CN102102341B - 一种高架桥面施工方法 - Google Patents

一种高架桥面施工方法 Download PDF

Info

Publication number
CN102102341B
CN102102341B CN200910201466.7A CN200910201466A CN102102341B CN 102102341 B CN102102341 B CN 102102341B CN 200910201466 A CN200910201466 A CN 200910201466A CN 102102341 B CN102102341 B CN 102102341B
Authority
CN
China
Prior art keywords
segmentation
bridge floor
case beam
steel case
deck
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910201466.7A
Other languages
English (en)
Other versions
CN102102341A (zh
Inventor
陈晓明
吴欣之
张�杰
吴轶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN200910201466.7A priority Critical patent/CN102102341B/zh
Publication of CN102102341A publication Critical patent/CN102102341A/zh
Application granted granted Critical
Publication of CN102102341B publication Critical patent/CN102102341B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种高架桥面施工方法,其特征在于有下列步骤组成:在不影响交通的部分开始桥面吊装,在已建成的桥面上安置后继桥面分段拼装用的胎架,用吊车把后继桥面分段的散件吊到胎架上,在拼装好的钢箱梁分段下面前后安装液压自动调整滑移小车,并在钢箱梁分段的下面后面安装下降托架,安装滑移顶推用的穿心式千斤顶及钢绞线和锚固架,顶起钢箱梁分段使之脱离胎架并滑移至桥面沿口,钢箱梁分段的前端荷载转换桥墩上的滑移桁架的滚动小车上,并将钢箱梁分段移出已建成的桥面,再由液压同步下降装置将钢箱梁同步下降至两个桥墩的设计位置。本发明的优点是施工时不占用地面,可以开放地面的交通。

