CN101713278B - 钻孔灌注桩成孔一桩双机施工方法 - Google Patents

钻孔灌注桩成孔一桩双机施工方法 Download PDF

Info

Publication number
CN101713278B
CN101713278B CN200910234010A CN200910234010A CN101713278B CN 101713278 B CN101713278 B CN 101713278B CN 200910234010 A CN200910234010 A CN 200910234010A CN 200910234010 A CN200910234010 A CN 200910234010A CN 101713278 B CN101713278 B CN 101713278B
Authority
CN
China
Prior art keywords
drilling
hole
drilling rig
boring
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910234010A
Other languages
English (en)
Other versions
CN101713278A (zh
Inventor
于金涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou City Pile Co ltd
Jiangsu Yang Jian Group Co ltd
Original Assignee
Yangzhou City Pile Co ltd
Jiangsu Yang Jian Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou City Pile Co ltd, Jiangsu Yang Jian Group Co ltd filed Critical Yangzhou City Pile Co ltd
Priority to CN200910234010A priority Critical patent/CN101713278B/zh
Publication of CN101713278A publication Critical patent/CN101713278A/zh
Application granted granted Critical
Publication of CN101713278B publication Critical patent/CN101713278B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明公开了一种钻孔灌注桩成孔一桩双机施工方法,包括如下施工步骤:上部粘土层及全风化岩层采用旋挖钻机钻孔,在桩位安装旋挖钻机,旋挖钻机的钻斗边镶焊切削刀具,在伸缩钻杆旋转驱动下,旋转切削土层。旋挖钻机钻孔为干取土,也可以带浆作业。到达强、中风化岩层,将旋挖钻机换成回转钻机,回转钻机上安装特种合金牙轮钻,采用正循环或反循环钻进工艺,泥浆循环护壁,钻孔至设计孔深停钻后,采用空气压缩机清孔或泥浆置换清孔。本发明方法简单、经济适用,钻孔速度提高50%,缩短成孔时间,降低成孔成本,减少用电量,节约能源,减少泥浆的排放,降低环境污染。提高成孔质量及整个建筑工程桩基施工的质量。

