CN101050632A - 预应力腰梁拆除代换结构及方法 - Google Patents

预应力腰梁拆除代换结构及方法 Download PDF

Info

Publication number
CN101050632A
CN101050632A CN 200710200649 CN200710200649A CN101050632A CN 101050632 A CN101050632 A CN 101050632A CN 200710200649 CN200710200649 CN 200710200649 CN 200710200649 A CN200710200649 A CN 200710200649A CN 101050632 A CN101050632 A CN 101050632A
Authority
CN
China
Prior art keywords
waist rail
prestressed
dismantling
concrete
shaped steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200710200649
Other languages
English (en)
Other versions
CN100572687C (zh
Inventor
胡裕新
汪亚冬
刘爱玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Liujian Construction Corporation
Original Assignee
BEIJING JIANGONG GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JIANGONG GROUP Co Ltd filed Critical BEIJING JIANGONG GROUP Co Ltd
Priority to CNB2007102006498A priority Critical patent/CN100572687C/zh
Publication of CN101050632A publication Critical patent/CN101050632A/zh
Application granted granted Critical
Publication of CN100572687C publication Critical patent/CN100572687C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

一种预应力腰梁拆除代换结构及方法,在基坑内侧壁有一排护坡桩(1),在桩间土体中有一排预应力锚杆(2),各预应力锚杆与要拆除代换的型钢腰梁(3)锚固在一起,拆除代换步骤:先在型钢腰梁(3)的后部切掉一条外宽内窄的剔除桩间土体(10),使预应力锚杆(2)的部分预应力钢绞线(6)露出,并将预应力钢绞线(6)的外皮清理干净;将露出的预应力钢绞线(6)用扣件(4)束紧并插入预埋锚件;绑扎砼腰梁内的钢筋(13);支模后在侧模内浇注砼,制作砼腰梁(9);待混凝土强度达到C20后,切断新浇砼腰梁外侧的预应力钢绞线(6);拆除型钢腰梁(3),完成腰梁代换。解决了拆除型钢腰梁会影响施工安全的问题。

Description

预应力腰梁拆除代换结构及方法
(一)技术领域
本发明涉及一种建筑工程基坑支护结构及其施工方法。
(二)背景技术
在地基工程中,传统的深基坑支护常常采用桩锚护壁结构,在护坡桩之间的作若干道预应力锚杆,通过型钢腰梁与护坡桩锚固在一起。当工程建筑物以桩身作为结构外边线时,施工到型钢腰梁部位时,就必须将其拆除。而此时,若预应力锚杆还在起着作用,贸然拆除型钢腰梁就会影响施工安全。为了防止工程事故发生,常常耽误工期。
(三)发明内容
本发明的目的是提供一种预应力腰梁拆除代换结构及方法,主要解决在桩锚护壁结构中,拆除型钢腰梁会影响施工安全的技术问题。
本发明的目的是这样实现的:
一种预应力腰梁拆除代换结构,基坑内侧壁有一排间隔设置的护坡桩(1),在桩间土体(12)有一排伸入基坑内侧壁中的预应力锚杆(2),各预应力锚杆与基坑内侧壁腰部要拆除代换的型钢腰梁(3)锚固在一起,其特征在于:两个护坡桩之间,在型钢腰梁(3)靠土体一侧并排设置一条砼腰梁(9),该砼腰梁(9)与预应力锚杆(2)中的预应力钢绞线(6)浇注连接,预应力钢绞线(6)在浇注连接部位有预埋锚件(5)。
一种预应力腰梁拆除代换方法,在基坑内侧壁有一排间隔设置的护坡桩(1),在桩间土体中有一排伸入基坑内侧壁的预应力锚杆(2),在桩间土体中垂直于基坑内侧壁有预应力锚杆(2),各预应力锚杆与基坑内侧壁腰部要拆除代换的型钢腰梁(3)锚固在一起,其特征在于拆除代换步骤为:
步骤1、先在型钢腰梁(3)的后部靠土体一侧、在护坡桩之间、预应力锚杆(2)的居中位置切掉一条外宽内窄的剔除桩间土体(10),使预应力锚杆(2)的部分预应力钢绞线(6)露出,并将预应力钢绞线(6)的外皮清理干净;
步骤2、将露出的预应力钢绞线(6)用扣件(4)束紧;
步骤3、在扣件内侧,垂直于预应力钢绞线(6),插入预埋锚件;
步骤4、在与型钢腰梁并排、被剔除土体的位置绑扎砼腰梁内的钢筋(13)及三边套子箍筋(15);
步骤5、支模,在型钢腰梁(3)的内侧支侧模(14);
步骤6、在侧模内浇注砼,制作砼腰梁(9);
步骤7、待砼腰梁的混凝土强度达到C20后,切断新浇砼腰梁外侧的预应力钢绞线(6);
步骤8、拆除型钢腰梁(3),完成腰梁代换。
优选的技术方案:
上述步骤1中,剔除桩间土体(10)进深可为500~600mm,高度可为200-400mm,底部可切平,上部可呈斜坡形。
上述步骤2中,预应力钢绞线(6)中的间隙中可填塞钢筋头,可用扣件(4)将预应力钢绞线束紧;
上述步骤3中,预埋锚件(5)可以是2根以上交叉的短钢筋棍、钢筋头或钢板。
上述步骤4中,砼腰梁内的钢筋(13)可为通长设置,在与护坡桩外侧交接部分不浇筑砼,露在护坡桩外面,两根钢筋可用三边套子箍筋(15)固定。
上述步骤5中,在预定浇注混凝土腰梁下部的土体已悬空的,要支底模;下部土体坚实的,可直接在土上浇筑。
上述步骤6中,砼腰梁的截面尺寸不小于300×500mm。
在步骤7中,切断预应力钢绞线(6)的方法可为:将焊把接长,用电焊先在位于型钢腰梁中间的拉结点切断预应力钢绞线,塔吊将型钢腰梁吊住,再用电焊在位于型钢腰梁内侧的拉结点切断预应力钢绞线,最后将型钢腰梁吊出。
本发明的有益效果:本发明的预应力腰梁拆除代换方法采用在桩间间隙浇筑混凝土腰梁,将预应力锚杆锚固在混凝土腰梁内,腰梁内适当配置钢筋,利用混凝土腰梁的抗剪能力,将预应力锚杆的锚固力转移到桩身上。型钢腰梁拆除代换技术具有缩短工期,处理费用低廉,安全可靠、简便易行的优点。
(四)附图说明
图1是代换后的砼腰梁立面结构示意图;
图2是砼腰梁在水平剖面的结构示意图;
图3是图2中砼腰梁配筋的A-A剖面示意图。
图4是代换前的型钢腰梁立面结构示意图。
图5是代换前的型钢腰梁水平剖面的示意图。
图6是剔除桩间土体和支模位置的示意图。
图7是浇注混凝土前卡紧预应力钢绞线和插入短钢筋棍的示意图。
图中:1-护坡桩、2-预应力锚杆、3-型钢腰梁、4-扣件、5-预埋锚件、6-预应力钢绞线、7-垫板、8-锚头、9-砼腰梁、10-剔除桩间土体、11-喷射砼护壁、12-桩间土、13-砼腰梁内的钢筋、14-侧模、15-三边套子箍筋、16-预应力钢绞线断茬。
(五)具体实施方式
实施例参见图4-5所示,这种预应力腰梁拆除代换结构,基坑内侧壁有一排间隔设置的护坡桩1和一层喷射砼护壁11,在桩间土12中有一排伸入基坑内侧壁中的预应力锚杆2,在桩间土体中垂直于基坑内侧壁有预应力锚杆2,各预应力锚杆与基坑内侧壁腰部要拆除代换的型钢腰梁3锚固在一起。
参见图1-2,在两个护坡桩1之间,在型钢腰梁靠土体一侧并排设置一条砼腰梁9,该砼腰梁9与预应力锚杆中的预应力钢绞线6浇注连接,预应力钢绞线6在浇注连接部位有预埋锚件5。虚线为砼腰梁9的外边线。
这种预应力腰梁拆除代换方法,在基坑内侧壁有一排间隔设置的护坡桩(1),在桩间土体中有一排伸入基坑内侧壁的预应力锚杆(2),在桩间土体中垂直于基坑内侧壁有预应力锚杆(2),各预应力锚杆与基坑内侧壁腰部要拆除代换的型钢腰梁(3)锚固在一起,其特征在于拆除代换步骤为:
步骤1参见图6,先在型钢腰梁(3)的后部靠土体一侧、在护坡桩之间、预应力锚杆(2)的居中位置切掉一条外宽内窄的剔除桩间土体(10),使预应力锚杆(2)的部分预应力钢绞线(6)露出,并将预应力钢绞线(6)的外皮清理干净。上述步骤1中,按砼护坡桩最外侧计算,剔除桩间土体(10)进深为500~600mm,高度为200-400mm,底部切平,上部呈斜坡形。
步骤2参见图7,将露出的预应力钢绞线(6)用φ48扣件(4)束紧。上述步骤2中,若预应力钢筋有间隙,在预应力钢绞线(6)中的间隙中填塞2~3根250mm长φ16钢筋头,用扣件(4)务必将预应力钢绞线束紧。扣件(4)尽可能靠近混凝土腰梁外侧。以不突出护坡桩外侧为限,以确保钢绞线与卡扣之间不出现滑移。卡扣后部插入钢筋头是向周围混凝土分散钢筋集中锚固力的,应尽量与卡扣贴紧。
步骤3参见图7,在扣件内侧,垂直于预应力钢绞线(6),插入预埋锚件。上述步骤3中,预埋锚件(5)是2根以上交叉的短钢筋棍、钢筋头或钢板。
步骤4参见图2、图3,在与型钢腰梁并排、被剔除土体的位置绑扎砼腰梁内的钢筋(13)及三边套子箍筋(15)。砼腰梁内的钢筋(13)为2φ20mm通长设置,在与护坡桩外侧交接部分可不浇筑砼,露在护坡桩外面。两根钢筋用φ8mm三边套子箍筋(15)固定,三边套子箍筋的间距为150mm。
步骤5参见图6,支模,在型钢腰梁(3)的内侧支侧模(14)。上述步骤5中,在预定浇注混凝土腰梁下部的土体已悬空的,要支底模;下部土体坚实的,可以直接在土上浇筑。可利用型钢腰梁作支顶。
步骤6参见图6,在侧模内图6的虚线部位内浇注砼,制作砼腰梁(9)。上述步骤6中,砼腰梁的截面尺寸不小于300×500mm。
步骤7,待砼腰梁的混凝土强度达到C20后,切断新浇砼腰梁外侧的预应力钢绞线(6)。切断预应力钢绞线(6)的方法为:先用细木方子将电焊焊把接长至一米以上,用电焊先在位于型钢腰梁中间的拉结点切断预应力钢绞线,塔吊将型钢腰梁吊住,再用电焊在位于型钢腰梁内侧的拉结点切断预应力钢绞线,最后将型钢腰梁吊出。
步骤8参见图1、2,拆除型钢腰梁(3),观察预应力钢绞线断茬16是否收缩。若预应力钢绞线断茬不出现收缩现象,说明腰梁代换工作已完成。

Claims (9)

1.一种预应力腰梁拆除代换结构,基坑内侧壁有一排间隔设置的护坡桩(1),在桩间土体(12)有一排伸入基坑内侧壁中的预应力锚杆(2),各预应力锚杆与基坑内侧壁腰部要拆除代换的型钢腰梁(3)锚固在一起,其特征在于:两个护坡桩之间,在型钢腰梁(3)靠土体一侧并排设置一条砼腰梁(9),该砼腰梁(9)与预应力锚杆(2)中的预应力钢绞线(6)浇注连接,预应力钢绞线(6)在浇注连接部位有预埋锚件(5)。
2.一种预应力腰梁拆除代换方法,在基坑内侧壁有一排间隔设置的护坡桩(1),在桩间土体中有一排伸入基坑内侧壁的预应力锚杆(2),在桩间土体中垂直于基坑内侧壁有预应力锚杆(2),各预应力锚杆与基坑内侧壁腰部要拆除代换的型钢腰梁(3)锚固在一起,其特征在于拆除代换步骤为:
步骤1、先在型钢腰梁(3)的后部靠土体一侧、在护坡桩之间、预应力锚杆(2)的居中位置切掉一条外宽内窄的剔除桩间土体(10),使预应力锚杆(2)的部分预应力钢绞线(6)露出,并将预应力钢绞线(6)的外皮清理干净;
步骤2、将露出的预应力钢绞线(6)用扣件(4)束紧;
步骤3、在扣件内侧,垂直于预应力钢绞线(6),插入预埋锚件;
步骤4、在与型钢腰梁并排、被剔除土体的位置绑扎砼腰梁内的钢筋(13)及三边套子箍筋(15);
步骤5、支模,在型钢腰梁(3)的内侧支侧模(14);
步骤6、在侧模内浇注砼,制作砼腰梁(9);
步骤7、待砼腰梁的混凝土强度达到C20后,切断新浇砼腰梁外侧的预应力钢绞线(6);
步骤8、拆除型钢腰梁(3),完成腰梁代换。
3.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:上述步骤1中,剔除桩间土体(10)进深为500~600mm,高度为200-400mm,底部切平,上部呈斜坡形。
4.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:上述步骤2中,预应力钢绞线(6)中的间隙中填塞钢筋头,用扣件(4)将预应力钢绞线束紧。
5.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:上述步骤3中,预埋锚件(5)是2~3根交叉的短钢筋棍、钢筋头或钢板。
6.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:上述步骤4中,砼腰梁内的钢筋(13)为通长设置,在与护坡桩外侧交接部分不浇筑砼,露在护坡桩外面,两根钢筋用三边套子箍筋(15)固定。
7.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:上述步骤5中,在预定浇注混凝土腰梁下部的土体已悬空的,要支底模;下部土体坚实的,直接在土上浇筑。
8.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:上述步骤6中,砼腰梁的截面尺寸不小于300×500mm。
9.根据权利要求2所述的预应力腰梁拆除代换方法,其特征在于:在步骤7中,切断预应力钢绞线(6)的方法为:将焊把接长,用电焊先在位于型钢腰梁中间的拉结点切断预应力钢绞线,塔吊将型钢腰梁吊住,再用电焊在位于型钢腰梁内侧的拉结点切断预应力钢绞线,最后将型钢腰梁吊出。
CNB2007102006498A 2007-05-18 2007-05-18 预应力腰梁拆除代换结构及方法 Expired - Fee Related CN100572687C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007102006498A CN100572687C (zh) 2007-05-18 2007-05-18 预应力腰梁拆除代换结构及方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007102006498A CN100572687C (zh) 2007-05-18 2007-05-18 预应力腰梁拆除代换结构及方法

Publications (2)

Publication Number Publication Date
CN101050632A true CN101050632A (zh) 2007-10-10
CN100572687C CN100572687C (zh) 2009-12-23

Family

ID=38782212

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007102006498A Expired - Fee Related CN100572687C (zh) 2007-05-18 2007-05-18 预应力腰梁拆除代换结构及方法

Country Status (1)

Country Link
CN (1) CN100572687C (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101280564B (zh) * 2008-06-06 2010-06-09 北京建工集团有限责任公司 基坑桩锚护壁混凝土腰梁结构及其施工方法
CN102409682A (zh) * 2011-11-25 2012-04-11 北京市第三建筑工程有限公司 连续拱形护坡桩预应力锚杆型钢内撑结构及其施工方法
CN102418340A (zh) * 2011-10-14 2012-04-18 中煤建筑安装工程公司第七十三工程处 护坡桩基精确成桩的施工方法
CN102535477A (zh) * 2011-12-29 2012-07-04 中铁十六局集团北京轨道交通工程建设有限公司 正在开挖基坑支护锚索切断的安全施工方法
CN102677680A (zh) * 2012-05-08 2012-09-19 广东省基础工程公司 一种混凝土腰梁的拆除方法
CN103774676A (zh) * 2014-02-18 2014-05-07 中建三局第二建设工程有限责任公司 一种基坑腰梁拆除的施工方法
CN104652447A (zh) * 2014-11-14 2015-05-27 北京地圣科创建设工程有限公司 可持续施加反力的覆板临时用预应力腰梁
CN106320346A (zh) * 2016-08-24 2017-01-11 陕西建工第六建设集团有限公司 排桩加锚索后注浆深基坑支护施工方法
CN106320345A (zh) * 2015-06-30 2017-01-11 上海勘测设计研究院有限公司 基坑围护结构
CN110700276A (zh) * 2019-10-24 2020-01-17 深圳市福田建安建设集团有限公司 后浇带预置撑架基坑腰梁内支撑转换体系及施工方法
CN113123344A (zh) * 2021-06-08 2021-07-16 长沙市公共工程建设中心 一种基坑支护的锚点结构及其设置方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031784B (zh) * 2011-01-12 2012-05-23 陕西建工集团第六建筑工程有限公司 深基坑灌注护坡桩加锚索支护施工方法

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101280564B (zh) * 2008-06-06 2010-06-09 北京建工集团有限责任公司 基坑桩锚护壁混凝土腰梁结构及其施工方法
CN102418340A (zh) * 2011-10-14 2012-04-18 中煤建筑安装工程公司第七十三工程处 护坡桩基精确成桩的施工方法
CN102409682A (zh) * 2011-11-25 2012-04-11 北京市第三建筑工程有限公司 连续拱形护坡桩预应力锚杆型钢内撑结构及其施工方法
CN102535477B (zh) * 2011-12-29 2014-05-14 中铁十六局集团北京轨道交通工程建设有限公司 正在开挖基坑支护锚索切断的安全施工方法
CN102535477A (zh) * 2011-12-29 2012-07-04 中铁十六局集团北京轨道交通工程建设有限公司 正在开挖基坑支护锚索切断的安全施工方法
CN102677680A (zh) * 2012-05-08 2012-09-19 广东省基础工程公司 一种混凝土腰梁的拆除方法
CN103774676A (zh) * 2014-02-18 2014-05-07 中建三局第二建设工程有限责任公司 一种基坑腰梁拆除的施工方法
CN104652447A (zh) * 2014-11-14 2015-05-27 北京地圣科创建设工程有限公司 可持续施加反力的覆板临时用预应力腰梁
CN106320345A (zh) * 2015-06-30 2017-01-11 上海勘测设计研究院有限公司 基坑围护结构
CN106320346A (zh) * 2016-08-24 2017-01-11 陕西建工第六建设集团有限公司 排桩加锚索后注浆深基坑支护施工方法
CN106320346B (zh) * 2016-08-24 2018-10-12 陕西建工第六建设集团有限公司 排桩加锚索后注浆深基坑支护施工方法
CN110700276A (zh) * 2019-10-24 2020-01-17 深圳市福田建安建设集团有限公司 后浇带预置撑架基坑腰梁内支撑转换体系及施工方法
CN110700276B (zh) * 2019-10-24 2021-07-13 深圳市福田建安建设集团有限公司 后浇带预置撑架基坑腰梁内支撑转换体系及施工方法
CN113123344A (zh) * 2021-06-08 2021-07-16 长沙市公共工程建设中心 一种基坑支护的锚点结构及其设置方法

Also Published As

Publication number Publication date
CN100572687C (zh) 2009-12-23

Similar Documents

Publication Publication Date Title
CN101050632A (zh) 预应力腰梁拆除代换结构及方法
CN101280564B (zh) 基坑桩锚护壁混凝土腰梁结构及其施工方法
CN2773156Y (zh) 桥梁现浇混凝土防撞护栏整体模板
CA2842249A1 (en) Prefabricated reinforced concrete wall panel and installation method
JP2994222B2 (ja) プレキャストコンクリート桁の場所打ち床版部の施工方法及びその型枠
CN201228356Y (zh) 基坑桩锚护壁混凝土腰梁结构
CN102704678A (zh) 用于高层建筑变形缝位置剪力墙的定型模板
CN111074950B (zh) 地下室外墙预封闭超前止水后浇带及施工方法
CN212714951U (zh) 一种用于悬臂式护岸挡墙的模板
CN212249179U (zh) 一种地下室外墙单面支模支撑体系
CN210737843U (zh) 一种预制装配式混凝土剪力墙
CN202247938U (zh) 一种楔形地脚螺栓预留孔芯模装置
CN207633740U (zh) 悬挑脚手架新型锚固装置
CN203022761U (zh) 一种新型竖井模板
CN215105454U (zh) 一种预制和现浇相结合的桩筏基础
CN214925430U (zh) 止水型窗台压顶预制构件组装模具
CN114622492A (zh) 一种超高空心薄壁墩大断面横隔板及施工方法
CN113931363A (zh) 钢桁架和压型钢板混凝土组合楼盖施工方法
CN208202336U (zh) 预制装配式钢-压型钢板混凝土组合梁
JP2001140221A (ja) 張出床版の補修工法及び型枠の支持構造
CN111424554A (zh) 一种海景栈桥悬空模板施工方法
CN110552292A (zh) 一种整体式桥梁跨中由单幅变双幅架梁施工方法
CN217974018U (zh) 一种超高空心薄壁墩大断面横隔板
CN213572926U (zh) 一种高边墙施工防护结构
KR102294467B1 (ko) 해안구조물용 전단연결재와 그 전단연결재를 이용한 해안구조물

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090417

Address after: Beijing, Xuanwu District, Beijing Road, No. 1, Canton Road, zip code: 100055

Applicant after: Beijing construction industry Refco Group Ltd

Co-applicant after: Beijing Liujian Construction Corporation

Address before: Beijing, Xuanwu District, Beijing Road, No. 1, Canton Road, zip code: 100055

Applicant before: Beijing Jiangong Group Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091223

Termination date: 20140518