Description

一种高架桥面施工方法
技术领域
本发明涉及一种高架桥面施工方法。
背景技术
目前随着城市建设的飞速发展,城市道路交通的压力巨增,因此为了减缓行车压力,许多城市在交通拥挤的区域建造高架道路,由于高架道路往往是在既有的路面或城市地面上施工,因此有的地方为了减少现有的交通对建造高架道路施工的影响,封闭了建造区域。但是还是有许多地方,由于各种原因,如该区域是交通道路的枢纽节点,无法进行封闭施工,因此就需要在开放道路交通的基础上进行高架道路的施工,因此现在常用的搭建脚手架,并铺设模板进行桥面施工的方法就无法进行,而用大型吊车将桥面梁一根一根吊运到桥面的方法也因起吊高度高,施工量大,并且还要占用大量的施工地面,也无法进行施工,因此亟待发明一种不占用地面交通道路的高架桥面施工方法
发明内容:
本发明的目的是解决现有技术中在既有道路及城市地面上进行高架桥面施工需要搭建脚手架所存在的影响地面交通的问题,提供一种高架桥面施工方法。本发明设计一种高架桥面施工方法,其特征在于有下列步骤组成:(1)在不影响交通的部分开始桥面吊装,(2)在已建成的桥面上安置后继桥面分段拼装用的胎架,用履带吊和龙门吊把后继桥面分段的散件吊到胎架上,以一跨钢箱梁作为一个施工单元完成桥面分段的拼装,(3)在拼装好的钢箱梁分段下面前后安装液压自动调整滑移小车,并在钢箱梁分段的下面后面安装下降托架,在钢箱梁分段后端安装滑移顶推用的穿心式千斤顶,千斤顶穿好钢绞线,在已施工好的下桥面前端安装顶推用的钢绞线锚固架,(4)顶起钢箱梁分段使之脱离胎架,在顶推千斤顶的作用下,使拼装好的钢箱梁分段在已经施工好的桥面上滑移至桥面沿口,(5)然后将钢箱梁分段的前端荷载转换到架设在欲安装钢箱梁分段的桥墩上的滑移桁架上的滚动小车上,拆除前端的滑移小车,然后使钢箱梁分段继续纵移至安装位置上方,并将钢箱梁分段移出已建成的桥面,并由仍在已建成的桥面上的下降托架支承,(6),再由液压同步下降装置将钢箱梁同步下降至两个桥墩的设计位置。其特征在于:步骤(6)的液压同步下降装置由前后两套组成,一套是前端的安装在地面上的下降装置,一套是后端的安装在已建成桥面上的下降装置,两套下降装置都采用液压千斤顶作为下降动力。本发明的优点是施工时不占用地面,可以开放地面的交通。
附图说明
图1——5为本发明的施工流程图,
图中1为桥墩,2为已建成桥面,3为钢箱梁分段,4为滑移小车,5为滚动小车,6为滑移桁架,7为下降托架,8为下降装置,
下面结合实例对本发明作详细使用说明。
具体实施方式:
(1)在不影响交通的部分开始桥面吊装,(2)在已建成的桥面上安置后继桥面分段拼装用的胎架,用履带吊和龙门吊把后继桥面分段的散件吊到胎架上,以一跨钢箱梁作为一个施工单元完成桥面分段的拼装,(3)在拼装好的钢箱梁分段下面前后安装液压自动调整滑移小车,并在钢箱梁分段的下面后面安装下降托架,在钢箱梁分段后端安装滑移顶推用的穿心式千斤顶,千斤顶穿好钢绞线,在已施工好的下桥面前端安装顶推用的钢绞线锚固架,(4)顶起钢箱梁分段使之脱离胎架,在顶推千斤顶的作用下,使拼装好的钢箱梁分段在已经施工好的桥面上滑移至桥面沿口,(5)然后将钢箱梁分段的前端荷载转换到架设在欲安装钢箱梁分段的桥墩上的滑移桁架上的滚动小车上,拆除前端的滑移小车,然后使钢箱梁分段继续纵移至安装位置上方,并将钢箱梁分段移出已建成的桥面,并由仍在已建成的桥面上的下降托架支承,(6),再由液压同步下降装置将钢箱梁分段同步下降至两个桥墩的设计位置。其特征在于:步骤(6)的液压同步下降装置由前后两套组成,一套是前端的安装在地面上的下降装置,一套是后端的安装在已建成桥面上的下降装置,两套下降装置都采用液压千斤顶作为下降动力。
具体实施时,在需要架高架桥面的两面已吊装好的桥面上安置后继桥面分段拼装用的胎架,即可以从两边同时施工,以加快施工的工期,
考虑到桥面线形复杂,如是由多段曲线组成的竖曲线,为了在滑移过程中保证滑移小车能够受力均匀,在滑移小车的支腿上设计了液压自动调整装置,这样在滑移过程中能随着桥面线形的变化自动调整滑移支腿的高度,同时液压调整支腿的高度可以在一定范围内升降,也方便了后继桥面分段脱离胎架,只要升高液压调整支腿就可使钢箱梁分段与胎架脱离;当后继分段滑出下桥面前端,荷载需要转换到滚动小车上时,液压调整支腿可调整分段的底标高,也方便了滚动小车的安装和荷载转换。
当桥面分段滑移到安装孔位时,由于搁置在小车上,离桥墩立柱顶上的永久支座还有2米多的距离,需用下降装置进行落架工作。下降装置有两套,一套是前端的安装在地面上的下降装置,一套是后端的安装在下桥面上的下降装置,两套装置都采用6000KN级的液压千斤顶作为下降动力。钢箱梁分段平移到位后用两套下降装置顶起钢箱梁分段,整个平移分段由下降装置支承,拆除前端的滚动小车和后端的下降托架支承,然后把钢箱梁分段慢慢的降下来,在下降过程中严格控制各支承点的高低差在20mm以内,避免因高低差过大而使得某一支承点的荷载过大,确保下降工作的安全。

Claims (2)

1.一种高架桥面施工方法,其特征在于有下列步骤组成:(1)在不影响交通的部分开始桥面吊装,(2)在已建成的桥面上安置后继桥面分段拼装用的胎架,用履带吊和龙门吊把后继桥面分段的散件吊到胎架上,以一跨钢箱梁作为一个施工单元完成桥面分段的拼装,(3)在拼装好的钢箱梁分段下面前后安装液压自动调整滑移小车,并在钢箱梁分段的下面后面安装下降托架,在钢箱梁分段后端安装滑移顶推用的穿心式千斤顶,千斤顶穿好钢绞线,在已施工好的下桥面前端安装顶推用的钢绞线锚固架,(4)顶起钢箱梁分段使之脱离胎架,在穿心式千斤顶的作用下,使拼装好的钢箱梁分段在已经施工好的桥面上滑移至桥面沿口,(5)然后将钢箱梁分段的前端荷载转换到架设在欲安装钢箱梁分段的桥墩上的滑移桁架上的滚动小车上,拆除前端的液压自动调整滑移小车,然后使钢箱梁分段继续纵移至安装位置上方,并将钢箱梁分段移出已建成的桥面,并由仍在已建成的桥面上的下降托架支承,(6),再由液压同步下降装置将钢箱梁同步下降至两个桥墩的设计位置。
2.按权利要求1所述的一种高架桥面施工方法,其特征在于:步骤(6)的液压同步下降装置由前后两套组成,一套是前端的安装在地面上的下降装置,一套是后端的安装在已建成桥面上的下降装置,两套下降装置都采用液压千斤顶作为下降动力。
CN200910201466.7A 2009-12-18 2009-12-18 一种高架桥面施工方法 Expired - Fee Related CN102102341B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910201466.7A CN102102341B (zh) 2009-12-18 2009-12-18 一种高架桥面施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910201466.7A CN102102341B (zh) 2009-12-18 2009-12-18 一种高架桥面施工方法

