CN100572681C - A kind of processing method of steady hydraulic permeability concrete basal layer soil body - Google Patents

A kind of processing method of steady hydraulic permeability concrete basal layer soil body Download PDF

Info

Publication number
CN100572681C
CN100572681C CNB2008100495244A CN200810049524A CN100572681C CN 100572681 C CN100572681 C CN 100572681C CN B2008100495244 A CNB2008100495244 A CN B2008100495244A CN 200810049524 A CN200810049524 A CN 200810049524A CN 100572681 C CN100572681 C CN 100572681C
Authority
CN
China
Prior art keywords
soil
soil body
concrete
processing method
dirt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2008100495244A
Other languages
Chinese (zh)
Other versions
CN101255687A (en
Inventor
郝卫增
佘如春
常佩顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN HONGQIQU CONSTRUCTION GROUP CO Ltd
Original Assignee
HENAN HONGQIQU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN HONGQIQU CONSTRUCTION GROUP CO Ltd filed Critical HENAN HONGQIQU CONSTRUCTION GROUP CO Ltd
Priority to CNB2008100495244A priority Critical patent/CN100572681C/en
Publication of CN101255687A publication Critical patent/CN101255687A/en
Application granted granted Critical
Publication of CN100572681C publication Critical patent/CN100572681C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of processing method of steady hydraulic permeability concrete basal layer soil body, this processing method is earlier the thick soil layer of soil matrix top 300~500mm that will handle the soil body to be carried out soil removal and replacement or compacting processing with clay, lay thick 1: 99 dirt of one deck 200~220mm then in the above, lay one deck 200g/m in the dirt 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled forms stabilized zone, shop one layer thickness is 200~220mm permeable concrete on stabilized zone at last.The stable soil body that adopts processing method of the present invention to form has been controlled the water yield that permeable concrete infiltrates effectively, is unlikely to lower floor's soil body is taken away, and causes basic unit's earth fall to fall into; And the stable soil body that forms can make lower floor's earth stress even, guarantees the stable of hydraulic permeability concrete basal layer soil body.

