CN101818644B - Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method - Google Patents

Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method Download PDF

Info

Publication number
CN101818644B
CN101818644B CN 201010172177 CN201010172177A CN101818644B CN 101818644 B CN101818644 B CN 101818644B CN 201010172177 CN201010172177 CN 201010172177 CN 201010172177 A CN201010172177 A CN 201010172177A CN 101818644 B CN101818644 B CN 101818644B
Authority
CN
China
Prior art keywords
well
drilling
borehole wall
mud
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201010172177
Other languages
Chinese (zh)
Other versions
CN101818644A (en
Inventor
刘志强
陈远坤
李文增
赵时运
王新
曹新宇
廖卫勇
丁明
李英全
赵立新
杨道召
马进
孙建荣
张清
陶余荣
郑翔鲲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA COAL CONSTRUCTION SPECIAL ENGINEERING TECHNOLOGY Co Ltd
China Coal Special Drilling Engineering (group) Corp Ltd
Beijing China Coal Mine Engineering Co ltd
Huaibei Mining Group Co Ltd
Original Assignee
CHINA COAL CONSTRUCTION SPECIAL ENGINEERING TECHNOLOGY Co Ltd
China Coal Special Drilling Engineering (group) Corp Ltd
Beijing China Coal Mine Engineering Co ltd
Huaibei Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA COAL CONSTRUCTION SPECIAL ENGINEERING TECHNOLOGY Co Ltd, China Coal Special Drilling Engineering (group) Corp Ltd, Beijing China Coal Mine Engineering Co ltd, Huaibei Mining Group Co Ltd filed Critical CHINA COAL CONSTRUCTION SPECIAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN 201010172177 priority Critical patent/CN101818644B/en
Publication of CN101818644A publication Critical patent/CN101818644A/en
Application granted granted Critical
Publication of CN101818644B publication Critical patent/CN101818644B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a well digging process of a mining vertical shaft by adopting a one-drilling well completion and well drilling method. The well digging process is mainly used for solving the problems of large equipment occupation rate, high engineering cost, low working efficiency and sloe well completion speed in the existing well completion process of the mining vertical shaft. The well digging process mainly comprises the following steps: 1) drilling the shaft; 2) prefabricating the well wall; 3) sinking the well wall; and 4) carrying out wall back filling; the well is completed by only adopting the way of a primary pilot hole and a primary core drilling hole in the 1) shaft drilling process, the process can greatly improve the well completion speed of well digging by the well drilling method by about 20%; furthermore, as the process only adopts the primary pilot hole for drilling, the process can reduce the equipment occupation rate, reduce the discharge amount of slurry by about 20% and reduce the environmental protection; due to the adoption of a high-power drilling machine, a special drilling tool and reasonable technical parameters, the skew ratio of the well completion is less than 0.04%.

