CN101845794B - 刚构桥、斜拉桥0#块施工支架的预应力预压方法 - Google Patents

刚构桥、斜拉桥0#块施工支架的预应力预压方法 Download PDF

Info

Publication number
CN101845794B
CN101845794B CN 201010131893 CN201010131893A CN101845794B CN 101845794 B CN101845794 B CN 101845794B CN 201010131893 CN201010131893 CN 201010131893 CN 201010131893 A CN201010131893 A CN 201010131893A CN 101845794 B CN101845794 B CN 101845794B
Authority
CN
China
Prior art keywords
bearing support
load bearing
primary load
cushion cap
distribution beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201010131893
Other languages
English (en)
Other versions
CN101845794A (zh
Inventor
魏天鸿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
China 19th Metallurgical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Corp filed Critical China 19th Metallurgical Corp
Priority to CN 201010131893 priority Critical patent/CN101845794B/zh
Publication of CN101845794A publication Critical patent/CN101845794A/zh
Application granted granted Critical
Publication of CN101845794B publication Critical patent/CN101845794B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种刚构桥主承力支架的预应力预压方法,具有可便于对主承力支架进行承压验证的目的。该刚构桥0#块施工支架的预应力预压方法,包括以下步骤:a、浇注承台以及支撑在承台上的桥墩;b、将主承力支架固定设置在桥墩上,并将分配梁设置在主承力支架上;c、采用施力装置施加向下的预压力在主承力支架与分配梁上,并利用承台作承力点使预压力的反向力作用在承台上;d、卸除施加在主承力支架与分配梁上的预压力,对主承力支架与分配梁的强度、刚度和稳定性进行检验。该方法不需要专门的预压材料堆放场地,简化了对0#块施工支架的试验条件,特别对于桥墩高、施工场地狭小的项目更具优越性,适合对各种承压件的承压能力进行受力验证。

