CN103046869B - Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction - Google Patents

Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction Download PDF

Info

Publication number
CN103046869B
CN103046869B CN201310021013.2A CN201310021013A CN103046869B CN 103046869 B CN103046869 B CN 103046869B CN 201310021013 A CN201310021013 A CN 201310021013A CN 103046869 B CN103046869 B CN 103046869B
Authority
CN
China
Prior art keywords
hole
explosion
creep
guiding
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310021013.2A
Other languages
Chinese (zh)
Other versions
CN103046869A (en
Inventor
杨忠兴
程志华
戈文武
刘昕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Yichang Dingcheng Engineering Technology Service Co ltd
China Gezhouba Group No 2 Engineering Co Ltd
Original Assignee
China Ge Zhou Ba Group Is Second Project Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Ge Zhou Ba Group Is Second Project Co Ltd filed Critical China Ge Zhou Ba Group Is Second Project Co Ltd
Priority to CN201310021013.2A priority Critical patent/CN103046869B/en
Publication of CN103046869A publication Critical patent/CN103046869A/en
Application granted granted Critical
Publication of CN103046869B publication Critical patent/CN103046869B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention is the construction method of passing through guiding CONTROL OF STRATA MOVEMENT bore direction, comprising: 1) creep into: by surveying setting-out determination tapping point, and accurately erection perforation of boring machine creeps into; 2) hole deviation is measured: in pilot hole drilling process, regularly adopts inclinometer deviational survey, grasps pilot hole drift rate in time; 3) explosion at the bottom of hole: occur deflection in drilling process, run into guiding rock stratum, take explosion at the bottom of hole, destroy its strike; 4) consolidation grouting: after explosion at the bottom of hole, is consolidated into entirety to carrying out cementation at the bottom of hole by blasting crack and sillar; 5) repeatedly creep into, explosion, consolidation grouting at the bottom of hole, to creep into: cementation continues to creep into after condensation bundle, explosion, underflow consolidation grouting at the bottom of hole, wait to coagulate, creep into, repeatedly repeatedly until successfully accurately pass through guiding rock stratum.The inventive method is simple, convenient, and speed is fast, effectively can pass through guiding rock stratum in keyhole orientation.