Description

A kind of processing method of steady hydraulic permeability concrete basal layer soil body
One, technical field:
The present invention relates to the processing method of a kind of stabilized base soil body, particularly relate to a kind of processing method of steady hydraulic permeability concrete basal layer soil body.
Two, background technology:
At present, permeable concrete commonly used is a kind of porous light concrete that is formed by aggregate, cement and the water system of mixing, this concrete has ventilative, permeable and lightweight characteristics, can make rainwater permeate the ground rapidly, reduce underground water, make groundwater resources obtain in time replenishing, keep advantages such as soil moisture.This concrete is as carrying capacity of environment minimizing type concrete, and the Experimental Study on Pervious Concrete exploitation more and more comes into one's own.
But, when permeable concrete is used for expansive soil, silt or sandy soil soil layer,, cause expansive soil, silt or sandy soil basic unit to subside, thereby destroy the permeable concrete surface layer because water can be taken away basic unit's soil to the discharging of the soil body.
In order to overcome the situation of subsiding that occurs when permeable concrete is used for expansive soil, silt or sandy soil soil layer, researching and developing a kind of processing method of steady hydraulic permeability concrete basal layer soil body, is very important with compactness, elimination settlement by soaking, the minimizing that improves soil matrix to the problems such as rain leakage amount of soil matrix.
Three, summary of the invention:
The objective of the invention is to overcome permeable concrete and be used for the shortcoming that expansive soil, silt or sandy soil soil layer occur, a kind of processing method of steady hydraulic permeability concrete basal layer soil body is provided.
Technical scheme of the present invention is:
The invention provides a kind of processing method of steady hydraulic permeability concrete basal layer soil body, the concrete steps of this processing method are:
A, described hydraulic permeability concrete basal layer soil body are the expansive soil soil body, or are the silt soil body, or are the sandy soil soil body;
B, earlier the thick soil layer of the soil matrix top 300~500mm of institute's expansive soil soil body to be processed or the silt soil body or the sandy soil soil body is carried out soil removal and replacement or compacting processing with clay;
C, lay 1: 9 thick dirt of one deck 200~220mm in the above then, lay one deck 200g/m in the dirt 2Geotextiles, form stabilized zone, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, shop one layer thickness is 200~220mm permeable concrete on stabilized zone at last.
For the processing method of above-mentioned steady hydraulic permeability concrete basal layer soil body, compacting described in the step b is treated to adopts general rammer that its soil layer compacting to be processed is got final product.
For the processing method of above-mentioned steady hydraulic permeability concrete basal layer soil body, 1: 9 dirt described in the step c is meant that the lime and the volume ratio of soil are 1: 9.
For the processing method of above-mentioned steady hydraulic permeability concrete basal layer soil body, permeable concrete described in the step c is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Positive beneficial effect of the present invention:
1, adopt processing method of the present invention, the stable soil body of formation can be controlled the water yield that permeable concrete infiltrates effectively, is unlikely to lower floor's soil body is taken away, and causes basic unit's earth fall to fall into.
2, the stable soil body that adopts processing method of the present invention to form can make lower floor's earth stress even, guarantees the stable of hydraulic permeability concrete basal layer soil body.
Four, the specific embodiment:
Following examples only in order to further specify the present invention, do not limit content of the present invention.
Embodiment one: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of expansive soil soil body soil matrix top 400mm, adopt clay to carry out soil removal and replacement, lay 1: 9 thick dirt of one deck 200mm then on argillic horizon, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled forms stabilized zone, shop one layer thickness gets final product for the 200mm permeable concrete on stabilized zone at last.Described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment two: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of silt soil body soil matrix top 500mm, adopt general rammer that the silt soil layer is tamped, lay 1: 9 thick dirt of one deck 200mm then in the above, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness gets final product for the 200mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment three: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of sandy soil soil body soil matrix top 300mm, adopt clay to carry out soil removal and replacement, lay 1: 9 thick dirt of one deck 200mm then on argillic horizon, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness gets final product for the 200mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment four: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of expansive soil soil body soil matrix top 500mm, adopt general rammer with its expansive soil soil layer compacting, lay 1: 9 thick dirt of one deck 210mm then in the above, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness gets final product for the 220mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment five: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of silt soil body soil matrix top 350mm, adopt clay to carry out soil removal and replacement, lay 1: 9 thick dirt of one deck 220mm then on argillic horizon, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness gets final product for the 210mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment six: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of sandy soil soil body soil matrix top 450mm, adopt general rammer with its sandy soil soil layer compacting, lay 1: 9 thick dirt of one deck 200mm then in the above, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness is the 200mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment seven: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Earlier with the thick soil layer of expansive soil soil body soil matrix top 300mm, adopt clay to carry out soil removal and replacement, lay 1: 9 thick dirt of one deck 220mm then on argillic horizon, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled forms stabilized zone, shop one layer thickness gets final product for the 210mm permeable concrete on stabilized zone at last.Described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment eight: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Concrete steps are as follows:
Earlier with the thick soil layer of silt soil body soil matrix top 400mm, adopt general rammer that the silt soil layer is tamped, lay 1: 9 thick dirt of one deck 210mm then in the above, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness gets final product for the 220mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
Embodiment nine: a kind of processing method of steady hydraulic permeability concrete basal layer soil body
Earlier with the thick soil layer of sandy soil soil body soil matrix top 500mm, adopt clay to carry out soil removal and replacement, lay 1: 9 thick dirt of one deck 210mm then on argillic horizon above it, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, establishes one deck 200g/m at grey soil layer middle berth 2Geotextiles, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, form stabilized zone, shop one layer thickness is the 210mm permeable concrete on stabilized zone at last, and described permeable concrete is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.

