) | Eco-composite type steel temporary construction and construction method thereof | |
CN105113513A (en) | Anti-seepage foundation pit supporting structure and construction method | |
CN109056804B (en) | Comprehensive pipe rack foundation pit supporting structure and implementation method thereof | |
KR101267688B1 (en) | The shore protection construction method using a precast finish panel | |
WO2009139510A1 (en) | Construction method for continuous cut-off wall using overlap casing | |
CN111593755A (en) | Open caisson | |
CN110424488A (en) | A kind of construction method of diaphram wall | |
CN205857212U (en) | Corrugated steel cofferdam borehole hollow pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: SAFEKEY ENGINEERING TECHNOLOGY (ZHENGZHOU), LTD., Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:HENAN POLYTECH INFRASTRUCTURE REHALILITATION LTD.;REEL/FRAME:034164/0420 Effective date: 20141029 |
|
STCF | Information on status: patent grant |
Free format text: PATENTED CASE |
|
AS | Assignment |
Owner name: WANG, FUMING, CHINA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SAFEKEY ENGINEERING TECHNOLOGY (ZHENGZHOU), LTD.;REEL/FRAME:039970/0439 Effective date: 20160718 |
|
MAFP | Maintenance fee payment |
Free format text: PAYMENT OF MAINTENANCE FEE, 4TH YR, SMALL ENTITY (ORIGINAL EVENT CODE: M2551) Year of fee payment: 4 |
|
MAFP | Maintenance fee payment |
Free format text: PAYMENT OF MAINTENANCE FEE, 8TH YR, SMALL ENTITY (ORIGINAL EVENT CODE: M2552); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY Year of fee payment: 8 |