Description

Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction
technical field:
The present invention relates to a kind of method of keyhole orientation, in particular a kind of construction method of passing through guiding CONTROL OF STRATA MOVEMENT bore direction.
background technology:
In water conservancy project, the vertical shaft of the object of construction production such as mining industry is particularly in deep shaft excavation construction, due to rock geology complicated condition, often run into " guiding " rock stratum, these " guiding " rock stratum is generally the steep dip rock stratum of comparing hard, direction and the strike angle of guiding are larger, these guiding rock stratum can have certain guide effect to boring direction in guide hole drilling process, hole scattering direction all tilts to same direction, the whole hole deviation proportion that can cause holing all far exceeds guide hole required precision becomes useless hole, adopt conventional " fill concrete, middle part adds stabiliser bar, the levelness of controlled drilling rate and rig " etc. satisfactory after correcting also its deviation proportion uncontrollable, have a strong impact on speed of application and construction quality.
summary of the invention:
The present invention seeks to overcome upper deficiency, provide a kind of construction technology simple, convenient, speed is fast, passes through steep dip guiding rock stratum safely and fast, effectively can pass through the construction method in the keyhole orientation of guiding rock stratum in keyhole orientation.
The object of the present invention is achieved like this:
The present invention passes through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction, and the method comprises the following steps:
1) creep into: by surveying setting-out determination tapping point, accurately erection perforation of boring machine creeps into;
2) hole deviation is measured: in pilot hole drilling process, and regularly adopt inclinometer deviational survey, grasp pilot hole drift rate in time, unusual circumstance takes measures to control, diligent deviational survey;
3) explosion at the bottom of hole: if there is deflection in drilling process, run into guiding rock stratum, take explosion at the bottom of hole, destroy its strike, blasting parameter is determined by explosion bulge test according to rocky condition;
4) consolidation grouting: after explosion at the bottom of hole, is consolidated into entirety to carrying out cementation at the bottom of hole by blasting crack and sillar, and when guaranteeing again to creep into, bit force is consistent, ensures correct drilling direction;
5) repeatedly creep into, explosion, consolidation grouting at the bottom of hole, to creep into: cementation continues to creep into after condensation bundle, explosion, underflow consolidation grouting at the bottom of hole, wait to coagulate, creep into, repeatedly repeatedly until successfully accurately pass through guiding rock stratum.    
Above-mentioned step 2) in the situation of undergoing an unusual development take to add stable drilling rod, control rate of penetration, control rig levelness.
In drilling process, occur in above-mentioned step 3) that deflection is taked to add stable drilling rod, controls rate of penetration, controlled rig levelness and carry out control and can not control deflection and run into guiding rock stratum and then take explosion at the bottom of hole to destroy strike.
Said method admixture water reducing agent, early strength admixture in filling process, to improve concentration of slurry, to improve slurries early strength, reduce and treat the solidifying time.
The inventive method is in vertical shaft pilot hole drilling process, run into guiding rock stratum, destroy attitude of rocks by explosion means and lose guide effect, carry out cementation be consolidated into entirety through splitting battle array to explosion sillar and explosion again, make drilling tool uniform force in its drilling process, thus achieve effectively control pilot hole bore direction, ensure that the drilling construction quality of pilot hole, and construction technology is simple, handling safety, speed of application are fast.
accompanying drawing illustrates:
Fig. 1 is that the present invention passes through guiding CONTROL OF STRATA MOVEMENT bore direction construction schematic diagram.
Fig. 2 is explosion schematic diagram at the bottom of hole.
Fig. 3 is consolidation grouting schematic diagram.
detailed description of the invention:
The present embodiment passes through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction, comprises the following steps:
1, creep into: see Fig. 1, by surveying setting-out determination pilot hole tapping point, accurately the perforate of erection rig 1 is crept into;
2, hole deviation is measured: see Fig. 1, in pilot hole 2 drilling process, regularly adopt inclinometer deviational survey, grasp pilot hole 2 drift rate in time, unusual circumstance is taked to add the measures such as stable drilling rod, control rate of penetration, control rig levelness and is controlled, diligent deviational survey;
3, explosion at the bottom of hole: see Fig. 1, Fig. 2, if there is deflection in drilling process, take fill concrete, middle part add stabiliser bar, the satisfactory after correcting such as the levelness of controlled drilling rate and rig also its deviation proportion uncontrollable and tilt to same direction time, explanation runs into guiding rock stratum 3, now take explosion 4 at the bottom of hole, destroy the strike of its guiding rock stratum 3, blasting parameter is determined by explosion bulge test according to rocky condition;
4, consolidation grouting: see Fig. 3, after explosion at the bottom of hole, to carrying out cementation at the bottom of hole, blasting crack and sillar are consolidated into overall 5, when guaranteeing again to creep into, bit force is consistent, ensures correct drilling direction.In filling process, admixture water reducing agent, early strength admixture are to improve concentration of slurry, to improve slurries early strength, reduce and treat the solidifying time;
5, repeatedly creep into, explosion, consolidation grouting at the bottom of hole, to creep into: cementation continues to creep into after condensation bundle, hole deviation is measured, explosion 4, underflow consolidation grouting 5 at the bottom of hole, wait to coagulate, creep into, repeatedly repeatedly until successfully accurately pass through guiding rock stratum;
Prove through a large amount of creative test: construction technology of the present invention is simple, handling safety, and speed of application is fast, achieves and effectively controls pilot hole bore direction, ensure that the drilling construction quality of pilot hole.
Above-described embodiment is further described foregoing of the present invention, but this should be interpreted as that the scope of the above-mentioned theme of the present invention is only limitted to above-described embodiment.All technology realized based on foregoing all belong to scope of the present invention.

Claims (4)

1. pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction, the method comprises the following steps:
1) creep into: by surveying setting-out determination tapping point, accurately erection perforation of boring machine creeps into;
2) hole deviation is measured: in pilot hole drilling process, and regularly adopt inclinometer deviational survey, grasp pilot hole drift rate in time, unusual circumstance controls, diligent deviational survey;
3) explosion at the bottom of hole: occur deflection in drilling process, run into guiding rock stratum, take explosion at the bottom of hole, destroy its strike;
4) consolidation grouting: after explosion at the bottom of hole, is consolidated into entirety to carrying out cementation at the bottom of hole by blasting crack and sillar, and when guaranteeing again to creep into, bit force is consistent, ensures correct drilling direction;
5) repeatedly creep into, explosion, consolidation grouting at the bottom of hole, to creep into: cementation continues to creep into after condensation bundle, explosion, underflow consolidation grouting at the bottom of hole, wait to coagulate, creep into, repeatedly repeatedly until successfully accurately pass through guiding rock stratum.
2. pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction as claimed in claim 1, it is characterized in that step 2) in unusual circumstance take to add stable drilling rod, control rate of penetration, control rig levelness and control.
3. pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction as claimed in claim 1, it is characterized in that occurring in drilling process in step 3) that deflection is taked to add stable drilling rod, controls rate of penetration, controlled rig levelness and carry out control and can not control deflection and run into guiding rock stratum and then take explosion at the bottom of hole, destroy strike.
4. the construction method of passing through guiding CONTROL OF STRATA MOVEMENT bore direction as described in claim 1 or 2 or 3, is characterized in that admixture water reducing agent, early strength admixture, to improve concentration of slurry, to improve slurries early strength, reduce and treat the solidifying time in filling process.
CN201310021013.2A 2013-01-21 2013-01-21 Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction Active CN103046869B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310021013.2A CN103046869B (en) 2013-01-21 2013-01-21 Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310021013.2A CN103046869B (en) 2013-01-21 2013-01-21 Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction

Publications (2)

Publication Number Publication Date
CN103046869A CN103046869A (en) 2013-04-17
CN103046869B true CN103046869B (en) 2015-10-14

Family

ID=48059696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310021013.2A Active CN103046869B (en) 2013-01-21 2013-01-21 Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction

Country Status (1)

Country Link
CN (1) CN103046869B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2530528A (en) * 2014-09-25 2016-03-30 Michael Mary Ignatius Mcloughlin Rock drill Position Analyser
CN109763769B (en) * 2017-11-09 2021-03-16 中国石油化工股份有限公司 Method for optimizing horizontal drilling direction of shale stratum
CN108759726A (en) * 2018-07-25 2018-11-06 河北工程大学 A kind of medium-length hole drift rate measuring device
CN109306850A (en) * 2018-09-27 2019-02-05 北京航天地基工程有限责任公司 Creep into method for correcting error in uneven mutually bed boundary

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6460630B2 (en) * 1998-12-10 2002-10-08 Sandvik Tamrock Oy Method and rock drilling apparatus for controlling rock drilling
CN1434191A (en) * 2002-01-25 2003-08-06 中国人民解放军工程兵第四十一旅 Bore construction method by bore explosion
CN101818644A (en) * 2010-05-14 2010-09-01 北京中煤矿山工程有限公司 Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method
CN102071682A (en) * 2011-01-20 2011-05-25 中铁二十二局集团有限公司 Method for correcting inclined hole formed by high strength stratum bridge drilling pile in karst growing area
CN102094580A (en) * 2009-12-10 2011-06-15 北京中煤矿山工程有限公司 Coal engineering hole directional drilling method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6460630B2 (en) * 1998-12-10 2002-10-08 Sandvik Tamrock Oy Method and rock drilling apparatus for controlling rock drilling
CN1434191A (en) * 2002-01-25 2003-08-06 中国人民解放军工程兵第四十一旅 Bore construction method by bore explosion
CN102094580A (en) * 2009-12-10 2011-06-15 北京中煤矿山工程有限公司 Coal engineering hole directional drilling method
CN101818644A (en) * 2010-05-14 2010-09-01 北京中煤矿山工程有限公司 Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method
CN102071682A (en) * 2011-01-20 2011-05-25 中铁二十二局集团有限公司 Method for correcting inclined hole formed by high strength stratum bridge drilling pile in karst growing area

Also Published As

Publication number Publication date
CN103046869A (en) 2013-04-17

Similar Documents

Publication Publication Date Title
CN102493822B (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN103046869B (en) Pass through the construction method of guiding CONTROL OF STRATA MOVEMENT bore direction
CN104481587B (en) The comprehensive coal working face top plate sandstone fissure water of putting of large mining depth, large span visits anti-method
CN106245626A (en) A kind of hard formation churning driven enters method
CN106089217B (en) Major long tunnel rapid constructing method under complex geological condition
CN104005415B (en) The efficient forming construction method thereof of diaphram wall in light weathered granite
CN102031775B (en) Construction technology of drilled pile in hard oblique rocks by medium hole blasting
CN109236297B (en) Coal mining method for remaining coal seam in residual mining area of cracking and filling combined ascending re-mining cutter column
CN106545362A (en) A kind of comprehensive determination method for putting gob side entry driving coal column Size of pillar
CN107084648B (en) It is a kind of to use pilot hole guide-localization and Smooth Blasting Construction method
CN102383813A (en) Construction method for ultralong loess accumulative roc tunnel
Bezuijen et al. Processes around a TBM
CN102966359A (en) Working face ventilation oxidization zone roof control method
CN103899351A (en) Filling and reinforcing method for processing complicated goafs
CN105625943A (en) Method for accurately controlling overbreak and underbreak by adopting peripheral hole formation through fine-adjustment drill rod of rock drilling jumbo
CN206801460U (en) A kind of rectangle friction pile drilling construction device
CN103670421A (en) Central inclined hole method parallel tunnel excavation method
CN104033155B (en) A kind of novel tunnel smooth surface digging rock drilling equipment and construction method
Zhao et al. Stability of boundary pillars in transition from open pit to underground mining
CN104179511A (en) Novel hole arrangement grouting method for enabling ground pre-grouting reinforcing roadway to penetrate through surrounding rocks at fault fracture zone
CN103643960A (en) Power tunnel construction method
CN104805830B (en) Non-shot rock uplift pile construction method
CN206503149U (en) A kind of ultra-deep steel pipe concrete continuous underground wall structure
Kostyuk et al. The Mine Working's Roof Stress-strain State Research in the Perspective of Development of New Coal Deposits of Kuzbass
CN206129278U (en) Earth pressure balance shield machine closely inclines and just props up undercut tunnel's construction structures

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 610091 Sichuan Province, Chengdu District of Qingyang City Industrial Development Zone (East) with the road No. 8 Building 10

Applicant after: CHINA GEZHOUBA GROUP SECOND ENGINEERING Co.,Ltd.

Address before: 610091 Sichuan Province, Chengdu District of Qingyang City Industrial Development Zone (East) with the road No. 8 Building 10

Applicant before: GEZHOUBA GROUP NO.2 ENGINEERING Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: GEZHOUBA GROUP NO.2 ENGINEERING CO.,LTD. TO: CHINA GE ZHOU BA GROUP IS SECOND PROJECT CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240522

Address after: 610091 building 15, zone n, Qingyang Industrial headquarters base, No. 239, Guangfu Road, Supo street, Qingyang District, Chengdu, Sichuan Province

Patentee after: CHINA GEZHOUBA GROUP SECOND ENGINEERING Co.,Ltd.

Country or region after: China

Patentee after: Hubei Yichang Dingcheng Engineering Technology Service Co.,Ltd.

Address before: 610091 building 10, No.8, Tongcheng Road, Industrial Development Zone (East District), Qingyang District, Chengdu City, Sichuan Province

Patentee before: CHINA GEZHOUBA GROUP SECOND ENGINEERING Co.,Ltd.

Country or region before: China