Description

Vertical shaft for mine pit shaft one is drilled to well sinking by boring technology
Technical field:
The present invention relates to adopt the construction technology of sinking by boring in the mine working construction, a kind of specifically vertical shaft for mine pit shaft one that is used for is drilled to well sinking by boring technology.
Background technology:
Sinking by boring is a kind of Fully-mechanized comprehensive sinking shaft technology, and the staff realizes digging a well and do not go into the well in ground handling.1. construction technology comprises the stratum broken rock and soil, carries, carries and separate; 2. expand well step by step; 3. well group temporary lining; 4. permanent support comprises the borehole wall manufacture, suspend sinking, support with backfilling, slip casting etc.Utilization drives drilling rod at the major diameter Rotary table for drilling machine of ground configuration, and drilling rod drives the drill bit rotation, and the hobboing cutter on the drill bit is realized rotation and revolution, and the stratum is produced impact, extruding, scraping comprehensive function, and layer is broken on the spot; After boring reaches the degree of depth, creep into and revise well and reach hole deviation partially through repeatedly expanding well again, when reaching intended diameter again with the steel concrete borehole wall prefabricated on the ground or steel plate concrete composite shaft lining, connect by joint with the steel flange dish, in mud-filled wellhole, suspension sinks down into the shaft bottom and makes permanent support.At last in borehole wall periphery with cement paste or other material, the filling well cementation of mud is replaced in segmentation according to formation condition.Existing sinking by boring technology is crept into link owing to comprise repeatedly reaming, though repeatedly reaming can relatively effectively utilize drill capacity, also has many problems: a plurality of reaming bits of needs, and the hold facility amount is big, the engineering cost height; Service working time is long, work efficiency is low, becomes well speed slow, can not satisfy quick shaft building needs.
Summary of the invention:
In order to reduce construction cost, reduce drilling time, accelerate into well speed, the invention provides a kind of vertical shaft for mine pit shaft " is drilled to well " sinking by boring technology.The method that the once leading hole drill of this process using advances improves the one-tenth well speed of sinking by boring greatly, safety, reliable, construction cost is low.
Technical scheme of the present invention is: 1, a kind of vertical shaft for mine pit shaft one is drilled to well sinking by boring technology, mainly comprises the following steps:
1. pit shaft creep into, 2. prefabricated, the 3. 4. support with backfilling of the borehole wall that sinks of the borehole wall.
1. pit shaft creeps into: boring adopts once whole hole, leading hole to become the form of well; It is AD130-1000 type rig that rig adopts the model of Luoyang mining machinery design and research institute and the co-design manufacturing of the special sinking shaft of middle coal company, and hobboing cutter or scraper can be selected insert cutter or middle tooth cutter by geological conditions; Drive kelly and common drilling rod by unit head, drive the drill bit rotation; Insert cutter or middle tooth cutter are housed on the drill bit, the broken rock of rotation under certain pressure, making catalase is landwaste, send into compressed air by the airduct in the drilling rod then, rise the mud that the liquid method will contain landwaste with calming the anger and drain into ground at a high speed, the mud that contains landwaste returns in the well after through ground precipitation purified treatment; The rig rotating speed is 0-18r/min during this time, drill pressure less than drill bit in mud weight 60%, when each stratum handing-over band and weathered zone crept into, the pressure of the drill suitably reduced 5-10T again on original basis.
Be the verticality of monitoring boring,, adopt the ultrasonic wave logging instrument, deviational survey is carried out in boring, can continue construction after meeting standard when creeping into certain depth or boring when finishing, otherwise, adopt correction to handle;
2. the borehole wall is prefabricated: when creeping into, and prefabricated lining on the ground, the borehole wall is the steel concrete borehole wall or steel plate composite shaft lining, does by restraining on the basis after the levelling on the ground;
3. the borehole wall sinks: utilize mud that the buoyancy of the borehole wall is added ballast water then in well, the borehole wall is slowly sunk, and control its hoverheight in mud, and during borehole wall spreading behind centering, weld, the borehole wall is set upright after sinking to the end, qualified after with suitable for reading fixing;
4. support with backfilling: be the annular space filling and injecting slurry between the borehole wall and rock group, from bottom to top branch plurality of sections height carries out, and adopts cement paste and rubble to replace filling, and the first filling section adopts the backfilling cement slurries, rock filling is inserted equably by well head, is consolidated into well then.
Beneficial effect of the present invention is mainly reflected in: owing to adopt above-mentioned technology, will hole and the classification reaming changes into and once holes into well, repeatedly reaming became well speed 25~30m/ month originally, changed the back and became well speed can reach 30~40m/ month, became well speed raising about 20%; Owing to shortened drilling time, it is about 20% that the mud emission amount reduces, and reduces a large amount of mud storage space areas, reduces the pollution to environment; Owing to adopted high-power rig and special drilling tool and rational technical data, make the useful area in the whole hole of drilling well satisfy the installation requirement that borehole wall suspension is sunk, become the deviating rate less than 0.04%.
Description of drawings
Fig. 1 is a leading hole schematic diagram;
Fig. 2 is the schematic diagram of drilling construction.
1-master cylinder among the figure, 2-drilling cramp, 3-balladeur train, 4-unit head, 5-hydraulic pressure, electrical system, 6-drilling machine platform, 7-seals flatcar, 8-drilling rod, 9-drill bit, 11-discharge trough, 13-discharge pipe, 15-ground mud pit, 16-mud groove, 17-mud, 18-wellhole, 19-fore shaft.
The specific embodiment:
The invention will be further described below in conjunction with accompanying drawing:
To shown in Figure 2, this vertical shaft for mine pit shaft one is drilled to well sinking by boring technology, mainly comprises the following steps: by Fig. 1
1. pit shaft creep into, 2. prefabricated, the 3. 4. support with backfilling of the borehole wall that sinks of the borehole wall;
