CN101566064A - 一种大断面隧道施工方法 - Google Patents
一种大断面隧道施工方法 Download PDFInfo
- Publication number
- CN101566064A CN101566064A CNA2009100523323A CN200910052332A CN101566064A CN 101566064 A CN101566064 A CN 101566064A CN A2009100523323 A CNA2009100523323 A CN A2009100523323A CN 200910052332 A CN200910052332 A CN 200910052332A CN 101566064 A CN101566064 A CN 101566064A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- base
- base tunnel
- rock
- construction
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 44
- 239000011435 rock Substances 0.000 claims abstract description 41
- 239000002689 soil Substances 0.000 claims abstract description 29
- 239000002699 waste materials Substances 0.000 claims abstract description 11
- 238000004880 explosion Methods 0.000 claims description 20
- 280000871617 Vault companies 0.000 claims description 11
- 238000009412 basement excavation Methods 0.000 claims description 11
- 230000000694 effects Effects 0.000 abstract description 4
- 230000003247 decreasing Effects 0.000 abstract 1
- 230000031877 prophase Effects 0.000 abstract 1
- 239000002893 slag Substances 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 2
- 210000000481 Breast Anatomy 0.000 description 1
- 230000036536 Cave Effects 0.000 description 1
- 238000005422 blasting Methods 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
Abstract
Description
一种大断面隧道施工方法技术领域本发明涉及一种隧道的开挖施工方法,尤其涉及对于土质比较硬,隧 道的开挖断面的高度比较高, 一般的台车无法进行二衬施工的一种大断面 卩蓮道施工方法。背景技术开挖隧道时一般根据土质的不同会采用不同的开挖方式,对于比较软 的土质适合用盾构对隧道进行开挖,对于土质很硬无法用盾构开挖隧道 时,需要用爆破的方式对隧道进行开挖。对于用爆破的方式开挖隧道时,一般采用这样的方式开挖隧道,参考图2a〜2j为传统的用爆破的方式开 挖隧道的步序图,首先开挖左上侧、右上侧的侧导坑201、 202,在开挖 完该导坑201、 202后安装支撑(参考图2a、 2b);接着开挖左中部、右 中部的侧导坑203、 204,在开挖完该导坑203、 204后安装支撑(参考图 2c、 2d);然后开挖左下侧、右下侧的侧导坑205、 206,在开挖完该导 坑205、 206后安装支撑(参考图2e、 2f);之后开挖左上侧导坑201和 右上侧侧导坑202之间的核心土 207 (参考图2g);在将左上侧导坑201 和右上侧导坑202之间的核心土 207开挖之后,将台车推入隧道中,利用 台车对开挖好的隧道的拱顶以及侧墙支撑,并对侧墙以及拱顶208浇筑(参考图2h);在对拱顶以及侧墙的浇筑完成后,将隧道中剩余的下半 部核心土 209开挖(参考图2i);最后完成仰拱210的浇筑(参考图2j )。 以上所述为传统的对于土质比较硬的隧道的一种开挖方法,而且该方法只 适用于施工断面比一支小的隧道,对于施工断面大的隧道,该施工方法并不 适用,因为对于施工断面大的隧道,现有的台车的高度不够,没有办法在 浇筑拱顶以及侧墙的时候对隧道起支撑的作用,就没有办法完成大断面隧 道的施工,因此对于大断面的隧道有必要4是出 一种新的施工方法。发明内容本发明要解决的技术问题在于提供一种大断面隧道施工方法,通过先开挖下部导坑方法,将隧道的底部垫高,从而可以使用现有的台车进行二 才于&工。