CN102182466B - 隧道双侧壁导坑结合拱部跳挖开挖方法 - Google Patents
隧道双侧壁导坑结合拱部跳挖开挖方法 Download PDFInfo
- Publication number
- CN102182466B CN102182466B CN 201110087799 CN201110087799A CN102182466B CN 102182466 B CN102182466 B CN 102182466B CN 201110087799 CN201110087799 CN 201110087799 CN 201110087799 A CN201110087799 A CN 201110087799A CN 102182466 B CN102182466 B CN 102182466B
- Authority
- CN
- China
- Prior art keywords
- tunnel
- arch
- excavation
- pilot
- supporting
- Prior art date
Links
- 238000009412 basement excavation Methods 0.000 claims abstract description 72
- 239000002689 soil Substances 0.000 claims abstract description 20
- 238000010276 construction Methods 0.000 claims abstract description 12
- 230000011218 segmentation Effects 0.000 claims description 6
- 210000000481 Breast Anatomy 0.000 claims description 4
- 239000011435 rock Substances 0.000 abstract description 10
- 230000000694 effects Effects 0.000 abstract description 4
- 238000010586 diagrams Methods 0.000 description 18
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000000034 methods Methods 0.000 description 2
- 238000004062 sedimentation Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 239000012141 concentrates Substances 0.000 description 1
- 230000002596 correlated Effects 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 230000000087 stabilizing Effects 0.000 description 1
- 238000003786 synthesis reactions Methods 0.000 description 1
Abstract
Description
隧道双侧壁导坑结合拱部跳挖开挖方法
技术领域
[0001] 本发明涉及隧道施工方法,具体涉及用于大跨度隧道的双侧壁导洞结合拱部跳挖法。
背景技术
[0002] 开挖是隧道施工的第一道エ序,在隧道的开挖过程中,围岩的稳定与否,除了与隧道周围的地质条件和注浆、管棚等预支护措施相关以外,还受到隧道断面的开挖方法的直接影响,尤其对于大跨度、大断面隧道,其开挖步骤较多,开挖步骤导致应カ变化频繁,从而引起隧道周围大范围塑性区,更易产生土体极限破坏。
[0003] 隧道工程施工质量的重要衡量标准是地表沉降以及围岩的稳定,大量的工程实践经验表明,针对隧道断面的大小及形状、围岩的工程地质条件、支护措施工期要求、エ区长度、机械配备能力、经济等相关因素综合分析,采用恰当的隧道开挖方法,能够有效的改善开挖对于围岩稳定的影响,减小隧道开挖引起的地表沉降。目前采用的开挖方法主要有全断面法、台阶法以及分部开挖法,对于软弱地层中的大断面隧道,由于全断面法一次性开挖断面面积过大以及台阶法支护结构的闭合时间长造成这两种开挖方法很难控制围岩的稳定以及地表的沉降。因此,目前在软弱地层中进行大断面隧道开挖多采用分部开挖方法,主要包括环形开挖预留核心土法、双侧壁导坑法、中隔壁法等,这些施工方法虽然在稳定围岩、减小沉降方面有了较大进步,但在其施工时为按部就班地由洞ロ往后进行隧道土体的开挖施工,使得洞ロ的应カ集中现象明显、受カ复杂,未考虑隧道土体开挖的空间效应,不利于围岩稳定。
发明内容
[0004] 本发明的目的是针对大断面隧道开挖方法的不足之处,提供ー种隧道双侧壁导坑结合拱部跳挖开挖方法,该方法的总原则是先墙后拱法,即双侧壁导洞及初支完成后,先施作边墙二次衬砌,然后再分块开挖拱部土体,施作初支结构,浇筑拱部ニ衬混凝土。开挖隧道拱部时首先开挖拱部中导洞,离开洞ロ从中导洞底部向两边开挖,形成拱部初支结构后立即施作拱部ニ衬混凝土,由里向外逐步完成大跨度隧道拱部结构的开挖。