Description

刚构桥、斜拉桥0#块施工支架的预应力预压方法
技术领域
本发明涉及一种检验承力构件承压能力的方法,具体涉及一种刚构桥、斜拉桥0#块施工支架的预应力预压方法。
背景技术
传统的刚构桥、斜拉桥0#块施工支架(包括主承力支架与分配梁)的预压均采用上部堆载施加荷载,实现对施工阶段支架体系的受力验证。但在该试验过程中所需装卸的材料量较大,造成施工成本的提高;且施工进度较慢;对场地的要求也较严格,即需要有专门的预压材料堆放场地。
发明内容
本发明所要解决的技术问题是提供一种便于对主承力支架进行承压验证的刚构桥、斜拉桥0#块施工支架的预应力预压方法。
本发明解决其技术问题所采用的技术方案是:刚构桥、斜拉桥0#块施工支架的预应力预压方法,包括以下步骤:
a、浇注承台以及支撑在承台上的桥墩;
b、将主承力支架固定设置在桥墩上,并将分配梁设置在主承力支架上;
c、采用施力装置施加向下的预压力在主承力支架与分配梁上,并利用承台作承力点使预压力的反向力作用在承台上;
d、卸除施加在主承力支架与分配梁上的预压力,对主承力支架与分配梁的强度、刚度和稳定性进行检验。
进一步的是,在步骤b中将分配梁设置在主承力支架上后,在分配梁上方设置张拉传力支架,在张拉传力支架上连接传力连接件穿过主承力支架与分配梁;在步骤c中将施力装置连接传力连接件。
进一步的是,在步骤a中浇注承台时,在承台内预埋张拉锚固件;传力连接件的底端固定连接张拉锚固件,使传力连接件顶端穿过主承力支架、分配梁与张拉传力支架并延伸至张拉传力支架上方;在步骤c中所述的施力装置为液压千斤顶,液压千斤顶的缸座连接在张拉传力支架上,液压千斤顶的活塞杆连接在传力连接件上。
进一步的是,所述传力连接件采用多根钢绞线组成,并沿主承力支架的中心对称布置,液压千斤顶施加的预压力沿主承力支架的中心对称分布。
本发明的有益效果是:采用本发明对0#块施工支架进行预应力预压,可避免现有技术中采用过多的堆载材料进行受力验证,只需要采用作用在0#块施工支架上的施力装置即可;该方法不需要专门的预压材料堆放场地,大大简化了对0#块施工支架的试验条件,且可节约施工成本,加快施工进度,也能保证质量和安全,特别对于桥墩高、施工场地狭小的项目更具优越性,适合对各种承压件的承压能力进行受力验证。
附图说明
图1为本发明的结构示意图。
图中标记为:承台1、桥墩2、主承力支架3、分配梁4、张拉锚固件5、张拉传力支架6、传力连接件7、液压缸8。
具体实施方式
下面结合附图和实施例对本发明进一步说明。
如图1所示,本发明的刚构桥、斜拉桥0#块施工支架的预应力预压方法,包括以下步骤:
a、浇注承台1以及支撑在承台1上的桥墩2;为后续主承力支架3的搭设作前置基础。
b、将主承力支架3固定设置在桥墩2上,并将分配梁4设置在主承力支架3上;
c、采用施力装置施加向下的预压力在主承力支架3与分配梁4上,并利用承台1作承力点使预压力的反向力作用在承台1上;施力装置在对主承力支架3与分配梁4施加预压力时,可以将施力装置设置在主承力支架3与承台1之间对主承力支架3与分配梁4施加向下的预压力,也可以是将施力装置设置在分配梁4上方对主承力支架3与分配梁4施加向下的预压力,施力装置施加的预压力应与主承力支架3和分配梁4承受的应力相当,以得到主承力支架3和分配梁4在实际工作中的承压能力。而在施加预压力时,必须具有一个预压力的承力点承受反向作用力,才能使施力装置的预压力作用在主承力支架3与承台1上时形成平衡,因此,本发明将承台1作承力点使预压力的反向力作用在承台1上,这样,当施力装置施加向下的预压力时,必然具有一个反向的作用力作用在承台1上,使得充分利用刚构桥修筑时的结构,简化预压的试验条件。
d、卸除施加在主承力支架3与分配梁4上的预压力,对主承力支架3与分配梁4的强度、刚度和稳定性进行检验。在步骤c中施加的预压力保持一段时间过后(一股为5~7天),即可卸除该施加的预压力,然后对主承力支架3与分配梁4的强度、刚度和稳定性进行检验,若均合格,则可将主承力支架3与分配梁4用于刚构桥、斜拉桥上的0#块施工作业,若不合格,则做改进加强后重复上述试验,合格后方可投入下道工序使用,避免带来后续施工的质量安全隐患。
采用上述a~d步骤进行试验,可避免现有技术中采用过多的堆载材料进行受力验证,只需要设置施力装置对主承力支架3与分配梁4施加向下的预应力即可,该施力装置主要包括采用液、气、电等形式实现的动力装置。该方法不需要专门的预压材料堆放场地,大大简化了对0#块施工支架(主承力支架3与分配梁4)的试验条件,且可节约施工成本,加快施工进度,也能保证质量和安全,特别对于桥墩高、施工场地狭小的项目更具优越性。
为提高主承力支架3与分配梁4的受力验证可靠性,在步骤b中将分配梁4设置在主承力支架3上后,在分配梁4上方设置张拉传力支架6,在张拉传力支架6上连接传力连接件7穿过主承力支架3与分配梁4;在步骤c中将施力装置连接传力连接件7。张拉传力支架6的设置,可使施力装置施加的向下预压力均匀传递到主承力支架3与分配梁4上,提高了主承力支架3与分配梁4的受力验证可靠性。在该实施方式中,可将传力连接件7顶端固定连接在张拉传力支架6上,其底端依次穿过分配梁4、主承力支架3延伸到承台1上方,然后将施力装置一端固定在承台1上,另一端连接在传力连接件7底端,当施力装置施加一个向下的预压力时,通过传力连接件7作用在张拉传力支架6上,并通过张拉传力支架6均匀传递到主承力支架3与分配梁4上,但该方式需要在结构下方施工,相对具有一定的安全隐患。作为优选的实施方式,在步骤a中浇注承台1时,在承台1内预埋张拉锚固件5;传力连接件7的底端固定连接张拉锚固件5,使传力连接件7顶端穿过主承力支架3、分配梁4与张拉传力支架6并延伸至张拉传力支架6上方;在步骤c中所述的施力装置为液压千斤顶8,液压千斤顶8的缸座连接在张拉传力支架6上,液压千斤顶8的活塞杆连接在传力连接件7上。这样,在布置施力装置即液压千斤顶8时,是在张拉传力支架6上进行布置,可大大提高安全性。
在上述实施方式中,为了达到对主承力支架3与分配梁4所施加预压力更均匀分布,所述传力连接件7采用多根钢绞线组成,并沿主承力支架3的中心对称布置,液压千斤顶8施加的预压力沿主承力支架3的中心对称分布。通过该布置形式后,可使主承力支架3与分配梁4的各部分受力更为均匀,更容易得到有效的受力验证数据。

