CN102031795A - 狭小空间内短桩加固技术 - Google Patents

狭小空间内短桩加固技术 Download PDF

Info

Publication number
CN102031795A
CN102031795A CN 201010199237 CN201010199237A CN102031795A CN 102031795 A CN102031795 A CN 102031795A CN 201010199237 CN201010199237 CN 201010199237 CN 201010199237 A CN201010199237 A CN 201010199237A CN 102031795 A CN102031795 A CN 102031795A
Authority
CN
China
Prior art keywords
construction
slurry
anchor rod
composite anchor
slurry injecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010199237
Other languages
English (en)
Inventor
孙胜臣
陈树禹
王立波
马栋
陈建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN 201010199237 priority Critical patent/CN102031795A/zh
Publication of CN102031795A publication Critical patent/CN102031795A/zh
Pending legal-status Critical Current

Links

Images

Abstract

狭小空间内短桩加固技术,包括测放复合锚杆桩孔位、制作复合锚杆、加工注浆管、安装注浆管、注浆养护及施作冠梁工艺,其特征是:所述测放复合锚杆桩孔位,按间隔施做,先外排,后内排;所述制作复合锚杆工艺采用:加工制作两块钢板定位器,将钢筋笼主筋从两块定位器的孔洞穿过,制作隔离环,定位支撑焊接;所述加工、安装注浆管工艺,借助自重,注浆管竖向,用接驳器,采用直螺纹机械连接方式;所述注浆养护工艺采用:施压密注浆,分三次注浆,所有注浆材料采用普通硅酸盐水泥。本发明属于地下结构施工穿越既有建(构)筑物过程中的防护施工领域,通过复合锚杆桩加固周边土体,解决新建地下通道结构穿越既有桥梁短桩基础的施工防护问题,控制地表沉降变形,工程精度高。

Description

狭小空间内短桩加固技术
技术领域
本发明属于土木工程领域,特别是涉及地下结构施工穿越既有建(构)筑物过程中的狭小空间内短桩加固技术。
背景技术
随着经济实力的不断提高,为了缓解日益增长的交通压力,地铁的施工在诸多城市建设中蓬勃发展。而受各种因素制约,地铁施工不可避免地需邻近或穿过各种构筑物。这些节点地段的施工往往成为工程建设的重中之重。因此,为了使地铁施工能够在保护好既有城市建筑环境的前提下安全有序地进行,就迫切需要研究地铁施工对其的影响与沉降变形控制。
国贸站是首次在桥区采用浅埋暗挖修建的大型地铁车站,没有任何经验可以借鉴,只能采取动态设计、动态施工。国贸站换乘通道是通过两个7.87m(高)×6.6m(宽)的支洞与既有1号线国贸站实行换乘的。此处两个支洞需要从三期施工的大北窑桥桥桩DB134、DB135、DB142号桥墩及其基础间侧下方穿过,距离桥墩基础最近只有1.45m,且换乘通道支洞开挖底面在桥桩桩底标高以下3.7m。因此,本课题的研究尤其显得非常重要。
发明内容
复合锚杆桩工法的主要工艺流程为:
锚杆+注浆管加工→平整工作面并测量放线→钻机就位后夯进成孔→下放钢筋笼并安装注浆管→第一次填充注浆并养护→第二次劈裂注浆并养护→第三次劈裂注浆并养护→扩大基础承台或施作冠梁。
每个桥墩基础周围采用52根φ150mm的内外双排复合锚杆桩进行注浆加固,作为围护桥桩结构。每根复合锚杆桩长21.6m,步距1000mm,内外排间距800mm,并对桩底周围进行注浆。
附图说明
图1换乘通道过桥桩地段具体位置关系;
图2换乘通道复合锚杆桩布置平面图;
图3复合锚杆桩骨架平剖面;
图4注浆管布置图。
具体实施方式
1、对既有桩基及地质条件进行核查现状,根据地质和现场条件情况,进行基础形式的设计,如复合锚杆桩直径、桩长、配筋和注浆浆液的选定。由于每个工程所在地的地质情况不同,在使用本技术时,必须根据场地实际情况,重新进行参数设计。
2、根据锚杆桩的直径和打入长度,成孔机械设备采用XY-4型地质钻机成孔,由于本工程的特点,桥下空间的限制(最低处净空2.0m),及设备本身的高度,施工复合锚杆桩前,在打桩位置开挖2m宽,1.5m的基槽(施工完成后回填混凝土,恢复至原地面高程),增大施工的空间,以便施工。
3、按照间隔施做,先外排,后内排的原则,结合现场实际,进行测放复合锚杆桩孔位。
4、复合锚杆制作
(1)现场加工制作两块1.5mm厚钢板定位器,将配好的钢筋笼主筋从两块定位器的孔洞穿过,保证每根主筋在同一水平面上。
(2)在钢筋圈制作台上制作隔离环内径30mm,φ12钢筋围成,纵向每米1环与钢筋及定位支撑焊接。定位支撑由φ18螺纹钢筋弯成宽40mm,高200mm的环行。
(3)将制作好的复合锚杆稳固放置在平整的地面上,防止变形。
5、移动钻机位置到孔位,调整钻杆垂直度,用φ150钻头成孔至设计的标高.
6、采用简易支撑架吊放,人工配合就位。每节吊起后缓慢落入桩孔内就位,借助自重保证支撑体系的标高及垂直度正确,用接驳器连接牢固。吊运时应防止扭转、弯曲,安装时对准孔位,吊直扶稳,缓慢下放,避免碰撞孔壁,就位后立即固定。
钢筋采用直螺纹机械连接方式,采取整体加工、分段下放的原则进行,注浆管则采用小直径的自来水管,同钢筋分段相同,采取丝口连接,编号后分段下放
7、复合锚杆就位后,准备注浆。注浆采用三根注浆管,每根注浆管出口范围距底端4m,注浆管φ20mm,出浆孔φ4mm,四孔竖向错开150mm。
注浆管竖向安装时,第一根注浆管端不封闭管璧无出浆孔,其他两根管端封闭,并且第二根注浆管比第一、第三根短4m,给第一根管注浆时,二、三根管的出浆孔用塑料胶带粘贴以隔离浆液,防止注浆时封赌出浆孔。
注浆采用施压密注浆,注浆分三次:第一次注浆采用常压注浆,注浆压力0.4~0.6MPa,孔口溢浆时结束本次注浆,水泥浆水灰比0.5∶1;第二次注浆采用中高压注浆,注浆压力1.0~1.5MPa,在第一次注浆完成后10~15小时进行,水泥浆水灰比0.75∶1;第三次注浆压力1.5~2.0MPa,在第二次注浆完成后5~10小时进行,水泥浆水灰比0.75∶1。所有注浆材料采用普硅525水泥。

Claims (4)

1.狭小空间内短桩加固技术,包括防护施工技术、狭小空间内短桩加固技术,其特征是:施工通道结构距离桥墩基础最近只有1.45m,且在施通道开挖底面在桥桩桩底标高以下3.7m。
2.根据权利要求1所述的的防护施工技术,其特征是:采用桩基周边打设复合锚杆桩加固,使复合锚杆桩加固的土体范围超过开挖深度,桩基承载面加深并扩大。
3.根据权利要求2所述的复合锚杆桩,其特征是:采用钢筋或钢管龙骨,注浆管采用全钢管或采用部分塑料、橡胶等替代管与钢管混用。
4.根据权利要求2所述的复合锚杆桩,采用注浆浆液采用水泥浆液或水泥水玻璃混合浆液等地层加固用浆液,注浆压力视地质情况控制在0.4~2.5MPa。
CN 201010199237 2010-06-12 2010-06-12 狭小空间内短桩加固技术 Pending CN102031795A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010199237 CN102031795A (zh) 2010-06-12 2010-06-12 狭小空间内短桩加固技术

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010199237 CN102031795A (zh) 2010-06-12 2010-06-12 狭小空间内短桩加固技术

Publications (1)

Publication Number Publication Date
CN102031795A true CN102031795A (zh) 2011-04-27

Family

ID=43885197

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010199237 Pending CN102031795A (zh) 2010-06-12 2010-06-12 狭小空间内短桩加固技术

Country Status (1)

Country Link
CN (1) CN102031795A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518450A (zh) * 2011-12-09 2012-06-27 王军 浅埋暗挖法地层加固普通水泥注浆取代超细水泥的注浆方法
CN107386274A (zh) * 2017-08-14 2017-11-24 中铁第勘察设计院集团有限公司 隧道侧穿桥桩的复合隔离桩及其加固施工方法
CN110241815A (zh) * 2019-06-20 2019-09-17 中国五冶集团有限公司 一种狭窄空间接桩加固方法
CN111560959A (zh) * 2020-06-01 2020-08-21 中铁十四局集团大盾构工程有限公司 邻近地铁的盾构始发井基坑开挖及支护方法
CN113338274A (zh) * 2021-06-01 2021-09-03 中铁十八局集团有限公司 一种地下空间拓建锚杆桩定位器
CN114017057A (zh) * 2021-11-11 2022-02-08 中铁十二局集团有限公司 一种高原铁路隧道双车道无轨运输辅助坑道现浇混凝土风渠隔板施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10102481A (ja) * 1996-09-30 1998-04-21 Okumura Corp 透水用矢板とこの矢板を用いた透水部を有する連続地中壁の構築方法
CN101070702A (zh) * 2007-06-14 2007-11-14 北京科技大学 一种单孔复合锚固桩
CN101413235A (zh) * 2008-11-25 2009-04-22 中国第一冶金建设有限责任公司 地道桥下穿铁路轨道施工前对铁路进行加固的方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10102481A (ja) * 1996-09-30 1998-04-21 Okumura Corp 透水用矢板とこの矢板を用いた透水部を有する連続地中壁の構築方法
CN101070702A (zh) * 2007-06-14 2007-11-14 北京科技大学 一种单孔复合锚固桩
CN101413235A (zh) * 2008-11-25 2009-04-22 中国第一冶金建设有限责任公司 地道桥下穿铁路轨道施工前对铁路进行加固的方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《铁道标准设计》 20081231 孙胜臣 地铁暗挖工程对既有结构影响的控制 44-46 1-4 , 第12期 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518450A (zh) * 2011-12-09 2012-06-27 王军 浅埋暗挖法地层加固普通水泥注浆取代超细水泥的注浆方法
CN102518450B (zh) * 2011-12-09 2014-06-18 温州大学 浅埋暗挖法地层加固普通水泥注浆取代超细水泥的注浆方法
CN107386274A (zh) * 2017-08-14 2017-11-24 中铁第勘察设计院集团有限公司 隧道侧穿桥桩的复合隔离桩及其加固施工方法
CN110241815A (zh) * 2019-06-20 2019-09-17 中国五冶集团有限公司 一种狭窄空间接桩加固方法
CN111560959A (zh) * 2020-06-01 2020-08-21 中铁十四局集团大盾构工程有限公司 邻近地铁的盾构始发井基坑开挖及支护方法
CN113338274A (zh) * 2021-06-01 2021-09-03 中铁十八局集团有限公司 一种地下空间拓建锚杆桩定位器
CN114017057A (zh) * 2021-11-11 2022-02-08 中铁十二局集团有限公司 一种高原铁路隧道双车道无轨运输辅助坑道现浇混凝土风渠隔板施工方法
CN114017057B (zh) * 2021-11-11 2023-05-02 中铁十二局集团有限公司 一种高原铁路隧道双车道无轨运输辅助坑道现浇混凝土风渠隔板施工方法

Similar Documents

Publication Publication Date Title
CN108060908B (zh) 建筑群下富水砂层长距离水平定向钻孔注浆加固工艺
CN101994513B (zh) 上半断面完成全断面帷幕注浆隧道施工方法
CN110821503B (zh) 一种超深盾构区间风井先隧后主体施工方法
CN202969392U (zh) 复杂地质深基坑联合支护
CN108678776B (zh) 砂质黏土地质隧道冒顶处理方法
CN109763483B (zh) 一种厚第四系深埋采空塌陷破碎地层上行式分段注浆工艺
CN107386274A (zh) 隧道侧穿桥桩的复合隔离桩及其加固施工方法
CN209924998U (zh) 一种浅覆土盾构隧道下穿道路加固保护结构
CN102031795A (zh) 狭小空间内短桩加固技术
CN110469332B (zh) 一种穿越泥石流堆积体隧道的超前支护固结方法
CN110566223B (zh) 一种深埋pba地铁车站断面设计方法
CN114233385B (zh) 一种斜井井筒突泥涌水的治理方法
CN104612696A (zh) 大断面暗挖地铁车站在粉细砂层中穿越高架桥柱洞法施工方法
CN103114595A (zh) 支护桩预留核心土双支墩斜内撑基坑支护方法及装置
CN104863183B (zh) 大断面隧道近接建筑物施工隔离减震桩结构及施工方法
CN112482364A (zh) 滨海地区强腐蚀性软弱地质条件下的旋挖灌注桩施工工艺
CN107965325A (zh) 一种小净距浅埋隧道初支拱架更换施工方法
CN111734425A (zh) 一种下穿机场航站楼的暗挖隧道的施工方法
CN109537579A (zh) 钻孔灌注桩的施工方法
CN103572764A (zh) 超深人工挖孔桩护壁止水结构及其施工方法
CN104863613B (zh) 岩质地层暗挖地下结构高边墙锚拉初支结构及施工方法
CN110644492B (zh) 陡倾角宽大裂隙地层综合灌浆施工方法
CN111560959A (zh) 邻近地铁的盾构始发井基坑开挖及支护方法
CN208803460U (zh) 一种增强水泥土搅拌桩截水效果的预制砼板桩
CN207109805U (zh) 一种隧道侧穿桥桩的复合隔离桩

Legal Events

Date Code Title Description
DD01 Delivery of document by public notice

Addressee: Chen Jian

Document name: Notification that Application Deemed not to be Proposed

C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110427