[0005] 本发明目的实现由以下技术方案完成:
[0006] ー种隧道双侧壁导坑结合拱部跳挖开挖方法,用于大跨度、大断面隧道,其特征在于所述方法首先开挖位于隧道两侧的侧壁导洞部分,之后开挖隧道拱部土体,其步骤是:首先开挖隧道拱部中导洞;之后离开拱部洞ロ从所述中导洞开挖深度的底部位置向隧道两侧边开挖位于隧道拱部两旁侧壁导洞;最后再由里向外逐步完成隧道拱部的开挖。
[0007] 所述侧壁导洞分块、逐一完成开挖,并施作临时支护结构,两侧壁导坑开挖时各侧导洞分块之间沿纵向必须具有一定的错距,即错距施工。
[0008] 之后进行隧道拱部中导洞开挖,开挖后左右两侧架立临时支撑、底部铺设临时横撑,然后从拱部中导洞底部向两边开挖拱部侧导洞,施作其拱部以及底部中导洞的支护结构和两边侧壁导洞的ニ衬混凝土衬砌,待拱部支护结构与边墙的支护结构闭合后,分段拆除两侧壁导洞临时支护结构。
[0009] 然后从里向外逐步完成隧道拱部土体的开挖,并拆除中导洞侧向临时支撑与临时横撑。
[0010] 本发明的优点在于充分考虑大跨度隧道拱部开挖的空间效应,減少开挖断面的应力集中,从而利于围岩稳定,并减少开挖引起的围岩扰动与变形。该方法可以起到控制大断面隧道开挖引起的较大的地面沉降,同时采用拱部中导洞先开挖然后从中导洞内部向两侧开挖拱部侧壁导坑的方法可以增加开挖面,提高开挖效率节约エ期。
附图说明
[0011] 图1为侧洞上导坑开挖示意图;
[0012] 图2为侧洞中导坑开挖示意图;
[0013] 图3为侧洞下导坑开挖示意图;
[0014] 图4为拱部中导洞开挖示意图;
[0015] 图5为模筑侧墙ニ衬混凝土示意图;
[0016] 图6为开挖拱部中导坑底部侧导坑示意图;
[0017] 图7为开挖洞ロ部位拱部侧导坑示意图;
[0018] 图8为开挖上部核心土示意图;
[0019] 图9为开挖下部核心土示意图;
[0020] 图10为隧道开挖完成示意图;
[0021] 图11为本发明设计拱部跳挖三维示意图;
[0022] 图12为本发明设计拱部跳挖平面示意图。
具体实施方式
[0023] 以下结合附图通过实施例对本发明设计特征及其它相关特征作进ー步详细说明,以便于同行业技术人员的理解:
[0024] 附图1-12中标号1-20代表的是左侧上导坑1、右侧上导坑2、左侧中导坑3、右侧中导坑4、左侧下导坑5、右侧下导坑6、拱部中导坑7、拱部侧导坑8、上部核心土 9、下部核心土 10、侧导坑初期支护11、测导坑临时支护12、横联13、中导坑立柱14、拱部初期支护15、仰拱初期支护16、侧墙二次衬砌17、仰拱二次衬砌18、中导坑横撑19、拱部二次衬砌20。
[0025] 如图1-10所示,本实施例针对的大跨度隧道是指高跨比小于0.8且隧道跨度大于IOm0
[0026] 施工エ序如下依次为:
[0027] 图1所示为侧洞上导坑开挖示意图。开挖左侧上导坑I和右侧上导坑2,施作侧导坑初期支护11、侧导坑临时支护12 (即中隔墙)以及横联13。
[0028] 图2所示为侧洞中导坑开挖示意图。开挖左侧中导坑3和右侧中导坑4,施作侧导坑初期支护11、侧导坑临时支护12以及横联13。
[0029] 图3所示为侧洞下导坑开挖示意图。开挖左侧下导坑5和右侧下导坑6,施作侧导坑初期支护11、侧导坑临时支护12。
[0030] 图4所示为拱部中导洞开挖示意图。开挖拱部中导坑7,左右侧架立立柱14,底部铺设临时横撑19,拱部施工初期支护15。
[0031] 图5所示为模筑侧墙ニ衬混凝土示意图。施工左侧洞与右侧洞边墙ニ衬混凝土17。
[0032] 图6所示为开挖拱部中导坑底部的侧导坑示意图。离开洞ロ从拱部中导坑底部向两边开挖拱部侧导坑8,施作拱部两侧初支结构15以及中导洞底部和两边侧导洞的ニ衬混凝土衬砌(即拱部二次衬砌20),待拱部支护结构与边墙支护结构闭合后,分段拆除左侧导洞1、2、3与右侧导洞4、5、6的横联13。
[0033] 图7所示为开挖洞ロ部位拱部侧导坑8示意图。从图6施工完成的隧道拱部结构向洞ロ方向继续开挖剩余的拱部侧导坑8,分段拆除拱部中导坑7的临时支护结构两侧エ字钢立柱14以及底部的钢管横撑19,逐步完成大跨度隧道的拱部结构开挖。
[0034] 图8所示为开挖上部核心土示意图。开挖上部核心土 9,分段拆除左侧导洞1、2、3与右侧导洞4、5、6的部分临时支护中隔墙12。
[0035] 图9所示为开挖下部核心土示意图。开挖下部核心土 10,分段拆除左侧导洞1、2、
3与右侧导洞4、5、6的部分临时支护中隔墙12,施工仰拱初期支护16,隧道初期支护结构闭合成环。
[0036] 图10所示为隧道开挖完成示意图。施工仰拱二次衬砌18,隧道二次衬砌结构闭合成环,本循环大跨度隧道开挖完成。
[0037] 图11所示为本发明设计拱部跳挖三维示意图,即隧道一次开挖循环的纵断面示意图。
[0038] 图12所示为本发明设计拱部跳挖平面示意图,即隧道一次开挖循环的横断面示意图。
[0039] 为了减小大跨隧道开挖引起的地表沉降量及地表沉降槽的范围,本发明设计在实施中须遵循以下原则:(I)两侧导洞不能齐头并进,必须在纵向前后保持一定的错距,単一侧导洞分三步开挖,每步至少保持4m的错距,以利于掌子面稳定;(2)拱部分三块开挖,先开挖拱部中导坑,然后从里向外跳挖两侧土体;(3)施作边墙及拱部ニ衬之后再开挖核心土,最后施作仰拱。
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110087799 CN102182466B (zh) | 2011-04-08 | 2011-04-08 | 隧道双侧壁导坑结合拱部跳挖开挖方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110087799 CN102182466B (zh) | 2011-04-08 | 2011-04-08 | 隧道双侧壁导坑结合拱部跳挖开挖方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102182466A CN102182466A (zh) | 2011-09-14 |
CN102182466B true CN102182466B (zh) | 2013-05-01 |
Family
ID=44568744
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110087799 CN102182466B (zh) | 2011-04-08 | 2011-04-08 | 隧道双侧壁导坑结合拱部跳挖开挖方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102182466B (zh) |
Families Citing this family (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102926757B (zh) * | 2012-09-07 | 2015-09-09 | 中铁五局(集团)有限公司 | 山岭软弱大跨隧道两台阶四步开挖支护的施工方法 |
CN103075163B (zh) * | 2012-12-28 | 2015-02-18 | 成都中铁隆工程集团有限公司 | 一种大断面隧道二衬施工换撑工艺 |
CN103306248A (zh) * | 2013-07-01 | 2013-09-18 | 中国水电顾问集团中南勘测设计研究院 | 一种高坝溢洪道地基排水系统及开挖方法 |
CN104653197B (zh) * | 2014-12-15 | 2017-02-08 | 中铁第四勘察设计院集团有限公司 | 超大变断面隧道施工方法 |
CN104929648B (zh) * | 2015-06-03 | 2017-03-01 | 西华大学 | 一种隧道分部导坑施工方法 |
CN105065032B (zh) * | 2015-07-29 | 2017-10-17 | 上海市隧道工程轨道交通设计研究院 | 适用于陡倾层状岩体的大断面隧道支护体系施工方法 |
CN106567718B (zh) * | 2015-10-10 | 2018-08-24 | 中铁隧道勘测设计院有限公司 | 一种复合地层单拱超大跨地铁车站拉槽支撑代换的施工方法 |
CN105888696A (zh) * | 2016-06-30 | 2016-08-24 | 中铁四局集团第四工程有限公司 | 大截面隧道的施工方法 |
CN106014449B (zh) * | 2016-07-05 | 2018-02-02 | 重庆建工市政交通工程有限责任公司 | 双线小净距大断面节理岩体地铁隧道的施工方法 |
CN106643361A (zh) * | 2016-12-22 | 2017-05-10 | 中建八局第二建设有限公司 | 超大暗挖隧道双侧壁上下导坑开挖施工方法 |
CN108222947B (zh) * | 2017-12-26 | 2019-05-21 | 长安大学 | 一种超大跨度隧道上台阶cd法向两台阶法转换的施工方法 |
CN108442943A (zh) * | 2018-03-05 | 2018-08-24 | 北京市政建设集团有限责任公司 | 一种渡线段隧道双侧壁导坑法施工方法 |
CN108487911A (zh) * | 2018-03-28 | 2018-09-04 | 中铁二院工程集团有限责任公司 | 复杂地质条件下大跨度隧道双侧墙复合十字交叉法施工方法 |
CN108590671A (zh) * | 2018-05-14 | 2018-09-28 | 姚晓宁 | 一种在超前强支护体系下的五台阶十四部开挖方法 |
CN109057801B (zh) * | 2018-07-26 | 2021-02-05 | 中铁十九局集团第六工程有限公司 | 双侧墙导坑复合台阶式大断面隧道开挖支护的施工方法 |
CN109611100B (zh) * | 2018-11-20 | 2020-07-21 | 中铁十二局集团有限公司 | 一种隧道中导洞双侧扩挖施工方法 |
CN109854277A (zh) * | 2019-01-11 | 2019-06-07 | 中国建筑第八工程局有限公司 | 大跨度超厚的隧道二衬结构的施工方法 |
CN110230497A (zh) * | 2019-06-24 | 2019-09-13 | 中铁隧道局集团有限公司 | 一种线隧道正洞身双侧壁导坑施工方法 |
CN110863841A (zh) * | 2019-11-29 | 2020-03-06 | 中交第二航务工程局有限公司 | 一种大跨度浅埋暗挖隧道二衬三步施工方法 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6520718B1 (en) * | 1998-11-27 | 2003-02-18 | Shigeki Nagatomo, Et Al. | Sardine-bone construction method for large-section tunnel |
JP4480907B2 (ja) * | 2001-02-15 | 2010-06-16 | 島田 巌乃 | トンネルの掘削工法 |
CN101566064B (zh) * | 2009-06-01 | 2011-06-08 | 中国建筑第八工程局有限公司 | 一种大断面隧道施工方法 |
CN101666232B (zh) * | 2009-09-27 | 2012-08-22 | 中铁四局集团有限公司 | 超大断面隧道六部开挖的施工方法 |
-
2011
- 2011-04-08 CN CN 201110087799 patent/CN102182466B/zh active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
CN102182466A (zh) | 2011-09-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104675403B (zh) | 一种地下空间施工方法及支护结构 | |
CN104763449B (zh) | 一种地下水封洞库水幕系统设计方法 | |
CN102606162B (zh) | 隧道软弱围岩浅埋易坍塌区快速施工方法 | |
Sirivachiraporn et al. | Ground movements in EPB shield tunneling of Bangkok subway project and impacts on adjacent buildings | |
CN101775988B (zh) | 软弱围岩斜井转正洞的施工方法 | |
CN104790978B (zh) | 小净距立体交叉隧道环形导坑施工方法 | |
CN104612698B (zh) | 一种浅埋暗挖隧道上台阶中隔壁施工方法 | |
CN101864963B (zh) | 一种大断面黄土隧道施工方法 | |
CN103306687B (zh) | 软岩隧道长悬臂水平旋喷变形控制施工方法 | |
CN101737061B (zh) | 既有单洞隧道改扩建为连拱隧道的施工方法 | |
CN106869944B (zh) | 复杂环境下地下立交交叉口超小净距隧道施工方法 | |
CN107060840A (zh) | 一种大断面隧道v级围岩开挖支护的施工方法 | |
CN102134998B (zh) | 一种风积沙隧道的施工方法 | |
CN102758632B (zh) | 岩质地层双初支分层法修建大型地下结构的方法 | |
CN104653197B (zh) | 超大变断面隧道施工方法 | |
CN103089275B (zh) | 富水极破碎围岩隧道塌方段围岩控制方法 | |
CN107339104B (zh) | 保安隔离矿柱回收方法 | |
CN103321644B (zh) | 机械与控制爆破组合开挖隧道的方法 | |
CN103470261B (zh) | 综采放顶煤采空区原巷道顶板下沿空掘巷的方法 | |
CN103306680B (zh) | 既有单线隧道扩建为多线隧道的施工方法 | |
CN102182472B (zh) | 隧道塌方空腔的回填修复方法 | |
CN204510205U (zh) | 一种竹节钢管桩 | |
CN105781571A (zh) | 一种软岩变形隧道衬砌支护拆换拱施工方法 | |
CN100567698C (zh) | 隧道超前支护风循环钻进施工方法及钻具 | |
JP4309219B2 (ja) | トンネル構築方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
C06 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
C10 | Entry into substantive examination | ||
GR01 | Patent grant | ||
C14 | Grant of patent or utility model |