Publications (2)

Publication Number Publication Date
CN102102341A CN102102341A (zh) 2011-06-22
CN102102341B true CN102102341B (zh) 2014-08-06

Family

ID=44155381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910201466.7A Expired - Fee Related CN102102341B (zh) 2009-12-18 2009-12-18 一种高架桥面施工方法

Country Status (1)

Country Link
CN (1) CN102102341B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251483B (zh) * 2011-05-23 2013-01-09 海波重型工程科技股份有限公司 自提升附着式吊机吊装钢管混凝土格构桥墩的施工方法
CN102605719B (zh) * 2012-04-17 2015-06-03 江阴大桥(北京)工程有限公司 混凝土预制梁节段拼装及架设的施工方法
CN113718659B (zh) * 2021-09-23 2023-01-06 联旺工程建设有限公司 一种城市道路桥梁施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1609342A (zh) * 2004-11-25 2005-04-27 中铁大桥局集团有限公司 下导梁式架桥机及其架梁方法
US7182316B2 (en) * 2004-02-05 2007-02-27 Sykes Richard D Adjustable support bracket
CN101255678A (zh) * 2007-12-28 2008-09-03 贵州省桥梁工程总公司 拖拉桥梁拱肋的滑移支架
CN101446068A (zh) * 2008-12-25 2009-06-03 湖南路桥建设集团公司 分段顶推架设悬索桥主桁的方法及所采用的重物滚移装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7182316B2 (en) * 2004-02-05 2007-02-27 Sykes Richard D Adjustable support bracket
CN1609342A (zh) * 2004-11-25 2005-04-27 中铁大桥局集团有限公司 下导梁式架桥机及其架梁方法
CN101255678A (zh) * 2007-12-28 2008-09-03 贵州省桥梁工程总公司 拖拉桥梁拱肋的滑移支架
CN101446068A (zh) * 2008-12-25 2009-06-03 湖南路桥建设集团公司 分段顶推架设悬索桥主桁的方法及所采用的重物滚移装置

Also Published As

Publication number Publication date
CN102102341A (zh) 2011-06-22

Similar Documents

Publication Publication Date Title
CN104612058B (zh) 一种刚性梁柔性拱桥的施工方法
JP5047680B2 (ja) 連続高架橋の施工方法
CN104060540B (zh) 一种空间缆索悬索桥临时横撑及其吊装施工方法
KR101287455B1 (ko) 교량의 상부구조물용 런칭시스템 및 이를 이용한 시공방법
CN107558378B (zh) 一种用于架设全预制梁的架桥机及其架桥方法
CN106545172A (zh) 一种高空大跨度钢桁架的安装方法
CN104762882A (zh) 桥梁节段吊装装置及吊装方法
CN102102341B (zh) 一种高架桥面施工方法
JP4796411B2 (ja) 橋梁一括撤去工法
CN104110002A (zh) 一种更换钢桁梁桥桥面板的方法
CN210366808U (zh) 一种用于轨道行走的升降拆除装置
CN110904861A (zh) 一种斜拉桥架梁吊机及其施工方法
CN111945572B (zh) 多联拱桥架桥机及多联拱桥架桥方法
CN115676683A (zh) 一种桥面施工用车辆升降平台
CN216515141U (zh) 一种新悬挑施工爬模装置
CN216336227U (zh) 一种采用液压顶升组件进行高层建筑施工的装置
CN212895958U (zh) 下挂移动式桥面吊机
CN202023149U (zh) 建筑用挂篮
CN204551280U (zh) 桥梁节段吊装装置
CN112482226B (zh) 一种上行式移动模架高空变跨接长施工方法
CN107237251B (zh) 一种引桥平推法架设临时钢桥的施工方法
CN208717748U (zh) 一种大跨度钢混组合梁架桥机支腿装置
KR101213377B1 (ko) 교량 상판의 리프트-런칭 공법 및 이를 위한 리프트-런칭 장치
CN111501562A (zh) 一种索塔操作平台模板分离提升系统
CN209704007U (zh) 一种液压爬模智能爬升系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Applicant after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Applicant before: Shanghai Mechanized Construction Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD. TO: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140806

Termination date: 20201218