CN101148869A - 大型悬臂梁建造方法 - Google Patents
大型悬臂梁建造方法 Download PDFInfo
- Publication number
- CN101148869A CN101148869A CNA2007101575858A CN200710157585A CN101148869A CN 101148869 A CN101148869 A CN 101148869A CN A2007101575858 A CNA2007101575858 A CN A2007101575858A CN 200710157585 A CN200710157585 A CN 200710157585A CN 101148869 A CN101148869 A CN 101148869A
- Authority
- CN
- China
- Prior art keywords
- plate
- main
- lower panel
- welding
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种大型悬臂梁建造方法,包括:将主复板水平放置,并与下面板焊接;将主复板翻转90度,下面板位于下方,将支撑板焊接到主复板和下面板上;将两次复合体翻转对置,下面板朝向外侧;在两次复合体的主复板之间焊接中间板构成侧板;在侧板上焊接管支架构成主梁结构;将主梁结构整体翻转90度,使得一侧下面板朝下平置;将两段主梁结构拼接加长;并以一侧加长的主梁结构为基准利用管支架装配底层平台;装配另一侧的主梁结构,并最终装配顶层平台;在悬臂梁合拢结束后散装悬臂梁下缘侧面的拖曳板。本发明大型悬臂梁的建造方法,能够满足大型悬臂梁精度高、承载能力大的要求,其施工方法具有合理有效、节省建造成本、缩短建造周期的优点。
Description
技术领域
本发明涉及一种梁架结构的建造方法,更具体地说,涉及钻井平台中大型悬臂梁的建造方法。
背景技术
悬臂梁位于钻井平台艉部甲板上,是钻塔、钻台、钻台塔底座等的承载结构,它由两条主梁及连接他们的平台和桁架组成。在使用过程中,要求它能承载包括钻塔等钻井设备向外滑移,以及钻台能够向左右横向滑移。国内曾建造和改造过一些小型的钻井平台的悬臂梁,这些钻井平台的尺寸较小,工作水深亦较小。与承载能力大于2000吨的大型悬臂梁相比,技术要求较低。对于大型的悬臂梁建造,在完工尺寸要求极为严格的情况下,需要采用一种合理有效的工艺流程,在节省成本、减少建造周期的基础上,保证悬臂梁的精度和结构强度。
发明内容
本发明针对大型悬臂梁精度要求高、承载能力要求大的前提下,提供了一种大型悬臂梁的建造方法,其目的旨在提供一种合理有效的施工方法,以达到大型悬臂梁建造成本的降低以及建造周期的缩短。
为了解决上述问题,本发明设计了一套大型悬臂梁建造方法以及利用本方法建造的大型悬臂梁。其中,大型悬臂梁包括侧板和平台。侧板包括主复板、在两侧主复板之间的中间板,以及主复板外侧焊接的下面板和支撑板。在侧板上焊接管支架构成主梁结构,在左右主梁结构之间装配层平台。本发明大型悬臂梁的建造方法包括如下步骤:
1、将主复板水平放置,并与下面板焊接;
2、将主复板翻转90度,下面板位于下方,将支撑板焊接到主复板和下面板上;
3、重复步骤1、2构成另一由主复板、下面板、支撑板构成的复合体;将两次复合体翻转对置,下面板朝向外侧;在两次复合体的主复板之间焊接中间板构成侧板;
4、在侧板上焊接管支架构成主梁结构;将主梁结构整体翻转90度,使得一侧下面板朝下平置;
5、重复步骤1-4获得多段主梁结构,将两段主梁结构拼接加长;并以一侧加长的主梁结构为基准利用管支架装配底层平台;
6、装配另一侧的主梁结构,并最终装配顶层平台。
7、在悬臂梁合拢结束后散装悬臂梁下缘侧面的拖曳板。
上述大型悬臂梁建造方法,其改进在于,在步骤4中,在侧板上焊接管支架采用对称焊接、分段跳焊以及退焊的焊接工艺方法。在步骤5、6之间还包括装配中间层平台,利用中间层平台和底层平台检测平台直线度,进而校正直线度后进行焊接装配。此外,在焊接下面板之前,对下面板施以预压反变形量的工步。
本发明通过提供一套大型悬臂梁的建造方法,从而满足大型悬臂梁精度高、承载能力大的要求,该施工方法具有合理有效、节省建造成本、缩短建造周期的优点。
附图说明
图1是本发明大型悬臂梁建造方法的工序流程图;
图2是本发明大型悬臂梁建造方法中针对下面板施以预压变形的结构示意图。
具体实施方式
如图1中i图所示,本发明所建造的大型悬臂梁,包括侧板7和平台6。其中,侧板7包括主复板1、两侧主复板1之间的中间板4,以及主复板1外侧焊接的下面板2和支撑板3;此外,侧板7上焊接管支架5构成主梁结构,在左右主梁结构之间装配1-3层平台6。
