CN100580187C - Pile forming method for one-stage bottom expanding steel pipe composite pile body - Google Patents

Pile forming method for one-stage bottom expanding steel pipe composite pile body Download PDF

Info

Publication number
CN100580187C
CN100580187C CN200710157283A CN200710157283A CN100580187C CN 100580187 C CN100580187 C CN 100580187C CN 200710157283 A CN200710157283 A CN 200710157283A CN 200710157283 A CN200710157283 A CN 200710157283A CN 100580187 C CN100580187 C CN 100580187C
Authority
CN
China
Prior art keywords
immersed tube
steel pipe
expanding
pile
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200710157283A
Other languages
Chinese (zh)
Other versions
CN101135164A (en
Inventor
童乐天
王国奋
吴伟林
陈宁华
王茂华
郑新俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Construction Engineering Group No2 Construction Engineering Co Ltd
Original Assignee
童乐天
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 童乐天 filed Critical 童乐天
Priority to CN200710157283A priority Critical patent/CN100580187C/en
Publication of CN101135164A publication Critical patent/CN101135164A/en
Application granted granted Critical
Publication of CN100580187C publication Critical patent/CN100580187C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to construction of building pile foundation engineering, and is especially piling process of one-stage under-reamed composite steel pipe pile. The piling process includes the following steps: 1. erecting prefabricated reinforced concrete immersed pile head on ground; 2. pressing immersed tube onto the reinforced concrete pile head; 3. immersing the immersed tube into hardpan to design elevation; 4. drawing upwards the immersed tube to designed distance; 5. forming lower base space and taking out soil; 6. setting steel dowels; and 6. pouring concrete into the immersed tube until reaching the ground level to form the composite steel pipe pile stem. The pile has the ratio between the base diameter and the pile stem diameter as great as 5-6, deduction coefficient up to 0.9-1.0, high material strength utilizing rate, great bearing capacity and other advantages.

Description

The piling method of one-stage bottom expanding steel pipe composite pile body
Technical field
The present invention relates to the piling method of a kind of construction of building pile foundation engineering, particularly a kind of one-stage bottom expanding steel pipe composite pile body.
Background technology
According to the national regulation whole body be cast-in-place (be the pile body Cast-in-place concrete, base also is a Cast-in-place concrete) its base diameter ratio maximum value of expanded bore pile is limited in 3-3.5, and pipe sinking prefabricated steel concrete club-footed pile, this stake is the prefabricated concrete of pile body, the base Cast-in-place concrete, obviously this ratio 3-3.5 is broken, generally 3.5-5 can be reached,, requirement of engineering can't be satisfied although bearing capacity is bigger, particularly, the opposite end bearing capacity to give a discount 0.9 when bellout diameter during greater than 1.5 meters.For this reason, immersed tube prefabricated multistage under-reamed pile has appearred again.Existing multiple bearing capacity dish stake technology has two common ground, and first all is to expand the end with positive crossover-circulating type method pore-forming; Second all carries out pile without immersed tube expands the end.This two point-to-points load dish (at the bottom of the multistage expansion) stake is quite unfavorable, in other words, bring two problems, 1), national building code requirement, expand the base end load at the end with positive crossover-circulating type method pile and will take advantage of 0.45 coefficient, because have mud existence and pile bottom sediment to clean out, (Zhejiang Province's standard is 0.24 discount) gives a discount too big, though a plurality of bases are arranged, loss end load is very big; 2); without immersed tube; condition of construction can not get protection; positive in addition crossover-circulating type method is operation under water; expand bottom application worker situation and cannot see, the difficult measurement noted down, when also usually taking place to expand the end under water; top soil body a slice situation that falls down also happens occasionally; also have because the multistage stake of prior art all is the whole body Cast-in-place concrete, and that the intensity of Cast-in-place concrete is done is not high, and difficult quality guarantee; and in water, water concrete; the difficult control of quality adds that the pile capacity of a plurality of bases is all bigger, and its pile body diameter of above factor must be done greatlyyer; and this a plurality of base is afraid of that pile body diameter is big most; development test shows that pile body diameter increases, and its bearing capacity decay is very serious.
Summary of the invention
The present invention is directed to problem that prior art exists, a kind of piling method of one-stage bottom expanding steel pipe composite pile body, purpose are provided is to make base diameter and pile body diameter ratio is bigger, security reliability is high, and single pile bearing capacity is big, the piling method advantages of simple.
The piling method of one-stage bottom expanding steel pipe composite pile body comprises following processing step: a, vertically stands on the precast reinforced concrete pile crown on the ground standby; B, immersed tube are contained on the precast reinforced concrete pile crown; C, immersed tube sink to hardpan to design elevation; D, on pull out immersed tube to setpoint distance H; E, expand base space down, get clean hack with the processing of mechanical bottom-expanding equipment; F, put down joint bar; G, form steel pipe composite pile body from immersed tube mouth perfusion concrete to ground level.
Expanding base space down with mechanical bottom-expanding equipment processing among the described operation e can be replaced by positive crossover-circulating type method.
Setpoint distance H among the described operation d is 0.6-1.0 a times of base diameter.
The mechanical bottom-expanding equipment expansion of usefulness among described operation e end processing base space concrete steps are as follows: the mark that the detent rail pin of bottom-expanding equipment is aimed on the immersed tube mouth is lowered to immersed tube, start equipment after the equipment upper end is also fixedly positioning and expand the end, expand the end and be vertical earlier expand the end again level expand the end, when reaching, construction stops automatically after design is marked deeply, base cavity pocket is formed on the bottom, expanding the work of undercutting sharpener this moment reaches when designing base diameter, be that power rail reaches predetermined number of revolutions, expand end shoveling and finish, bottom-expanding equipment is hung out ground.
The concrete steps of getting clean hack among the above-mentioned operation e are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
The present invention compared with prior art, owing to do protection and support with immersed tube, and steel concrete pile crown and trustship are not taken out, be that immersed tube is again the steel pipe of steel pipe composite pile body and base and pile body poured into technical measures such as fuse together, and have base diameter and the bigger 5-6 of reaching of pile body diameter ratio through evidence, the supporting capacity of single pile obviously improves, the reliable degree height, and reduction coefficient can reach the advantages such as utilization rate that 0.9-1.0 makes full use of the strength of materials; The one-level expanded bore pile that while the inventive method is made reaches the Expected Results of design.
Description of drawings
Fig. 1 a-1e is the view of master operation construction of the present invention.
Among the figure 1, the precast reinforced concrete pile crown; 2, immersed tube; H is the 0.6-1.0 of base diameter; 3, base space; 4, joint bar.
The specific embodiment
Embodiments of the invention are described in detail in conjunction with the accompanying drawings.
As shown in the figure, the piling method of one-stage bottom expanding steel pipe composite pile body of the present invention comprises following processing step: a, vertically stands on precast reinforced concrete pile crown 1 on the ground standby; B, immersed tube 2 are contained on the precast reinforced concrete pile crown 1; C, immersed tube 2 sink to hardpan to design elevation; D, on pull out immersed tube 2 to setpoint distance H, the 0.6-1.0 that its H value is a base diameter is doubly; E, with a kind of processing base space 3 in mechanical bottom-expanding equipment or the positive crossover-circulating type method, get the interior hack of clean base space 3 with the suction indigenous equipment; F, put down joint bar 4 into; G, form steel pipe composite pile body from 2 mouthfuls of immersed tube perfusion concrete to ground level.
The mechanical bottom-expanding equipment expansion of usefulness among described operation e end processing base space concrete steps are as follows: the mark that the detent rail pin of bottom-expanding equipment is aimed on the immersed tube mouth is lowered to immersed tube, start equipment after the equipment upper end is also fixedly positioning and expand the end, expand the end and be vertical earlier expand the end again level expand the end, when reaching, construction stops automatically after design is marked deeply, base cavity pocket is formed on the bottom, expanding the work of undercutting sharpener this moment reaches when designing base diameter, be that power rail reaches predetermined number of revolutions, expand end shoveling and finish, bottom-expanding equipment is hung out ground.
The concrete steps of getting clean hack among the above-mentioned operation e are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
The inventive method, owing to will descend joint bar 4 to extend upwardly to more than the hardpan from base, and do not extract immersed tube 2 with base, pile body casting complete together, good integrity, form steel pipe composite pile body, so bearing capacity is done more, the reliable degree height constitutes a kind of new structure form of immersed tube prefabricated one-level expanded bore pile.

Claims (5)

1, the piling method of one-stage bottom expanding steel pipe composite pile body is characterized in that comprising following processing step: a, vertically stands on the precast reinforced concrete pile crown on the ground standby; B, immersed tube are contained on the precast reinforced concrete pile crown; C, immersed tube sink to hardpan to design elevation; D, on pull out immersed tube to setpoint distance H; E, expand base space down, get clean hack with the processing of mechanical bottom-expanding equipment; F, put down joint bar; G, form steel pipe composite pile body from immersed tube mouth perfusion concrete to ground level.
2, the piling method of one-stage bottom expanding steel pipe composite pile body according to claim 1 is characterized in that expanding base space down with mechanical bottom-expanding equipment processing among the described operation e can be replaced by positive crossover-circulating type method.
3, the piling method of one-stage bottom expanding steel pipe composite pile body according to claim 1, it is characterized in that setpoint distance H among the described operation d be base diameter 0.6-1.0 doubly.
4, the piling method of one-stage bottom expanding steel pipe composite pile body according to claim 1, it is characterized in that the mechanical bottom-expanding equipment expansion of the usefulness end processing base space concrete steps among the described operation e are as follows: the mark that the detent rail pin of bottom-expanding equipment is aimed on the immersed tube mouth is lowered to immersed tube, start equipment after the equipment upper end is also fixedly positioning and expand the end, expand the end and be vertical earlier expand the end again level expand the end, when reaching, construction stops automatically after design is marked deeply, base cavity pocket is formed on the bottom, expanding the work of undercutting sharpener this moment reaches when designing base diameter, be that power rail reaches predetermined number of revolutions, expand end shoveling and finish, bottom-expanding equipment is hung out ground.
5, the piling method of one-stage bottom expanding steel pipe composite pile body according to claim 1, the concrete steps that it is characterized in that getting among the described operation e clean hack are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
CN200710157283A 2007-09-29 2007-09-29 Pile forming method for one-stage bottom expanding steel pipe composite pile body Expired - Fee Related CN100580187C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710157283A CN100580187C (en) 2007-09-29 2007-09-29 Pile forming method for one-stage bottom expanding steel pipe composite pile body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710157283A CN100580187C (en) 2007-09-29 2007-09-29 Pile forming method for one-stage bottom expanding steel pipe composite pile body

Publications (2)

Publication Number Publication Date
CN101135164A CN101135164A (en) 2008-03-05
CN100580187C true CN100580187C (en) 2010-01-13

Family

ID=39159472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710157283A Expired - Fee Related CN100580187C (en) 2007-09-29 2007-09-29 Pile forming method for one-stage bottom expanding steel pipe composite pile body

Country Status (1)

Country Link
CN (1) CN100580187C (en)

Also Published As

Publication number Publication date
CN101135164A (en) 2008-03-05

Similar Documents

Publication Publication Date Title
CN100580187C (en) Pile forming method for one-stage bottom expanding steel pipe composite pile body
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135161A (en) Mixed pile forming method for one-stage bottom expanding steel pipe composite pile body
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101135158A (en) Mechanical pile forming method for high-bearing multi-stage club-footed pile
CN101135145A (en) Pile forming method for high-bearing one-stage club-footed pile
CN101135168A (en) Extrusion pile forming method for one-stage bottom expanding steel pipe composite pile body
CN101173513A (en) Mechanical piling method for third level bottom-expanded combined pile body
CN101135165A (en) Extrusion pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101135160A (en) Mixed pile forming method for high-bearing one-stage club-footed pile
CN101130979A (en) Blasting pile-forming method for primary expanding bottom steel pipe compound pile body
CN101130968A (en) Pile-forming method for two-level expanding bottom prefabricated pile body
CN101135143A (en) Extrusion pile forming method for three-stage bottom expanding prefabricated and cast-in-situs steel concrete composite pile body
CN101130966A (en) Pile-forming method for two-level expanding bottom prefabricated pile body
CN101397785A (en) Pile-forming method of immersed tube pile
CN101130965A (en) Pile-forming method for three-level expanding bottom combined pile body
CN101135146A (en) Pile forming method for high-bearing multi-stage club-footed pile
CN101130973A (en) Pile-forming method for three-level expanding bottom pile body combined by prefabricated and cast-in-situ steel concrete
CN101397781A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101135150A (en) Mixed pile forming method for high-bearing prefabricated and cast-in-situs steel concrete composite pile body
CN101130967A (en) Pile-forming method for two-level expanding bottom pile of immersed tube
CN101397783A (en) Pile-forming method of belled prefabricated pile body
CN101135153A (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101397787A (en) Mixed pile-forming method of prefabricated pile body

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GCEGL NO.2 CONSTRUCTION ENGINGEERING CO.,LTD OF GU

Free format text: FORMER OWNER: TONG YUETIAN

Effective date: 20110126

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 315040 JIANGDONG NEW SKY ELECTRONICS CO., LTD., JIANGDONG DISTRICT, NINGBO CITY, ZHEJIANG PROVINCE TO: 530022 NO. 29, XINZHU ROAD, QINGXIU DISTRICT, NANNING CITY, GUANGXI ZHUANG AUTONOMOUS REGION

TR01 Transfer of patent right

Effective date of registration: 20110126

Address after: 530022 the Guangxi Zhuang Autonomous Region Nanning Qingxiu District Hsinchu Road No. 29

Patentee after: Guangxi Construction Engineering Group No.2 Construction Engineering Co., Ltd.

Address before: 315040 Jiangdong Xintian Electronics Co., Ltd., Jiangdong District, Zhejiang, Ningbo

Patentee before: Tong Letian