CN101805622B - 焦炉炭化室底部砖热补工艺 - Google Patents
焦炉炭化室底部砖热补工艺 Download PDFInfo
- Publication number
- CN101805622B CN101805622B CN 201010151098 CN201010151098A CN101805622B CN 101805622 B CN101805622 B CN 101805622B CN 201010151098 CN201010151098 CN 201010151098 CN 201010151098 A CN201010151098 A CN 201010151098A CN 101805622 B CN101805622 B CN 101805622B
- Authority
- CN
- China
- Prior art keywords
- brick
- oven
- coke
- temperature
- batch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
本发明属于焦化炉体耐材工艺改进技术领域,是一种焦炉炭化室底部砖热补工艺,提前对修补炉号降温,目标炉温为机侧1120℃、焦侧1180℃;炉头温度控制950--1000℃;修补炉号推完焦后炉温降至850--900℃,炉头温度控制800--850℃;降温的同时,在离检修段往焦侧1m处焦侧方向从炉顶大盖口处放保温砖挡墙;当修补炉号降温至800-850℃时,确保墙面温度大于700℃;清理破损面;用莫来石高铝粘土砖代替硅砖;上好机侧炉门,待温度升至1100℃开启机侧炉门观察检修效果。本发明可以完全避免补砖出现炸裂的问题,实现了非正常工况下焦炉生产的维持,延长焦炉一代炉龄。
Description
技术领域
本发明属于焦化炉体耐材工艺改进技术领域,具体的说是一种焦炉炭化室底部砖热补工艺。
背景技术
焦炉炭化室底部砖设计时除了头尾两块是用粘土砖砌筑,中间则全部采用硅砖进行砌筑。当一座焦炉由冷态砌筑转入正常生产,这种工艺设计完全能满足焦炉强度需要,而且硅砖的热性能也完全能满足生产需要。但当焦炉炭化室底部砖出现掉转后要恢复就出现技术问题。原先设计的硅砖材质就不能满足热态修补需要,新补进的硅砖则出现炸裂。例如一台2004年5月投产的焦炉,到今年2010年生产6年不到,出现一孔炭化室底部砖掉转,砖型为330*95*230的硅砖材质,必须及时进行热态修补,否则将严重影响该孔的出焦生产。常规修补工艺是用同型号的硅砖进行修复,可刚将硅砖放进800度的炉内半个小时后就出现炸裂,修补工作受阻。
发明内容
本发明所要解决的技术问题是:针对以上现有技术存在的缺点,提出一种焦炉炭化室底部砖热补工艺,可以解决焦炉炭化室底部砖掉转后的热补,延长焦炉炉龄。
本发明解决以上技术问题的技术方案是:
焦炉炭化室底部砖热补工艺,按以下步骤进行:
(1)提前对修补炉号降温,延长结焦时间,结焦时间延长到32小时,目标炉温为机侧1120℃、焦侧1180℃;炉头温度控制950--1000℃,相邻炉号根据检修时间降温延长结焦时间,结焦时间延长到26小时;
(2)修补炉号推完焦后炉温降至850--900℃,炉头温度控制800--850℃,同时相邻炉号开始保温;
(3)降温的同时,在离检修段往焦侧1m处焦侧方向从炉顶大盖口处放保温砖挡墙;
(4)当修补炉号降温至800-850℃时,墙面贴保温毡高度:2-3米,确保墙面温度大于700℃;
(5)清理破损面,将破砖及灰清理掉,并用压缩空气吹干净,保证底面平整无灰;
(6)用莫来石高铝粘土砖代替硅砖,铺砖顺序由里到外干排,最后一块砖现场加工,两侧各留10-15mm砖缝,砖与砖之间留5-10mm,表面要求平整,最后用硅火泥灌浆,并用刮刀将多余灰浆刮干净;
(7)上好机侧炉门,待温度升至1100℃开启机侧炉门观察检修效果,具备条件后推空炉开始投煤,相应周转时间延长至24h。
据热态下炭化室温度在800度的工作特点,必须寻找尺寸相近而又抗急冷急热性能的新材质。莫来石高铝粘土砖这种材质可以胜任该工况要求。由于炭化室底部宽是330mm,考虑到膨胀,采用宽300mm。原材质硅砖厚度为95mm,由于是经过长时间的生产,炭化室底部砖出现不同程度的磨损,补进去的新砖在高度方向不能出现逆向错台。砖型为设计为300*75*150mm的莫来石高铝砖。
本发明的优点是:使用本发明的焦炉炭化室底部砖热补工艺对炭化室底部砖进行修补,可以完全避免补砖出现炸裂的问题,实现了非正常工况下焦炉生产的维持,保证了焦炉一代25年以上的炉龄。
具体实施方式
实施例一
焦炉炭化室底部砖热补工艺,按以下步骤进行:
(1)提前对修补炉号降温,延长结焦时间,结焦时间延长到32小时,目标炉温为机侧1120℃、焦侧1180℃;炉头温度控制950℃,相邻炉号根据检修时间降温延长结焦时间,结焦时间延长到26小时;
(2)修补炉号推完焦后炉温降至850℃,炉头温度控制800℃,同时相邻炉号开始保温;
(3)降温的同时,在离检修段往焦侧1m处焦侧方向从炉顶大盖口处放保温砖挡墙;
(4)当修补炉号降温至800℃时,墙面贴保温毡高度2m,确保墙面温度大于700℃;
(5)清理破损面,将破砖及灰清理掉,并用压缩空气吹干净,保证底面平整无灰;
(6)用莫来石高铝粘土砖代替硅砖,砖型设计为300*75*150mm,铺砖顺序由里到外干排,最后一块砖现场加工,两侧各留10mm砖缝,砖与砖之间留5mm,表面要求平整,最后用硅火泥灌浆,并用刮刀将多余灰浆刮干净;
(7)上好机侧炉门,待温度升至1100℃开启机侧炉门观察检修效果,具备条件后推空炉开始投煤,相应周转时间延长至24h。
实施例二
焦炉炭化室底部砖热补工艺,按以下步骤进行:
(1)提前对修补炉号降温,延长结焦时间,结焦时间延长到32小时,目标炉温为机侧1120℃、焦侧1180℃;炉头温度控制980℃,相邻炉号根据检修时间降温延长结焦时间,结焦时间延长到26小时;
(2)修补炉号推完焦后炉温降至880℃,炉头温度控制830℃,同时相邻炉号开始保温;
(3)降温的同时,在离检修段往焦侧1m处焦侧方向从炉顶大盖口处放保温砖挡墙;
(4)当修补炉号降温至840℃时,墙面贴保温毡高度2.5m,确保墙面温度大于700℃;
(5)清理破损面,将破砖及灰清理掉,并用压缩空气吹干净,保证底面平整无灰;
(6)用莫来石高铝粘土砖代替硅砖,砖型设计为300*75*150mm,铺砖顺序由里到外干排,最后一块砖现场加工,两侧各留12mm砖缝,砖与砖之间留8mm,表面要求平整,最后用硅火泥灌浆,并用刮刀将多余灰浆刮干净;
(7)上好机侧炉门,待温度升至1100℃开启机侧炉门观察检修效果,具备条件后推空炉开始投煤,相应周转时间延长至24h。
实施例三
焦炉炭化室底部砖热补工艺,按以下步骤进行:
(1)提前对修补炉号降温,延长结焦时间,结焦时间延长到32小时,目标炉温为机侧1120℃、焦侧1180℃;炉头温度控制950--1000℃,相邻炉号根据检修时间降温延长结焦时间,结焦时间延长到26小时;
(2)修补炉号推完焦后炉温降至900℃,炉头温度控制850℃,同时相邻炉号开始保温;
(3)降温的同时,在离检修段往焦侧1m处焦侧方向从炉顶大盖口处放保温砖挡墙;
(4)当修补炉号降温至850℃时,墙面贴保温毡高度大于3m,确保墙面温度大于700℃;
(5)清理破损面,将破砖及灰清理掉,并用压缩空气吹干净,保证底面平整无灰;
(6)用莫来石高铝粘土砖代替硅砖,砖型设计为300*75*150mm,铺砖顺序由里到外干排,最后一块砖现场加工,两侧各留15mm砖缝,砖与砖之间留10mm,表面要求平整,最后用硅火泥灌浆,并用刮刀将多余灰浆刮干净;
(7)上好机侧炉门,待温度升至1100℃开启机侧炉门观察检修效果,具备条件后推空炉开始投煤,相应周转时间延长至24h。
本发明还可以有其它实施方式,凡采用同等替换或等效变换形成的技术方案,均落在本发明要求保护的范围之内。
Claims (1)
1.焦炉炭化室底部砖热补工艺,其特征在于:按以下步骤进行:
⑴提前对修补炉号降温,延长结焦时间, 结焦时间延长到32小时,目标炉温为机侧1120℃、焦侧1180℃;炉头温度控制950--1000℃,相邻炉号根据检修时间降温延长结焦时间,结焦时间延长到26小时;
⑵修补炉号推完焦后炉温降至850--900℃,炉头温度控制800--850℃,同时相邻炉号开始保温;
⑶降温的同时,在离检修段往焦侧1m处焦侧方向从炉顶大盖口处放保温砖挡墙;
⑷当修补炉号降温至800-850℃时,墙面贴保温毡高度为2-3米,确保墙面温度大于700℃;
⑸清理破损面,将破砖及灰清理掉,并用压缩空气吹干净,保证底面平整无灰;
⑹用莫来石高铝粘土砖代替硅砖,铺砖顺序由里到外干排,最后一块砖现场加工,两侧各留10-15mm 砖缝,砖与砖之间留5-10mm ,表面要求平整,最后用硅火泥灌浆,并用刮刀将多余灰浆刮干净;
⑺上好机侧炉门,待温度升至1100℃开启机侧炉门观察检修效果,具备条件后推空炉开始投煤,相应周转时间延长至24h;所述莫来石高铝粘土砖的砖型为:300*75*150 mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010151098 CN101805622B (zh) | 2010-04-15 | 2010-04-15 | 焦炉炭化室底部砖热补工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010151098 CN101805622B (zh) | 2010-04-15 | 2010-04-15 | 焦炉炭化室底部砖热补工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101805622A CN101805622A (zh) | 2010-08-18 |
CN101805622B true CN101805622B (zh) | 2013-01-02 |
Family
ID=42607578
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010151098 Expired - Fee Related CN101805622B (zh) | 2010-04-15 | 2010-04-15 | 焦炉炭化室底部砖热补工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101805622B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104073269B (zh) * | 2013-03-29 | 2016-09-14 | 上海梅山钢铁股份有限公司 | 焦炉炭底砖深度维修方法 |
CN104342175B (zh) * | 2013-07-30 | 2016-09-21 | 中国一冶集团有限公司 | 焦炉热修炭化室墙局部破损的方法 |
CN105385463B (zh) * | 2015-12-14 | 2018-08-17 | 芜湖新兴铸管有限责任公司 | 密封焦炉干燥孔塞子砖维护结构 |
CN108277025B (zh) * | 2018-04-12 | 2023-10-20 | 山东泰山焦化有限公司 | 焦炉炭化室在生产中进行的炉墙修补方法及专用组合工具 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3814613A (en) * | 1972-12-21 | 1974-06-04 | Steel Corp | Coke-oven patching material |
US4259120A (en) * | 1978-08-02 | 1981-03-31 | United States Steel Corporation | Coke oven patching and sealing material |
CN1613967A (zh) * | 2003-11-07 | 2005-05-11 | 酒泉钢铁(集团)有限责任公司 | 焦炉炭化室整墙热维修新工艺 |
CN1978590A (zh) * | 2005-12-10 | 2007-06-13 | 攀枝花新钢钒股份有限公司 | 一种焦炉炭化室底部耐火砖的热态修补方法 |
CN101381607A (zh) * | 2008-10-06 | 2009-03-11 | 中冶宝钢技术服务有限公司 | 炭化室炉墙人工修补工艺 |
-
2010
- 2010-04-15 CN CN 201010151098 patent/CN101805622B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3814613A (en) * | 1972-12-21 | 1974-06-04 | Steel Corp | Coke-oven patching material |
US4259120A (en) * | 1978-08-02 | 1981-03-31 | United States Steel Corporation | Coke oven patching and sealing material |
CN1613967A (zh) * | 2003-11-07 | 2005-05-11 | 酒泉钢铁(集团)有限责任公司 | 焦炉炭化室整墙热维修新工艺 |
CN1978590A (zh) * | 2005-12-10 | 2007-06-13 | 攀枝花新钢钒股份有限公司 | 一种焦炉炭化室底部耐火砖的热态修补方法 |
CN101381607A (zh) * | 2008-10-06 | 2009-03-11 | 中冶宝钢技术服务有限公司 | 炭化室炉墙人工修补工艺 |
Non-Patent Citations (1)
Title |
---|
许胜利等.焦炉加热控制的建模与优化.《宝钢技术》.2008,(第6期),第29-33页. * |
Also Published As
Publication number | Publication date |
---|---|
CN101805622A (zh) | 2010-08-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101974339B (zh) | 一种硅砖焦炉炭化室挖补方法 | |
CN102424753B (zh) | 大型焦炉炭化室底部砖修复方法 | |
CN101805622B (zh) | 焦炉炭化室底部砖热补工艺 | |
CN104498059A (zh) | 焦炉炭化室修补保护装置、其制造方法及炭化室修补方法 | |
CN102504837B (zh) | 大型焦炉机焦侧炉头同步切除揭顶维修方法 | |
CN109294601B (zh) | 一种焦炉碳化室底部快速修补方法 | |
CN1978590A (zh) | 一种焦炉炭化室底部耐火砖的热态修补方法 | |
CN104357067A (zh) | 焦炉维修方法 | |
CN103937521B (zh) | 外热立式翻转热解炉 | |
CN110330986B (zh) | 一种更换焦炉碳化室炉底砖的方法 | |
CN101701273A (zh) | 内燃式热风炉燃烧室大墙顶砖修复方法 | |
CN1283752C (zh) | 焦炉炭化室整墙热维修工艺 | |
CN104073269A (zh) | 焦炉炭底砖深度维修方法 | |
CN107201237A (zh) | 一种用于干熄炉中修后复产的烘炉升温方法 | |
CN107892926A (zh) | 一种节能型焦炉炉门衬砖 | |
CN204718409U (zh) | 一种可热态更换氧化还原口砖的阳极炉 | |
CN207738687U (zh) | 一种节能型焦炉炉门衬砖 | |
CN201553699U (zh) | 一种维修焦炉炉底的隔热装置 | |
CN110041946A (zh) | 焦炉炭化室炉底砖的热态维修方法 | |
CN214032340U (zh) | 一种焦炉炉底砖的更换工具 | |
CN103643053A (zh) | 一种回转式阳极炉透气砖热态更换方法 | |
CN103353231B (zh) | 固定式冶金炉炉拱的不停炉修补方法 | |
CN104357607A (zh) | 一种高炉烘炉方法 | |
CN113503738B (zh) | 一种纯碱生产中竖窑窑壁修补装置 | |
CN210367522U (zh) | 一种焦炉砖煤气道压浆密封管 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130102 Termination date: 20210415 |