为解决以上技术问题本发明提供一种大断面隧道施工方法,其特征在于包括施工步骤:在隧道中部预留一水平岩梁,将侧导坑分成4个小隧道分别为左上侧 导坑、右上侧导坑、左下侧导坑以及右下侧导坑进行开挖,由水平岩梁与 隧道中部的核心土形成"十字"形支撑;在预留好水平岩梁后,利用爆破的方式开挖左上侧导坑、右上侧导坑、 左下侧导坑、右下侧导坑,每开挖好一个侧导坑后,对侧导坑进行初支;在开挖好左下侧导坑后,对该左下侧导坑浇筑导坑仰拱,浇筑导坑边 墙;在开挖好右下侧导坑后,对该右下侧导坑浇筑导坑仰拱,浇筑导坑边 墙;利用爆破的方式解除左侧岩梁,并利用爆破后的弃渣填实左侧导坑, 从而形成一左侧下台阶;利用爆破的方式解除右侧岩梁,并利用爆破后的 弃渣填实右侧导坑,从而形成一右侧下台阶;解除左上侧导坑和右上侧导坑之间的核心土 ;在解除了左上侧导坑和右上侧导坑之间的核心土之后,利用左侧下台 阶和右侧下台阶,将台车推入隧道中对隧道的换顶及边墙进行二衬浇筑;在完成了隧道拱顶及边墙的二衬浇筑后,解除剩余隧道中的土,之后 将废渣运出隧道,对隧道的中部仰拱进行浇筑,完成隧道的施工。本发明的进 一 步改进在于:所述的解除隧道中剩余的土的步骤还包 括,按分层解除的方式解除隧道中的剩余土。本发明的进一步改进在于:所述解除左侧岩梁和右侧岩梁的步骤还包 括,在解除左侧岩梁和右侧岩梁时,首先将左下侧导坑和右下侧导坑的上 部支撑解除。通过以上所述的技术方案,本发明提供的大断面隧道施工方法可以充 分利用大断面隧道特性,利用预留岩梁作用,将隧道侧导坑分成四个小隧 道,该四个小隧道可同时开挖,因此可以增加可开挖工作面,加快隧道前 期开挖速度;并且利用预留岩梁的作用,可简化内侧临时支护强度,降低 施工难度,减少工程成本;最重要的是,在挖完下侧导坑后,解除预留岩 梁,利用解除岩梁的弃渣填实下侧导坑,这样就可以将隧道垫高,在将隧 道垫高后,可以利用现有的台车来支撑隧道并浇筑侧墙拱顶,从而解决大4断面模板台车问题。 附图说明图la~ll为本发明一较佳实施例的一种大断面隧道施工方法的步序 图;以及图2a ~ 2j为现有的隧道施工方法的步序图。 具体实施方式对于土质硬的隧道进行隧道开挖,不适合用盾构的方法进行开挖,一 般釆用爆破的方式进行开挖,在爆破开挖时,将隧道分成若干个小隧道, 然后分别对各个小隧道进行开挖,并且在开挖该若干个小隧道时其施工步 骤很重要,否则将会造成隧道坍塌,影响隧道开挖并且会有安全隐患。传 统的隧道施工方法只适用于施工断面小,即隧道高度比较低的隧道的施 工,对于施工断面大即隧道高度比较高的隧道,由于无法利用现有的台车 进4亍施工,传统的施工方法不再适用。参考图la~ll为本发明一较佳实施例的一种大断面隧道施工方法的 步序图。在开挖隧道时,首先在隧道中部预留一水平岩梁105,将侧导坑 分成4个小隧道分别为左上侧导坑101、右上侧导坑102、左下侧导坑103 以及右下侧导坑104进行开挖,由水平岩梁105与隧道中部的核心土形成 "十字"形支撑;在预留好水平岩梁后,利用爆破的方式开挖左上侧导坑101、右上侧 导坑102、左下侧导坑103、右下侧导坑104,每开挖好一个侧导坑后, 对导坑进行初支(参考图la〜ld);其中在该施工步骤中,因为有水平 岩梁105与隧道中部的核心土形成"十字"形支撑的作用,左上侧导坑 101、右上侧导坑102、左下侧导坑103、右下侧导坑104,可以同时进4亍 开挖,也可以根据施工的需要按一定的顺序开挖,其施工顺序不影响隧道 的开挖,在该施工步骤中,由于四个侧导坑可以同时进行开挖,因此可以 加快施工进度,缩^豆施工工期;在开挖好左下侧导坑103后,对该左下侧导坑103浇筑导坑仰拱106, 在浇筑完导坑仰拱106后浇筑导坑边墙1Q8;在开挖好右下侧导坑1G4后, 对该右下侧导坑104浇筑导坑仰拱107,之后浇筑导坑边墙109 (参考图 le ~lf );在完成了四个侧导坑的施工,并对左下侧导坑103的仰拱106以及边 墙108的浇筑完成后,利用爆破的方式解除岩梁105的左侧岩梁1051, 并利用爆破后的弃渣填实左侧导坑103,从而形成一左侧下台阶,同时对 左侧岩梁1051的右侧墙做初支,并且在解除岩梁时,首先要将左下侧导 坑103的上部的支撑解除(参考图lg);在完成了四个侧导坑的施工,并对右下侧导坑104的仰拱107以及边 墙109的浇筑完成后利用爆破的方式解除水平岩梁105的右侧岩梁1052, 并利用爆破后的弃渣填实右侧导坑104,从而形成一右侧下台阶,同时对 右侧岩梁1052的左侧墙做初支,并且在解除岩梁时,首先要将右下侧导 坑104上部的支撑解除(参考图lh);在完成了下台阶的施工后,爆破解除左上侧导坑101和右上侧导坑 102之间的核心土 110,此时在隧道中形成一空间可以供台车进入(参考 图li);在解除了左上侧导坑101和右上侧导坑102之间的核心土 110之后, 利用左侧下台阶和右侧下台阶,将台车推入隧道中对隧道的拱顶及边墙进 行二衬111浇筑(lj );在完成了隧道拱顶及边墙的二衬111浇筑后,解除隧道中剩余的.土 112(参考图lk),其中在解除隧道中剩余的土 112时,可以采用分层解 除该剩余的土的方法,首先解除中部的土,接着解除下部的土;最后将废渣运出隧道,对隧道的中部仰拱113进行浇筑,完成隧道的 施工(参考图11 )。该大断面施工方法,通过首先对隧道下侧的左右两个导坑进行开挖, 之后再对中部岩梁进行解除,从而在隧道的底部形成了左右两个下台阶, 以此可以将隧道垫高,使只适用于 一般断面的台车可以适用在大断面隧道 的施工中,解决大断面隧道施工中台车的问题;另外,对于该施工方法, 首先预留的水平岩梁的支撑作用,可以同时对四个侧导坑进行开挖,这样 可以缩短工期,-提高施工的效率。 •6
