CN101831851A - 红砂岩路基施工方法 - Google Patents

红砂岩路基施工方法 Download PDF

Info

Publication number
CN101831851A
CN101831851A CN 201010140922 CN201010140922A CN101831851A CN 101831851 A CN101831851 A CN 101831851A CN 201010140922 CN201010140922 CN 201010140922 CN 201010140922 A CN201010140922 A CN 201010140922A CN 101831851 A CN101831851 A CN 101831851A
Authority
CN
China
Prior art keywords
red sandstone
roadbed
construction
red
rolling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010140922
Other languages
English (en)
Other versions
CN101831851B (zh
Inventor
童宗胜
王洁
宣善宏
王可武
钱叶琳
殷铭
佐群
马双建
常乃坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Water Resources Development Co Ltd
Anhui Road and Bridge Engineering Group Co Ltd
Original Assignee
ANHUI CONSTRUCTION ENGINEERING GROUP Co Ltd
Anhui Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI CONSTRUCTION ENGINEERING GROUP Co Ltd, Anhui Road and Bridge Engineering Group Co Ltd filed Critical ANHUI CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN2010101409224A priority Critical patent/CN101831851B/zh
Publication of CN101831851A publication Critical patent/CN101831851A/zh
Application granted granted Critical
Publication of CN101831851B publication Critical patent/CN101831851B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

本发明涉及红砂岩路基的施工方法,采用专用机械组合:针对I、II类红砂岩的力学及路用性能的分析,采用大吨位的专用压实机械进行碾压,包括激震力45t的YZTY-22T拖式羊角碾破碎挤密,YZ32超大激振力振动压路机碾压,QCY360(25KJ三边形双轮)冲击压路机冲击补强。因为高速公路的线形标准高,填切工程量大,布线设计无法避让较宽广的红砂岩地带,在施工中必须要开挖出大量的红砂岩。若将这些红砂岩弃之不用,而远运其他材料填筑路基,不但延误工期,而且造价昂贵。同时,山区借土和弃土的场地难寻,并会造成环境污染,带来许多后患。本发明很好的利用了现场的红砂岩,降低造价,节约资源,有利于文明施工及环境保护。

