CN101173513A - Mechanical piling method for third level bottom-expanded combined pile body - Google Patents

Mechanical piling method for third level bottom-expanded combined pile body Download PDF

Info

Publication number
CN101173513A
CN101173513A CNA2007101572900A CN200710157290A CN101173513A CN 101173513 A CN101173513 A CN 101173513A CN A2007101572900 A CNA2007101572900 A CN A2007101572900A CN 200710157290 A CN200710157290 A CN 200710157290A CN 101173513 A CN101173513 A CN 101173513A
Authority
CN
China
Prior art keywords
pile body
pile
immersed tube
equipment
mechanical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007101572900A
Other languages
Chinese (zh)
Inventor
周亚萍
吴伟林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA2007101572900A priority Critical patent/CN101173513A/en
Publication of CN101173513A publication Critical patent/CN101173513A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a mechanical pile forming method for there level belled composite pile body, comprising the craft steps that: a, a sinking pipe with a metal pile head is immersed into hardpan to design elevation; b, the metal pile head is taken out; c, a lower base space is processed by a belled device, the sinking pile is drawn upward to setting distance H1, an intermediate base space is processed, the pulverizing soil in the base space is cleaned by drawing out soil device, a prefabricated hollow pile body with an inserted reinforcement arranged at the lower end is run into the sinking pile, the lower base, the intermediate base and the lower pile body are poured by concrete pouring; d, the sinking pile is drawn upward to setting distance H2, an upper base space is processed, the pulverizing soil is fell into the inner of prefabricated hollow pile body, the upper base is poured by concrete pouring; e, an upper prefabricated hollow pile body with an inserted reinforcement arranged at the lower end is run into the sinking pile, the inserted reinforcement is anchored with the upper base; f, the sinking pile is run out, cement slurry is injected into the gaps on the external surface of the pile body. The invention has the advantages of improving the utilization ratio of materials strength and reducing the cost of construction.

Description

The mechanical piling method of third level bottom-expanded combined pile body
Technical field
The present invention relates to the piling method of a kind of construction of building pile foundation engineering, particularly a kind of third level bottom-expanded combined pile body.It is the job practices of the multistage base large bearing capacity of highrise building pile foundation engineering first-selection.
Background technology
According to the national regulation whole body be cast-in-place (be the pile body Cast-in-place concrete, base also is a Cast-in-place concrete) its base diameter ratio maximum value of expanded bore pile is limited in 3-3.5, and pipe sinking prefabricated steel concrete club-footed pile, this stake is the prefabricated concrete of pile body, the base Cast-in-place concrete, obviously this ratio 3-3.5 is broken, generally 3.5-5 can be reached,, requirement of engineering can't be satisfied although bearing capacity is bigger, particularly, the opposite end bearing capacity to give a discount 0.9 when bellout diameter during greater than 1.5 meters.For this reason, immersed tube prefabricated multistage under-reamed pile has appearred again.Existing multiple bearing capacity dish stake technology has two common ground, and first all is to expand the end with positive crossover-circulating type method pore-forming; Second all carries out pile without immersed tube expands the end.This two point-to-points load dish (at the bottom of the multistage expansion) stake is quite unfavorable, in other words, bring two problems, 1), national building code requirement, expand the base end load at the end with positive crossover-circulating type method pile and will take advantage of 0.45 coefficient, because have mud existence and pile bottom sediment to clean out, (Zhejiang Province's standard is 0.24 discount) gives a discount too big, though a plurality of bases are arranged, loss end load is very big; 2); without immersed tube; condition of construction can not get protection; positive in addition crossover-circulating type method is operation under water; expand bottom application worker situation and cannot see, the difficult measurement noted down, when also usually taking place to expand the end under water; top soil body a slice situation that falls down also happens occasionally; also have because the multistage stake of prior art all is the whole body Cast-in-place concrete, and that the intensity of Cast-in-place concrete is done is not high, and difficult quality guarantee; and in water, water concrete; the difficult control of quality adds that the pile capacity of a plurality of bases is all bigger, and its pile body diameter of above factor must be done greatlyyer; and this a plurality of base is afraid of that pile body diameter is big most; development test shows that pile body diameter increases, and its bearing capacity decay is very serious.
Summary of the invention
The problem that the present invention is directed to the prior art existence provides a kind of mechanical piling method of third level bottom-expanded combined pile body, purpose is to improve the utilization rate and the reduction coefficient of the strength of materials, make single pile bearing capacity big, guaranteeing that pile foundation quality reaches the Expected Results of design, and can reduce cost.
The mechanical piling method of third level bottom-expanded combined pile body of the present invention, the immersed tube that it comprises following processing step: a, have a metal pile head sinks to hardpan to design elevation; B, taking-up metal pile head; C, with mechanical bottom-expanding equipment processing lower base space, on pull out immersed tube to setpoint distance H 1, with mechanical bottom-expanding equipment processing center base space, with the hack in the peace and quiet base space of borrow equipment, the precast hollow pile body that the lower end has joint bar is lowered in the immersed tube, and the perfusion concrete waters and pours down, middle base reaches pile body down; D, on pull out immersed tube to the distance H of setting 2, with mechanical bottom-expanding equipment processing upper base space, its hack falls in the precast hollow pile body, perfusion concrete cast upper bed-plate; E, the last precast pile that the lower end is had a joint bar are lowered in the immersed tube, and joint bar and upper bed-plate are anchored; F, extract immersed tube, outside pile body, inject cement paste in the slit.
The mechanical piling method of third level bottom-expanded combined pile body, the immersed tube that it comprises following processing step: a, have a metal pile head sinks to hardpan to design elevation; B, taking-up metal pile head; C, with mechanical bottom-expanding equipment processing lower base space, on pull out immersed tube to setpoint distance H 1, with mechanical bottom-expanding equipment processing center base space, with the hack in the peace and quiet base space of borrow equipment, the precast hollow pile body that the lower end has joint bar is lowered in the immersed tube, and the perfusion concrete waters and pours down, middle base reaches pile body down; D, on pull out immersed tube to the distance H of setting 2, with mechanical bottom-expanding equipment processing upper base space, its hack falls in the precast hollow pile body, perfusion concrete cast upper bed-plate; E is lowered to reinforcing bar and be anchored with upper bed-plate from immersed tube, with pile body on the concrete pouring; F, taking-up immersed tube.
Concrete steps with the hack in the peace and quiet base space of borrow equipment among the above-mentioned operation c are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
The mechanical bottom-expanding equipment of above-mentioned operation c and the usefulness among the d expands the end, and to process upper and lower base space concrete steps as follows: the mark that the detent rail pin of bottom-expanding equipment is aimed on the immersed tube mouth is lowered to immersed tube, start equipment after the equipment upper end is also fixedly positioning and expand the end, expand the end and be vertical earlier expand the end again level expand the end, when reaching, construction stops automatically after design is marked deeply, base cavity pocket is formed on the bottom, expanding the work of undercutting sharpener this moment reaches when designing base diameter, be that power rail reaches predetermined number of revolutions, expand end shoveling and finish, bottom-expanding equipment is hung out ground.
The setpoint distance H of described operation c and d 1And H 2Be base diameter 2-10 doubly.
Borrow equipment among the described operation c is to be used for pipe sinking prefabricated steel concrete club-footed pile to inhale indigenous equipment.
Last precast pile among the described operation e can replace with pile body on the cast-in-place notes steel concrete.
On immersed tube, pull out to setpoint distance H among the described operation d 2Cement injection between precast hollow pile body and soil afterwards.
The present invention is compared with prior art owing to adopt immersed tube to do protection and rely on, and three bases and down pile body be cast-in-place notes steel concrete pile body, in to go up pile body be technical measures such as precast pile, and expand end precision height, accurate positioning good concentricity through the evidence construction; Base diameter and pile body diameter ratio can reach 3.5-5.0, and reduction coefficient can reach 0.9, obviously improve the utilization rate of the strength of materials, and it is little to satisfy multistage under-reamed pile requirement pile body diameter fully, and bearing capacity is big, the requirement that quality requirement is high; Not only eliminate the defective that prior art exists, but also reached the Expected Results of design; Can also reduce construction cost.
Description of drawings
Fig. 1 a-Fig. 1 f is the construction view of the embodiment of the invention 1 each operation.
Fig. 2 is the construction view of the embodiment of the invention 2 master operations.
Among the figure 1, pile body down; 2, immersed tube; 3, precast hollow pile body; 4, lower base space; 5, center base space; 6, upper base space; 7, go up precast pile; 8, reinforcing bar.
The specific embodiment
Embodiments of the invention 1a-Fig. 1 f and Fig. 2 in conjunction with the accompanying drawings are described in detail.
Embodiment 1:
The mechanical piling method of third level bottom-expanded combined pile body of the present invention, the immersed tube 2 that comprise following processing step: a, has a metal pile head sinks to the hardpan design elevation; B, taking-up metal pile head; C, prop up a kind of processing lower base space 4 in the disc shaping machine with mechanical bottom-expanding equipment, explosive forming and YEJ-800 hydraulic pressure, on pull out immersed tube 2 to setpoint distance H 1, processing center base space 5 is expanded the end with immersed tube prefabricated steel concrete and is inhaled indigenous equipment and get hack in the clean lower base space 4, and the precast hollow pile body 3 that the lower end is had a joint bar is lowered in the immersed tube 2 cast-in-place base, pile body, the middle bases down of pouring down of perfusion concretes; D, on pull out immersed tube 2 to the distance H of setting 2, between the slit of precast hollow pile body 3 and soil, inject cement paste, with mechanical bottom-expanding equipment processing upper base space 6, the cleaning hack makes it to fall in the precast hollow pile body 3, existing pour concrete upper bed-plate; E, the solid or hollow precast pile 7 of going up that the lower end is had a joint bar are lowered in the immersed tube 2, and make joint bar and upper bed-plate anchor it under; F, extract immersed tube 2, outside pile body, inject cement paste, pile in the slit.The setpoint distance H of described operation c and d 1And H 2Be base diameter 2-10 doubly.Adopt the inventive method to make three grades of expanded bore piles, and the like can process the expanded bore pile of 4-20 level.
Embodiment 2:
Its operation a to d is identical with embodiment 1, and operation e is lowered to reinforcing bar 8 and be anchored with upper bed-plate from immersed tube 2, with pile body on the concrete pouring; F, taking-up immersed tube.
Concrete steps with the hack in the peace and quiet base space of borrow equipment among the above-mentioned operation c are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
The mechanical bottom-expanding equipment of above-mentioned operation c and the usefulness among the d expands the end, and to process upper and lower base space concrete steps as follows: the mark that the detent rail pin of bottom-expanding equipment is aimed on the immersed tube mouth is lowered to immersed tube, start equipment after the equipment upper end is also fixedly positioning and expand the end, expand the end and be vertical earlier expand the end again level expand the end, when reaching, construction stops automatically after design is marked deeply, base cavity pocket is formed on the bottom, expanding the work of undercutting sharpener this moment reaches when designing base diameter, be that power rail reaches predetermined number of revolutions, expand end shoveling and finish, bottom-expanding equipment is hung out ground.

Claims (7)

1. the mechanical piling method of third level bottom-expanded combined pile body is characterized in that it comprises following processing step: a, the immersed tube that has a metal pile head sinks to hardpan to design elevation; B, taking-up metal pile head; C, with mechanical bottom-expanding equipment processing lower base space, on pull out immersed tube to setpoint distance H 1, with mechanical bottom-expanding equipment processing center base space, with the hack in the peace and quiet base space of borrow equipment, the precast hollow pile body that the lower end has joint bar is lowered in the immersed tube, and the perfusion concrete waters and pours down, middle base reaches pile body down; D, on pull out immersed tube to the distance H of setting 2, with mechanical bottom-expanding equipment processing upper base space, its hack falls in the precast hollow pile body, perfusion concrete cast upper bed-plate; E is lowered to reinforcing bar and be anchored with upper bed-plate from immersed tube, with pile body on the concrete pouring; F, taking-up immersed tube.
2. the mechanical piling method of third level bottom-expanded combined pile body according to claim 1, it is characterized in that the concrete steps with the hack in the peace and quiet base space of borrow equipment are as follows among the described operation c: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
3. the mechanical piling method of third level bottom-expanded combined pile body according to claim 1, it is characterized in that the mechanical bottom-expanding equipment of above-mentioned operation c and the usefulness among the d expands in the end processing, the lower base space concrete steps are as follows: the mark that the detent rail pin of bottom-expanding equipment is aimed on the immersed tube mouth is lowered to immersed tube, start equipment after the equipment upper end is also fixedly positioning and expand the end, expand the end and be vertical earlier expand the end again level expand the end, when reaching, construction stops automatically after design is marked deeply, base cavity pocket is formed on the bottom, expanding the work of undercutting sharpener this moment reaches when designing base diameter, be that power rail reaches predetermined number of revolutions, expand end shoveling and finish, bottom-expanding equipment is hung out ground.
4. the mechanical piling method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the setpoint distance H of described operation c and d 1And H 2Be base diameter 2-10 doubly.
5. the mechanical piling method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the borrow equipment among the described operation c is to be used for pipe sinking prefabricated steel concrete club-footed pile to inhale indigenous equipment.
6. the mechanical piling method of third level bottom-expanded combined pile body according to claim 1 is characterized in that the last precast pile among the described operation e, can replace with pile body on the cast-in-place notes steel concrete.
7. the mechanical piling method of third level bottom-expanded combined pile body according to claim 1 is characterized in that pulling out on immersed tube to setpoint distance H among the described operation d 2Cement injection between precast hollow pile body and soil afterwards.
CNA2007101572900A 2007-09-29 2007-09-29 Mechanical piling method for third level bottom-expanded combined pile body Pending CN101173513A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007101572900A CN101173513A (en) 2007-09-29 2007-09-29 Mechanical piling method for third level bottom-expanded combined pile body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007101572900A CN101173513A (en) 2007-09-29 2007-09-29 Mechanical piling method for third level bottom-expanded combined pile body

Publications (1)

Publication Number Publication Date
CN101173513A true CN101173513A (en) 2008-05-07

Family

ID=39422246

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007101572900A Pending CN101173513A (en) 2007-09-29 2007-09-29 Mechanical piling method for third level bottom-expanded combined pile body

Country Status (1)

Country Link
CN (1) CN101173513A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590399A (en) * 2013-10-24 2014-02-19 叶香雄 Expanded pile construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590399A (en) * 2013-10-24 2014-02-19 叶香雄 Expanded pile construction method
CN103590399B (en) * 2013-10-24 2017-01-11 叶香雄 Expanded pile construction method

Similar Documents

Publication Publication Date Title
CN101173513A (en) Mechanical piling method for third level bottom-expanded combined pile body
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135165A (en) Extrusion pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101130965A (en) Pile-forming method for three-level expanding bottom combined pile body
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135147A (en) Blasting pile forming method for three-stage bottom expanding composite pile body
CN100580187C (en) Pile forming method for one-stage bottom expanding steel pipe composite pile body
CN101135158A (en) Mechanical pile forming method for high-bearing multi-stage club-footed pile
CN101135152A (en) Mixed pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101135148A (en) Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body
CN101130961A (en) Mixed pile-forming method for three-level expanding bottom combined pile body
CN101397783A (en) Pile-forming method of belled prefabricated pile body
CN101397787A (en) Mixed pile-forming method of prefabricated pile body
CN101397789A (en) Extrusion pile-forming method of belled prefabricated pile body
CN101135150A (en) Mixed pile forming method for high-bearing prefabricated and cast-in-situs steel concrete composite pile body
CN101397781A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101135166A (en) Blasting pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101130968A (en) Pile-forming method for two-level expanding bottom prefabricated pile body
CN101135160A (en) Mixed pile forming method for high-bearing one-stage club-footed pile
CN101130966A (en) Pile-forming method for two-level expanding bottom prefabricated pile body
CN101397785A (en) Pile-forming method of immersed tube pile
CN101135153A (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135143A (en) Extrusion pile forming method for three-stage bottom expanding prefabricated and cast-in-situs steel concrete composite pile body
CN101135146A (en) Pile forming method for high-bearing multi-stage club-footed pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080507