CN101397783A CNA2007101572421A CN200710157242A CN101397783A CN 101397783 A CN101397783 A CN 101397783A CN A2007101572421 A CNA2007101572421 A CN A2007101572421A CN 200710157242 A CN200710157242 A CN 200710157242A CN 101397783 A CN101397783 A CN 101397783A
Authority
CN
China
Prior art keywords
pile
pile body
base
immersed tube
hack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007101572421A
Other languages
Chinese (zh)
Inventor
王国奋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA2007101572421A priority Critical patent/CN101397783A/en
Publication of CN101397783A publication Critical patent/CN101397783A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a construction method for building pile foundation engineering, in particular to a pile forming method of an enlarged-base precast pile body, which is the preferred construction method of multi-stage base large-bearing-capacity piles. The pile forming method of the invention comprises the following process steps: an immersed tube with a metal pile head is sunk to a hard soil layer for designing elevation; the metal pile head is drawn out; a lower base space is formed and kept free from remained fine earth; a lower base is cast; a precast pile body and dowels are put into and anchored with the lower base; the immersed tube is pulled upward to a preset height H; an upper base space is formed and kept free from fine earth; flowing concrete is drained into the opening of the immersed tube to cast an upper base, and then the preset pile body with dowels is put into and anchored with the upper base; and the immersed tube is pulled out, and slurry is poured into the gap. The construction method has the advantages that: the bearing capacity and the reduction factor of a single pile are enhanced, the utilization rate of the material strength is improved, and the construction method is safe and stable, and the construction cost of the pile base is reduced, therefore, the expected design effect is reached.

Description

The piling method of bottom-enlarging prefabricated pile body
Technical field
The present invention relates to the piling method of a kind of construction of building pile foundation engineering, particularly a kind of bottom-enlarging prefabricated pile body.It is the job practices of the big bearing peg first-selection of multistage base.
Background technology
According to the national regulation whole body be cast-in-place (be the pile body Cast-in-place concrete, base also is a Cast-in-place concrete) its base diameter ratio maximum value of expanded bore pile is limited in 3-3.5, and pipe sinking prefabricated steel concrete club-footed pile, this stake is the prefabricated concrete of pile body, the base Cast-in-place concrete, obviously this ratio 3-3.5 is broken, generally 3.5-5 can be reached,, requirement of engineering can't be satisfied although bearing capacity is bigger, particularly, the opposite end bearing capacity to give a discount 0.9 when bellout diameter during greater than 1.5 meters.For this reason, immersed tube prefabricated multistage under-reamed pile has appearred again.Existing multiple bearing capacity dish stake technology has two common ground, and first all is to expand the end with positive crossover-circulating type method pore-forming; Second all carries out pile without immersed tube expands the end.This two point-to-points load dish (at the bottom of the multistage expansion) stake is quite unfavorable, in other words, bring two problems, 1), national building code requirement, expand the base end load at the end with positive crossover-circulating type method pile and will take advantage of 0.45 coefficient, because have mud existence and pile bottom sediment to clean out, (Zhejiang Province's standard is 0.24 discount) gives a discount too big, though a plurality of bases are arranged, loss end load is very big; 2); without immersed tube; condition of construction can not get protection; positive in addition crossover-circulating type method is operation under water; expand bottom application worker situation and cannot see, the difficult measurement noted down, when also usually taking place to expand the end under water; top soil body a slice situation that falls down also happens occasionally; also have because the multistage stake of prior art all is the whole body Cast-in-place concrete, and that the intensity of Cast-in-place concrete is done is not high, and difficult quality guarantee; and in water, water concrete; the difficult control of quality adds that the pile capacity of a plurality of bases is all bigger, and its pile body diameter of above factor must be done greatlyyer; and this a plurality of base is afraid of that pile body diameter is big most; development test shows that pile body diameter increases, and its bearing capacity decay is very serious.
Summary of the invention
The present invention is directed to problem that prior art exists provide a kind of piling method of bottom-enlarging prefabricated pile body, purpose be make that bearing capacity of single pile is big, strength of materials utilization rate height, reduction coefficient height, safe and reliable, guarantee the pile foundation engineering quality, reduce cost, technology is reasonable.
The piling method of bottom-enlarging prefabricated pile body of the present invention comprises following processing step: a, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, expand the end with extrusion equipment and form lower base space, and get clean hack, keep the noresidue hack; D, cast lower bottom base; E, put into down precast pile, joint bar and lower bottom base is anchored; F, on pull out immersed tube to the distance H of setting; G, expand the end with extrusion equipment and form upper base space, and get clean hack, keep the noresidue hack; H, put into the concrete cast upper bed-plate that flows, will put into upper bed-plate with the last precast pile of joint bar again and be anchored from the immersed tube mouth; I, extract immersed tube, and between the slit, inject cement paste.
Described extrusion equipment is that hydraulic pressure props up disc shaping machine.
Getting clean hack among described operation c and the g is to get the hack that is dug down only with inhaling indigenous equipment or mixing method.
The concrete steps that described mixing method is got the hack that is dug down only are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
Distance H among the described operation f is 2-10 a times of base diameter.
It is a kind of in precast hollow pile body and the solid precast pile or both combinations that following in described e and the h operation gone up precast pile.
The piling method of bottom-enlarging prefabricated pile body comprises following processing step: a, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, expand the end with extrusion equipment and form lower base space, and get clean hack, keep the noresidue hack; D, cast lower bottom base; E, put into down precast pile, joint bar and lower bottom base is anchored; F, on pull out immersed tube to the distance H of setting; G, expand the end with extrusion equipment and form upper base space, and get clean hack, keep the noresidue hack; H, put into the top that reinforcing bar 7 extends into down the precast hollow pile body, with pile body 5 on flow concrete cast upper bed-plate and the cast-in-situ steel concrete from the immersed tube mouth; Operation i extracts immersed tube 2 and inject cement paste in the slit; I, extract immersed tube, and between the slit, inject cement paste.
The present invention is compared with prior art owing to changed traditional piling method; do protection and support with immersed tube; rationally arrange operation to eliminate the defective of existing piling method effectively in addition; and significantly improve the supporting capacity and the reduction coefficient of single pile through evidence; improved the utilization rate of the strength of materials; and safe and reliable, reduce the pile foundation engineering cost, reached the Expected Results of design.
Description of drawings
Fig. 1 a-1g is the construction view of each operation process of the present invention.
The construction view of the master operation of Fig. 2 embodiment 2.
Among the figure 1, lower base space; 2, immersed tube; 3, following precast pile; 4, go up precast pile; 5, pile body on the cast-in-place notes; 6, joint bar; 7, reinforcing bar; 8, upper base space.
The specific embodiment
Embodiment 1:
Embodiments of the invention 1a-1g in conjunction with the accompanying drawings are described in detail.
The piling method of bottom-enlarging prefabricated pile body of the present invention comprises following processing step: a, the immersed tube 2 that has metal pile head is sunk to hardpan to design elevation; B, taking-up metal pile head; C, expand the end with extrusion equipment and form lower base space 1, hack is got hack only with the suction indigenous equipment; D, pour in the immersed tube 2 or hang in the concrete cast lower bottom base that flows with barreled; E, put into down precast pile 3, joint bar and lower bottom base are anchored; F, on pull out immersed tube 2 to the distance H of setting, its H be base diameter 2-10 doubly, its value size depends on that what of base progression are relevant with the pile body height; G, expand the end with extrusion equipment and form upper base space 8, hack is got hack only with the suction indigenous equipment, and following precast pile 3 is that its hollow hack falls in the hollow preformed pile body and needn't clear up; H, put into the concrete cast upper bed-plate that flows from 2 mouthfuls of immersed tube, the solid precast pile 4 of going up that will have joint bar 6 is again put into upper bed-plate and is anchored; I, extract immersed tube 2, in the slit, inject cement paste.
Above-mentioned extrusion equipment is that hydraulic pressure props up disc shaping machine.
Getting clean hack among above-mentioned operation c and the g is to get the hack that is dug down only with inhaling indigenous equipment or mixing method.Wherein to get the concrete steps of the hack that is dug down only as follows for mixing method: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
Embodiment 2:
Its operation a to g is identical with embodiment 1, and operation h puts into the top that reinforcing bar 7 extends into down the precast hollow pile body from the immersed tube mouth, with pile body 5 on flow concrete cast upper bed-plate and the cast-in-situ steel concrete; Operation i extracts immersed tube 2 and inject cement paste in the slit.Pile body 5 on the cast-in-place notes as shown in Figure 2.
It is a kind of in precast hollow pile body and the solid precast pile or both combinations that following described in embodiment one and the embodiment two gone up precast pile.

Claims (7)

1, the piling method of bottom-enlarging prefabricated pile body is characterized in that it comprises following processing step: a, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, expand the end with extrusion equipment and form lower base space, and get clean hack, keep the noresidue hack; D, cast lower bottom base; E, put into down precast pile, joint bar and lower bottom base is anchored; F, on pull out immersed tube to the distance H of setting; G, expand the end with extrusion equipment and form upper base space, and get clean hack, keep the noresidue hack; H, put into the concrete cast upper bed-plate that flows, will put into upper bed-plate with the last precast pile of joint bar again and be anchored from the immersed tube mouth; I, extract immersed tube, and between the slit, inject cement paste.
2, the piling method of bottom-enlarging prefabricated pile body according to claim 1 is characterized in that described extrusion equipment is that hydraulic pressure props up disc shaping machine.
3, the piling method of bottom-enlarging prefabricated pile body according to claim 1, it is characterized in that getting among described operation c and the g clean hack is to get the hack that is dug down only with inhaling indigenous equipment or mixing method.
4, the piling method of bottom-enlarging prefabricated pile body according to claim 3, it is as follows to it is characterized in that described mixing method is got the concrete steps of the hack that is dug down only: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
5, the piling method of bottom-enlarging prefabricated pile body according to claim 1, it is characterized in that distance H among the described operation f be base diameter 2-10 doubly.
6, the piling method of bottom-enlarging prefabricated pile body according to claim 1 is characterized in that it is a kind of in precast hollow pile body and the solid precast pile or both combinations that following in the described e operation gone up precast pile.
7, the piling method of bottom-enlarging prefabricated pile body according to claim 1 is characterized in that it is a kind of in precast hollow pile body and the solid precast pile or both combinations that following in the described h operation gone up precast pile.
CNA2007101572421A 2007-09-29 2007-09-29 Pile-forming method of belled prefabricated pile body Pending CN101397783A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007101572421A CN101397783A (en) 2007-09-29 2007-09-29 Pile-forming method of belled prefabricated pile body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007101572421A CN101397783A (en) 2007-09-29 2007-09-29 Pile-forming method of belled prefabricated pile body

Publications (1)

Publication Number Publication Date
CN101397783A true CN101397783A (en) 2009-04-01

Family

ID=40516607

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007101572421A Pending CN101397783A (en) 2007-09-29 2007-09-29 Pile-forming method of belled prefabricated pile body

Country Status (1)

Country Link
CN (1) CN101397783A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643675A (en) * 2013-10-23 2014-03-19 叶长青 Expansion pile construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643675A (en) * 2013-10-23 2014-03-19 叶长青 Expansion pile construction method
CN103643675B (en) * 2013-10-23 2015-11-25 叶长青 A kind of construction method expanding body stake

Similar Documents

Publication Publication Date Title
CN101126237A (en) Blasting pile-forming method for three-stage bottom-enlarging prefabricated and cast-in-situ steel concrete combination pile body
CN101397783A (en) Pile-forming method of belled prefabricated pile body
CN101397789A (en) Extrusion pile-forming method of belled prefabricated pile body
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101397787A (en) Mixed pile-forming method of prefabricated pile body
CN101397781A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101135165A (en) Extrusion pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101397790A (en) Pile-forming method of belled prefabricated pile body with high bearing ability
CN101397788A (en) Blasting pile-forming method of belled prefabricated pile body with high bearing ability
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101130968A (en) Pile-forming method for two-level expanding bottom prefabricated pile body
CN101126236A (en) Blasting pile-forming method for multi-stage club-footed pile
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101397786A (en) Pile-forming method of prefabricated pile body
CN101173513A (en) Mechanical piling method for third level bottom-expanded combined pile body
CN101135147A (en) Blasting pile forming method for three-stage bottom expanding composite pile body
CN101397782A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN100580187C (en) Pile forming method for one-stage bottom expanding steel pipe composite pile body
CN101135158A (en) Mechanical pile forming method for high-bearing multi-stage club-footed pile
CN101135148A (en) Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body
CN101397791A (en) Pile-forming method of belled pile
CN101397784A (en) Pile-forming method of immersed tube belled pile
CN101130959A (en) Extruding pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101130960A (en) Extruding pile-forming method for multilevel expanding bottom pile
CN101135143A (en) Extrusion pile forming method for three-stage bottom expanding prefabricated and cast-in-situs steel concrete composite pile body

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090401