Description

红砂岩路基施工方法
技术领域:
本发明涉及一种高速公路路基的施工方法,具体地说是一种直接利用I、II类红砂岩为材料作为高速公路路基的施工方法。
背景技术:
红砂岩是一种性质特殊的工程材料,I、II类红砂岩具有干燥状态下强度较高,遇水则软化、崩解等不良工程性质。以前红砂岩多用于弃方或低等级道路的填筑,I、II类红砂岩用在高速公路上较少,而且一般都是用在93区(下路堤)和94区(上路堤),使用在96区(路床)的极少。即使在低等级道路的路堤填筑中,采用常规的石方填筑方法和常规的施工工艺,也不能达到规范要求的标准,经常发生沉降和坍落等质量问题,导致路面或路基边坡的损坏。
发明内容:
为克服现有常规施工方法不能保证路基填筑质量的问题,本发明的目的在于提供一种以红砂岩为材料进行高速公路路基的施工方法,将I、II类红砂岩用于路堤和96区路床的填筑,该方法不仅能解决常规方法施工易出现的质量问题,而且机械利用率高,施工进度快,路基成型效果好。
本发明解决技术问题采用如下技术方案:
本发明红砂岩路基施工方法,采用以下步骤进行施工:
(1)施工前原料的处理,红砂岩爆破开挖后,在料场用破碎锤对大块红砂岩进行解小处理以有效降低其活性;
(2)耙压、整平,解小后的红砂岩运至施工现场,用推土机将红砂岩填料推平、压碎,之后耙出较大的颗粒,再次推平、压碎,直至大颗粒基本压碎以使红砂岩最大粒径不大于20cm,使红砂岩颗粒转变为低液限粘土或粉质粘土;
(3)控制红砂岩含水量,红砂岩路基填料的含水量控制在最佳含水量0~2%范围内,对现场填料采样后在现场试验室进行酒精燃烧法测定含水量,若含水量偏高,翻晒处理,含水量偏低,进行洒水处理;
(4)路拱及层间连接措施,施工中路拱横坡采用4%,遇雨或雨后,施工表面不干时,不得开放交通,雨后进行施工,下层填方须重新压实,符合要求后方可施工。在下一层填筑前,将已完工的路基用羊角碾重新振压一遍,形成凹凸面,可以加强上下层面间的联结;
(5)冲击碾压补强,采用45t拖式羊角碾和32t重型振动压路机碾压,进一步提高路堤均匀性与整体强度,对路基94区顶、96区顶,以及93区以下路基每填高2m部分,均采用冲击压路机补充冲击碾压;
(6)、边坡防护处理,由于红砂岩土层的水平向渗透系数较大,为了提高边坡的稳定性,在红砂岩填方段设立砼拱型骨架护坡,骨架中设置积水沟,减少坡面冲刷,并施工后在框格中植草,防止冲刷,以增加边坡稳定性。
与已有技术相比,本发明的有益效果体现在:
经济效益分析:高速公路的线形标准高,填切工程量大,布线设计无法避让较宽广的红砂岩地带,在施工中必须要开挖出大量的红砂岩。若将这些红砂岩弃之不用,而远运其他材料填筑路基,不但工期难以保证,而且造价昂贵。同时,山区借土和弃土的场地难寻,并会造成环境污染,带来许多后患。本发明施工方法很好的利用了现场的红砂岩,降低造价,节约资源,有利于文明施工及环境保护。
(1)红砂岩利用填方每方在4.5元左右,按照现在对I、II类红砂岩的一般处理方法,是在红砂岩中掺入一定量的石灰或水泥,一般是上层掺量5%,下层3%左右,现按掺4.5%水泥计算,每方需水泥88.65kg,按市场调查,不计入拌和机械人工费用,仅材料费约为28.5元,以71万方红砂岩填方计算,仅在材料上就可节约1704万元;若是按掺入石灰计算,则在材料上可以节约1258万元;按照换土处理,不计取土等其他费用,71万方可节约710万元。
(2)完全采用自然崩解处理,工期需要延长,以71万方土方计算,工期需延长至少3个月,对建设单位造成的投资回收具有较大影响。
结合上述分析,以71万方土方计算,除去机械费用的增加,采用红砂岩比掺入石灰材料可以节约1063万元,比掺入水泥节约1509万元;同时节约了换土所需要的占地和其他资源费用,具有很大的社会和经济效益。
综合效益分析:本发明总结的关键技术,对红砂岩分布较广地区的其他公路建设,具有很大的推广价值。本发明有效利用红砂岩挖方,作为路基的填方使用,节省了弃方用地,节约了材料,大大降低了成本,保护了生态环境,具有节约和环保的双重意义。
以下通过具体实施方式,并结合附图对本发明作进一步说明。
具体实施方式:
实施例:本发明所述的红砂岩路基施工方法,采用以下步骤:
(1)施工前原料的处理,红砂岩爆破开挖后,在料场直接采用破碎锤对大块红砂岩解小,进行工前崩解处理可有效降低红砂岩的活性。
(2)耙压、整平,解小后的红砂岩运至施工现场,用推土机将红砂岩填料推平,借助履带将粗颗粒压碎,再以推土机后面拖挂的松土齿耙松,并耙出较大的颗粒,再推、压较大颗粒,如此反复多次,直至大颗粒基本压碎,一般耙压遍数不得少于三遍。崩解不充分的红砂岩运至填方路段后,相应的“耙压”遍数需增加一倍。严格控制经耙压后的填料最大粒径不大于20cm。经过松土齿耙压,再推平压碎反复4~6次后,使红砂岩颗粒转变为低液性粘土或粉质粘土。
(3)控制红砂岩含水量,红砂岩路基填料的含水量控制在最佳含水量0~2%范围内,对现场填料采样后在现场试验室进行酒精燃烧法测定含水量,若含水量偏高,翻晒处理,含水量偏低,进行洒水处理;
(4)碾压、密实,针对I、II类红砂岩的力学及路用性能的分析,采用大吨位的专用压实机械进行碾压,包括激震力45t的YZTY-22T拖式羊角碾破碎挤密,YZ32超大激振力振动压路机碾压,QCY360(25KJ三边形双轮)冲击压路机冲击补强。
(5)路拱及层间连接措施,施工中路拱横坡采用4%,遇雨或雨后,施工表面不干时,不得开放交通,雨后进行施工,下层填方须重新压实,符合要求后方可施工。在下一层填筑前,将已完工的路基用羊角碾重新振压一遍,形成凹凸面,可以加强上下层面间的联结;
(6)冲击碾压补强,采用45t拖式羊角碾和32t重型振动压路机碾压,进一步提高路堤均匀性与整体强度,对路基94区顶、96区顶,以及93区以下路基每填高2m部分,均采用冲击压路机补充冲击碾压;
(7)、边坡防护处理,由于红砂岩土层的水平向渗透系数较大,为了提高边坡的稳定性,在红砂岩填方段设立砼拱型骨架护坡,骨架中设置积水沟,减少坡面冲刷,并施工后在框格中植草,防止冲刷,以增加边坡稳定性。