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100523323A CN101566064B (zh) | 2009-06-01 | 2009-06-01 | 一种大断面隧道施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100523323A CN101566064B (zh) | 2009-06-01 | 2009-06-01 | 一种大断面隧道施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101566064A true CN101566064A (zh) | 2009-10-28 |
CN101566064B CN101566064B (zh) | 2011-06-08 |
Family
ID=41282405
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100523323A CN101566064B (zh) | 2009-06-01 | 2009-06-01 | 一种大断面隧道施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101566064B (zh) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182466A (zh) * | 2011-04-08 | 2011-09-14 | 中铁上海设计院集团有限公司 | 隧道双侧壁导坑结合拱部跳挖开挖方法 |
CN102425422A (zh) * | 2011-11-17 | 2012-04-25 | 大同煤矿集团有限责任公司 | 主巷不间断运输条件下全煤特大断面交岔硐室施工方法 |
CN102704939A (zh) * | 2012-06-26 | 2012-10-03 | 中国建筑第五工程局有限公司 | 特大断面隧道组合型钢临时支撑开挖法 |
CN102704958A (zh) * | 2012-06-14 | 2012-10-03 | 中国水电顾问集团华东勘测设计研究院 | 一种大断面地下洞室开挖支护的施工方法 |
CN103195455A (zh) * | 2013-03-11 | 2013-07-10 | 中铁二院工程集团有限责任公司 | 软弱地质环境大断面隧道施工支护体系及施工方法 |
CN104564085A (zh) * | 2014-12-23 | 2015-04-29 | 中铁十一局集团第五工程有限公司 | 城市超浅埋条件下超大断面隧道开挖综合施工方法 |
CN105888696A (zh) * | 2016-06-30 | 2016-08-24 | 中铁四局集团第四工程有限公司 | 大截面隧道的施工方法 |
CN106499417A (zh) * | 2016-10-25 | 2017-03-15 | 中铁隧道集团二处有限公司 | 特大断面浅埋地铁车站预留t字岩梁岩柱施工工法 |
CN106643361A (zh) * | 2016-12-22 | 2017-05-10 | 中建八局第二建设有限公司 | 超大暗挖隧道双侧壁上下导坑开挖施工方法 |
CN107130967A (zh) * | 2017-06-08 | 2017-09-05 | 重庆工程职业技术学院 | 特大断面深埋隧道及附属结构的施工方法 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6520718B1 (en) * | 1998-11-27 | 2003-02-18 | Shigeki Nagatomo, Et Al. | Sardine-bone construction method for large-section tunnel |
CN100538011C (zh) * | 2007-12-20 | 2009-09-09 | 中铁十二局集团有限公司 | 铁路大断面隧道接触网预埋滑槽施工方法 |
CN101182773A (zh) * | 2007-12-20 | 2008-05-21 | 中铁十二局集团有限公司 | 铁路大断面隧道椭圆台面帽檐斜切式洞门施工方法 |
-
2009
- 2009-06-01 CN CN2009100523323A patent/CN101566064B/zh active IP Right Grant
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182466A (zh) * | 2011-04-08 | 2011-09-14 | 中铁上海设计院集团有限公司 | 隧道双侧壁导坑结合拱部跳挖开挖方法 |
CN102425422A (zh) * | 2011-11-17 | 2012-04-25 | 大同煤矿集团有限责任公司 | 主巷不间断运输条件下全煤特大断面交岔硐室施工方法 |
CN102704958B (zh) * | 2012-06-14 | 2015-03-18 | 中国水电顾问集团华东勘测设计研究院 | 一种大断面地下洞室开挖支护的施工方法 |
