CN101451361B - 三通式电缆工作井 - Google Patents

三通式电缆工作井 Download PDF

Info

Publication number
CN101451361B
CN101451361B CN2007101714884A CN200710171488A CN101451361B CN 101451361 B CN101451361 B CN 101451361B CN 2007101714884 A CN2007101714884 A CN 2007101714884A CN 200710171488 A CN200710171488 A CN 200710171488A CN 101451361 B CN101451361 B CN 101451361B
Authority
CN
China
Prior art keywords
well
member piece
prefabricated component
upper member
connectivity mouth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2007101714884A
Other languages
English (en)
Other versions
CN101451361A (zh
Inventor
吴建高
汪一华
曹雪峰
王承
姜晓敏
姜云
诸谧玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiurui Electric Power Pipeline Engineering Technology Co., Ltd.
Shanghai Jiulong Electric Power Group Co Ltd
State Grid Shanghai Municipal Electric Power Co
Original Assignee
SHANGHAI JIURUI ELECTRIC POWER PIPELINE ENGINEERING TECHNOLOGY Co Ltd
Shanghai Jiulong Electric Power Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI JIURUI ELECTRIC POWER PIPELINE ENGINEERING TECHNOLOGY Co Ltd, Shanghai Jiulong Electric Power Group Co Ltd filed Critical SHANGHAI JIURUI ELECTRIC POWER PIPELINE ENGINEERING TECHNOLOGY Co Ltd
Priority to CN2007101714884A priority Critical patent/CN101451361B/zh
Publication of CN101451361A publication Critical patent/CN101451361A/zh
Application granted granted Critical
Publication of CN101451361B publication Critical patent/CN101451361B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

本发明公开了一种地下工程技术领域的三通式电缆工作井。本发明包括:预制构件块、密封件和连接件,所述预制构件块包括端头上构件块、端头下构件块、过渡段上构件块、过渡段下构件块、井口端上构件块、井口端下构件块、积水井构件块,各互相配对的上、下构件块叠加后高度为井体高度;由预制构件块拼装成直通井体,其两端各有通口,在井体的任一侧还设有第三通口;所有预制构件块相拼接的接缝处均垫有密封件,预制构件块之间由连接件连接。本发明既具有三个通口扩大了作业空间,又能适应电缆不同排布方式。便于电缆故障抢修,降低抢修成本,符合电缆敷设的实用性。

Description

三通式电缆工作井
技术领域
本发明涉及的是一种地下工程技术领域的工作井,具体是一种三通式电缆工作井。
背景技术
现有地下管线工作井有这样几种形式:采用粘土砖砌成的工作井、现浇混凝土工作井、混凝土砌块式工作井、预制构件拼装和钢筋混凝土现浇方式相结合的工作井以及预制构件拼装式工作井。其中,前四种形式的工作井或存在强度低、易渗漏、不耐久的缺陷,或有施工工期长、工程质量可靠性差的不足。
经对现有技术文献的检索发现,公开号为CN1880591A(公开日:2006年12月20日)的中国发明专利“预制拼装式电缆工作井及其施工方法”公开的是一种直通式电缆工作井,仅包括两个通口。因结构过于简单,使地下管线的布置受到限制,已不能满足各种施工场合的需要。
发明内容
本发明的目的在于克服现有技术中的不足,提供一种三通式电缆工作井,本发明具有三个通口扩大了作业空间,又能适应电缆不同排布方式。便于电缆故障抢修,降低抢修成本,符合电缆敷设的实用性。
本发明是通过以下技术方案实现的,本发明三通式电缆工作井包括:预制构件块、密封件和连接件,所述预制构件块包括端头上构件块、端头下构件块、过渡段上构件块、过渡段下构件块、井口端上构件块、井口端下构件块、积水井构件块,各互相配对的上、下构件块叠加后高度为井体高度;由预制构件块拼装成直通井体,其两端各有通口,在井体的任一侧还设有第三通口;所有预制构件块相拼接的接缝处均垫有密封件,预制构件块之间由连接件连接。
所述第三通口,是由第三通口上构件块和第三通口下构件块拼装叠加而成;在第三通口上构件块的靠井体侧有突出的梯形台,与第三通口相拼接的三块过渡段上构件块也分别有梯形台,第三通口上构件块与三块过渡段上构件块之间通过互补的梯形台相配合。
第三通口与井体之间形成的转角,优选弧形。
井体水平方向相邻的预制构件块的垂直高度互不相同,即相邻的上、下构件块的水平方向接缝不处于同一水平线。
与现有技术相比,本发明具有三个通口扩大了作业空间,又能适应电缆不同排布方式。第三通口通过设有梯形台结构与井体面的三块过渡段上构件块相配合,可免去井体上表面上加设横梁。第三通口与井体之间的转角呈弧形,以防止电缆在转角处磨损。井体水平方向相邻的预制构件块的垂直高度互不相同,即相邻的上、下构件块的水平方向接缝不处于同一水平线,以增强井体的拼装强度。
附图说明
图1为本发明整体结构示意图;
图2为第三通口上构件块的结构示意图;
图3为三个过渡段上构件块的结构示意图;
图4为第三通口上构件块与过渡段上构件块之间相配合的截面结构示意图。
标记如下:
1-端头上构件块,2-过渡段上构件块,3-井口端上构件块,4-第三通口上构件块,1’-端头下构件块,2’-过渡段下构件块,3’-井口端下构件块,4’-第三通口下构件块。
具体实施方式
以下结合附图对本发明的实施例作详细说明:本实施例在以本发明技术方案为前提下进行实施,给出了详细的实施方式和过程,但本发明的保护范围不限于下述的实施例。
如图1所示,本实施例包括:预制构件块、密封件和连接件,预制构件块包括端头上构件块1、端头下构件块1’、过渡段上构件块2、过渡段下构件块2’、井口端上构件块3、井口端下构件块3’、积水井构件块,各互相配对的上、下构件块叠加后高度为井体高度;由预制构件块拼装成直通井体,其两端各有通口,在井体的任一侧还设有第三通口;所有预制构件块相拼接的接缝处均垫有密封件,预制构件块之间由连接件连接。
如图1、图2、图3和图4所示的第三通口,是由第三通口上构件块4和第三通口下构件块4’拼装叠加而成;在第三通口上构件块4的靠井体侧有突出的梯形台,与第三通口相拼接的三块过渡段上构件块2也分别有梯形台,第三通口上构件块4与三块过渡段上构件块2之间通过互补的梯形台相配合。
第三通口与井体之间形成弧形转角。
井体水平方向相邻的预制构件块的垂直高度互不相同,即相邻的上、下构件块的水平方向接缝不处于同一水平线。
若要需要改变井体纵向的长度,可以通过增减过渡段上、下构件块的数目来实现。
与现有技术相比,本实施例具有三个通口扩大了作业空间,又能适应电缆不同排布方式。第三通口通过设有梯形台结构与井体面的三块过渡段上构件块2相配合,可免去井体上表面上加设横梁。第三通口与井体之间的转角呈弧形,以防止电缆在转角处磨损。井体水平方向相邻的预制构件块的垂直高度互不相同,即相邻的上、下构件块的水平方向接缝不处于同一水平线,以增强井体的拼装强度。

Claims (4)

1.一种三通式电缆工作井,包括:预制构件块、密封件和连接件,所述预制构件块包括端头上构件块、端头下构件块、过渡段上构件块、过渡段下构件块、井口端上构件块、井口端下构件块、积水井构件块,各互相配对的上、下构件块叠加后高度为井体高度,其特征在于,由预制构件块拼装成直通井体,其两端各有通口,在井体的任一侧还设有第三通口;所有预制构件块相拼接的接缝处均垫有密封件,预制构件块之间由连接件连接。
2.如权利要求1所述的三通式电缆工作井,其特征在于,所述第三通口是由第三通口上构件块和第三通口下构件块拼装叠加而成;在第三通口上构件块的靠井体侧有突出的梯形台,与第三通口相拼接的三块过渡段上构件块也分别有梯形台,第三通口上构件块与三块过渡段上构件块之间通过互补的梯形台相配合。
3.如权利要求1所述的三通式电缆工作井,其特征在于,第三通口与井体之间形成弧形转角。
4.如权利要求1至3任一所述的三通式电缆工作井,其特征在于,所述的预制构件块在井体水平方向相邻之间的垂直高度互不相同。
CN2007101714884A 2007-11-30 2007-11-30 三通式电缆工作井 Active CN101451361B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007101714884A CN101451361B (zh) 2007-11-30 2007-11-30 三通式电缆工作井

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007101714884A CN101451361B (zh) 2007-11-30 2007-11-30 三通式电缆工作井

Publications (2)

Publication Number Publication Date
CN101451361A CN101451361A (zh) 2009-06-10
CN101451361B true CN101451361B (zh) 2010-08-25

Family

ID=40733826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007101714884A Active CN101451361B (zh) 2007-11-30 2007-11-30 三通式电缆工作井

Country Status (1)

Country Link
CN (1) CN101451361B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409699A (zh) * 2010-09-25 2012-04-11 河南省电力公司焦作供电公司 整体三通式电缆工作井

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4920722A (en) * 1987-05-14 1990-05-01 Europlast S.P.A. Composable well
US6074130A (en) * 1998-09-25 2000-06-13 Duran, Inc. Inside drop system for manholes
CN2799671Y (zh) * 2005-06-14 2006-07-26 上海加晟管材有限公司 预制拼装式电缆工作井
CN2799672Y (zh) * 2005-06-14 2006-07-26 上海加晟管材有限公司 电缆工作井
CN201128917Y (zh) * 2007-11-30 2008-10-08 上海久隆电力(集团)有限公司 三通式电缆工作井

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4920722A (en) * 1987-05-14 1990-05-01 Europlast S.P.A. Composable well
US6074130A (en) * 1998-09-25 2000-06-13 Duran, Inc. Inside drop system for manholes
CN2799671Y (zh) * 2005-06-14 2006-07-26 上海加晟管材有限公司 预制拼装式电缆工作井
CN2799672Y (zh) * 2005-06-14 2006-07-26 上海加晟管材有限公司 电缆工作井
CN201128917Y (zh) * 2007-11-30 2008-10-08 上海久隆电力(集团)有限公司 三通式电缆工作井

Also Published As

Publication number Publication date
CN101451361A (zh) 2009-06-10

Similar Documents

Publication Publication Date Title
CN105256838B (zh) 管廊预制件及预制式综合管廊
CN100580195C (zh) 大深度地下连续墙止水接头装置
CN205171549U (zh) 管廊预制件及预制式综合管廊
CN206143899U (zh) 适用于污水管道纳入综合管廊的交叉节点结构
CN204290230U (zh) 装配式高压单芯电缆砼槽
CN101451361B (zh) 三通式电缆工作井
CN201128917Y (zh) 三通式电缆工作井
CN106356768A (zh) 沿曲线轨迹能快速圆滑铺设的电力铺设装置
CN106356796A (zh) 多用途电力槽
CN207553133U (zh) 一种地下管廊结构
CN109458192A (zh) 预制片连接组件及具有其的仰拱结构
CN208136954U (zh) 预制拼装式管廊结构
CN110797827A (zh) 一种电缆排管预制混凝土模块
CN206956775U (zh) 一种简易式地下三舱综合管廊
CN208690872U (zh) 一种预制电缆排管
CN201826446U (zh) 一种房屋泛水装置
CN211446883U (zh) 一种地下连续墙防渗漏连接结构
CN213143030U (zh) 一种预制地下连续墙及地下连续墙结构
CN210724048U (zh) 一种方便连接的mpp电缆套管
CN205051311U (zh) 震区及土质疏松地区使用的线缆槽
KR20120134677A (ko) 전단연결재가 보강된 프리캐스트 콘크리트 암거 및 암거의 시공방법
CN212427204U (zh) 一种装配式地下综合管廊
CN219862942U (zh) 装配式预制管廊
CN218933209U (zh) 一种带榫卯结构的预制拼装式电缆工作井
CN212582882U (zh) 一种连接结合度高的预制内墙

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI JIURUI ELECTRIC POWER PIPELINE ENGINEERIN

Free format text: FORMER OWNER: SHANGHAI JIURUI ELECTRIC POWER PIPELINE ENGINEERING TECHNOLOGY CO., LTD.

Effective date: 20131022

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20131022

Address after: 200070 Shanghai city Zhabei District Minli Road No. 183

Patentee after: Shanghai Jiulong Electric Power (Group) Co., Ltd.

Patentee after: Shanghai Jiurui Electric Power Pipeline Engineering Technology Co., Ltd.

Patentee after: State Grid Shanghai Municipal Electric Power Company

Address before: 200070 Shanghai city Zhabei District Minli Road No. 183

Patentee before: Shanghai Jiulong Electric Power (Group) Co., Ltd.

Patentee before: Shanghai Jiurui Electric Power Pipeline Engineering Technology Co., Ltd.