CN102031876B - 建筑物新增立柱的方法 - Google Patents

建筑物新增立柱的方法 Download PDF

Info

Publication number
CN102031876B
CN102031876B CN200910196705.4A CN200910196705A CN102031876B CN 102031876 B CN102031876 B CN 102031876B CN 200910196705 A CN200910196705 A CN 200910196705A CN 102031876 B CN102031876 B CN 102031876B
Authority
CN
China
Prior art keywords
crossbeam
column
section
concrete
upright column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910196705.4A
Other languages
English (en)
Other versions
CN102031876A (zh
Inventor
金春宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN200910196705.4A priority Critical patent/CN102031876B/zh
Publication of CN102031876A publication Critical patent/CN102031876A/zh
Application granted granted Critical
Publication of CN102031876B publication Critical patent/CN102031876B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及建筑物支柱施工方法领域,具体为一种建筑物新增立柱的方法。包括在底板上生根连接立柱(1)、穿越楼板(2)和穿越横梁(3)三步骤,其特征是:立柱(1)与底板之间的生根连接采用植筋方式,将楼板(2)中和立柱(1)截面重叠部分的混凝土凿去,保留钢筋,在横梁(3)和立柱(1)截面重叠部分靠近边缘处开贯通横梁(3)的钢筋孔(31)。本发明工程作业量小,成本低,经济性好,质量好。

Description

建筑物新增立柱的方法
技术领域
本发明涉及建筑物支柱施工方法领域,具体为一种建筑物新增立柱的方法。
背景技术
在建筑工程中,由于结构或建筑功能的改变,避免不了在原有结构上新增钢筋混凝土柱。为保证新增构件与原结构可靠连接,新增截面与原截面粘结牢固,形成整体共同工作,并避免对未加固部分以及相关的结构、构件和地基基础造成不利的影响,需要对原结构或构件加以有效的支顶措施,如钢管脚手架支撑或钢格构柱等支撑措施,并对原结构或部件与新增构件的连接部位进行剔除、凿毛处理,最后绑扎钢筋、支模,验收合格后用微膨胀混凝土浇筑。目前常规的新增柱施工方法是:根据新增柱与原有结构或构件的连接情况,采取有效的支顶措施,并对新增柱与原有结构或构件连接部位的混凝土进行剔除、凿毛处理,柱遇梁、板时,需先对梁、板结构采取有效的支顶措施,且遇梁时,原结构梁需断开。在施工实践中,这种方法存在如下不足:1.在新增柱的施工过程中,需要对新增柱周边一定范围的结构采取有效的支顶措施,还需要对原结构与新增柱的连接部位较大范围内的混凝土进行剔除,从而增加了作业工程量,也提高了施工成本。2.即使采取有效的支顶措施,原结构不可避免存在沉降现象,根据以前的施工经验,沉降量一般在2mm~5mm。3.连接部位的楼板和横梁之间存在较长的施工缝及原结构不可避免存在沉降现象,不仅影响结构强度,也不美观。
发明内容
为了克服现有技术的缺陷,提供一种不破坏原结构、操作方便、节约成本的施工方法,本发明公开了一种建筑物新增立柱的方法。
本发明通过如下技术方案达到发明目的:
一种建筑物新增立柱的方法,包括在底板上生根连接立柱、穿越楼板和穿越横梁三步骤,楼板架设在横梁之上,其特征是:
在底板上生根连接立柱时,立柱与底板之间采用植筋方式,锚固长度为植筋所用钢筋直径的15倍,
穿越楼板时,将楼板中和立柱截面重叠部分的混凝土凿去,保留钢筋,
穿越横梁时,按横梁的截面宽度分两种情况施工:
当横梁的截面宽度小于800mm时,在横梁和立柱截面重叠部分靠近边缘处开贯通横梁的钢筋孔,重叠部分每一边开1~5个钢筋孔,钢筋孔的数量根据设计图纸要求并结合横梁的截面宽度和新增立柱的配筋情况而定,通常截面宽度300mm的横梁其重叠部分每边可开1~3个钢筋孔,钢筋孔不宜过多。钢筋孔内穿入立柱的钢筋,穿入后应立即进行钢筋孔内的孔道灌浆,孔道内水泥浆应饱满、密实,以防钢筋锈蚀,同时增加结构的抗裂性和耐久性。灌浆用灰浆除应满足强度和粘结力要求外,尚应具有较大的流动性和较小的干缩性。故灌浆宜用标号不低于42.5级普通硅酸盐水泥配制的水泥浆。灌浆前,砼孔道应用压力水冲刷干净并润湿孔壁,冲刷时可用电动或手动压力泵进行灌浆。
当横梁的截面宽度不小于800mm时,在横梁和立柱截面重叠部分靠近边缘处,宜采用上下植筋的方式予以连接固定。
所述的建筑物新增立柱的方法,其特征是:穿越楼板时,立柱和楼板之间的结合处宜采用微膨胀混凝土浇筑,以避免与原砼结构之间产生收缩裂缝。新旧砼连接缝按施工缝处理。浇筑砼时应除掉松动的石子,加以湿润并冲洗干净。
所述的建筑物新增立柱的方法,其特征是:穿越横梁时,立柱和横梁之间的结合处宜采用微膨胀混凝土浇筑,微膨胀混凝土选用以粒化高炉矿渣加入硅酸盐水泥熟料和石膏混合均匀后磨细制成,横梁表面与立柱的接触面予以凿毛处理,凿毛处理是将横梁表面的混凝土凿去一层且不使混凝土内主筋外露。
采用本发明对原有建筑物进行新增柱施工时,不需要对原结构采取支顶措施,也不需破坏原结构梁,而采用钻孔、穿筋的方法代替,避免的施工后的沉降现象,也不存在施工缝。本发明的有益效果是:减少工程作业量,降低成本,经济性好,且施工质量好。
附图说明
图1是本发明中穿越楼板的示意图;
图2是本发明中穿越横梁的示意图。
具体实施方式
以下通过具体实施例进一步说明本发明。
实施例1
某三层地下室工程,由于结构要求需在原有结构的基础上新增两方形混凝土柱,标高为-13.5m~-5.7m,楼板2架设在横梁3之上,采用建筑物新增立柱的方法施工,包括在底板上生根连接立柱1、穿越楼板2和穿越横梁3三步骤,具体步骤是:
首先在底板上生根连接立柱1,立柱1与底板之间采用植筋方式,锚固长度为植筋所用钢筋直径的15倍。
接着搭建立柱1穿越楼板2,如图1所示,将楼板2中和立柱1截面重叠部分21的混凝土凿去,保留钢筋,立柱和楼板之间的结合处宜采用微膨胀混凝土浇筑,以避免与原砼结构之间产生收缩裂缝。新旧砼连接缝按施工缝处理。浇筑砼时应除掉松动的石子,加以湿润并冲洗干净。
再搭建立柱1穿越横梁3,按横梁3的截面宽度分两种情况施工:
当横梁3的截面宽度小于800mm时,如图2所示,在横梁3和立柱1截面重叠部分靠近边缘处开贯通横梁3的钢筋孔31,重叠部分每一边开1~5个钢筋孔31,钢筋孔31的数量根据设计图纸要求并结合横梁3的截面宽度和立柱1的配筋情况而定,通常截面宽度300mm的横梁其重叠部分每边可开1~3个钢筋孔,本实施例每边开2个,钢筋孔不宜过多。钢筋孔31内穿入立柱1的钢筋,穿入后立即进行钢筋孔内的孔道灌浆,孔道内水泥浆应饱满、密实,以防钢筋锈蚀,同时增加结构的抗裂性和耐久性。灌浆用灰浆除应满足强度和粘结力要求外,尚应具有较大的流动性和较小的干缩性。故灌浆宜用标号不低于42.5级普通硅酸盐水泥配制的水泥浆。灌浆前,砼孔道应用压力水冲刷干净并润湿孔壁,冲刷时可用电动或手动压力泵进行灌浆。
当横梁3的截面宽度不小于800mm时,此时在横梁3上钻孔就显得非常困难,因此采用如下方法:立柱1分别竖直立于横梁3上下两面,在横梁3和立柱1截面重叠部分靠近边缘处,采用上下植筋的方式予以连接固定。
穿越横梁3时,立柱1和横梁3之间的结合处宜采用微膨胀混凝土浇筑,微膨胀混凝土选用以粒化高炉矿渣加入硅酸盐水泥熟料和石膏混合均匀后磨细制成,横梁3表面与立柱1的接触面予以凿毛处理,凿毛处理是将横梁表面的混凝土凿去一层且不使混凝土内主筋外露。

Claims (1)

1.一种建筑物新增立柱的方法,包括在底板上生根连接立柱(1)、穿越楼板(2)和穿越横梁(3)三步骤,楼板(2)架设在横梁(3)之上,其特征是:
在底板上生根连接立柱(1)时,立柱(1)与底板之间采用植筋方式,锚固长度为植筋所用钢筋直径的15倍,
穿越楼板(2)时,将楼板(2)中和立柱(1)截面重叠部分(21)的混凝土凿去,保留钢筋,立柱(1)和楼板(2)之间的结合处采用微膨胀混凝土浇筑;
穿越横梁(3)时,按横梁(3)的截面宽度分两种情况施工:
当横梁(3)的截面宽度小于800mm时,在横梁(3)和立柱(1)截面重叠部分靠近边缘处开贯通横梁(3)的钢筋孔(31),在重叠部分每一边开1~5个钢筋孔(31),钢筋孔(31)内穿入立柱(1)的钢筋,
当横梁(3)的截面宽度不小于800mm时,在横梁(3)和立柱(1)截面重叠部分靠近边缘处,采用上下植筋的方式予以连接固定,
立柱(1)和横梁(3)之间的结合处采用微膨胀混凝土浇筑,横梁(3)表面与立柱(1)的接触面予以凿毛处理,凿毛处理是将横梁(3)表面的混凝土凿去一层且不使混凝土内主筋外露。
CN200910196705.4A 2009-09-29 2009-09-29 建筑物新增立柱的方法 Expired - Fee Related CN102031876B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910196705.4A CN102031876B (zh) 2009-09-29 2009-09-29 建筑物新增立柱的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910196705.4A CN102031876B (zh) 2009-09-29 2009-09-29 建筑物新增立柱的方法

Publications (2)

Publication Number Publication Date
CN102031876A CN102031876A (zh) 2011-04-27
CN102031876B true CN102031876B (zh) 2015-02-04

Family

ID=43885271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910196705.4A Expired - Fee Related CN102031876B (zh) 2009-09-29 2009-09-29 建筑物新增立柱的方法

Country Status (1)

Country Link
CN (1) CN102031876B (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806448B (zh) * 2012-11-12 2016-01-13 深圳市工勘岩土工程有限公司 基坑钢筋混凝土水平支撑体系立柱替换结构及其施工方法
CN104775631A (zh) * 2015-02-16 2015-07-15 中交一航局第一工程有限公司 一种后增混凝土立柱施工方法
CN106401207B (zh) * 2016-10-13 2019-04-02 浙江杰地建筑设计有限公司 用于既有建筑增设柱子基础的叠合连接结构及其施工方法
CN109137929A (zh) * 2018-08-29 2019-01-04 中铁上海工程局集团有限公司 一种混凝土环形支撑与围护桩之间连接的施工方法
CN110017032B (zh) * 2019-03-29 2021-04-02 中国一冶集团有限公司 一种厂房结构改造穿梁加柱的方法
CN112376935A (zh) * 2020-11-13 2021-02-19 浙江绿城建筑设计有限公司 既有建筑上新增偏位柱子的加固结构及其施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08333901A (ja) * 1995-06-06 1996-12-17 Ohbayashi Corp 既存柱部材の補強方法
CN1358919A (zh) * 2002-01-18 2002-07-17 崔旭中 在不停产条件下厂房抬梁抽柱的方法
CN201180376Y (zh) * 2008-01-23 2009-01-14 贵州大学 外包预应力紧固式钢管混凝土矩形柱或圆柱

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08333901A (ja) * 1995-06-06 1996-12-17 Ohbayashi Corp 既存柱部材の補強方法
CN1358919A (zh) * 2002-01-18 2002-07-17 崔旭中 在不停产条件下厂房抬梁抽柱的方法
CN201180376Y (zh) * 2008-01-23 2009-01-14 贵州大学 外包预应力紧固式钢管混凝土矩形柱或圆柱

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
使用功能变更后的增柱施工技术;赵新文;《山西建筑》;20060531;第32卷(第9期);第120页左栏第1.2节、右栏第3节 *
置换混凝土加固技术在结构柱质量处理中的应用;李杨等;《广东土木与建筑》;20070930(第9期);全文 *

Also Published As

Publication number Publication date
CN102031876A (zh) 2011-04-27

Similar Documents

Publication Publication Date Title
CN102031876B (zh) 建筑物新增立柱的方法
CN101899907B (zh) 钢筋混凝土柱置换加固方法和卸载钢筋混凝土柱负荷装置
CN202945622U (zh) 一种地下室钢筋混凝土底板裂缝的复合修补结构
CN206667459U (zh) 一种预制型钢筋混凝土剪力墙预拼结构装配式建筑
CN107013040A (zh) 一种套筒预埋式后浇楼板的施工方法
CN102787595A (zh) 一种双重作用自应力组合抗拔桩及成桩方法
CN201567584U (zh) 预制建筑钢筋砼承台基础
CN110130670A (zh) 钢筋混凝土上下牛腿式临时支撑系统及其施工方法
CN109403509A (zh) 一种基于自复位组合端柱-浆锚剪力墙的装配式复合剪力墙
CN108265969A (zh) 一种地梁和承台工程的建筑塑料模板及其安装方法
CN106592777B (zh) 装配式钢-混结合梁柱节点结构及其实施方法
CN206157913U (zh) 一种装配式方钢管混凝土柱与钢梁连接节点
CN209837314U (zh) 一种预制装配式墙板节点快速连接结构
CN208534081U (zh) 一种老建筑构造柱的改造结构
CN108240037A (zh) 一种预制板墙层间横缝连接节点
CN106592630A (zh) 现浇与预制相结合的综合管廊结构及其施工方法
CN106567554A (zh) 砌体结构建筑物的加固施工方法
CN206844316U (zh) 一种带套管的装配式钢筋混凝土柱与柱拼接节点
CN111350311B (zh) 一种针对套筒内连接钢筋被截断的加固结构及其施工方法
CN206128281U (zh) 一种阳台板安装节点
CN208762895U (zh) 铰缝加固装置
CN209114733U (zh) 一种便于对接和灌浆的装配式建筑结构
CN110424573A (zh) 一种预制装配式无筋混凝土剪力墙及其施工方法
CN110424534A (zh) 一种预制装配式无筋混凝土框架及其施工方法
CN206873663U (zh) 全装配式预应力低损伤板墙结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190816

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150204

Termination date: 20210929

CF01 Termination of patent right due to non-payment of annual fee