CN102704958A (zh) * | 2012-06-14 | 2012-10-03 | 中国水电顾问集团华东勘测设计研究院 | 一种大断面地下洞室开挖支护的施工方法 |
CN102704939A (zh) * | 2012-06-26 | 2012-10-03 | 中国建筑第五工程局有限公司 | 特大断面隧道组合型钢临时支撑开挖法 |
CN102704939B (zh) * | 2012-06-26 | 2014-10-01 | 中国建筑第五工程局有限公司 | 特大断面隧道组合型钢临时支撑开挖法 |
CN103195455A (zh) * | 2013-03-11 | 2013-07-10 | 中铁二院工程集团有限责任公司 | 软弱地质环境大断面隧道施工支护体系及施工方法 |
CN103195455B (zh) * | 2013-03-11 | 2016-05-11 | 中铁二院工程集团有限责任公司 | 软弱地质环境大断面隧道施工支护体系及施工方法 |
CN104564085A (zh) * | 2014-12-23 | 2015-04-29 | 中铁十一局集团第五工程有限公司 | 城市超浅埋条件下超大断面隧道开挖综合施工方法 |
CN105888696A (zh) * | 2016-06-30 | 2016-08-24 | 中铁四局集团第四工程有限公司 | 大截面隧道的施工方法 |
CN106499417A (zh) * | 2016-10-25 | 2017-03-15 | 中铁隧道集团二处有限公司 | 特大断面浅埋地铁车站预留t字岩梁岩柱施工工法 |
CN106499417B (zh) * | 2016-10-25 | 2019-01-08 | 中铁隧道集团二处有限公司 | 特大断面浅埋地铁车站预留t字岩梁岩柱施工工法 |
CN106643361A (zh) * | 2016-12-22 | 2017-05-10 | 中建八局第二建设有限公司 | 超大暗挖隧道双侧壁上下导坑开挖施工方法 |
CN107130967A (zh) * | 2017-06-08 | 2017-09-05 | 重庆工程职业技术学院 | 特大断面深埋隧道及附属结构的施工方法 |
CN107130967B (zh) * | 2017-06-08 | 2019-01-01 | 重庆工程职业技术学院 | 特大断面深埋隧道及附属结构的施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN101566064B (zh) | 2011-06-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102155233B (zh) | 一种隧道开挖施工方法 | |
JP4184400B2 (ja) | 地下構造物の構築方法 | |
CN100577986C (zh) | 三软地质条件下采空区留巷围岩支护方法 | |
CN102226403B (zh) | 地铁大跨度车站主体拱盖法施工方法及车站主体结构 | |
CN101666232B (zh) | 超大断面隧道六部开挖的施工方法 | |
CN101408106B (zh) | 小管棚超前注浆法 | |
CN101440708B (zh) | Pba浅埋暗挖近距离大断面三洞分离岛式结构施工方法 | |
CN106088650B (zh) | 一种适用于砖混结构建筑物地下增层的方法及建筑物 | |
CN105298507B (zh) | 一种上部明挖下部掘进机施工的地下管廊施工方法 | |
CN103161480B (zh) | 主动支撑巷旁充填沿空留巷的方法 | |
CN104653197B (zh) | 超大变断面隧道施工方法 | |
KR101285372B1 (ko) | 지하철 정거장 및 지하철 정거장의 시공방법 | |
CN102704939B (zh) | 特大断面隧道组合型钢临时支撑开挖法 | |
CN102733827B (zh) | 隧道换拱施工方法及用于隧道换拱施工中的施工结构 | |
CN102182472B (zh) | 隧道塌方空腔的回填修复方法 | |
CN100557148C (zh) | 一种逆作法工程采用车道法进行开挖施工的方法 | |
CN103628894B (zh) | 一种基于变角伞状超前注浆的富水断层破碎带垮塌巷道巷修方法 | |
CN103306680B (zh) | 既有单线隧道扩建为多线隧道的施工方法 | |
CN101769154A (zh) | 一种隧道施工的开挖支护方法 | |
CN102425454B (zh) | 一种砌筑填充组合式沿空留巷墙体的构筑方法 | |
CN100554646C (zh) | 盾构法与浅埋暗挖法结合建造地铁车站的施工方法 | |
CN105041349B (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的暗挖施工方法 | |
JP2007217911A (ja) | 地中空洞の施工方法およびトンネル工法 | |
CN105804748B (zh) | 一种露天运输系统下分区开采挂帮矿的方法 | |
CN106761778B (zh) | 一种适用于上软下硬地层的地铁车站暗挖施工工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |