CN102094494A - 在坡度大于60度的屋面上铺设s形瓦的施工工艺 - Google Patents
在坡度大于60度的屋面上铺设s形瓦的施工工艺 Download PDFInfo
- Publication number
- CN102094494A CN102094494A CN2010106187494A CN201010618749A CN102094494A CN 102094494 A CN102094494 A CN 102094494A CN 2010106187494 A CN2010106187494 A CN 2010106187494A CN 201010618749 A CN201010618749 A CN 201010618749A CN 102094494 A CN102094494 A CN 102094494A
- Authority
- CN
- China
- Prior art keywords
- tiles
- watt
- paving
- mortar
- laying
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
本发明公开了一种在坡度大于60度的屋面上铺设S形瓦的施工工艺,包括如下步骤:(1)基层处理;(2)基底找平;(3)铺设镀锌钢丝网;(4)抹抗裂砂浆;(5)CAD空间模拟试排,确定分格线和裁瓦尺寸;(6)铺设S形瓦:在S形瓦顶部预留双孔,背面铺满掺有粘结剂的砂浆,根据排版墨线铺贴,粘贴后,用钢钉固定,然后勾缝、补色,本发明在坡度大于60°的屋面上铺设S形瓦时,在瓦片上预留了固定孔,并用水泥钢钉固定在屋面上,铺设后瓦片不易脱落,由于运用了CAD空间模拟排版技术,减少了损耗,加快了施工速度,确保了S形瓦搭接紧密,行列横平竖直,檐口瓦出檐尺寸一致,屋脊、斜沟顺直,立体观感效果好。
Description
技术领域
本发明涉及S形瓦的施工工艺,特别是涉及一种在坡度大于60度的屋面上铺设S形瓦的施工工艺。
背景技术
随着社会的进步,物质文明的高速发展,人们对建筑物不仅仅局限于满足居住功能,更追求其外形、造型的搭配及鲜明的视觉享受,古典式的斜屋面在工程中得到了越来越广泛的应用,S形瓦屋面由于其简洁、大方、规格多样得到广泛推广。传统的S形瓦屋面的坡度通常在25°~60°之间,但这种坡度的屋面有时不能满足建筑设计及立面效果的要求,在实际建筑过程终逐渐出现了坡度大于60°的S形瓦屋面,如果用传统施工工艺在坡度大于60°的屋面上施工,由于坡度过大,施工后容易开裂,S形瓦容易脱落。
发明内容
本发明所要解决的技术问题是提供一种能够在坡度大于60°的屋面上铺设S形瓦的施工工艺,施工后屋面不易开裂,S形瓦不会脱落。
为了解决上述技术问题,本发明采用如下的技术方案:
本发明在坡度大于60度的屋面上铺设S形瓦的施工工艺,包括如下步骤:
(1)基层处理:清理屋面,铲平5mm以上的凸起物,拉毛,养护;
(2)基底找平:用砂浆进行底层抹灰后扫毛,凝固后抹面层砂浆,养护;
(3)铺设镀锌钢丝网:铺设丝径不小于0.9mm、孔网不大于20×20的热镀锌钢丝网;
(4)抹抗裂砂浆;
(5)CAD空间模拟试排,确定分格线和裁瓦尺寸;
(6)铺设S形瓦:在S形瓦顶部预留双孔,背面铺满掺有粘结剂的砂浆,根据排版墨线铺贴,粘贴后,用钢钉固定,然后勾缝、补色。
具体的,在上述方法中,采用如下的方法进行处理:
在铺设S形瓦时,面对屋面从中间往两边、从下往上进行,同时纵、横向每间隔三片瓦应拉通长线,跟线铺贴,瓦搭接部位尺寸偏差控制在3mm以内,在S形瓦顶部预留双孔,背面铺满掺有粘结剂的砂浆,根据排版墨线铺贴,铺贴后用50mm长水泥钢钉固定,瓦头和瓦尾的搭接长度为50~70mm,然后进行勾缝、补色。
在基层处理时,清理屋面,铲平5mm以上的凸起物,用水泥:砂:界面剂的重量比为1:1:1的浆料采用磙子、扫帚或抹子进行拉毛,终凝后浇水养护,待界面剂干燥后再进行基底找平处理。
在基底找平处理时,先用砂浆进行底层抹灰,厚度为5~10mm,用扫帚扫毛,过夜,然后将墙面湿润,抹面层砂浆,面层砂浆的厚度为5~10mm,搓平,养护。
在铺设镀锌钢丝网时,沿经纬向剪裁热镀锌钢丝网,并预留不小于400mm的搭接长度,从上而下、从左至右用80mm长的膨胀锚栓进行铺钉,膨胀锚栓的间距为300mm,钉入深度不小于50mm。
铺设完镀锌钢丝网后,抹抗裂砂浆,厚度为10~15mm。
与现有技术相比,本发明在坡度大于60°的屋面上铺设S形瓦时,在瓦片上预留了固定孔,并用水泥钢钉固定在屋面上,铺设后瓦片不易脱落,由于运用了CAD空间模拟排版技术,屋脊、檐口、斜沟处S形瓦根据排版结果进行统一编号切割,避免切割时无精确尺寸造成浪费,减少了损耗(可将定额核定损耗2.5%降至1.5%以内),加快了施工速度(与传统做法相比可缩短工期20%以上),确保了S形瓦搭接紧密,行列横平竖直,檐口瓦出檐尺寸一致,屋脊、斜沟顺直,立体观感效果好。