参考图1中的小图,逐一说明本发明的大型悬臂梁建造方法。其中,
1、图a所示,将主复板1水平放置,并与下面板2焊接。
2、图a至图b,将主复板1翻转90度,下面板2位于下方,将支撑板3焊接到主复板1和下面板2上。
3、图c至图d,重复步骤1、2构成另一由主复板1、下面板2、支撑板3构成的复合体;将两次复合体翻转对置,下面板2朝向外侧;在两次复合体的主复板1之间焊接中间板4构成侧板7。
4、参见图e至图f,在侧板7上焊接管支架5构成主梁结构;将主梁结构整体翻转90度,使得一侧下面板2朝下平置;其中侧板7上焊接管支架5采用对称焊接、分段跳焊以及退焊的焊接工艺方法。
5、如图g,重复1-4步骤获得多段主梁结构,将两段主梁结构拼接加长;此时,垂直大组右侧主梁,焊后重新检验主梁的直线度,若有偏差,应及时矫正。
而后,如图h,以右侧加长的主梁结构为基准利用管支架5装配底层平台6,此时,平台为单侧支撑状态
6、如图i,装配左侧主梁结构,并重新找正直线度后进行焊接工作,其过程为,装配中间层平台,利用中间层平台和底层平台检测平台直线度,进而校正直线度后进行焊接装配。此后,如图j,装配顶层平台6,即装配管架甲板。
7、在悬臂梁合拢结束后散装悬臂梁下缘侧面的拖曳板10。
本发明主要通过独特的组立顺序,以达到在完工精度方面的严格等级,同时它也为组织施工带来了很大的方便。其建造要点如下
1、在悬臂梁主立板的制作中,为尽量减小焊接变形的影响,我们选用了特殊的焊接方法,并且制定了专门的焊接顺序,这有力的保证了该悬臂梁建造的尺寸精度。
2、悬臂梁下面板的挠曲度要求也极为严格,如图2所示。 对此,针对复板的翘曲度在施工前进行了焊接变形试验,根据试验结下面板适当采取预压反变形量的措施,另外运用适当的装配和焊接方法予以控制。
3悬臂梁下缘侧面的拖曳板10的安装精度要求较高,尤其是左右对称开孔在悬臂梁长度方向的公差不得大于3毫米,因此要求它必须在悬臂梁合拢结束后再行散装。
4由于悬臂梁在宽度方向的精度要求严格(18米宽度,误差为3毫米),因此控制起来很棘手,因此我们采取了主船体结构与悬臂梁结构分别成型后,及时测绘相互修正的方法,通过我们制定合理的装配方法,使该方案成为可行。
5、采用本发明的方法,可以达到如下精度等级,
悬臂梁在完工尺寸上对精度要求相当高,长度方向的公差要求为±1.5mm,宽度方向的公差要求为±3mm,悬臂梁下面板T型材的宽度公差要求为+1.6/-0.8mm,下面板宽度方向的翘曲度公差要求为±1.6mm。完整悬臂梁的垂向变形不得大于1.7mm/10000mm,总变形量不得大于5.7mm。完整悬臂梁侧向的变形不得大于3.3mm/10000mm,总变形量不得大于11.3mm。
6、本发明在装配方法上,主要采用了左右对称部位的结构同时上胎,由同一个施工队伍同时施工,以保证它们的装配和焊接方法完全相同。在整个悬臂梁的装配方法上,我们设计了一个简捷、有效的方案,它特别适合于大尺寸悬臂梁的建造,该方案使装配更方便,并且质量更有保证。
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明披露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。
Claims (5)
1.一种大型悬臂梁建造方法,其特征在于,其中悬臂梁包括侧板(7)和平台(6),所述侧板(7)包括主复板(1)、下面板(2)、支撑板(3)和中间板(4),其建造方法包括如下步骤:
S1、将主复板(1)水平放置,并与下面板(2)焊接;
S2、将主复板(1)翻转90度,下面板(2)位于下方,将支撑板(3)焊接到主复板(1)和下面板(2)上;
S3、重复S1、S2构成另一由主复板(1)、下面板(2)、支撑板(3)构成的复合体;将两次复合体翻转对置,下面板(2)朝向外侧;在两次复合体的主复板(1)之间焊接中间板(4)构成侧板(7);
S4、在侧板(7)上焊接管支架(5)构成主梁结构;将主梁结构整体翻转90度,使得一侧下面板(2)朝下平置;
S5、重复S1-S4步骤获得多段主梁结构,将两段主梁结构拼接加长;并以一侧加长的主梁结构为基准利用管支架(5)装配底层平台(6);
S6、装配另一侧的主梁结构,并最终装配顶层平台(6);
S7、在悬臂梁合拢结束后散装悬臂梁下缘侧面的拖曳板(10)。
2.根据权利要求1所述的大型悬臂梁建造方法,其特征在于,在步骤S4中,在侧板(7)上焊接管支架(5)采用对称焊接、分段跳焊以及退焊的焊接工艺方法。
3.根据权利要求1所述的大型悬臂梁建造方法,其特征在于,在步骤S6中,还包括装配中间层平台,利用中间层平台和底层平台检测平台直线度,进而校正直线度后进行焊接装配。
4.根据权利要求1-3任一所述的大型悬臂梁建造方法,其特征在于,在焊接下面板(2)之前,对下面板(2)施以预压反变形量的工步。
