CN206503149U - A kind of ultra-deep steel pipe concrete continuous underground wall structure - Google Patents
A kind of ultra-deep steel pipe concrete continuous underground wall structure Download PDFInfo
- Publication number
- CN206503149U CN206503149U CN201720174265.2U CN201720174265U CN206503149U CN 206503149 U CN206503149 U CN 206503149U CN 201720174265 U CN201720174265 U CN 201720174265U CN 206503149 U CN206503149 U CN 206503149U
- Authority
- CN
- China
- Prior art keywords
- steel
- construction
- ultra
- pipe pile
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 33
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 32
- 239000010959 steel Substances 0.000 title claims abstract description 32
- 238000005259 measurement Methods 0.000 claims abstract description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 8
- 239000002689 soil Substances 0.000 claims description 7
- 238000007789 sealing Methods 0.000 claims description 6
- 238000004826 seaming Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 37
- 230000010412 perfusion Effects 0.000 abstract description 2
- 238000005553 drilling Methods 0.000 description 11
- 238000000034 method Methods 0.000 description 8
- 241001074085 Scophthalmus aquosus Species 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 230000002045 lasting effect Effects 0.000 description 1
- 238000003801 milling Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000010410 reperfusion Effects 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model is related to a kind of ultra-deep steel pipe concrete continuous underground wall structure and its construction method in the underground engineering field in field of civil engineering, the ultra-deep steel pipe concrete continuous underground wall structure includes steel-pipe pile (1), guide frame between stake, fill concrete (10), the part of inclination measurement device (8) four, in work progress, pass through construction steel pile tube (1) control construction perpendicularity, and ensure adjacent pile driving construction perfect parallelism not jag, continuous steel pipe (shaped steel) concrete diaphram wall body is formed in steel-pipe pile and adjacent stake seam crossing perfusion concrete, perpendicularity of constructing can be in work progress timely monitor and processing with perfect parallelism problem, construction depth is unrestricted, steady quality is reliable, it is particularly suitable for use in construction and the Foundation Pit Support Engineering of ultra-deep underground structure.
Description
Technical field
The utility model is related to the underground engineering field in field of civil engineering.
Background technology
Gone along with sb. to guard him for ultra-deep foundation pit, substantially gone along with sb. to guard him, when depth chin-deep, can be adopted using diaphram wall at present
Slotter grooving, or use is used to grab milling combination grooving, mud off, descending reinforcing cage after grooving, Reperfu- sion concrete, the ground commonly used at present
The lower general depth of diaphragm wall is up to 40~60 meters, for deeper foundation ditch, and reinforced concrete construction of diaphragm wall technique suffers from huge
Big challenge, is primarily due to construct for ultra-deep underground continuous wall, whether grabs native grooving or slotter grooving, grooving it is vertical
Straight degree high-precision control is world today's level problem, for the diaphram wall of nearly hundred meters of depths, even millesimal vertical
Degree error may also cause bottom 20cm jag, so as to not reach the purpose of earth-retaining sealing, even if using most advanced in the world
Equipment, it is also difficult to ensure reliable construction quality.Therefore, for Retaining Structure of Extra-deep Excavation, it is necessary to change prior art structure
Direction is thought, using reliable, measurable technical measures and technological means, it is ensured that perfectly safe.The utility model people proposes before this
From continuous piling wall construction technology is crept into, solving adjacent steel tube pile construction ensures not jag problem, is that ultra-deep foundation pit goes along with sb. to guard him form
Appearance specify direction.
The content of the invention
The purpose of this utility model is to provide a kind of ultra-deep steel pipe concrete continuous underground wall structure, and the ultra-deep steel pipe concrete underground connects
Continuous wall construction reliable construction quality, particularly can ensure that the parallel not jag of adjacent stake, and degree control precision is high, there is concrete filling between adjacent stake
Note, can form continuous shaped steel (steel pipe) concrete wall, construction depth is unrestricted, is particularly suitable for use in ultra-deep foundation pit and goes along with sb. to guard him and underground
The construction of structure.
Guide frame, filling concrete, inclination measurement device four between ultra-deep steel pipe concrete continuous underground wall structure Baogang pile tube, the stake
Part, wherein, guide frame includes the guider being connected respectively with adjacent steel-pipe pile and guider two parts between stake, is oriented to
Device is the sub-buckle or box that are mutually socketed with guider, and filling concrete is located between steel-pipe pile or stake in connection gap, deviational survey
Guide frame is connected between device and steel-pipe pile or stake.
In above-mentioned ultra-deep steel pipe concrete continuous underground wall structure, it can be set at above-mentioned adjacent steel-pipe pile seaming position
Put water stopping trough and water sealing structure.
The underground of depth is continuous needed for ultra-deep steel pipe concrete continuous underground wall structure of the present utility model can realize any engineering
Wall construction, and the parallel not jag of adjacent stake of successively construction can be accurately controlled, can the timely monitor control construction in work progress
The perpendicularity of wall, reliable construction quality, speed is fast, low cost.
Brief description of the drawings
Fig. 1 is a kind of ultra-deep steel pipe concrete continuous underground wall structure construction signal used in one embodiment of the present utility model
Figure.
Embodiment
As one embodiment of the present utility model as shown in Figure 1, introduced mainly in conjunction with Fig. 1 of the present utility model super
The construction procedure of deep steel pipe concrete diaphram wall and the steel pipe concrete continuous underground wall structure formed after the completion of construction method and construction
Construction.As shown in figure 1, the construction of the present utility model ultra-deep steel pipe concrete diaphram wall to be completed is included between steel-pipe pile (1), stake
Guide frame, filling concrete (10), the part of inclination measurement device (8) four, wherein, guide frame is connected with steel-pipe pile (1) between stake, is filled
Fill out concrete (10) to be located between steel-pipe pile (1) or stake in connection gap, knot is oriented between inclination measurement device (8) and steel-pipe pile (1) or stake
Structure is connected.In the present embodiment, guide frame may be designed as the guider (4) being connected respectively with adjacent stake and guider between stake
(5) two parts, guider (4) and guider (5) can be connected by H profile steel (2) as shown in Figure 1 with steel-pipe pile (1), work as H
, can be using connecting plate (6) as shown in Figure 1 even when shaped steel (2) size is unable to good match with steel-pipe pile (1) and its connector
Connect.In the present embodiment, in order to improve the water-stagnating effect that adjacent staking is stitched, it can be set at adjacent steel-pipe pile (1) seaming position
Water stopping trough (7) as shown in Figure 1 and water sealing structure (9), water sealing structure (9) can be water-swellable body or fill
The sealing bag of water, main purpose is the adjacent staking seam of closure.In the present embodiment, the web (3) of H profile steel (2) and steel-pipe pile (1) it
Between space can also using filling concrete (10) filling.This reality is introduced mainly in conjunction with Fig. 1 in the following part of the present embodiment
With the construction procedure and method of new ultra-deep steel pipe concrete underground continuous structure.The ultra-deep steel pipe concrete construction method of underground continuous wall
Comprise the following steps:The first step, is fixedly mounted leading truck, and the effect of leading truck is mainly first steel-pipe pile (1) of control and applied
Perpendicularity during work, because steel-pipe pile (1) lateral stiffness is big, by controlling the vertical control of steel-pipe pile (1) in work progress
The perpendicularity of steel pipe concrete diaphram wall after the completion of system construction.The first step of the present utility model is completed, into second step.In this step
In rapid, the steel-pipe pile (1) with guider (5) is positioned in leading truck, drill bit is installed in steel-pipe pile (1) bottom so that
Drilling rod is located in steel-pipe pile (1), and installs inclination measurement device (8) in steel-pipe pile (1) side wall, and the diameter of drill bit can compare steel-pipe pile
(1) external diameter is big, and so, after the completion of construction, drill bit can be placed in soil, and a dismounting drilling rod is recycled.Main purpose is so that
The bore diameter got out is more than the diameter of steel-pipe pile (1), is easy to steel-pipe pile (1) to adjust perpendicularity in work progress.Can also
The diameter of drill bit is slightly less than the diameter of steel-pipe pile (1), the brill of larger diameter is got out by drill bit rocking in drilling process
Hole.When the rated capacity of the calibrator (-ter) unit of use is higher, bore diameter can also be made to be less than the external diameter of steel-pipe pile (1), so
Benefit be that need not handle the hole on the outside of pile body after the completion of steel-pipe pile (1) piling construction.Otherwise, needed after pile sinking to steel-pipe pile
(1) space on periphery is handled.The all spaces of stake can be blocked by connecting Grouting Pipe slip casting in the outside of steel-pipe pile (1),
The space on steel-pipe pile (1) periphery can be blocked using the method for high-pressure rotary-spray, it is contemplated that steel-pipe pile (1) belongs to ultra-deep underground structure, can
The drilling rod of high-pressure rotary jet grouting pile or the guiding of drill bit are pre-set in the side wall of steel-pipe pile (1), to prevent rotary churning pile inclined at far-reaching place
From steel-pipe pile (1).So as to complete the second step of the present embodiment, into the 3rd step.In this step, drill bit is driven to bore by drilling rod
Enter the soil body, the soil body of steel-pipe pile (1) bottom is drilled loose or be drilled to mud, steel-pipe pile (1) is sunk into the soil body, steel-pipe pile (1) is sunk to
The casing of drilled pile can be doubled as after the soil body, protects hole wall not cave in, during steel-pipe pile (1) sinks to drilling, is measured simultaneously
The perpendicularity of steel-pipe pile is adjusted, steel-pipe pile (1) is remained vertical, while drilling can be ensured by the constraint of steel-pipe pile (1)
All the time it is vertical, and make drilling all the time with adjacent stake perfect parallelism.The 3rd step is completed, into the 4th step.This step is mainly lasting brill
Hole is to desired depth, while steel-pipe pile (1) is sunk down into expected absolute altitude.After the piling construction of steel-pipe pile (1) is completed, it will can put
Take out and recycle in the drilling rod in steel-pipe pile (1).The 4th step of the present embodiment is completed, into the 5th step.In this step, it will treat
In the guider (5) for the steel-pipe pile (1) that guider (4) insertion on the steel-pipe pile (1) of construction is formerly constructed, and to construct
Steel-pipe pile (1) bottom install drill bit so that drilling rod be located at steel pipe in, and steel-pipe pile (1) side wall install inclinometer pipe, repeat
3rd step to the 4th step, completes the piling construction of next steel-pipe pile (1).In the present embodiment, guider (4) and guider
(5) it can be sub-buckle or box in double buckle, the 5th step of the present embodiment be completed, into the 6th step.In this step, pass through
Whether the perpendicularity that inclination measurement device (8) determines construction steel pile tube (1) meets design requirement, and determine adjacent stake whether jag, such as
Be unsatisfactory for design requirement, then can on pull out steel-pipe pile (1) and construct again, if meeting design requirement, steel-pipe pile, adjacent stake can be connected
The space perfusion concrete at place, and next pile construction can be continued, so as to complete ultra-deep steel pipe concrete diaphram wall of the present utility model
Construction method.In the present embodiment, in the 3rd above-mentioned step, vibratory drilling method or static pressure method can be aided with by steel-pipe pile (1) and its connected
Fitting sinks to the soil body.In addition, in the present embodiment, in the 3rd above-mentioned step, using slotter drill bit can be replaced to complete square
The construction of steel pipe concrete stake diaphram wall.
This patent includes but is not limited to alternative other construction methods used of professional person in the art.
Claims (2)
1. a kind of ultra-deep steel pipe concrete continuous underground wall structure, it is characterized in that mixed including guide frame, filling between steel-pipe pile (1), stake
Solidifying soil (10), the part of inclination measurement device (8) four, wherein, between stake guide frame include respectively with leading that adjacent steel-pipe pile (1) is connected
To device (4) and guider (5) two parts, guider (4) is the sub-buckle or box that are mutually socketed, filling with guider (5)
Concrete (10) is located between steel-pipe pile (1) or stake in connection gap, guide frame between inclination measurement device (8) and steel-pipe pile (1) or stake
Connection.
2. ultra-deep steel pipe concrete continuous underground wall structure according to claim 1, it is characterized in that in above-mentioned adjacent steel pipe
Water stopping trough (7) and water sealing structure (9) are set at stake (1) seaming position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720174265.2U CN206503149U (en) | 2017-02-24 | 2017-02-24 | A kind of ultra-deep steel pipe concrete continuous underground wall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720174265.2U CN206503149U (en) | 2017-02-24 | 2017-02-24 | A kind of ultra-deep steel pipe concrete continuous underground wall structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206503149U true CN206503149U (en) | 2017-09-19 |
Family
ID=59842058
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720174265.2U Active CN206503149U (en) | 2017-02-24 | 2017-02-24 | A kind of ultra-deep steel pipe concrete continuous underground wall structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206503149U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836236A (en) * | 2017-02-24 | 2017-06-13 | 张继红 | A kind of ultra-deep steel pipe concrete continuous underground wall structure and its construction method |
CN114657998A (en) * | 2022-02-09 | 2022-06-24 | 中国建筑第八工程局有限公司 | Subway station deep foundation pit support structure and construction method thereof |
-
2017
- 2017-02-24 CN CN201720174265.2U patent/CN206503149U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836236A (en) * | 2017-02-24 | 2017-06-13 | 张继红 | A kind of ultra-deep steel pipe concrete continuous underground wall structure and its construction method |
CN114657998A (en) * | 2022-02-09 | 2022-06-24 | 中国建筑第八工程局有限公司 | Subway station deep foundation pit support structure and construction method thereof |
CN114657998B (en) * | 2022-02-09 | 2024-03-12 | 中国建筑第八工程局有限公司 | Subway station deep foundation pit retaining structure and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106245626A (en) | A kind of hard formation churning driven enters method | |
CN104153352B (en) | Karst geology rotary-drilling bored concrete pile hole forming process | |
CN104563098B (en) | A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method | |
CN105275381B (en) | Impact drill drilling construction method in rich water pebble layer | |
CN105951747B (en) | A kind of construction method of the pre-buried lattice column of contrary sequence method | |
CN107130592B (en) | construction method for long spiral drill and impact drill double-machine composite hole-forming cast-in-place pile | |
CN106836206A (en) | Casing rotary digging bore forming method | |
JP6342126B2 (en) | Ground injection method | |
CN103774690A (en) | Grabbing, drilling and punching combined underground continuous wall grooving construction method | |
CN102628266A (en) | Construction method of long spiral cast-in-situ bored pile | |
CN106193042A (en) | Next-door neighbour's underground structure sandy soil layer is gone along with sb. to guard him obstacle pile sweep-out method at ground wall | |
CN101586340A (en) | Preconditioning process of continuous wall for weak weathering terrane grooving construction | |
CN112196494B (en) | Construction process and construction equipment for geological pipeline jointed between rock and soil layer | |
CN111691397A (en) | Karst tunnel bottom filling bead string type karst cave steel pipe pile grouting hole forming method | |
CN110306531A (en) | High water level erratic boulder stratum construction of diaphragm wall technique | |
CN107084648A (en) | One kind uses pilot hole guide-localization and Smooth Blasting Construction method | |
CN105064381A (en) | High-low cutting edge double-wall steel cofferdam reinforced concrete once bottom sealing construction method | |
CN206503149U (en) | A kind of ultra-deep steel pipe concrete continuous underground wall structure | |
CN115369860A (en) | Construction method of super-long isolation pile close to subway | |
CN106836236A (en) | A kind of ultra-deep steel pipe concrete continuous underground wall structure and its construction method | |
CN105200994A (en) | Construction method for reserved shield crossing composite foundation pit support device | |
CN211500533U (en) | Hole guiding device for geological static pressure pile in rich thick sand layer | |
CN107964940A (en) | A kind of construction method of continuous wall trench underground | |
CN103806444A (en) | Soft soil layer rotary excavating pile construction method | |
CN107143335A (en) | The guide hole construction method of ultra-deep shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20181102 Address after: 200086 502, room 4, Lane 306, Helen Road, Hongkou District, Shanghai. Patentee after: Shanghai Solid Earth Rock Engineering Co., Ltd. Address before: 200086 502, room 4, Lane 306, Helen Road, Hongkou District, Shanghai. Patentee before: Zhang Jihong |
|