Claims (3)

1.刚构桥、斜拉桥0#块施工支架的预应力预压方法,包括以下步骤:
a、浇注承台(1)以及支撑在承台(1)上的桥墩(2);
b、将主承力支架(3)固定设置在桥墩(2)上,并将分配梁(4)设置在主承力支架(3)上;
c、采用施力装置施加向下的预压力在主承力支架(3)与分配梁(4)上,并利用承台(1)作承力点使预压力的反向力作用在承台(1)上;
d、卸除施加在主承力支架(3)与分配梁(4)上的预压力,对主承力支架(3)与分配梁(4)的强度、刚度和稳定性进行检验;
在步骤b中将分配梁(4)设置在主承力支架(3)上后,在分配梁(4)上方设置张拉传力支架(6),在张拉传力支架(6)上连接传力连接件(7)穿过主承力支架(3)与分配梁(4);在步骤c中将施力装置连接传力连接件(7);
在步骤a中浇注承台(1)时,在承台(1)内预埋张拉锚固件(5);传力连接件(7)的底端固定连接张拉锚固件(5),使传力连接件(7)顶端穿过主承力支架(3)、分配梁(4)与张拉传力支架(6)并延伸至张拉传力支架(6)上方。
2.如权利要求1所述的刚构桥、斜拉桥0#块施工支架的预应力预压方法,其特征是:在步骤c中所述的施力装置为液压千斤顶(8),液压千斤顶(8)的缸座连接在张拉传力支架(6)上,液压千斤顶(8)的活塞杆连接在传力连接件(7)上。
3.如权利要求2所述的刚构桥、斜拉桥0#块施工支架的预应力预压方法,其特征是:所述传力连接件(7)采用多根钢绞线组成,并沿主承力支架(3)的中心对称布置,液压千斤顶(8)施加的预压力沿主承力支架(3)的中心对称分布。
CN 201010131893 2010-03-24 2010-03-24 刚构桥、斜拉桥0#块施工支架的预应力预压方法 Active CN101845794B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010131893 CN101845794B (zh) 2010-03-24 2010-03-24 刚构桥、斜拉桥0#块施工支架的预应力预压方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010131893 CN101845794B (zh) 2010-03-24 2010-03-24 刚构桥、斜拉桥0#块施工支架的预应力预压方法

Publications (2)

Publication Number Publication Date
CN101845794A CN101845794A (zh) 2010-09-29
CN101845794B true CN101845794B (zh) 2012-12-12

Family

ID=42770594

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010131893 Active CN101845794B (zh) 2010-03-24 2010-03-24 刚构桥、斜拉桥0#块施工支架的预应力预压方法

Country Status (1)