5.由权利要求1-4建造的一种大型悬臂梁,包括侧板(7)和平台(6),其特征在于,所述侧板(7)包括主复板(1)、两侧主复板(1)之间的中间板(4),以及主复板(1)外侧焊接的下面板(2)和支撑板(3);
所述侧板(7)上焊接管支架(5)构成主梁结构,在左右主梁结构之间装配1-3层所述平台(6)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007101575858A CN100519948C (zh) | 2007-10-18 | 2007-10-18 | 大型悬臂梁建造方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007101575858A CN100519948C (zh) | 2007-10-18 | 2007-10-18 | 大型悬臂梁建造方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101148869A true CN101148869A (zh) | 2008-03-26 |
CN100519948C CN100519948C (zh) | 2009-07-29 |
Family
ID=39249559
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2007101575858A Active CN100519948C (zh) | 2007-10-18 | 2007-10-18 | 大型悬臂梁建造方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100519948C (zh) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101806053A (zh) * | 2010-05-17 | 2010-08-18 | 大连船舶重工集团有限公司 | 自升式钻井平台悬臂梁的整体安装方法 |
CN103862235A (zh) * | 2014-02-26 | 2014-06-18 | 招商局重工(江苏)有限公司 | 一种自升式钻井平台悬臂梁轨道的制作方法 |
CN104802924A (zh) * | 2014-05-27 | 2015-07-29 | 烟台中集来福士海洋工程有限公司 | 悬臂梁顶层管甲板及其建造方法 |
CN104943819A (zh) * | 2014-03-25 | 2015-09-30 | 上海外高桥造船有限公司 | 悬臂梁两段式建造方法 |
CN106475741A (zh) * | 2016-10-20 | 2017-03-08 | 南通振华重型装备制造有限公司 | 一种自升式钻井平台悬臂梁推拉架建造技术 |
CN108311804A (zh) * | 2017-01-16 | 2018-07-24 | 烟台中集来福士海洋工程有限公司 | 自升式平台悬臂梁的大梁建造方法 |
CN108487213A (zh) * | 2018-03-16 | 2018-09-04 | 南通振华重型装备制造有限公司 | 一种自升式钻井平台悬臂梁主梁建造方法 |
CN111571054A (zh) * | 2020-05-22 | 2020-08-25 | 浙江东南网架股份有限公司 | 多腔体钢板剪力墙单元体的加工方法 |
-
2007
- 2007-10-18 CN CNB2007101575858A patent/CN100519948C/zh active Active
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101806053B (zh) * | 2010-05-17 | 2014-10-08 | 大连船舶重工集团有限公司 | 自升式钻井平台悬臂梁的整体安装方法 |
CN101806053A (zh) * | 2010-05-17 | 2010-08-18 | 大连船舶重工集团有限公司 | 自升式钻井平台悬臂梁的整体安装方法 |
CN103862235A (zh) * | 2014-02-26 | 2014-06-18 | 招商局重工(江苏)有限公司 | 一种自升式钻井平台悬臂梁轨道的制作方法 |
CN103862235B (zh) * | 2014-02-26 | 2016-03-30 | 招商局重工(江苏)有限公司 | 一种自升式钻井平台悬臂梁轨道的制作方法 |
CN104943819A (zh) * | 2014-03-25 | 2015-09-30 | 上海外高桥造船有限公司 | 悬臂梁两段式建造方法 |
CN104943819B (zh) * | 2014-03-25 | 2017-06-16 | 上海外高桥造船有限公司 | 悬臂梁两段式建造方法 |
CN104802924B (zh) * | 2014-05-27 | 2018-04-03 | 烟台中集来福士海洋工程有限公司 | 悬臂梁顶层管甲板及其建造方法 |
CN104802924A (zh) * | 2014-05-27 | 2015-07-29 | 烟台中集来福士海洋工程有限公司 | 悬臂梁顶层管甲板及其建造方法 |
CN106475741A (zh) * | 2016-10-20 | 2017-03-08 | 南通振华重型装备制造有限公司 | 一种自升式钻井平台悬臂梁推拉架建造技术 |
CN106475741B (zh) * | 2016-10-20 | 2018-11-09 | 南通振华重型装备制造有限公司 | 一种自升式钻井平台悬臂梁推拉架建造技术 |
CN108311804A (zh) * | 2017-01-16 | 2018-07-24 | 烟台中集来福士海洋工程有限公司 | 自升式平台悬臂梁的大梁建造方法 |
CN108311804B (zh) * | 2017-01-16 | 2020-11-06 | 烟台中集来福士海洋工程有限公司 | 自升式平台悬臂梁的大梁建造方法 |
CN108487213A (zh) * | 2018-03-16 | 2018-09-04 | 南通振华重型装备制造有限公司 | 一种自升式钻井平台悬臂梁主梁建造方法 |
CN108487213B (zh) * | 2018-03-16 | 2019-11-15 | 南通振华重型装备制造有限公司 | 一种自升式钻井平台悬臂梁主梁建造方法 |
CN111571054A (zh) * | 2020-05-22 | 2020-08-25 | 浙江东南网架股份有限公司 | 多腔体钢板剪力墙单元体的加工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN100519948C (zh) | 2009-07-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100519948C (zh) | 大型悬臂梁建造方法 | |
CN109334858B (zh) | 一种船舶上层建筑建造的方法 | |
CN108103938B (zh) | 一种大型钢桁梁的双层桥面模块立体试装方法 | |
CN110667801B (zh) | 一种lng船穹顶甲板分段制造方法 | |
CN106460384A (zh) | 结构模块化建筑物连接器 | |
CN111021539B (zh) | 一种钢结构悬臂梁梁柱连接节点的装配方法 | |
CN106065664B (zh) | 可重复利用的活动屋架与立柱的连接节点及连接方法 | |
CN202380401U (zh) | 钢桁梁柔性拱正交异性桥面板板块的拼装胎架 | |
CN201132952Y (zh) | 高精准大型悬臂梁 | |
CN108457374A (zh) | 一种箱型梁与柱连接装配式节点制备工艺及其节点 | |
CN203127978U (zh) | 组合式自动扶梯桁架 | |
CN104961058B (zh) | 一种双z型支撑钢梁和含其的起重机支撑构件及制作方法 | |
CN106869324B (zh) | 行车梁模块化安装方法 | |
CN102019511A (zh) | 加热炉升降框架的组焊工艺 | |
CN102556085A (zh) | 不锈钢地铁司机室组装工艺方法 | |
CN212772814U (zh) | 一种钢结构节点连接结构 | |
CN205476062U (zh) | 一种模块化建筑用长条板 | |
CN210002576U (zh) | 一种斜钢骨柱与斜钢骨梁的连接结构 | |
CN204504600U (zh) | 用于自升平台桩腿焊接的辅助平台及其支撑装置 | |
CN210032278U (zh) | 一种桁架结构屋面 | |
CN110607743A (zh) | 一种全螺栓连接类蜂窝式多层h型钢桥结构及其装配方法 | |
CN214005982U (zh) | 一种箱型截面柱间支撑连接节点 | |
CN214940973U (zh) | 一种模块化钢结构件的连接节点及其模块化钢结构 | |
CN213897553U (zh) | 一种多高层房屋框架连接件体系中柱连接件的连接结构 | |
CN215857151U (zh) | 一种关于钢箱梁内桁架单元件拼装总成 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |