CN101294369B - Method and device for hanging and transferring bracket of movable mould frame - Google Patents
Method and device for hanging and transferring bracket of movable mould frame Download PDFInfo
- Publication number
- CN101294369B CN101294369B CN200810047798XA CN200810047798A CN101294369B CN 101294369 B CN101294369 B CN 101294369B CN 200810047798X A CN200810047798X A CN 200810047798XA CN 200810047798 A CN200810047798 A CN 200810047798A CN 101294369 B CN101294369 B CN 101294369B
- Authority
- CN
- China
- Prior art keywords
- pole
- bracket
- guide
- main
- shoulder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明属于桥梁施工时的移动模架托架技术,具体涉及一种适于不需大型起重设备的移动模架托架吊挂转运技术。The invention belongs to the mobile formwork bracket technology during bridge construction, and in particular relates to a mobile formwork bracket hanging transfer technology suitable for no need of large lifting equipment.
背景技术Background technique
移动模架是一种自带模板、利用纵梁承重、对混凝土桥梁进行现场浇筑的施工机械。该技术于50年代起源于西欧,现已推广于全世界。因为移动模架建桥方法与以往的建桥方法相比有诸多优势,现已成为最主要的建桥方法之一。移动模架的支撑形式有:支撑在桥面上、支撑在承台上、支撑在墩身(均为重力式墩)上。由于移动模架的托架在移动时需要大型起重设备来实现,而对于高度较大的轻型独柱式墩,特别是在山区丘陵地带,由于施工场地的限制,不能使用大型起重设备,因此目前对于高度较大的轻型独柱式墩还没有办法采用移动模架施工。The mobile formwork is a construction machine with its own formwork, which uses longitudinal beams to bear the load and cast concrete bridges on site. This technology originated in Western Europe in the 1950s and has now been promoted all over the world. Because the mobile formwork bridge construction method has many advantages compared with the previous bridge construction methods, it has become one of the most important bridge construction methods. The supporting forms of the mobile formwork include: supporting on the bridge deck, supporting on the cap, and supporting on the pier body (both are gravity piers). Because the bracket of the mobile formwork needs large-scale lifting equipment to realize when moving, and for the light single-column pier with a large height, especially in mountainous and hilly areas, due to the limitation of the construction site, large-scale lifting equipment cannot be used. Therefore, there is no way to adopt mobile formwork construction for the larger light-duty single-column pier at present.
发明内容Contents of the invention
本发明提供一种能适于高度较大的轻型独柱式墩上使用的移动模架托架吊挂装置及移动模架托架吊挂转运方法,以使移动模架在高度较大的轻型独柱式墩桥梁中也能使用。The invention provides a mobile formwork bracket hanging device and a method for hanging and transporting the mobile formwork bracket that are suitable for use on a light single-column pier with a large height, so that the mobile formwork can It can also be used in bridges with single-column piers.
解决本发明移动模架托架吊挂装置的技术方案为:它包括与主梁连接的导梁,导梁和主梁上沿梁的纵向设导轨,导轨上设可沿导轨移动的吊具,导梁上设扁担梁,扁担梁上连接用于托架吊装装置。The technical scheme to solve the mobile formwork bracket hanging device of the present invention is: it comprises a guide beam connected with the main girder, a guide rail is arranged on the guide beam and the main girder along the longitudinal direction of the beam, a hanger movable along the guide rail is arranged on the guide rail, and the guide girder A shoulder pole beam is arranged on it, and the shoulder pole beam is connected with a bracket hoisting device.
所述扁担梁包括导梁下弦设的可横向伸缩折叠的下扁担梁,导梁上弦设的上扁担梁,上扁担梁与下扁担梁一侧或两侧之间连接倒链。The shoulder pole beam includes a horizontally telescopic and foldable lower pole beam arranged on the lower chord of the guide beam, an upper pole beam arranged on the upper chord of the guide beam, and an inverted chain is connected between one side or both sides of the upper pole beam and the lower pole beam.
解决本发明移动模架托架吊挂转运的技术方案为:它是利用导梁上的扁担梁将可拆式托架主梁从一个桥墩柱上分离,再将分离后的可拆装式托架主梁转置到导梁上的吊具上;吊具沿导梁将可拆装式托架主梁运至下一个桥墩柱处,将可拆式托架主梁转置到该处导梁上的扁担梁,再利用扁担梁的吊挂将可拆装式托架主梁安装在该桥墩柱上。The technical solution to solve the hanging and transshipment of the mobile formwork bracket of the present invention is: it uses the pole beam on the guide beam to separate the main beam of the detachable bracket from a pier column, and then separates the detachable bracket after separation. The main girder of the frame is transposed to the spreader on the guide beam; The pole beam on the beam, and then the detachable bracket main beam is installed on the pier column by hanging the pole beam.
本发明采用在与主梁连接的导梁上设置用于托架吊挂的扁担梁,其结构简单,操作方便,构思巧妙,很好的解决了在没有大型起重设备情况下托架的拆装、吊挂和转运的问题,从而在高度较大的轻型独柱式墩桥梁建造中使用移动模架技术。对山区丘陵地带非常适用,还可减少经济投入。The present invention adopts the pole beam used for hanging the bracket on the guide beam connected with the main beam, which has simple structure, convenient operation and ingenious conception, and solves the problem of dismantling the bracket without large-scale lifting equipment. Therefore, the mobile formwork technology is used in the construction of light single-column pier bridges with large heights. It is very suitable for mountain and hilly areas, and can also reduce economic investment.
附图说明Description of drawings
图1移动模架系统示意图。Figure 1 Schematic diagram of the mobile formwork system.
图2移动模架中托架示意图。Figure 2 is a schematic diagram of the bracket in the mobile formwork.
图3托架结构俯视示意图。Figure 3 is a schematic top view of the bracket structure.
图4导梁上的扁担梁与托架结构示意图。Figure 4 is a schematic diagram of the structure of the pole beam and the bracket on the guide beam.
图5导梁导轨示意图。Figure 5 Schematic diagram of guide beam guide rail.
图6导梁上的扁担梁结构示意图。Figure 6 is a schematic diagram of the structure of the pole beam on the guide beam.
图7~图16本发明托架装拆转运步骤示意图。Figures 7 to 16 are schematic diagrams of the steps of assembly, disassembly and transfer of the bracket of the present invention.
具体实施方式Detailed ways
如图1所示,移动模架系统包括与桥梁墩柱500连接的托架系统100、桥梁墩柱500上设的主梁移动系统200(包括移动平台及横移千斤顶)、主梁移动系统200上支撑的主梁300、与主梁300两端连接的前导梁400和后导梁401、模架支承系统、模板以及主梁后吊挂设施(图中未示)等。主梁500是由钢板焊接而成的钢箱梁结构,前导梁400和后导梁401是由型钢焊接而成的桁架式结构。托架系统100主要起支承调整主梁标高和横移分离移动模架系统以及移动模架系统纵向移动过孔的作用。托架101是移动模架的重要支撑系统。上述移动模架系统与现有的移动模架托架技术相同,具体结构不再此累述。As shown in Figure 1, the mobile formwork system includes a
如图2所示,托架系统100包括托架101,托架101通过牛腿与桥梁墩柱500连接,托架101上设吊点112,吊点112由连接杆113(螺纹钢筋)与桥梁墩柱500上部预埋的型钢120连接。托架系统两端设外接平台119。托架系统通过牛腿102、103、104、105与桥墩柱500连接如图3所示,托架101包括相互连接的托架主梁106、107和相互连接的托架主梁108、109;托架主梁106、107端部设牛腿102、103伸入桥梁墩柱500一侧的孔中;托架主梁108、109的端部设牛腿104、105伸入桥梁墩柱500另一侧的孔中。托架主梁106与托架主梁108之间可拆卸地连接拉杆110、111;托架主梁107与托架主梁109之间可拆卸地连接拉杆110、111;这样构成可拆卸的托架系统。托架主梁106、107、108、109上开设吊孔119。托架主梁106和107之间,托架主梁108和109之间由对接连接头118连接,对接连接头118包括连接板和销轴122。As shown in Figure 2, the
如图4所示,所述导梁是后导梁401上设扁担梁600,扁担梁600在吊挂转运时可以通过设在扁担梁600上的托架吊装装置,这里托架吊装装置是5t电动葫芦与托架主梁106、107、108、109连接。导梁和主梁上沿梁的纵向设导轨,导轨上设可沿导轨移动的吊具。本实施例中,在沿前导梁400、后导梁401和主梁300侧面纵向用型钢焊接成三角形架402,三角形架402顶面上设有导轨421,导轨421上设电动葫芦416,如图5所示。As shown in Figure 4, the guide beam is that the
本实施例以后导梁上的扁担梁进行说明;前导梁上的扁担梁结构与后导梁上的结构相同;扁担梁设在桥梁墩柱处。如图6所示,后导梁401的上弦上设上扁担梁615;上扁担梁615上设卡柱601,卡柱601之间形成卡口602与导梁上弦横向定位,即上扁担梁615通过卡口602卡在后导梁的上弦梁上;这样保证上扁担梁615横向的限位,同时也不妨碍上扁担梁615作纵向的小移动。In this embodiment, the pole beam on the rear guide beam will be described; the structure of the pole beam on the front guide beam is the same as that on the rear guide beam; the pole beam is arranged at the bridge pier. As shown in Figure 6, an
后导梁401的下弦上设下扁担梁614,下扁担梁614可以可横向伸缩折叠。下扁担梁614实现横向伸缩折叠可有多种结构形式,如多节梁构成的横向伸缩结构(如同伸缩杆的结构),如多节梁构成的旋转折叠结构,本实施例采用多节梁构成的旋转折叠结构。上扁担梁615与下扁担梁614之间连接倒链617。A
如图6所示;下扁担梁614包括扁担主梁603,扁担主梁603两端设的扁担附梁604。扁担主梁603设在导梁的下弦梁403上,扁担主梁603和下弦梁403之间连接U型卡610,U型卡起临时固定作用,限制扁担主梁603的纵向移动。扁担主梁603与扁担附梁604之间以销轴连接可实现扁担附梁604的转动折叠,5电动葫芦吊挂在扁担附梁604上。具体的,扁担主梁603上下连接固定板605,扁担附梁604设在两固定板605之间,固定板605与扁担附梁604之间连接销轴606,这里为了增加固定板605与扁担附梁604连接强度,固定板605与扁担附梁604之间连接2个销轴606。在进行旋转折叠时抽出一个销轴。在吊挂托架时,扁担主梁603与扁担附梁604之间还设有横向连接定位装置包括连接定位板607,连接定位板607与扁担附梁之间连接螺栓608,连接定位板607与扁担主梁之间连接螺栓608。As shown in FIG. 6 ; the lower
在托架吊挂转运时,When the bracket is hung and transferred,
如图7所示:As shown in Figure 7:
将墩处的托架拆装下扁担梁614打开(展开连接成如图6的连接状态);并将上扁担梁615与下扁担梁614用5t倒链拉紧;同时将前后导梁与墩柱间抄死;Disassemble the bracket at the pier and open the lower pole beam 614 (expand and connect to the connection state as shown in Figure 6); and tighten the
将托架按四片托架主梁106、107、108、109分别吊挂在下扁担梁614上,拆除吊挂精轧螺纹钢筋即连接杆113;Hang the bracket on the
把横移外接平台拆除,捆绑在托架主梁上。Remove the laterally moving external platform and bind it to the main beam of the bracket.
如图8所示As shown in Figure 8
将托架主梁对接处的销轴及螺栓拆掉;Remove the pins and bolts at the joint of the main beam of the bracket;
然后按顺序拆除可拆卸地连接拉杆110、111即对拉筋、倒链、斜撑杆,并将拆除的杆件分开捆绑在托架主梁上;Then remove the detachably
最后拆除连接托架主梁106、107的连接销轴,拆除连接托架主梁108、109的连接销轴;Finally, remove the connecting pin shafts of the connecting bracket
上扁担梁615、下扁担梁614在后导梁上同步向前移动。将托架主梁106、107缓慢同步向前拉出孔洞。The
如图9、10所示As shown in Figure 9 and 10
托架主梁106、107分别向外拉开;
然后用托架吊装装置5t电动葫芦将托架主梁106、107分别吊起,并移动至电动葫芦416下,起吊系统转换。Then
如图11所示(参照图15)As shown in Figure 11 (refer to Figure 15)
1、将下扁担梁614外侧端向内旋收拢(即内旋折叠);1. Fold the outer end of the
2、然后用5t电动葫芦将托架主梁106、107提升,高出托架主梁108、109,同时托架主梁106、107向外旋转90度。2. Then use a 5t electric hoist to lift the bracket
3、用5t电动葫芦416将托架主梁106、107运往下一个墩柱502。3. Use a 5t electric hoist 416 to transport the
如图12所示(参照图17)As shown in Figure 12 (refer to Figure 17)
将托架主梁106、107吊至下一个墩墩柱502的前方;同时下放吊至预留孔洞501位置;Lift the bracket
然后将托架主梁106、107向内旋转90度。The carrier beams 106, 107 are then rotated 90 degrees inwardly.
如图13、14所示(参照图19、20)As shown in Figures 13 and 14 (refer to Figures 19 and 20)
将墩502处的扁担梁展开连接成如图6的连接状态;Expand and connect the pole beam at the
然后将托架主梁106、107转换到下扁担梁614上,并收紧,电动葫芦416松卸载。Then the bracket
托架主梁106、107在下扁担梁614上如图缓慢横向向墩柱方向移动。The bracket
如图15、16所示(参照图21、22)As shown in Figure 15 and 16 (refer to Figure 21 and 22)
托架主梁106、107对齐合拢后,连同下扁担梁614、上扁担梁615在前导梁上纵向向墩柱方向缓慢移动;After the
将牛腿102、103插入墩柱预留孔洞501中,并塞紧;Insert the
同时把电动葫芦416退回到墩500处。At the same time, the electric hoist 416 is returned to the
再将托架主梁108、109按上述方法从墩柱500转运墩柱502。Then the
把托架主梁106和107、108和109接头处对齐后插上销轴并上紧螺栓,安装并张拉吊挂精轧螺纹钢筋即连接杆113。After aligning the joints of bracket
再将托架主梁106和108、107和109之间连接成如图3的结构形式。最后撤掉下扁担梁614和上扁担梁615间的倒链617,将下扁担梁收起。Then the bracket
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN200810047798XA CN101294369B (en) | 2008-05-22 | 2008-05-22 | Method and device for hanging and transferring bracket of movable mould frame |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN200810047798XA CN101294369B (en) | 2008-05-22 | 2008-05-22 | Method and device for hanging and transferring bracket of movable mould frame |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101294369A CN101294369A (en) | 2008-10-29 |
| CN101294369B true CN101294369B (en) | 2010-10-06 |
Family
ID=40064883
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN200810047798XA Active CN101294369B (en) | 2008-05-22 | 2008-05-22 | Method and device for hanging and transferring bracket of movable mould frame |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101294369B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104416352A (en) * | 2013-08-28 | 2015-03-18 | 中国一冶集团有限公司 | Construction method and device for installing and disassembling gantry crane in radial type |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105648920B (en) * | 2016-01-26 | 2017-09-26 | 盈都桥梁钢构工程有限公司 | A kind of construction method for hanging of bridge floor shoulder pole girder |
| CN110158469B (en) * | 2018-04-03 | 2021-01-26 | 中铁十五局集团有限公司 | Integral downward hanging method for formwork for bridge hanging basket construction |
| CN112030777B (en) * | 2020-09-10 | 2021-07-20 | 保利长大工程有限公司 | A down-type mobile formwork support bracket spanning transfer construction method |
| CN112095475B (en) * | 2020-09-15 | 2024-12-20 | 广西路桥工程集团有限公司 | A kind of assembled construction platform and installation method thereof |
| CN116654761B (en) * | 2023-07-04 | 2024-01-26 | 北京建工集团有限责任公司 | Rooting device with hoisting and temporary fixing functions and use method thereof |
-
2008
- 2008-05-22 CN CN200810047798XA patent/CN101294369B/en active Active
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104416352A (en) * | 2013-08-28 | 2015-03-18 | 中国一冶集团有限公司 | Construction method and device for installing and disassembling gantry crane in radial type |
| CN104416352B (en) * | 2013-08-28 | 2017-03-08 | 中国一冶集团有限公司 | Installed using radial type, remove the method that the constructing device of straddle truck is constructed |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101294369A (en) | 2008-10-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107059640B (en) | Bridge girder erection machine for prefabricated segmental beam span-by-span construction and construction method thereof | |
| CN102359303B (en) | UHV ordinary line iron tower assembly method | |
| CN100476076C (en) | Mobile integral construction platform, construction method and special spreader | |
| CN101294369B (en) | Method and device for hanging and transferring bracket of movable mould frame | |
| CN102797222A (en) | Hanging bracket hinge joint type bridge maintenance vehicle capable of avoiding bridge-side obstacles | |
| KR20140084107A (en) | Self-Launching Movable Scaffolding System | |
| CN109267490B (en) | A kind of long guide beam type mobile formwork and construction method thereof | |
| CN104594198B (en) | For the method for setting up juxtaposition case beam in tunnel | |
| CN109024291A (en) | A kind of integration Bridge Erector and its working method | |
| CN105905781B (en) | The hanging method of big segment steel truss girder | |
| CN112195798A (en) | Segmental assembling integrated bridge girder erection machine and construction method thereof | |
| CN208122371U (en) | On across the high-speed rail safe guarding shed fast dismounting device of operation line | |
| CN105088970B (en) | Construction method of corrugated steel web PC box girder cable-stayed bridge | |
| CN102296808A (en) | Template hoisting system for building | |
| CN103061262B (en) | A kind of deck erection gantry and application process thereof | |
| JP5032787B2 (en) | Heavy equipment installation equipment | |
| CN102330413B (en) | Construction method for enabling bridge girder erection machine to independently go up and down girder carrier | |
| CN210341665U (en) | Installation device for corrugated steel web of suspension casting bridge | |
| CN103754770B (en) | Hoisting device for reinforcement cage | |
| CN110562848B (en) | A high-low position conversion device for box beam transportation | |
| CN106639303A (en) | Hydraulic climbing formwork frame special for lift | |
| CN111648313A (en) | Bailey beam dismantling and transporting device and construction method applying same | |
| CN211200095U (en) | Matching structure of support leg and main beam of bridge girder erection machine | |
| CN204139067U (en) | A kind of mobile formwork reinforced mesh transporter | |
| CN209741672U (en) | Simultaneous construction formwork for the central anti-collision guardrail of a double-width parallel viaduct |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD. Effective date: 20150212 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20150212 Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No. Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau Address before: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No. Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd. |