CN101135148A CNA2007101572898A CN200710157289A CN101135148A CN 101135148 A CN101135148 A CN 101135148A CN A2007101572898 A CNA2007101572898 A CN A2007101572898A CN 200710157289 A CN200710157289 A CN 200710157289A CN 101135148 A CN101135148 A CN 101135148A
Authority
CN
China
Prior art keywords
pile
pile body
immersed tube
extrusion
forming method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007101572898A
Other languages
Chinese (zh)
Inventor
周亚萍
吴伟林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA2007101572898A priority Critical patent/CN101135148A/en
Publication of CN101135148A publication Critical patent/CN101135148A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The present invention is extruding piling process of three-stage under-reamed pile stem. The extruding piling process includes the following steps: 1. immersing immersed tube with metal pile head into hardpan; 2. taking out the metal pile head; 3. forming the lower base space, drawing the immersed tube to the first designed distance, forming the middle base space and taking out soil, setting the prefabricated pile stem with steel dowels in the lower end into the immersed tube, pouring the lower base, the middle base and the lower pile stem with concrete; 4. drawing the immersed tube to the second designed distance, forming the upper base space and pouring the upper base with concrete; 5. setting the upper prefabricated pile stem with steel dowels in the lower end into the immersed tube, and connecting the steel dowels to the upper base; and 6. withdrawing the immersed tube and pouring cement mortar into gap. The pile has high material strength utilizing rate and low construction cost.

Description

The extrusion pile forming method of third level bottom-expanded combined pile body
Technical field
The present invention relates to the piling method of a kind of construction of building pile foundation engineering, particularly a kind of third level bottom-expanded combined pile body.It is the job practices of the multistage base large bearing capacity of highrise building pile foundation engineering first-selection.
Background technology
According to the national regulation whole body be cast-in-place (be the pile body Cast-in-place concrete, base also is a Cast-in-place concrete) its base diameter ratio maximum value of expanded bore pile is limited in 3-3.5, and pipe sinking prefabricated steel concrete club-footed pile, this stake is the prefabricated concrete of pile body, the base Cast-in-place concrete, obviously this ratio 3-3.5 is broken, generally 3.5-5 can be reached,, requirement of engineering can't be satisfied although bearing capacity is bigger, particularly, the opposite end bearing capacity to give a discount 0.9 when bellout diameter during greater than 1.5 meters.For this reason, immersed tube prefabricated multistage under-reamed pile has appearred again.Existing multiple bearing capacity dish stake technology has two common ground, and first all is to expand the end with positive crossover-circulating type method pore-forming; Second all carries out pile without immersed tube expands the end.This two point-to-points load dish (at the bottom of the multistage expansion) stake is quite unfavorable, in other words, bring two problems, 1), national building code requirement, expand the base end load at the end with positive crossover-circulating type method pile and will take advantage of 0.45 coefficient, because have mud existence and pile bottom sediment to clean out, (Zhejiang Province's standard is 0.24 discount) gives a discount too big, though a plurality of bases are arranged, loss end load is very big; 2); without immersed tube; condition of construction can not get protection; positive in addition crossover-circulating type method is operation under water; expand bottom application worker situation and cannot see, the difficult measurement noted down, when also usually taking place to expand the end under water; top soil body a slice situation that falls down also happens occasionally; also have because the multistage stake of prior art all is the whole body Cast-in-place concrete, and that the intensity of Cast-in-place concrete is done is not high, and difficult quality guarantee; and in water, water concrete; the difficult control of quality adds that the pile capacity of a plurality of bases is all bigger, and its pile body diameter of above factor must be done greatlyyer; and this a plurality of base is afraid of that pile body diameter is big most; development test shows that pile body diameter increases, and its bearing capacity decay is very serious.
Summary of the invention
The problem that the present invention is directed to the prior art existence provides a kind of extrusion pile forming method of third level bottom-expanded combined pile body, purpose is to improve the utilization rate and the reduction coefficient of the strength of materials, make single pile bearing capacity big, guaranteeing that pile foundation quality reaches the Expected Results of design, and can reduce cost.
The extrusion pile forming method of third level bottom-expanded combined pile body of the present invention, the immersed tube that it comprises following processing step: a, have a metal pile head sinks to hardpan to design elevation; B, taking-up metal pile head; C, expand end processing lower base space with extrusion equipment, on pull out immersed tube to setpoint distance H 1, with mechanical bottom-expanding equipment processing center base space, with the hack in the peace and quiet base space of borrow equipment, the precast hollow pile body that the lower end has joint bar is lowered in the immersed tube, and the perfusion concrete waters and pours down, middle base reaches pile body down; D, on pull out immersed tube to the distance H of setting 2, expanding end processing upper base space with extrusion equipment, its hack falls in the precast hollow pile body, perfusion concrete cast upper bed-plate; E, the last precast pile that the lower end is had a joint bar are lowered in the immersed tube, and joint bar and upper bed-plate are anchored; F, extract immersed tube, outside pile body, inject cement paste in the slit.
The extrusion pile forming method of third level bottom-expanded combined pile body, the immersed tube that it comprises following processing step: a, have a metal pile head sinks to hardpan to design elevation; B, taking-up metal pile head; C, expand end processing lower base space with extrusion equipment, on pull out immersed tube to setpoint distance H 1, with mechanical bottom-expanding equipment processing center base space, with the hack in the peace and quiet base space of borrow equipment, the precast hollow pile body that the lower end has joint bar is lowered in the immersed tube, and the perfusion concrete waters and pours down, middle base reaches pile body down; D, on pull out immersed tube to the distance H of setting 2, expanding end processing upper base space with extrusion equipment, its hack falls in the precast hollow pile body, perfusion concrete cast upper bed-plate; E is lowered to reinforcing bar and be anchored with upper bed-plate from immersed tube, with pile body on the concrete pouring; F), take out immersed tube.
Concrete steps with the hack in the peace and quiet base space of borrow equipment among the above-mentioned operation c are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
Above-mentioned operation c and the extrusion equipment among the d are that hydraulic pressure props up disc shaping machine.
The setpoint distance H of described operation c and d 1And H 2Be base diameter 2-10 doubly.
Borrow equipment among the described operation c is to be used for pipe sinking prefabricated steel concrete club-footed pile to inhale indigenous equipment.
Last precast pile among the described operation e can replace with pile body on the cast-in-place notes steel concrete.
On immersed tube, pull out to setpoint distance H among the described operation d 2Cement injection between precast hollow pile body and soil afterwards.
The present invention is compared with prior art owing to adopt immersed tube to do protection and rely on, and three bases and down pile body be cast-in-place notes steel concrete pile body, in to go up pile body be technical measures such as precast pile, and expand end precision height, accurate positioning good concentricity through the evidence construction; Base diameter and pile body diameter ratio can reach 3.5-5.0, and reduction coefficient can reach 0.9, obviously improve the utilization rate of the strength of materials, and it is little to satisfy multistage under-reamed pile requirement pile body diameter fully, and bearing capacity is big, the requirement that quality requirement is high; Not only eliminate the defective that prior art exists, but also reached the Expected Results of design; Can also reduce construction cost.
Description of drawings
Fig. 1 a-Fig. 1 f is the construction view of the embodiment of the invention 1 each operation.
Fig. 2 is the construction view of the embodiment of the invention 2 master operations.
Among the figure 1, pile body down; 2, immersed tube; 3, precast hollow pile body; 4, lower base space; 5, center base space; 6, upper base space; 7, go up precast pile; 8, reinforcing bar.
The specific embodiment
Embodiments of the invention 1a-Fig. 1 f and Fig. 2 in conjunction with the accompanying drawings are described in detail.
Embodiment 1:
The extrusion pile forming method of third level bottom-expanded combined pile body of the present invention, the immersed tube 2 that comprise following processing step: a, has a metal pile head sinks to the hardpan design elevation; B, taking-up metal pile head; C, prop up disc shaping machine with extrusion equipment hydraulic pressure and expand end processing lower base space 4, on pull out immersed tube 2 to setpoint distance H 1, with mechanical bottom-expanding equipment processing center base space 5, expanding the end with immersed tube prefabricated steel concrete and inhale indigenous equipment and get hack in the clean lower base space 4, the precast hollow pile body 3 that the lower end is had a joint bar is lowered in the immersed tube 2 cast-in-place base, pile body, the middle bases down of pouring down of perfusion concretes; D, on pull out immersed tube 2 to the distance H of setting 2, between the slit of precast hollow pile body 3 and soil, inject cement paste, prop up disc shaping machine with extrusion equipment hydraulic pressure and expand end processing upper base space 6, the cleaning hack makes it to fall in the precast hollow pile body 3, existing pour concrete upper bed-plate; E, the solid or hollow precast pile 7 of going up that the lower end is had a joint bar are lowered in the immersed tube 2, and make joint bar and upper bed-plate anchor it under; F, extract immersed tube 2, outside pile body, inject cement paste, pile in the slit.The setpoint distance H of described operation c and d 1And H 2Be base diameter 2-10 doubly.Adopt the inventive method to make three grades of expanded bore piles, and the like can process the expanded bore pile of 4-20 level.
Embodiment 2:
Its operation a to d is identical with embodiment 1, and operation e is lowered to reinforcing bar 8 and be anchored with upper bed-plate from immersed tube 2, with pile body on the concrete pouring; F, taking-up immersed tube.
Concrete steps with the hack in the peace and quiet base space of borrow equipment among the above-mentioned operation c are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.

Claims (7)

1. the extrusion pile forming method of third level bottom-expanded combined pile body is characterized in that it comprises following processing step: a, the immersed tube that has a metal pile head sinks to hardpan to design elevation; B, taking-up metal pile head; C, with mechanical bottom-expanding equipment processing lower base space, on pull out immersed tube to setpoint distance H 1, with extrusion equipment expansion end processing center base space, with the hack in the peace and quiet base space of borrow equipment, the precast hollow pile body that the lower end has joint bar is lowered in the immersed tube, and the perfusion concrete waters and pours down, middle base reaches pile body down; D, on pull out immersed tube to the distance H of setting 2, expanding end processing upper base space with extrusion equipment, its hack falls in the precast hollow pile body, perfusion concrete cast upper bed-plate; E, the last precast pile that the lower end is had a joint bar are lowered in the immersed tube, and joint bar and upper bed-plate are anchored; F, extract immersed tube, outside pile body, inject cement paste in the slit.
2. the extrusion pile forming method of third level bottom-expanded combined pile body according to claim 1, it is characterized in that the concrete steps with the hack in the peace and quiet base space of borrow equipment are as follows among the described operation c: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
3. the extrusion pile forming method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the extrusion equipment among described operation c and the d is that hydraulic pressure props up disc shaping machine.
4. the extrusion pile forming method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the setpoint distance H of described operation c and d 1And H 2Be base diameter 2-10 doubly.
5. the extrusion pile forming method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the borrow equipment among the described operation c is to be used for pipe sinking prefabricated steel concrete club-footed pile to inhale indigenous equipment.
6. the extrusion pile forming method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the last precast pile among the described operation e, can replace with pile body on the cast-in-place notes steel concrete.
7. the extrusion pile forming method of third level bottom-expanded combined pile body according to claim 1 is characterized in that pulling out on immersed tube to setpoint distance H among the described operation d 2Cement injection between precast hollow pile body and soil afterwards.
CNA2007101572898A 2007-09-29 2007-09-29 Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body Pending CN101135148A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007101572898A CN101135148A (en) 2007-09-29 2007-09-29 Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007101572898A CN101135148A (en) 2007-09-29 2007-09-29 Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body

Publications (1)

Publication Number Publication Date
CN101135148A true CN101135148A (en) 2008-03-05

Family

ID=39159456

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007101572898A Pending CN101135148A (en) 2007-09-29 2007-09-29 Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body

Country Status (1)

Country Link
CN (1) CN101135148A (en)

Similar Documents

Publication Publication Date Title
CN101126237A (en) Blasting pile-forming method for three-stage bottom-enlarging prefabricated and cast-in-situ steel concrete combination pile body
CN101135165A (en) Extrusion pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101135148A (en) Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101173513A (en) Mechanical piling method for third level bottom-expanded combined pile body
CN101135147A (en) Blasting pile forming method for three-stage bottom expanding composite pile body
CN101135143A (en) Extrusion pile forming method for three-stage bottom expanding prefabricated and cast-in-situs steel concrete composite pile body
CN101130965A (en) Pile-forming method for three-level expanding bottom combined pile body
CN101397783A (en) Pile-forming method of belled prefabricated pile body
CN101397789A (en) Extrusion pile-forming method of belled prefabricated pile body
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101397781A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101135166A (en) Blasting pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101135158A (en) Mechanical pile forming method for high-bearing multi-stage club-footed pile
CN100580187C (en) Pile forming method for one-stage bottom expanding steel pipe composite pile body
CN101135149A (en) Extrusion pile forming method for high-bearing prefabricated and cast-in-situs steel concrete composite pile body
CN101135167A (en) Mechanical pile forming method for two-stage bottom expanding prefabricated pile body
CN101397791A (en) Pile-forming method of belled pile
CN101135150A (en) Mixed pile forming method for high-bearing prefabricated and cast-in-situs steel concrete composite pile body
CN101130959A (en) Extruding pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101135152A (en) Mixed pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101130961A (en) Mixed pile-forming method for three-level expanding bottom combined pile body
CN101130960A (en) Extruding pile-forming method for multilevel expanding bottom pile
CN101126236A (en) Blasting pile-forming method for multi-stage club-footed pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080305