具体实施方式
工艺流程:基层处理→界面剂砂浆拉毛→吊垂直、套方、弹控制线、做灰、冲筋、做口→20mm厚1:2.5水泥砂浆找平层→铺设热镀锌钢丝网+锚固钉→抹15mm厚抗裂砂浆压入钢丝网→25厚(最薄处)1:1.4水泥砂浆坐砌S形瓦,内掺粘结剂,并在每片瓦预留孔采用50mm水泥钢钉固定。
施工工艺:
1、基层处理:墙面应清理干净,无油渍、浮尘等,墙面松动、风化部分应剔凿清除干净,墙表面凸起物≥5㎜应铲平,用水泥:砂:界面剂的重量比为1:1:1的浆料采用磙子滚、扫帚拉或抹子抹进行拉毛,按施工需要将浆料用水调至适合的稠度,保证所有的屋面都做拉毛处理,不漏刷,终凝后浇水养护,3~5天后待界面剂干燥后再开始找平。
2、基底找平:首先,水泥砂浆搅拌均匀后进行底层抹灰操作(砂浆要随拌随用,拌合及使用砂浆时间不宜超过60min,严禁使用过夜砂浆),底灰抹灰厚度为5~10mm,在底灰凝固之前用扫帚扫毛,第二天即可抹面层砂浆,首先将基底湿润,配合比同底层砂浆,抹灰厚度在5~10mm左右,凝固前要用木抹子搓平,养护。水泥砂浆养护是最重要环节,应根据现场气温及湿度进行定期养护,以防止水泥砂浆开裂、空鼓等质量通病。同时注意在抹面层灰以前,先检查底层砂浆有无空、裂现象,如有空裂,应剔凿返修后再抹面层灰;另外注意底层砂浆上的尘土、污垢等应先清净,浇水湿润后,方可进行面层抹灰。
3、铺设镀锌钢丝网:镀锌钢丝网应用于抹面抗裂砂浆中,选择丝径不小于0.9mm、孔网不大于20×20的热镀锌钢丝网,镀锌钢丝网按楼层尺寸沿经纬向事先裁好,并预留不小于400mm的搭接长度,铺钉热镀锌钢丝网应按从上而下,从左至右的顺序进行施工,用80mm长的膨胀锚栓固定,锚栓间距为300mm,钉入深度不小于50mm,梅花型分布。
4、抹抗裂砂浆:镀锌钢丝网铺贴完毕并验收合格后,即可抹抗裂砂浆,厚度为10~15mm,抗裂砂浆面层必须平整。
5、CAD空间模拟试排,确定分格线和裁瓦尺寸。
6、铺设S形瓦:待抗裂砂浆有一定强度后进行瓦铺贴,S形瓦铺设时应面对屋面从中间往两边、从下往上进行,同时纵、横向每间隔三片瓦应拉通长线,要求每片瓦必须跟线进行铺设,瓦搭接部位尺寸偏差控制在3mm以内;铺瓦施工前在S形瓦顶部预留双孔,采用掺有粘结剂的砂浆粘贴,首先在瓦的背面铺满砂浆,然后根据排版墨线行进铺贴;S形瓦随贴随用50mm水泥钢钉在每片瓦预留孔固定,瓦头和瓦尾的搭接长度50~70mm,然后进行勾缝、补色处理,将脊瓦两侧与平瓦相交的的缝隙用水泥砂浆填实,屋脊、斜沟等暴露部分的砂浆以及S形瓦的切断口处均应涂刷与瓦屋面颜色一致的建筑颜料,确保屋面的整体效果。
7、成品保护:瓦屋面施工前各项配套工程应提前完成,避免交叉作业,损伤瓦屋面;S形瓦铺设时应小心轻放。
Claims (6)
1.一种在坡度大于60度的屋面上铺设S形瓦的施工工艺,其特征在于:包括如下步骤:
(1)基层处理:清理屋面,铲平5mm以上的凸起物,拉毛,养护;
(2)基底找平:用砂浆进行底层抹灰后扫毛,凝固后抹面层砂浆,养护;
(3)铺设镀锌钢丝网:铺设丝径不小于0.9mm、孔网不大于20×20的热镀锌钢丝网;
(4)抹抗裂砂浆;
(5)CAD空间模拟试排,确定分格线和裁瓦尺寸;
(6)铺设S形瓦:在S形瓦顶部预留双孔,背面铺满掺有粘结剂的砂浆,根据排版墨线铺贴,粘贴后,用钢钉固定,然后勾缝、补色。
2.按照权利要求1所述在坡度大于60度的屋面上铺设S形瓦的施工工艺,其特征在于:在铺设S形瓦时,面对屋面从中间往两边、从下往上进行,同时纵、横向每间隔三片瓦应拉通长线,跟线铺贴,瓦搭接部位尺寸偏差控制在3mm以内,在S形瓦顶部预留双孔,背面铺满掺有粘结剂的砂浆,根据排版墨线铺贴,铺贴后用50mm长水泥钢钉固定,瓦头和瓦尾的搭接长度为50~70mm,然后进行勾缝、补色。
3.按照权利要求1所述在坡度大于60度的屋面上铺设S形瓦的施工工艺,其特征在于:在基层处理时,清理屋面,铲平5mm以上的凸起物,用水泥:砂:界面剂的重量比为1:1:1的浆料采用磙子、扫帚或抹子进行拉毛,终凝后浇水养护,待界面剂干燥后再进行基底找平处理。
4.按照权利要求1所述在坡度大于60度的屋面上铺设S形瓦的施工工艺,其特征在于:在基底找平处理时,先用砂浆进行底层抹灰,厚度为5~10mm,用扫帚扫毛,过夜,然后将墙面湿润,抹面层砂浆,面层砂浆的厚度为5~10mm,搓平,养护。
5.按照权利要求1所述在坡度大于60度的屋面上铺设S形瓦的施工工艺,其特征在于:在铺设镀锌钢丝网时,沿经纬向剪裁热镀锌钢丝网,并预留不小于400mm的搭接长度,从上而下、从左至右用80mm长的膨胀锚栓进行铺钉,膨胀锚栓的间距为300mm,钉入深度不小于50mm。
6.按照权利要求1所述在坡度大于60度的屋面上铺设S形瓦的施工工艺,其特征在于:铺设完镀锌钢丝网后,抹抗裂砂浆,厚度为10~15mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010106187494A CN102094494A (zh) | 2010-12-31 | 2010-12-31 | 在坡度大于60度的屋面上铺设s形瓦的施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010106187494A CN102094494A (zh) | 2010-12-31 | 2010-12-31 | 在坡度大于60度的屋面上铺设s形瓦的施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102094494A true CN102094494A (zh) | 2011-06-15 |
Family
ID=44127742
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010106187494A Pending CN102094494A (zh) | 2010-12-31 | 2010-12-31 | 在坡度大于60度的屋面上铺设s形瓦的施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102094494A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107190983A (zh) * | 2017-06-02 | 2017-09-22 | 康博达节能科技有限公司 | 一种预制装配式檐口的施工方法 |
CN107489239A (zh) * | 2016-06-13 | 2017-12-19 | 宜兴市周铁镇生力钻探机械厂 | 一种现浇砼屋面挂瓦施工工艺 |
CN109518888A (zh) * | 2018-12-18 | 2019-03-26 | 中建四局第六建筑工程有限公司 | 一种倾斜角度70°以上屋面瓦的施工方法及结构 |
CN110359427A (zh) * | 2019-07-22 | 2019-10-22 | 四川省都江堰人民渠第二管理处 | 一种红层地区灌区明渠边坡挂网抹面施工工艺 |
CN111877658A (zh) * | 2020-07-22 | 2020-11-03 | 北京城建六建设集团有限公司 | 乳胶漆内墙基体交接节点处抗放结合防裂体系及施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5056234A (en) * | 1990-06-14 | 1991-10-15 | Curtis Han | Roofing tile course marking device |
CN2217052Y (zh) * | 1995-03-28 | 1996-01-10 | 吴贤良 | 连体衔接屋面瓦 |
CN2243490Y (zh) * | 1995-07-23 | 1996-12-25 | 段伟中 | 多用途波形瓦固定装置 |
CN2285799Y (zh) * | 1996-05-14 | 1998-07-08 | 展志华 | 屋面波形瓦防漏紧固钉 |
CN1784316A (zh) * | 2003-03-07 | 2006-06-07 | 斯温森工具有限公司 | 建筑者的测量和划线工具 |
CN101495706A (zh) * | 2006-06-02 | 2009-07-29 | 克努德·艾瑞克·约翰森 | 一种用于在屋顶结构上定位和锁扣条板的方法 |
-
2010
- 2010-12-31 CN CN2010106187494A patent/CN102094494A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5056234A (en) * | 1990-06-14 | 1991-10-15 | Curtis Han | Roofing tile course marking device |
CN2217052Y (zh) * | 1995-03-28 | 1996-01-10 | 吴贤良 | 连体衔接屋面瓦 |
CN2243490Y (zh) * | 1995-07-23 | 1996-12-25 | 段伟中 | 多用途波形瓦固定装置 |
CN2285799Y (zh) * | 1996-05-14 | 1998-07-08 | 展志华 | 屋面波形瓦防漏紧固钉 |
CN1784316A (zh) * | 2003-03-07 | 2006-06-07 | 斯温森工具有限公司 | 建筑者的测量和划线工具 |
CN101495706A (zh) * | 2006-06-02 | 2009-07-29 | 克努德·艾瑞克·约翰森 | 一种用于在屋顶结构上定位和锁扣条板的方法 |
Non-Patent Citations (1)
Title |
---|
刘剑锐: "尖顶斜屋面挂瓦施工技术", 《施工技术》, 30 June 2010 (2010-06-30) * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107489239A (zh) * | 2016-06-13 | 2017-12-19 | 宜兴市周铁镇生力钻探机械厂 | 一种现浇砼屋面挂瓦施工工艺 |
CN107190983A (zh) * | 2017-06-02 | 2017-09-22 | 康博达节能科技有限公司 | 一种预制装配式檐口的施工方法 |
CN107190983B (zh) * | 2017-06-02 | 2019-08-30 | 康博达节能科技有限公司 | 一种预制装配式檐口的施工方法 |
CN109518888A (zh) * | 2018-12-18 | 2019-03-26 | 中建四局第六建筑工程有限公司 | 一种倾斜角度70°以上屋面瓦的施工方法及结构 |
CN110359427A (zh) * | 2019-07-22 | 2019-10-22 | 四川省都江堰人民渠第二管理处 | 一种红层地区灌区明渠边坡挂网抹面施工工艺 |
CN111877658A (zh) * | 2020-07-22 | 2020-11-03 | 北京城建六建设集团有限公司 | 乳胶漆内墙基体交接节点处抗放结合防裂体系及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101565997A (zh) | 大面积不规则地面砖施工方法 | |
CN107254954A (zh) | 地面铺贴瓷砖施工工艺 | |
CN106193624A (zh) | 一种改进的加气混凝土砌块墙体防裂缝施工技术 | |
CN102094494A (zh) | 在坡度大于60度的屋面上铺设s形瓦的施工工艺 | |
CN102505831A (zh) | 一种地面人造石胶泥铺贴施工方法 | |
CN105649285A (zh) | 一种上人屋面保温层组合式排气孔施工工法 | |
CN107152145A (zh) | 一种石材楼地面施工方法 | |
CN104120855A (zh) | 一种地砖地面贴铺施工方法 | |
CN106284706A (zh) | 外墙外保温岩棉板的施工方法 | |
CN107130766A (zh) | 一种结晶封釉无缝石材地面施工方法 | |
CN109797920A (zh) | 一种室内涂饰施工方法 | |
CN106284998A (zh) | 内墙抹灰满铺玻璃纤维网格布施工方法 | |
CN103821252A (zh) | 采用覆膜养护工艺的加气混凝土砌块填充墙施工工艺 | |
CN108468413A (zh) | 一种加气混凝土砌块免抹灰防空鼓施工方法 | |
CN112267628A (zh) | 建筑工程内墙装修免抹灰系统施工方法 | |
CN110424775A (zh) | 木混结构攒尖仿古亭及其施工方法 | |
CN113006397A (zh) | 一种厨卫空间规方找平的施工方法 | |
CN106150032A (zh) | 一种摊铺型高耐磨合金地坪的施工方法 | |
CN108130992A (zh) | 毛石板、聚苯板及多孔砖复合保温装饰外墙施工工法 | |
CN106592812A (zh) | 一种现场加工打磨砖及砌筑清水砖墙的施工方法 | |
CN207553357U (zh) | 毛石板、聚苯板及多孔砖复合保温装饰外墙 | |
CN101457582B (zh) | 水磨石双铜条变形缝施工工法 | |
CN203834826U (zh) | 一种新型楼梯间滴水槽 | |
CN110005174A (zh) | 提高机喷砂浆抹灰质量的施工方法 | |
CN106401103A (zh) | 一种墙面大规格玻化砖综合法施工工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20110615 |