CN101844604A - 管架结构整体吊装定位方法 - Google Patents

管架结构整体吊装定位方法 Download PDF

Info

Publication number
CN101844604A
CN101844604A CN200910048067A CN200910048067A CN101844604A CN 101844604 A CN101844604 A CN 101844604A CN 200910048067 A CN200910048067 A CN 200910048067A CN 200910048067 A CN200910048067 A CN 200910048067A CN 101844604 A CN101844604 A CN 101844604A
Authority
CN
China
Prior art keywords
deck
integral hoisting
partial
positioning method
pipe frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910048067A
Other languages
English (en)
Other versions
CN101844604B (zh
Inventor
曾骥
陈刚
王�琦
马曙光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Waigaoqiao Shipbuilding Co Ltd
Shanghai Jiangnan Changxing Heavy Industry Co Ltd
Original Assignee
Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Waigaoqiao Shipbuilding Co Ltd filed Critical Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority to CN 200910048067 priority Critical patent/CN101844604B/zh
Publication of CN101844604A publication Critical patent/CN101844604A/zh
Application granted granted Critical
Publication of CN101844604B publication Critical patent/CN101844604B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种管架结构整体吊装定位方法,其包括以下步骤:先将管架结构拆成多个水平分片结构;划分出部分甲板区域;将水平分片先行与部分甲板预装成部分主甲板结构;将带有部分主甲板结构的管架整体吊装上船;将管架结构与船体主甲板总组定位。采用本发明的整体吊装定位方法,可使整体吊装总组时,定位精度高且安装容易。

Description

管架结构整体吊装定位方法
技术领域
本发明涉及一种吊装定位方法,特别是涉及一种应用在超大型FPSO、半潜式钻井平台,及自升式钻井平台等海洋工程中的大型管架结构的整体吊装定位技术。
背景技术
目前,海洋工程诸如超大型浮点式管架结构、半潜式钻井平台及自升式钻井平台等海洋工程中,经常需要将大型且形状特殊的管架结构或型钢结构与船体相接,由于这种管架结构严重不对称,且重量大,在与船体进行吊装时,通常是采取先在船体甲板上预制基座或桩腿,然后再分片吊装定位。这种分片总组的方法,不仅难度大、周期长、且定位精度不高、安全性差。
发明内容
本发明要解决的技术问题是为了克服现有大型管架结构吊装难度大,存在安装周期长、定位精度不高、安全性差的缺陷,提供一种安装周期短、且定位精度高、吊装定位容易的大型管架结构整体吊装定位方法。
本发明是通过下述技术方案来解决上述技术问题的:一种管架结构整体吊装定位方法,其特点在于,其包括以下步骤:
S1、先将管架结构拆成多个水平分片结构;
S2、划分出部分甲板区域;
S3、将水平分片先行与部分甲板预装成部分主甲板结构;
S4、将带有部分主甲板结构的管架整体吊装上船;
S5、将管架结构与船体主甲板总组定位。
其中,步骤S3中预装部分主甲板结构的步骤为:
S31、固定该部分甲板;
S32、将该水平分片结构在该部分甲板基础上组合成一部分主甲板结构。
其中,步骤S2中的部分甲板为船体主甲板上与该水平分片结构相连的局部甲板部分。
其中,步骤S3中还包括在该部分甲板的纵向和横向的一边预留嵌补结构的步骤。
其中,步骤S3中的将该水平分片结构与该部分甲板预装中,是以该部分甲板为基准进行的。
其中,步骤S3中的预装还包括以该部分甲板为基准进行的该管架结构的各管架之间的组装。
其中,步骤S5中的定位还包括对主甲板上与部分主甲板结构相配的挖空部分进行嵌补的步骤。
其中,该管架结构为海洋工程组合管架或半潜式钻井平台架。
本发明的积极进步效果在于:
1、本发明通过将与船体甲板相连接区域的部分甲板结构,单独划分出来先与管架结构组合成整体后,再与船体上的甲板焊接整平,可大幅提高整体吊装的定位精确度。
2、本发明的复杂管架结构,是先拆分成多个水平片结构在平地上建好组合后,再吊装上船,提高了超大型海洋工程结构整体吊装的安全性。
3、本发明通过在部分甲板结构的纵向侧和横向侧,预留出用于与船体甲板整平的嵌补结构,为吊装后的连接平整留下弥补的余地,提高了定位的精确性和一次吊装的成功率。
4、本发明最后通过一次性整体吊装定位,可以使吊装定位操作容易,且精度高,极大地缩短了建造周期。
附图说明
图1为本发明较佳实施例中的管架结构与船体主甲板吊装组合结构图。
具体实施方式
下面结合附图给出本发明较佳实施例,以详细说明本发明的技术方案。
如图1所示,本发明提供一种管架结构吊装定位方法,其步骤如下:
1、根据结构图纸,将复杂管架结构1拆分成各个水平分片分别建造;
2、将大型管架结构1与船体主甲板3相连部分的局部甲板21划分出来,作为部分主甲板结构2单独建造;且分别在其纵向和横向的一边预留300mm左右宽的嵌补结构;用于调整纵向和横向的定位精度。
3、将划分出来的部分甲板21先固定,接着,以部分甲板21为基准,将水平分片与部分甲板21精确焊接,组合成部分主甲板结构2。这样就提高了整体的安装精度。
4、再将带有部分主甲板结构2的大型管架结构整体与船体主甲板3吊装,并进行精确定位。
5、待定好位后,再组装用于修整定位精度的嵌补结构。其中,嵌补结构的处理运用为现有技术,在此不作赘述。
6、最后实现一次性整体吊装定位。
为了保证大型管架结构的整体吊装定位精度,本发明特将部分甲板21挖出,在平地上先行与大型管架一起预装,成为部分主甲板结构2,然后对船体主甲板3上与该部分甲板21装焊的挖空部分进行嵌补。采用上述的整体吊装定位技术,通过将复杂结构拆分成多个水平片结构分别建造不但施工简单而且确保了建造精度。本实施例中将连接区域的部分甲板结构2单独划分出来建造,且在纵向和横向的一边预留300mm左右宽的嵌补结构,可使得整体吊装时定位容易、安装精度高。实际吊装过程中,一般可先用临时胎架将划分出来的部分甲板21固定住,再将水平分片和个别特殊的单根结构在部分甲板21基础上进行结构总组,预装成为部分主甲板结构2,再行上船与主甲板3组装,可使大型管架整体吊装中,操作简单、安全,且总组周期短。
同理,本发明的管架结构整体吊装定位方法还可适用于半潜式钻井平台钻台结构的整体。
虽然以上描述了本发明的具体实施方式,但是本领域的技术人员应当理解,这些仅是举例说明,在不背离本发明的原理和实质的前提下,可以对这些实施方式做出多种变更或修改。因此,本发明的保护范围由所附权利要求书限定。

Claims (8)

1.一种管架结构整体吊装定位方法,其特征在于,其包括以下步骤:
S1、先将管架结构拆成多个水平分片结构;
S2、划分出部分甲板区域;
S3、将水平分片先行与部分甲板预装成部分主甲板结构;
S4、将带有部分主甲板结构的管架整体吊装上船;
S5、将管架结构与船体主甲板总组定位。
2.如权利要求1所述的管架结构整体吊装定位方法,其特征在于,步骤S3中预装部分主甲板结构的步骤为:
S31、固定该部分甲板;
S32、将该水平分片结构在该部分甲板基础上组合成一部分主甲板结构。
3.如权利要求1所述的管架结构整体吊装定位方法,其特征在于,步骤S2中的部分甲板为船体主甲板上与该水平分片结构相连的局部甲板部分。
4.如权利要求1所述的管架结构整体吊装定位方法,其特征在于,步骤S3中还包括在该部分甲板的纵向和横向的一边预留嵌补结构的步骤。
5.如权利要求1所述的管架结构整体吊装定位方法,其特征在于,步骤S3中的将该水平分片结构与该部分甲板预装中,是以该部分甲板为基准进行的。
6.如权利要求1所述的管架结构整体吊装定位方法,其特征在于,步骤S3中的预装还包括以该部分甲板为基准进行的该管架结构的各管架之间的组装。
7.如权利要求1所述的管架结构整体吊装定位方法,其特征在于,步骤S5中的定位还包括对主甲板上与部分主甲板结构相配的挖空部分进行嵌补的步骤。
8.如权利要求1至7中任意一项所述的管架结构整体吊装定位方法,其特征在于,该管架结构为海洋工程组合管架或半潜式钻井平台架。
CN 200910048067 2009-03-24 2009-03-24 管架结构整体吊装定位方法 Expired - Fee Related CN101844604B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910048067 CN101844604B (zh) 2009-03-24 2009-03-24 管架结构整体吊装定位方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910048067 CN101844604B (zh) 2009-03-24 2009-03-24 管架结构整体吊装定位方法

Publications (2)

Publication Number Publication Date
CN101844604A true CN101844604A (zh) 2010-09-29
CN101844604B CN101844604B (zh) 2012-12-26

Family

ID=42769457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910048067 Expired - Fee Related CN101844604B (zh) 2009-03-24 2009-03-24 管架结构整体吊装定位方法

Country Status (1)

Country Link
CN (1) CN101844604B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102328727A (zh) * 2011-06-01 2012-01-25 江苏熔盛造船有限公司 深水铺管起重船的重型海洋工程起重机底座的分段方法
CN102795318A (zh) * 2012-08-31 2012-11-28 上海海事大学 一种海洋工程浮式网架结构
CN104259808A (zh) * 2014-09-12 2015-01-07 上海船厂船舶有限公司 海上井架拼装及整吊上船方法
CN104802924A (zh) * 2014-05-27 2015-07-29 烟台中集来福士海洋工程有限公司 悬臂梁顶层管甲板及其建造方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5609441A (en) * 1995-03-15 1997-03-11 Khachaturian; Jon E. Method and apparatus for the offshore installation of multi-ton prefabricated deck packages on partially submerged offshore jacket foundations

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102328727A (zh) * 2011-06-01 2012-01-25 江苏熔盛造船有限公司 深水铺管起重船的重型海洋工程起重机底座的分段方法
CN102328727B (zh) * 2011-06-01 2014-03-12 江苏熔盛造船有限公司 深水铺管起重船的重型海洋工程起重机底座的分段方法
CN102795318A (zh) * 2012-08-31 2012-11-28 上海海事大学 一种海洋工程浮式网架结构
CN104802924A (zh) * 2014-05-27 2015-07-29 烟台中集来福士海洋工程有限公司 悬臂梁顶层管甲板及其建造方法
CN104802924B (zh) * 2014-05-27 2018-04-03 烟台中集来福士海洋工程有限公司 悬臂梁顶层管甲板及其建造方法
CN104259808A (zh) * 2014-09-12 2015-01-07 上海船厂船舶有限公司 海上井架拼装及整吊上船方法

Also Published As

Publication number Publication date
CN101844604B (zh) 2012-12-26

Similar Documents

Publication Publication Date Title
KR101646493B1 (ko) 해상풍력 지지구조물 및 그 자켓형 하부구조물의 설치 방법
CN101844604B (zh) 管架结构整体吊装定位方法
CN103422482B (zh) 一种拼装桁架式桩腿装置
CN103174166B (zh) 一种成套整体安装的游乐设施预埋件及其安装方法
CN105220776B (zh) 一种具有双向限位功能的h型钢梁双向滑动支座节点
CN104386219A (zh) 自升式平台桩靴后续入坞工艺
CN108426097A (zh) 一种乙二醇锑原料输送管道的地面减震装置
CN104120802B (zh) 一种隔震支座安装定位简易方法
CN107620262A (zh) 一种保留全部锚固螺栓的盆式支座更换施工方法
CN101264790A (zh) 一种艉人架的安装方法
KR101665329B1 (ko) 해양 작업 설치선의 레그 시스템
CN103225311A (zh) 用于海上风机导管架基础安装的固定调平结构
CN103255740A (zh) 立桩定位浮动码头
CN203238651U (zh) 用于海上风机导管架基础安装的固定调平结构
CN205440788U (zh) 一种自升式钻井平台桩腿与桩靴的连接结构
CN104476055A (zh) 一种米字型撑管的桩腿制作方法
CN103215915A (zh) 立桩与浮桥调节结构及应用有该调节结构的浮动码头
CN204979132U (zh) 一种船舶艉轴安装用辅助装置
CN104947868B (zh) 一种悬挑片装式栏杆立柱的底座
CN104389348B (zh) 一种带蒙皮拱结构的安装方法
CN204876084U (zh) 钢柱脚锚栓固定支架
CN207129101U (zh) 一种抛石塔基座
CN203834448U (zh) 一种新型6腿平台导管架
CN207405876U (zh) 一种用于柱构件的固定底座
CN113356263A (zh) 一种导管架-桩灌浆连接结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI WAIGAOQIAO SHIPBUILDING CO., LTD.

Effective date: 20140610

Owner name: SHANGHAI JIANGNAN CHANGXING HEAVY INDUSTRY CO., LT

Free format text: FORMER OWNER: SHANGHAI WAIGAOQIAO SHIPBUILDING CO., LTD.

Effective date: 20140610

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200137 PUDONG NEW AREA, SHANGHAI TO: 201913 PUDONG NEW AREA, SHANGHAI

TR01 Transfer of patent right

Effective date of registration: 20140610

Address after: 201913, room 1, 2203 Pudong Avenue, Shanghai, Pudong New Area

Patentee after: Shanghai Jiangnan Changxing Heavy Industry Co.,Ltd.

Patentee after: Shanghai Waigaoqiao Shipbuilding Co., Ltd.

Address before: 200137 Shanghai city Pudong New Area Zhouhai Road No. 3001

Patentee before: Shanghai Waigaoqiao Shipbuilding Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121226

Termination date: 20160324