Country Link
CN (1) CN101845794B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102023092B (zh) * 2010-10-29 2012-02-29 中国一冶集团有限公司 手推移动式预制构件对桥梁支撑架进行加载试验的方法
CN102587283B (zh) * 2012-03-14 2014-11-26 中国十九冶集团有限公司 一种现浇混凝土桥梁的现浇施工方法
CN102704401A (zh) * 2012-05-28 2012-10-03 宁波二十冶建设有限公司 满堂支架分区预压技术
CN102840996B (zh) * 2012-09-20 2014-11-05 中铁八局集团第一工程有限公司 检测施工支架承载能力和变形的反拉预压方法
CN105040598A (zh) * 2015-08-26 2015-11-11 江苏省交通工程集团有限公司 一种悬浇箱梁0号块的预压施工装置及其预压施工方法
CN107012795A (zh) * 2017-05-22 2017-08-04 中国铁建大桥工程局集团有限公司 一种连续梁桥支架预压装置及其施工方法
CN109883843A (zh) * 2019-04-01 2019-06-14 河南省交通规划设计研究院股份有限公司 一种试验装置及采用该装置对预制拼装桥墩进行试验的方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201128884Y (zh) * 2007-11-15 2008-10-08 中交第一公路工程局有限公司 悬浇挂篮加载预压装置
CN101368371A (zh) * 2008-09-26 2009-02-18 中铁十二局集团第二工程有限公司 铁路客运专线满布支架现浇连续梁施工方法
CN101440604A (zh) * 2008-12-29 2009-05-27 中铁大桥局股份有限公司 一种钢索对拉式墩旁托架
CN101666158A (zh) * 2009-09-15 2010-03-10 中冶实久建设有限公司 滑模法施工倒锥形水塔筒身结构工程提升平台支承杆的纠偏方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201128884Y (zh) * 2007-11-15 2008-10-08 中交第一公路工程局有限公司 悬浇挂篮加载预压装置
CN101368371A (zh) * 2008-09-26 2009-02-18 中铁十二局集团第二工程有限公司 铁路客运专线满布支架现浇连续梁施工方法
CN101440604A (zh) * 2008-12-29 2009-05-27 中铁大桥局股份有限公司 一种钢索对拉式墩旁托架
CN101666158A (zh) * 2009-09-15 2010-03-10 中冶实久建设有限公司 滑模法施工倒锥形水塔筒身结构工程提升平台支承杆的纠偏方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
丁远江.用张拉钢绞线进行高墩桥挂篮的施工预压.《浙江建筑》.2009,(第04期), *
卜东平.山区高墩大跨斜拉桥百米高空下横梁施工新技术.《建筑施工》.2009,(第02期), *
卜东平.斜拉桥现浇段施工创新研究.《筑路机械与施工机械化》.2009,(第04期), *

Also Published As

Publication number Publication date
CN101845794A (zh) 2010-09-29

Similar Documents

Publication Publication Date Title
CN101845794B (zh) 刚构桥、斜拉桥0#块施工支架的预应力预压方法
CN103033385A (zh) 一种自平衡便携式自动控制剪力墙水平竖向荷载共同作用性能试验装置及方法
CN102353590B (zh) 一种监测钢丝微动疲劳状态的试验方法及装置
CN113335560B (zh) 一种复杂载荷盒段或筒段试验装置及方法
CN106702906A (zh) 一种挂篮预压装置及其预压方法
CN110359374A (zh) 一种挂篮预压反力支架及其施工方法
CN110205940A (zh) 0#块施工托架及其反拉预压方法
CN103952982B (zh) 桥梁箱梁挂篮锚地拉杆式千斤顶预压装置及预压方法
CN202766971U (zh) 连续梁悬臂现浇施工挂篮地面反拉预压装置
CN105259043A (zh) 批量钢管混凝土自平衡加载装置
CN205223871U (zh) 一种悬索桥桥塔横梁支架预压装置
CN102704412B (zh) 桥梁断柱顶升施工方法
CN201122142Y (zh) 一种32m/900t预应力混凝土先张箱梁静载试验台座
CN103015330A (zh) 顶升桥梁钢抱箍支架系统
CN105369745A (zh) 一种桥梁支座更换顶升反力架
CN206267033U (zh) 一种挂篮预压装置
CN104458311A (zh) 结构柱抗爆试验装置
CN2828765Y (zh) 一种新型轨道衡称体结构
CN201738246U (zh) 连续梁挂篮地面预压装置
CN211848977U (zh) 应用于高墩托架预压施工中的对拉预压装置
CN202416193U (zh) 桥梁悬臂浇筑施工挂篮非对称加载预压装置
CN217442801U (zh) 一种混合结构桥墩静力加载试验装置
CN203298984U (zh) 塔式起重机通用试验平台
CN201187038Y (zh) 挂篮整体吊装装置
CN202793828U (zh) 一种悬灌梁挂篮承载力测试装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA 19TH METALLURGICAL CORPORATION

Free format text: FORMER OWNER: MCC SHIJIU CONSTRUCTION CO., LTD.

Effective date: 20110318

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 617023 NO. 350, RENMIN STREET, PANZHIHUA CITY, SICHUAN PROVINCE TO: 617000 NO. 350, RENMIN STREET, EAST DISTRICT, PANZHIHUA CITY, SICHUAN PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20110318

Address after: 617000 Panzhihua, Sichuan, East Street, No. 350

Applicant after: China 19th Metallurgical Corporation

Address before: 617023 No. 350 Renmin Street, Sichuan, Panzhihua

Applicant before: MCC Shijiu Construction Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant