CN101397791A - Pile-forming method of belled pile - Google Patents

Pile-forming method of belled pile Download PDF

Info

Publication number
CN101397791A
CN101397791A CNA200710157285XA CN200710157285A CN101397791A CN 101397791 A CN101397791 A CN 101397791A CN A200710157285X A CNA200710157285X A CN A200710157285XA CN 200710157285 A CN200710157285 A CN 200710157285A CN 101397791 A CN101397791 A CN 101397791A
Authority
CN
China
Prior art keywords
pile
immersed tube
base
extrusion equipment
expanded bore
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA200710157285XA
Other languages
Chinese (zh)
Inventor
王国奋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA200710157285XA priority Critical patent/CN101397791A/en
Publication of CN101397791A publication Critical patent/CN101397791A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a construction method for building pile foundation engineering, in particular to a pile forming method of a two-stage enlarged-base pile. The pile forming method of the two-stage enlarged-base pile of the invention comprises the following process steps: a. an immersed tube with a metal pile head is sunk to a hard soil layer for designing elevation; b. the metal pile head is drawn out; c. a lower base space is formed by extrusion equipment, and all fine earth is thoroughly taken out; d. the immersed tube is pulled upward by a height H; e. an upper base space is formed by the extrusion equipment and all fine earth is taken out; f. steel bars are put into from an opening of the immersed tube; g. flowing concrete is poured; h. a recast pile body with dowels are put into from the opening of the immersed tube and anchored with the steel bars; and i. the immersed tube is pulled out, and concrete slurry is injected into the gap for forming pile. The construction method has the advantages and effects that the pile body diameter is small, and the bearing capacity can be designed very large, and the quality can be ensured through inspection, thus being applicable to the multi-base large-bearing-capacity pile.

Description

The piling method of expanded bore pile
Technical field
The present invention relates to the piling method of the secondary expanded bore pile of a kind of construction of building pile foundation engineering, particularly a kind of expanded bore pile.
Background technology
According to the national regulation whole body is cast-in-place expanded bore pile, i.e. pile body Cast-in-place concrete, and base also is a Cast-in-place concrete, its base diameter ratio maximum value is limited in 3-3.5, and pipe sinking prefabricated steel concrete club-footed pile, this stake is the prefabricated concrete of pile body, the base Cast-in-place concrete, obviously this ratio 3-3.5 is broken, generally 3.5-5 can be reached,, requirement of engineering can't be satisfied although bearing capacity is bigger, particularly, the opposite end bearing capacity to give a discount 0.9 when bellout diameter during greater than 1.5 meters.For this reason, immersed tube prefabricated multistage under-reamed pile has appearred again.Existing multiple bearing capacity dish stake technology has two common ground, and first all is to expand the end with positive crossover-circulating type method pore-forming; Second all carries out pile without immersed tube expands the end.This two point-to-points load dish (at the bottom of the multistage expansion) stake is quite unfavorable, in other words, bring two problems, 1), national building code requirement, expand the base end load at the end with positive crossover-circulating type method pile and will take advantage of 0.45 coefficient, because have mud to exist and pile bottom sediment can't be cleaned out, and Zhejiang Province's standard is 0.24 discount, it is too big to give a discount, though a plurality of bases are arranged, loss end bearing capacity is very big; 2); without immersed tube; condition of construction can not get protection; positive in addition crossover-circulating type method is operation under water; expand bottom application worker situation and cannot see, the difficult measurement noted down, when also usually taking place to expand the end under water; top soil body a slice situation that falls down also happens occasionally; also have because the multistage stake of prior art all is the whole body Cast-in-place concrete, and that the intensity of Cast-in-place concrete is done is not high, and difficult quality guarantee; and in water, water concrete; the difficult control of quality adds that the pile capacity of a plurality of bases is all bigger, and its pile body diameter of above factor must be done greatlyyer; and this a plurality of base is afraid of that pile body diameter is big most; development test shows that pile body diameter increases, and its bearing capacity decay is very serious.
Summary of the invention
The problem that the present invention is directed to the prior art existence provides a kind of piling method of expanded bore pile, purpose be process rationally, guarantee pile quality, give full play to the utilization rate of the strength of materials, make bearing capacity of single pile higher, all the time be in work under the most economical state, reduction coefficient reaches 0.9-1.0, obviously improves the cost performance of stake, reaches the Expected Results of design.
Piling method of the present invention comprises following processing step:
A, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, expand the end with extrusion equipment and form lower base space, and get clean hack; D, pulling out the H distance on the immersed tube; E, expand the end with extrusion equipment and form upper base space, get clean hack; F, put into reinforcing bar from the immersed tube mouth; G, the mobile concrete of perfusion; H, put into precast pile, and dock with reinforcing bar with joint bar from the immersed tube mouth; I, extract immersed tube, and between the slit, inject cement paste, pile.
The concrete steps of getting clean hack among described operation c and the e are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
Extrusion equipment among described operation c and the e is that hydraulic pressure props up disc shaping machine.
The 2-10 that pulls out distance H on the immersed tube among the described operation d and be base diameter doubly.
Also be included among the described operation e between two Up/down bases and extrude the triangle space that is the cross setting with extrusion equipment.
Described extrusion equipment is that hydraulic pressure props up disc shaping machine.
Compared with prior art owing to do protection and rely on immersed tube, precision, degree of safety, quality that the end is expanded in construction all improve greatly in the present invention, the more important thing is it can direct visual record see below whole work progresss; Because immersed tube prefabricated multistage under-reamed pile has adopted precast pile, steel pipe pile body and prefabricated pile body of answering in advance, these pile body diameters are little, and it is very big that bearing capacity can be done, and quality can be checked and guarantee, adapts to very much the large bearing capacity pile that a plurality of bases are arranged and uses.It is little to meet multistage under-reamed pile requirement pile body diameter fully, and bearing capacity is big, the requirement that quality requirement is high.In addition, in environmental protection, energy-conservation all significantly better than prior art.
Description of drawings
Fig. 1 a-1i is each operation status of processes schematic diagram of the present invention.
Among the figure 1, metal pile head; 2, immersed tube; H is 2-10 a times of base diameter; 4, lower bottom base; 5, be the crosswise triangle space; 6, reinforcing bar; 7, upper bed-plate; 8, precast pile; 9, joint bar.
The specific embodiment
Embodiments of the invention 1a-1i in conjunction with the accompanying drawings are described in detail.
The piling method of expanded bore pile of the present invention comprises following processing step:
A, as shown in Figure 1a sinks to the hardpan design elevation to the immersed tube 2 that has metal pile head 1; B, shown in Fig. 1 b, take out metal pile head; C, shown in Fig. 1 c, prop up disc shaping machine with hydraulic pressure and expand the end and form upper base space 4, inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth; D, shown in Fig. 1 d, pulling out the H distance on the immersed tube 2, its H be base diameter 2-10 doubly; E, shown in Fig. 1 e, prop up disc shaping machine with hydraulic pressure and expand end formation upper bed-plate 7, inhaling indigenous equipment with air fetches earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth, and props up the disc shaping machine extruding at the position between two bases 4,7 up and down with YEJ800 type hydraulic pressure and overlook and be triangle space 5 that crosswise is provided with the frictional resistance between increase pile body and the hardpan; F, shown in Fig. 1 f, put into reinforcing bar 6 from the immersed tube mouth; G, shown in Fig. 1 g, the perfusion concrete that flows; H, shown in Fig. 1 h, put into the precast pile 8 that has joint bar 9, and dock with reinforcing bar 6 from the immersed tube mouth; I, shown in Fig. 1 i, extract immersed tube, in pile body and mud layer slit, inject cement paste or after the inwall of immersed tube injects cement paste, extract immersed tube again, pile.

Claims (6)

1, the piling method of expanded bore pile is characterized in that comprising the steps: a, the immersed tube that has metal pile head is sunk to the hardpan design elevation; B, taking-up metal pile head; C, expand the end with extrusion equipment and form lower base space, and get clean hack; D, pulling out the H distance on the immersed tube; E, expand the end with extrusion equipment and form upper base space, get clean hack; F, put into reinforcing bar from the immersed tube mouth; G, the mobile concrete of perfusion; H, put into precast pile, and dock with reinforcing bar with joint bar from the immersed tube mouth; I, extract immersed tube, and between the slit, inject cement paste, pile.
2, the piling method of expanded bore pile according to claim 1, the concrete steps that it is characterized in that getting among described operation c and the e clean hack are as follows: inhale indigenous equipment with air and fetch earth, when only surplus a small amount of loosing during soil in the base, from immersed tube mouth pouring, pouring limit, limit sops up, and is clean up to fetching earth.
3, the piling method of expanded bore pile according to claim 1 is characterized in that the extrusion equipment among described operation c and the e is that hydraulic pressure props up disc shaping machine.
4, the piling method of expanded bore pile according to claim 1, the 2-10 that it is characterized in that pulling out on the immersed tube among the described operation d distance H and be base diameter doubly.
5, the piling method of expanded bore pile according to claim 1 is characterized in that also being included among the described operation e triangle space that is the cross setting between two Up/down bases with the extrusion equipment extrusion.
6, the piling method of expanded bore pile according to claim 5 is characterized in that described extrusion equipment is that hydraulic pressure props up disc shaping machine.
CNA200710157285XA 2007-09-29 2007-09-29 Pile-forming method of belled pile Pending CN101397791A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA200710157285XA CN101397791A (en) 2007-09-29 2007-09-29 Pile-forming method of belled pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA200710157285XA CN101397791A (en) 2007-09-29 2007-09-29 Pile-forming method of belled pile

Publications (1)

Publication Number Publication Date
CN101397791A true CN101397791A (en) 2009-04-01

Family

ID=40516615

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA200710157285XA Pending CN101397791A (en) 2007-09-29 2007-09-29 Pile-forming method of belled pile

Country Status (1)

Country Link
CN (1) CN101397791A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064336A (en) * 2015-08-07 2015-11-18 中国铁建大桥工程局集团有限公司 Hole forming construction method for three-section type pedestal pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064336A (en) * 2015-08-07 2015-11-18 中国铁建大桥工程局集团有限公司 Hole forming construction method for three-section type pedestal pile

Similar Documents

Publication Publication Date Title
CN101397791A (en) Pile-forming method of belled pile
CN101397795A (en) Pile-forming method of belled pile with high bearing ability
CN101397792A (en) Pile-forming method
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101135144A (en) Pile forming method for two-stage club-footed pile
CN101135165A (en) Extrusion pile forming method for high-bearing three-stage bottom expanding composite pile body
CN101397789A (en) Extrusion pile-forming method of belled prefabricated pile body
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101397781A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101397783A (en) Pile-forming method of belled prefabricated pile body
CN101135147A (en) Blasting pile forming method for three-stage bottom expanding composite pile body
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101397784A (en) Pile-forming method of immersed tube belled pile
CN101126236A (en) Blasting pile-forming method for multi-stage club-footed pile
CN101135148A (en) Extrusion pile forming method for three-grade bottom expanding steel pipe composite pile body
CN101173513A (en) Mechanical piling method for third level bottom-expanded combined pile body
CN101135160A (en) Mixed pile forming method for high-bearing one-stage club-footed pile
CN101135143A (en) Extrusion pile forming method for three-stage bottom expanding prefabricated and cast-in-situs steel concrete composite pile body
CN101397787A (en) Mixed pile-forming method of prefabricated pile body
CN101397782A (en) Extrusion pile-forming method of belled prefabricated pile body with high bearing ability
CN101397785A (en) Pile-forming method of immersed tube pile
CN101135158A (en) Mechanical pile forming method for high-bearing multi-stage club-footed pile
CN101130959A (en) Extruding pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN101130960A (en) Extruding pile-forming method for multilevel expanding bottom pile
CN101135167A (en) Mechanical pile forming method for two-stage bottom expanding prefabricated pile body

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090401