Description

钻孔灌注桩成孔一桩双机施工方法
技术领域
发明涉及建筑工程桩基施工的一种钻孔灌注桩成孔施工方法,属于建筑施工技术领域。
背景技术
在现代的建筑工程中,经常需要对地基和基础进行处理,其中钻孔灌注桩以其适应性强、成本经济、施工简便等特点被广泛地应用于多种建筑工程领域。影响灌注桩施工质量的因素很多,如灌注桩成孔施工方法、护壁、灌注等,若成孔方法不当,就会影响施工进度和质量。现有的钻孔灌注桩施工始终采用一台钻机成孔,直至桩基施工完成。而在复杂地质条件下,特别在上面是普通土层、下面是坚硬的岩石的地质条件下,采用一种钻机难以顺利成孔,钻孔进度慢,成孔时间长,成本高,成孔质量差。
发明内容
本发明的目的就是针对现有的工程灌注桩成孔施工存在的上述不足,提供一种采用两种不同的钻机来成孔的钻孔灌注桩成孔施工方法。
本发明的目的是这样实现的,钻孔灌注桩成孔施工方法,其特征是包括如下施工步骤:
(1)选择旋挖钻机和回转钻机,上部粘土层及全风化岩层采用旋挖钻机钻孔,在桩位安装旋挖钻机,主钻盘中心要对准桩位,垂直度偏差<1%,对中偏差<1cm;
(2)旋挖钻机是在一个可闭合、开启的钻斗边对称镶焊两片硬质钢板制作的切削刀具以及两片普通钢板制作的挡土板,在伸缩钻杆旋转驱动下,旋转切削土层,同时使切削挖掘下来的土渣进入钻斗,钻斗装满后提出孔外卸土,如此循环成孔,旋挖钻机钻孔可以直接进行干取土,也可以带浆作业;
(3)根据土样、泥浆颜色,结合地质报告分析,判断钻头到达的土层、岩层状况,到达强、中风化岩层,及时将旋挖钻机调换成回转钻机;
(4)回转钻机上安装石油勘探工程中广泛使用的特种合金牙轮钻,采用正循环或反循环钻进工艺,泥浆循环护壁,使钻头在回转中切入岩土层,切削的土或岩层通过泥浆排渣,开始钻孔时,要轻压慢转,当钻头正常工作后,逐渐加大转速,调整压力至正常状态;
(5)进入强、中风化岩层时,适当加大泥浆浓度,确保磨碎的岩粒随浆排出孔外,钻进时发现排量减少或出水中含钻渣量较多时,应降低给进速度,在钻孔过程中,根据进尺速度,泥浆颜色、浆液中的岩粒,结合地质报告来判断进入岩层的深度,采用计算钻杆余尺和测绳直接测量的方法来确定入岩深度及终孔深度;
(6)钻孔至设计孔深停钻后,采用空气压缩机清孔或泥浆置换清孔,清孔后泥浆密度小于1.25g/cm3,孔内残渣厚度小于50mm。
本发明方法简单、经济适用,钻孔速度提高50%,缩短成孔时间,降低成孔成本,减少用电量,节约能源,减少泥浆的排放,降低环境污染。提高成孔质量及整个建筑工程桩基施工的质量。
具体实施方式
1施工准备
测量定位放线:根据总平面图和坐标、高程基准点按图纸测放好轴线、桩位及高程控制点。埋设护筒:钢护筒四周用粘土填实,顶端超过地表约0.2m,中心线允许偏差5cm。桩机就位:旋挖钻机就位,机架平直,机座垫稳。主钻盘中心要对准桩位,垂直度偏差<1%,对中偏差<1cm。制备泥浆:上部粘土干取土,可少量清水润滑,硬塑粘土层钻进用原土造浆,钻进岩层使用。
2旋挖钻机施工
上部粘土采用旋挖钻机钻孔,可带浆作业或直接干取土,硬塑粉质粘土及全风化岩层带浆作业。上部粘土软土层选小切削角、小刃角、齿宽稍大钻斗,硬土层选较大切削角、较窄的弯曲齿套钻斗。控制钻斗升降速度(表1)。
表1  钻斗升降速度
  桩径(mm)   装满渣土钻斗提升(m/s)   空钻斗升降(m/s)   桩径(mm)   装满渣土钻斗提升(m/s)   空钻斗升降(m/s)
  700   0.973   1.210   1300   0.628   0.830
  1200   0.748   0.830   1500   0.575   0.830
根据土样、泥浆颜色,结合地质报告判断进入深度,到达强、中风化岩层,及时将旋挖钻机调换成回转钻机。回转钻机就位,机架平直,机座垫稳,主钻盘中心要对准桩位,垂直度偏差<1%,对中偏差<20mm。旋挖钻机钻孔取土结束的半截孔,保持孔内泥浆液面高度,确保内外压力平衡,大面积施工前进行工艺试验。
3回转钻机施工
下部岩层由回转钻机钻孔施工,采用反循环工艺成孔。钻进参数根据地层、桩径、砂石泵的合理排量和钻机的经济钻速等加以选择和调整。采用特种合金牙轮钻,开始钻孔时轻压慢转,钻头正常工作后,逐渐加大转速,调整压力。进入强、中风化岩层时,适当加大泥浆浓度,确保磨碎的岩粒随浆排出孔外。钻进时发现排量减少或出水中钻渣量较多时,应降低给进速度。钻孔过程中,采用计算钻杆余尺和测绳直接测量的方法确定入岩深度及终孔深度。钻至设计孔深停钻后,空气压缩机清孔或泥浆置换清孔;清孔后泥浆密度不大于1.25g/cm3,孔内残渣厚度不大于50mm。
4.在钻好的桩孔中安放钢筋笼与混凝土灌注施工
分段制作的钢筋笼不宜小于6.0m。钢筋笼安放采用两根φ10钢筋对称焊接在钢筋笼两侧主筋上并固定于桩机底盘来控制。安放导管选用螺丝扣连接,每节长度一般2m,底管长度4~6m,导管底部至孔底50cm左右。混凝土灌注前对桩孔二次清孔,使孔底沉渣厚度≤50mm,孔底500mm以内泥浆密度<1.25g/cm3,含砂率≤8%,粘度≤28s等后安放隔水栓。二次清孔后浇注混凝土。

Claims (1)

1.一种钻孔灌注桩成孔一桩双机施工方法,其特征是包括如下步骤:
(1)选择旋挖钻机和回转钻机,上部粘土层及全风化岩层采用旋挖钻机钻孔,在桩位安装旋挖钻机,主钻盘中心要对准桩位,垂直度偏差<1%,对中偏差<1cm;
(2)旋挖钻机是在一个可闭合、开启的钻斗边对称镶焊两片硬质钢板制作的切削刀具以及两片普通钢板制作的挡土板,在伸缩钻杆旋转驱动下,旋转切削土层,同时使切削挖掘下来的土渣进入钻斗,钻斗装满后提出孔外卸土,如此循环成孔,旋挖钻机钻孔是直接进行干取土,或带浆作业;
(3)根据土样、泥浆颜色,结合地质报告分析,判断钻头到达的土层、岩层状况,到达强、中风化岩层,及时将旋挖钻机调换成回转钻机;
(4)回转钻机上安装石油勘探工程中广泛使用的特种合金牙轮钻,采用正循环或反循环钻进工艺,泥浆循环护壁,使钻头在回转中切入岩土层,切削的土或岩层通过泥浆排渣,开始钻孔时,要轻压慢转,当钻头正常工作后,逐渐加大转速,调整压力至正常状态;
(5)进入强、中风化岩层时,适当加大泥浆浓度,确保磨碎的岩粒随浆排出孔外,钻进时发现排量减少或出水中含钻渣量较多时,应降低给进速度,在钻孔过程中,根据进尺速度,泥浆颜色、浆液中的岩粒,结合地质报告来判断进入岩层的深度,采用计算钻杆余尺和测绳直接测量的方法来确定入岩深度及终孔深度;
(6)钻孔至设计孔深停钻后,采用空气压缩机清孔或泥浆置换清孔,清孔后泥浆密度小于1.25g/cm3,孔内残渣厚度小于50mm。
CN200910234010A 2009-11-19 2009-11-19 钻孔灌注桩成孔一桩双机施工方法 Expired - Fee Related CN101713278B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910234010A CN101713278B (zh) 2009-11-19 2009-11-19 钻孔灌注桩成孔一桩双机施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910234010A CN101713278B (zh) 2009-11-19 2009-11-19 钻孔灌注桩成孔一桩双机施工方法

Publications (2)

Publication Number Publication Date
CN101713278A CN101713278A (zh) 2010-05-26
CN101713278B true CN101713278B (zh) 2012-09-05

Family

ID=42417231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910234010A Expired - Fee Related CN101713278B (zh) 2009-11-19 2009-11-19 钻孔灌注桩成孔一桩双机施工方法

Country Status (1)

Country Link
CN (1) CN101713278B (zh)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102359128A (zh) * 2011-11-01 2012-02-22 中国建筑第八工程局有限公司 桩基入岩判定方法
CN102644274A (zh) * 2012-04-17 2012-08-22 中铁隧道集团三处有限公司 一种围护桩穿越既有结构成桩施工工法
CN102913132B (zh) * 2012-09-29 2016-06-01 中铁十九局集团有限公司 临近既有线岩溶区钻孔桩斜岩处理方法
CN104074462A (zh) * 2014-06-13 2014-10-01 上海市机械施工集团有限公司 一种钻削成孔内螺杆浆泥提升系统
CN106013092A (zh) * 2016-06-08 2016-10-12 深圳市宏业基基础工程有限公司 一种钻孔灌注桩施工方法
CN106675539A (zh) * 2016-12-24 2017-05-17 中铁四局集团有限公司 一种高效速溶泥浆粉及其制备方法
CN109339700A (zh) * 2018-11-08 2019-02-15 上海市基础工程集团有限公司 大直径桩中的强风化下带旋挖成孔施工方法
CN110886577B (zh) * 2019-11-29 2021-06-04 深圳宏业基岩土科技股份有限公司 深厚填石区旋挖硬咬合桩垂直度控制的施工方法
CN111677439A (zh) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 反循环回旋钻机钻进成孔方法
CN111851477A (zh) * 2020-07-23 2020-10-30 山东省机械施工有限公司 旋挖螺纹桩施工方法及其装置
CN112431587B (zh) * 2020-12-22 2022-12-23 山东省交通规划设计院集团有限公司 一种勘探孔深实时探测装置及方法
CN113219550B (zh) * 2021-05-25 2024-05-14 甘肃酒钢集团宏兴钢铁股份有限公司 一种露天矿逆向钻孔地质编录和矿体圈定方法
CN113250262B (zh) * 2021-06-25 2021-10-08 徐州徐工基础工程机械有限公司 双轮铣削搅拌机及其铣削装置速度控制方法
CN114808942A (zh) * 2022-01-27 2022-07-29 海洋石油工程股份有限公司 一种lng储罐一体化成桩冬季施工方法
CN117248817B (zh) * 2023-11-17 2024-03-26 亚核智造(江苏)科技有限公司 一种正循环旋挖钻机及其施工方法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1003072C1 (nl) * 1996-05-09 1997-11-18 Visser & Smit Bouw Bv Werkwijze en inrichting voor het in de grond aanbrengen van een funderingselement.
DE20105076U1 (de) * 2001-03-23 2002-05-08 Mathieu, Hans, 66132 Saarbrücken Drehbohreinrichtung
CN1462827A (zh) * 2003-06-21 2003-12-24 阎瑞明 一种成桩的施工方法及工具
CN1831250A (zh) * 2005-03-07 2006-09-13 徐州工程机械科技股份有限公司徐工研究院 旋挖钻孔机干取土成孔法施工工艺
KR20080041170A (ko) * 2008-04-21 2008-05-09 한동덕 중공식 암반 굴착장치
CN101328712A (zh) * 2008-07-29 2008-12-24 上海市第二建筑有限公司 一种适用于软土及带障碍物土层中的咬合桩施工方法
CN201258698Y (zh) * 2008-09-27 2009-06-17 中冶京唐建设有限公司 回转钻孔灌注桩用钻杆
CN101487252A (zh) * 2009-02-13 2009-07-22 中建八局第一建设有限公司 一种钻孔灌注桩施工工艺
CN101519875A (zh) * 2009-04-08 2009-09-02 昆明捷程桩工有限责任公司 复杂地层的组合式成桩方法
CN101566043A (zh) * 2009-05-19 2009-10-28 李征 一种现浇筒桩旋挖钻机及其成桩方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1003072C1 (nl) * 1996-05-09 1997-11-18 Visser & Smit Bouw Bv Werkwijze en inrichting voor het in de grond aanbrengen van een funderingselement.
DE20105076U1 (de) * 2001-03-23 2002-05-08 Mathieu, Hans, 66132 Saarbrücken Drehbohreinrichtung
CN1462827A (zh) * 2003-06-21 2003-12-24 阎瑞明 一种成桩的施工方法及工具
CN1831250A (zh) * 2005-03-07 2006-09-13 徐州工程机械科技股份有限公司徐工研究院 旋挖钻孔机干取土成孔法施工工艺
KR20080041170A (ko) * 2008-04-21 2008-05-09 한동덕 중공식 암반 굴착장치
CN101328712A (zh) * 2008-07-29 2008-12-24 上海市第二建筑有限公司 一种适用于软土及带障碍物土层中的咬合桩施工方法
CN201258698Y (zh) * 2008-09-27 2009-06-17 中冶京唐建设有限公司 回转钻孔灌注桩用钻杆
CN101487252A (zh) * 2009-02-13 2009-07-22 中建八局第一建设有限公司 一种钻孔灌注桩施工工艺
CN101519875A (zh) * 2009-04-08 2009-09-02 昆明捷程桩工有限责任公司 复杂地层的组合式成桩方法
CN101566043A (zh) * 2009-05-19 2009-10-28 李征 一种现浇筒桩旋挖钻机及其成桩方法

Also Published As

Publication number Publication date
CN101713278A (zh) 2010-05-26

Similar Documents

Publication Publication Date Title
CN101713278B (zh) 钻孔灌注桩成孔一桩双机施工方法
CN100572683C (zh) 大直径超深入岩钻孔扩底灌注桩施工方法
CN104153352B (zh) 一种岩溶地质旋挖灌注桩成孔工艺
CN101962949B (zh) 长螺旋二重管高压搅喷桩施工方法及其装置
CN104563098B (zh) 一种超大直径全钢护筒干作业成孔灌注桩施工方法
CN109594564A (zh) 一种地铁深基坑明挖防坍塌施工方法
CN101660309B (zh) 多钻头高压喷射搅拌基础防渗加固设备的施工方法
CN104120716A (zh) 一种泥浆护壁钻孔灌注桩施工方法
CN103088814A (zh) 一种旋挖钻机配合冲击钻机成孔施工方法
CN103266599B (zh) 土砂夹层地基旋挖钻干挖成孔桩的施工方法
AU2021106928A4 (en) Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports
CN104895055A (zh) 一种建筑灌注桩桩基施工方法
CN102296630A (zh) 长螺旋高压搅喷水泥土连续墙施工方法
CN103015402A (zh) 一种用水泥土加固法抑制水平冻结冻胀融沉的施工方法
CN108589707A (zh) 一种全套管长螺旋钻与旋挖钻组合式施工工法
CN101255689A (zh) 长螺旋旋喷搅拌水泥土帷幕桩及其施工方法
CN109488202A (zh) 一种含漂卵石层的砂砾岩层桩基成孔施工工法
CN103266603A (zh) 一种预应力混凝土异形桩预钻成孔扩底注浆施工工法
CN107246007B (zh) 一种cfg桩的施工方法
CN108867631A (zh) 一种旋挖钻孔灌注桩的施工方法
CN107191188A (zh) 基岩段不良含水层定位靶向注浆立井井壁结构、施工装置及方法
CN106677166A (zh) 卵砾石――风化岩地层钻孔灌注桩双机联合成桩流水施工方法
CN105926592A (zh) 一种钻孔桩施工方法
CN201534974U (zh) 多钻头高压喷射搅拌基础防渗加固设备
CN112252310A (zh) 采用高压旋喷桩机进行深基坑止水帷幕施工的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120905