At first 1., pit shaft creeps into: boring adopts once whole hole, leading hole to become the form of well, and as shown in Figure 1,2 is drilling cramp among the figure, and 17 is mud, and 9 is the whole drill in leading hole; The vertical trepan that boring adopts power unit type hydraulic cylinder to promote is made by Luoyang mining machinery design and research institute and the special sinking shaft of middle coal company co-design, and model is an AD130-1000 type rig; Drilling tool can be selected insert cutter or middle tooth cutter according to geological conditions, and topsoil is generally used middle tooth cutter, and rock section is generally used insert cutter; Creep into as shown in Figure 2, drilling machine platform 6 is installed on the ground fore shaft 19, and install and seals flatcar 7 at the female end place of fore shaft 19, and drilling machine platform 6 is equipped with hydraulic pressure, electrical system 5; Process is as follows: master cylinder 1 is by drilling cramp 2 guiding, propulsion power head 4 moves down along balladeur train 3, drive common drilling rod and kelly 8 in the process that moves down, drive drill bit 9 rotations, insert cutter or middle tooth cutter are housed on the drill bit 9, the broken rock of rotation under certain pressure, form wellhole 18 when making catalase be landwaste, send into compressed air by the airduct in the drilling rod 8 then, rise the mud 17 that liquid will contain landwaste with calming the anger and drain into ground mud pit 15 by drilling rod 8 and discharge pipe 13 at a high speed through discharge trough 11, the mud that contains landwaste returns in the well by mud groove 16 after through ground precipitation purified treatment.Technical data is during this time: rig moment of torsion 600kNm, unit head rotating speed 0-18r/min; Drill pressure less than drill bit in mud weight 60%, when each stratum handing-over band and weathered zone crept into, the pressure of the drill suitably reduced 5-10T again on original basis.
Be the verticality of monitoring boring,, adopt the ultrasonic wave logging instrument, deviational survey is carried out in boring, can continue construction after meeting standard when creeping into certain depth or boring when finishing, otherwise, adopt correction to handle;
2. the borehole wall is prefabricated: when creeping into, and prefabricated lining on the ground, the borehole wall is the steel concrete borehole wall and steel plate composite shaft lining, does by restraining on the basis after the levelling on the ground;
3. the borehole wall sinks: be to utilize mud that the buoyancy of the borehole wall is added ballast water then in well, the borehole wall is slowly sunk, and control its hoverheight in mud, and behind centering, weld during borehole wall spreading, what aligning method generally adopted is to fasten a meter word line at borehole wall center, fastens a vertical line and a rice word line central point centering then; The borehole wall is set upright after sinking to the end, and the setting upright of pit shaft just generally adopted two 20-30T jack tops, notes needing to guarantee the synchronism of jack, will suitable for readingly fix after qualified;
4. support with backfilling: be the annular space filling and injecting slurry between the borehole wall and rock group, from bottom to top branch plurality of sections height carries out, adopt cement paste and rubble to replace filling, pipe slip casting method in the first filling section adopts, the backfilling cement slurries, both arranged 5 interior grouting pipelines in pit shaft, wherein 4 are used for first section high filling, and remaining one is used for checking secondary after-teeming slurry behind the wall; Rock filling is inserted equably by well head, is consolidated into well then.
When implementing vertical shaft for mine pit shaft " expands into well " sinking by boring technology, the main technique technical requirements is as follows:
(1) control of pit shaft deflection: drill bit all guarantees to aim at drill center under its free state before creeping into, and its Deviation Control is in 5mm; The employed the pressure of the drill of borings at different levels all less than drill bit in mud weight 60%; When each stratum handing-over band and weathered zone crept into, the pressure of the drill suitably reduced 5-10T again on original basis; Adopting SKD-1 type ultrasonic wave logging instrument, the verticality and the hole diameter of borings at different levels are measured timely, so that in time take satisfactory after correcting, generally is will carry creeping into capable cleaning bottom of hole, reaches requirement up to deviation proportion and hole diameter.
(2) well group is stable: strict control drilling parameter; the pressure of the drill less than drill bit in mud weight 60%; the leading general rotating speed 5r/min in hole; moment of torsion is the 40%-60% of rig peak torque; the general 3r/min of reaming; moment of torsion is 80% of a rig maximum capacity; and take all factors into consideration the mud property parameter; 1. suppress pulping: adopt the high molecular polymer chemical agent, utilize its special construction preferentially to occupy the adsorbable zone on landwaste surface, form topping on its surface; stop effectively with mud in the contacting of Free water; suppress the aquation of slime water, broken landwaste is kept intact substantially, thereby suppress the complete pulping of soil block in creeping into drilling cuttings.2. reduce sand factor: utilize sedimentation basin to lean on the bigger landwaste of action of gravity sedimentation diameter; Discharge less landwaste with cyclone again; And then with more tiny landwaste of sodium phosphate trimer flocculating setting and flour sand.3. reduce fluid loss: if mud viscosity surpasses 24s, first thin up (fluid loss may raise, but the mud skin forms, can not cause too big harm) to 24s adds CMC again, and fluid loss is lowered.4. mud parameter is controlled principle: to control fluid loss, to relax density value is means, and to form the head of liquid of the inboard head of liquid of hole wall greater than the hole wall outside, the assurance well is helped stable.
(3) processing of balled bit: take various several measures, as reducing the mud viscosity, control fluid loss, strict control drilling parameter is offered side draught and is closed up, and strengthens the mud uptake.
This technology becomes well speed to improve about 20% owing to adopt once leading hole to become the technology of well; It is about 20% that the mud emission amount reduces, and reduces the pollution to environment; Owing to adopted high-power rig and special drilling tool and rational technical data, made into the deviating rate less than 0.04%.This technology is not only used coal industry, also can use in other similar underground mine engineering.

Claims (1)

1. a vertical shaft for mine pit shaft one is drilled to well sinking by boring technology, mainly comprises the following steps:
1. pit shaft creep into, 2. prefabricated, 3. the sink borehole wall, 4. support with backfilling of the borehole wall,
Described 1. pit shaft creeps into: whole hole, leading hole is adopted in boring, it is AD130-1000 type rig that rig adopts the model of Luoyang mining machinery design and research institute and the co-design manufacturing of the special sinking shaft of middle coal company, hobboing cutter or scraper are pressed geological conditions and are selected insert cutter or middle tooth cutter, drive kelly and common drilling rod by unit head, drive the drill bit rotation; Insert cutter or middle tooth cutter are housed on the drill bit, the broken rock of rotation under the driving pressure of unit head, making catalase is landwaste, send into compressed air by the airduct in the drilling rod then, rise the mud that the liquid method will contain landwaste with calming the anger and drain into ground at a high speed, the mud that contains landwaste returns in the well after through ground precipitation purified treatment; During pit shaft crept into, the rig rotating speed was 0-18r/min, drill pressure less than drill bit in mud weight 60%, when each stratum handing-over band and weathered zone crept into, the pressure of the drill suitably reduced 5-10T again on original basis.
Be the verticality of monitoring boring,, adopt the ultrasonic wave logging instrument, deviational survey is carried out in boring, can continue construction after meeting standard when creeping into certain depth or boring when finishing, otherwise, adopt correction to handle;
2. the borehole wall is prefabricated: when creeping into, and prefabricated lining on the ground, the borehole wall is the steel concrete borehole wall or steel plate composite shaft lining, does by restraining on the basis after the levelling on the ground;
3. the borehole wall sinks: utilize mud that the buoyancy of the borehole wall is added ballast water then in well, the borehole wall is slowly sunk, and control its hoverheight in mud, and during borehole wall spreading behind centering, weld, the borehole wall is set upright after sinking to the end, qualified after with suitable for reading fixing;
4. support with backfilling: be the annular space filling and injecting slurry between the borehole wall and rock group, from bottom to top branch plurality of sections height carries out, and adopts cement paste and rubble to replace filling, and the first filling section adopts the backfilling cement slurries, rock filling is inserted equably by well head, is consolidated into well then.
CN 201010172177 2010-05-14 2010-05-14 Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method Expired - Fee Related CN101818644B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010172177 CN101818644B (en) 2010-05-14 2010-05-14 Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010172177 CN101818644B (en) 2010-05-14 2010-05-14 Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method

Publications (2)

Publication Number Publication Date
CN101818644A CN101818644A (en) 2010-09-01
CN101818644B true CN101818644B (en) 2011-11-30

Family

ID=42653896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010172177 Expired - Fee Related CN101818644B (en) 2010-05-14 2010-05-14 Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method

Country Status (1)

Country Link
CN (1) CN101818644B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924978A (en) * 2014-04-25 2014-07-16 淮南久诺矿用设备加工有限公司 Construction method for sinking inner layer well wall with freezing method
CN110094162A (en) * 2019-04-15 2019-08-06 锡林郭勒盟山金白音呼布矿业有限公司 A kind of drilling equipment and boring method of the pack hole for mine capital construction construction

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493809A (en) * 2011-12-12 2012-06-13 北京中煤矿山工程有限公司 Comprehensive shaft sinking method of positive and raising boring for vertical shaft
CN102425370B (en) * 2011-12-21 2014-03-26 中冶交通工程技术有限公司 Hole bottom oil pressure motor lithoclast combined power drilling tool construction method and device
CN103046931B (en) * 2012-12-03 2015-01-14 云南建工水利水电建设有限公司 Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN103046869B (en) * 2013-01-21 2015-10-14 中国葛洲坝集团第二工程有限公司 Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction
CN103133004B (en) * 2013-01-25 2015-03-04 北京中煤矿山工程有限公司 Technological process of ground prefabrication and installation of inner shaft wall of freezing shaft
CN109025908A (en) * 2018-08-08 2018-12-18 中国恩菲工程技术有限公司 Anti-corrosion drilling shaft lining for salt mine
CN109519174A (en) * 2019-01-09 2019-03-26 东北大学 A kind of shaft wall supporting construction
CN110344767B (en) * 2019-08-05 2021-05-07 鲁维彬 Vertical shaft excavating equipment connected and stabilized by using centrifugal force
CN110486018B (en) * 2019-08-14 2020-07-31 西安科技大学 Lattice type composite shaft structure and construction method
CN113374481A (en) * 2021-06-09 2021-09-10 中交第二公路勘察设计研究院有限公司 Well drilling method well sinking process with drilling before and after

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1025799C (en) * 1990-12-18 1994-08-31 鹤壁矿务局 Displacement grouting process for aven shaft sinking through quick sand layer
CN1187575A (en) * 1997-01-08 1998-07-15 中国京冶建设工程承包公司 Large diameter pile slip wall holing technique
CN1081266C (en) * 1997-06-06 2002-03-20 中国京冶建设工程承包公司 Hole forming process by wall sliding of large diameter pile
CA2476080C (en) * 2002-02-15 2012-01-03 Enventure Global Technology Mono-diameter wellbore casing

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924978A (en) * 2014-04-25 2014-07-16 淮南久诺矿用设备加工有限公司 Construction method for sinking inner layer well wall with freezing method
CN103924978B (en) * 2014-04-25 2015-11-18 淮南久诺矿用设备加工有限公司 The construction method of freeze-wellboring inner layer well wall
CN110094162A (en) * 2019-04-15 2019-08-06 锡林郭勒盟山金白音呼布矿业有限公司 A kind of drilling equipment and boring method of the pack hole for mine capital construction construction

Also Published As

Publication number Publication date
CN101818644A (en) 2010-09-01

Similar Documents

Publication Publication Date Title
CN101818644B (en) Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method
CN102493809A (en) Comprehensive shaft sinking method of positive and raising boring for vertical shaft
CN106245626A (en) A kind of hard formation churning driven enters method
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN103953386A (en) Upstream-blocking and downstream-seepage method for extracting gas in mining area
Liu et al. Key technologies of drilling process with raise boring method
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN110630321A (en) Goaf on-well filling equipment and method thereof
CN101858218B (en) Shaft sinking process for expansion well completion of mine vertical shaft with boring method
CN105156035A (en) PDC (polycrystalline diamond compact) drill bit with movable teeth
CN102777185A (en) Inclined well shaft construction technology
CN105697018A (en) Shaft excavation construction technology
CN110656947A (en) Method for tunneling raised section of seabed bedrock
CN216922116U (en) Shaft tunneling cutter head and shaft tunneling equipment
CN113653492B (en) Method for preventing rock burst in filling mining
CN112855029B (en) Goaf drilling external pipe expansion construction method
CN104141300A (en) Foundation pile hole drilling construction process
CN107313743B (en) Method for repairing weak zone of coal seam floor water-resisting layer by utilizing coal seam gas well
CN107762408B (en) Cave-making method for coal bed gas directional well
CN204827244U (en) Oscillating tooth PDC drill bit
CN116291471A (en) Construction method and tunneling equipment for large-diameter vertical shaft of upper soft and lower hard stratum
CN116220546A (en) Construction method for combining super-thick hard rock condition large-diameter long piles into holes
CN112360468B (en) Excavation supporting method for vertical shaft slag sliding well
CN105134125A (en) Construction process for blocking bottom end of annular space behind gas vertical well wall
CN104763332A (en) Percussive-rotary drilling method and system for horizontal directional drilling crossing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111130

Termination date: 20140514