Claims (1)

1.红砂岩路基施工方法,其特征是采用以下步骤:
(1)施工前原料的处理,红砂岩爆破开挖后,在料场用破碎锤对大块红砂岩进行解小处理以有效降低其活性;
(2)耙压、整平,解小后的红砂岩运至施工现场,用推土机将红砂岩填料推平、压碎,之后耙出较大的颗粒,再次推平、压碎,直至大颗粒基本压碎以使红砂岩最大粒径不大于20cm,使红砂岩颗粒转变为低液限粘土或粉质粘土;
(3)控制红砂岩含水量,红砂岩路基填料的含水量控制在最佳含水量0~2%范围内,对现场填料采样后在现场试验室进行酒精燃烧法测定含水量,若含水量偏高,翻晒处理,含水量偏低,进行洒水处理;
(4)路拱及层间连接措施,施工中路拱横坡采用4%,遇雨或雨后,施工表面不干时,不得开放交通,雨后进行施工,下层填方须重新压实,符合要求后方可施工,在下一层填筑前,将已完工的路基用羊角碾重新振压一遍,形成凹凸面,可以加强上下层面间的联结;
(5)冲击碾压补强,采用45t拖式羊角碾和32t重型振动压路机碾压,进一步提高路堤均匀性与整体强度,对路基94区顶、96区顶,以及93区以下路基每填高2m部分,均采用冲击压路机补充冲击碾压;
(6)、边坡防护处理,由于红砂岩土层的水平向渗透系数较大,为了提高边坡的稳定性,在红砂岩填方段设立砼拱型骨架护坡,骨架中设置积水沟,减少坡面冲刷,并施工后在框格中植草,防止冲刷,以增加边坡稳定性。
CN2010101409224A 2010-04-08 2010-04-08 红砂岩路基施工方法 Expired - Fee Related CN101831851B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101409224A CN101831851B (zh) 2010-04-08 2010-04-08 红砂岩路基施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101409224A CN101831851B (zh) 2010-04-08 2010-04-08 红砂岩路基施工方法

Publications (2)

Publication Number Publication Date
CN101831851A true CN101831851A (zh) 2010-09-15
CN101831851B CN101831851B (zh) 2012-07-04

Family

ID=42716051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101409224A Expired - Fee Related CN101831851B (zh) 2010-04-08 2010-04-08 红砂岩路基施工方法

Country Status (1)

Country Link
CN (1) CN101831851B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031743A (zh) * 2010-12-17 2011-04-27 河南省新开元路桥工程咨询有限公司 泥岩填筑路堤的施工方法
CN102943423A (zh) * 2012-11-20 2013-02-27 中铁十九局集团第三工程有限公司 一种高液限粘土路基施工工艺
CN106087627A (zh) * 2016-06-16 2016-11-09 中交四公局第二工程有限公司 红砂岩路基填筑施工工艺
CN107747262A (zh) * 2017-09-28 2018-03-02 中国十七冶集团有限公司 一种多雨地区红砂岩路基填筑结构与施工方法
CN108239987A (zh) * 2017-12-13 2018-07-03 中航勘察设计研究院有限公司 一种采用大吨位振动碾压处理珊瑚砂地层地基的方法
CN108385486A (zh) * 2018-02-05 2018-08-10 浙江八达隧道工程股份有限公司 一种红砂岩路基施工方法及其加固装置
CN108978385A (zh) * 2018-06-13 2018-12-11 中国水利水电第九工程局有限公司 一种通村路的路基施工方法
CN111021173A (zh) * 2019-12-31 2020-04-17 郑州一建集团有限公司 一种市政道路填砂路基施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279105A (ja) * 1994-04-08 1995-10-24 Kanegafuchi Chem Ind Co Ltd 路盤の凍上防止工法
JP2003166201A (ja) * 2001-11-29 2003-06-13 Mitsui Takeda Chemicals Inc 床版防水工法及び該工法からなる構造体
WO2004097117A1 (en) * 2003-04-29 2004-11-11 Tapijtfabriek H. Desseaux N.V. Sports floor and method for constructing such a sports floor
CN101343852A (zh) * 2008-08-19 2009-01-14 中交第二公路勘察设计研究院有限公司 一种利用废钢渣填筑公路路基的方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279105A (ja) * 1994-04-08 1995-10-24 Kanegafuchi Chem Ind Co Ltd 路盤の凍上防止工法
JP2003166201A (ja) * 2001-11-29 2003-06-13 Mitsui Takeda Chemicals Inc 床版防水工法及び該工法からなる構造体
WO2004097117A1 (en) * 2003-04-29 2004-11-11 Tapijtfabriek H. Desseaux N.V. Sports floor and method for constructing such a sports floor
CN101343852A (zh) * 2008-08-19 2009-01-14 中交第二公路勘察设计研究院有限公司 一种利用废钢渣填筑公路路基的方法

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031743A (zh) * 2010-12-17 2011-04-27 河南省新开元路桥工程咨询有限公司 泥岩填筑路堤的施工方法
CN102943423A (zh) * 2012-11-20 2013-02-27 中铁十九局集团第三工程有限公司 一种高液限粘土路基施工工艺
CN106087627A (zh) * 2016-06-16 2016-11-09 中交四公局第二工程有限公司 红砂岩路基填筑施工工艺
CN107747262A (zh) * 2017-09-28 2018-03-02 中国十七冶集团有限公司 一种多雨地区红砂岩路基填筑结构与施工方法
CN108239987A (zh) * 2017-12-13 2018-07-03 中航勘察设计研究院有限公司 一种采用大吨位振动碾压处理珊瑚砂地层地基的方法
CN108239987B (zh) * 2017-12-13 2021-09-21 中航勘察设计研究院有限公司 一种采用大吨位振动碾压处理珊瑚砂地层地基的方法
CN108385486A (zh) * 2018-02-05 2018-08-10 浙江八达隧道工程股份有限公司 一种红砂岩路基施工方法及其加固装置
CN108978385A (zh) * 2018-06-13 2018-12-11 中国水利水电第九工程局有限公司 一种通村路的路基施工方法
CN111021173A (zh) * 2019-12-31 2020-04-17 郑州一建集团有限公司 一种市政道路填砂路基施工方法

Also Published As

Publication number Publication date
CN101831851B (zh) 2012-07-04

Similar Documents

Publication Publication Date Title
CN101831851B (zh) 红砂岩路基施工方法
CN102383413B (zh) 一种加固饱和流塑淤泥软土地基的施工方法
CN105951672B (zh) 一种新型堤岸与护坡的施工工艺
CN110965416B (zh) 一种针对山区高填方路基加固的竹材加筋体系及施工方法
CN106835884A (zh) 一种高填方段永久路基施工方法
CN110777588A (zh) 一种土石混合高填路基的压填施工方法
CN108677638A (zh) 基于建筑垃圾的高速公路路基填筑方法
CN109137659A (zh) 渣土类建筑废弃物填筑高速公路路基的施工方法
CN109736155A (zh) 建筑废弃物填筑高速公路路基施工工法
CN102031743A (zh) 泥岩填筑路堤的施工方法
CN107513992A (zh) 一种淤泥浅表层固化剂固结连续施工方法
CN102465481A (zh) 道路土工袋路基及方法
CN102296506A (zh) 土工袋台背路基及应用方法
CN206666953U (zh) 一种建筑垃圾再生集料的路基结构
CN101906774A (zh) 挖掘机锤击夯
CN103806434A (zh) 一种级配建渣土工袋处理钻前工程饱和过湿土地基的方法
CN111206598B (zh) 建筑垃圾在堆山造景工程中协同利用方法
CN210263007U (zh) 一种便于携带地基铺平装置
CN211142675U (zh) 一种渣土类建筑废弃物填筑的高速公路的路基结构
CN110158387B (zh) 一种用于修建防护堤的多层压实路基及其施工方法
CN102912702A (zh) 灰土加山皮石处理软土路基方法
CN102261075B (zh) 用固结充填材料优化排岩场护坡的方法
CN1326033A (zh) 一种土壤压实法和专用机具
CN102561364B (zh) 块石高填方强夯处理地基的“三步三层法” 堆填填筑施工工艺
CN102322016A (zh) 一种沥青路面沥青颗粒石料加楔夯实修补法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170420

Address after: High tech Zone Hefei city Anhui province 230088 Wangjiang Road 502 West Shushan Daxia

Co-patentee after: ANHUI WATER RESOURCES DEVELOPMENT Co.,Ltd.

Patentee after: ANHUI ROAD & BRIDGE ENGINEERING GROUP Co.,Ltd.

Address before: 230061 Anhui City, Hefei Province, No. 71 Jinzhai Road, building 15

Co-patentee before: ANHUI CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Patentee before: ANHUI ROAD & BRIDGE ENGINEERING GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120704