Claims (3)

1, a kind of processing method of steady hydraulic permeability concrete basal layer soil body is characterized in that the concrete steps of described processing method are:
A, described hydraulic permeability concrete basal layer soil body are the expansive soil soil body, or are the silt soil body, or are the sandy soil soil body;
B, earlier the thick soil layer of the soil matrix top 300~500mm of institute's expansive soil soil body to be processed or the silt soil body or the sandy soil soil body is carried out soil removal and replacement or compacting processing with clay;
C, lay 1: 9 thick dirt of one deck 200~220mm in the above then, described 1: 9 dirt is meant that the lime and the volume ratio of soil are 1: 9, lays one deck 200g/m in the dirt 2Geotextiles, form stabilized zone, each wide 300mm of the every side of width roadbed that dirt and soil matrix are handled, shop one layer thickness is 200~220mm permeable concrete on stabilized zone at last.
2, the processing method of steady hydraulic permeability concrete basal layer soil body according to claim 1 is characterized in that: compacting described in the step b is treated to adopts general rammer that its soil layer compacting to be processed is got final product.
3, the processing method of steady hydraulic permeability concrete basal layer soil body according to claim 1 is characterized in that: permeable concrete described in the step c is the porous light concrete a kind of commonly used that is formed by aggregate, cement and the water system of mixing.
CNB2008100495244A 2008-04-11 2008-04-11 A kind of processing method of steady hydraulic permeability concrete basal layer soil body Expired - Fee Related CN100572681C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2008100495244A CN100572681C (en) 2008-04-11 2008-04-11 A kind of processing method of steady hydraulic permeability concrete basal layer soil body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2008100495244A CN100572681C (en) 2008-04-11 2008-04-11 A kind of processing method of steady hydraulic permeability concrete basal layer soil body

Publications (2)

Publication Number Publication Date
CN101255687A CN101255687A (en) 2008-09-03
CN100572681C true CN100572681C (en) 2009-12-23

Family

ID=39890766

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2008100495244A Expired - Fee Related CN100572681C (en) 2008-04-11 2008-04-11 A kind of processing method of steady hydraulic permeability concrete basal layer soil body

Country Status (1)

Country Link
CN (1) CN100572681C (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103161109A (en) * 2011-12-13 2013-06-19 中国二十冶集团有限公司 Method for subgrade filling of peat soil subgrade by sea sand
CN103993536A (en) * 2014-05-30 2014-08-20 北京建筑大学 Paving system of plastic grid sand-based water permeable bricks
CN109469086A (en) * 2018-11-10 2019-03-15 中国石油化工股份有限公司临汾煤层气分公司 A kind of Collapsible Loess District pump house ground Simple treatment method

Also Published As

Publication number Publication date
CN101255687A (en) 2008-09-03

Similar Documents

Publication Publication Date Title
CN102767302B (en) Distributed underground reservoir and construction method thereof
CN202503890U (en) Water and soil improvement system of saline and alkaline land
CN106759825A (en) A kind of construction method of sponge urban green space water storage system
CN106192907B (en) Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN104163550B (en) Cascading style ladder artificial wet land system and constructional method thereof
CN104878678A (en) Construction method for water-permeable and water-retaining water-permeable pavement structure
CN105297570A (en) Special soil subgrade structure and construction method thereof
CN110629629A (en) Recycled aggregate permeable pavement structure and method
CN100572681C (en) A kind of processing method of steady hydraulic permeability concrete basal layer soil body
CN108532401A (en) A kind of coral sand concrete road surface structure and its construction method
CN105019426A (en) Anti-blocking rapid vacuum preloading and solidifying method for flow-state mud with straw as drainage bodies
CN104763017B (en) Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system
CN108457241B (en) Ecological waterproof permeability-reducing method for artificial lake of saline-alkali soil
CN103215950B (en) Pile foundation extension construction method in backfilling area
CN103195051B (en) Limestone soil and pervious concrete pile composite foundation and treatment method thereof
CN106337422B (en) A method of processing Collapsible Loess District fill foundation
CN102839683A (en) Discrete pile-water permeability concrete pile novel binary composite foundation and treatment method of composite foundation
CN108086459A (en) A kind of construction method of sponge urban green space water storage system
CN206971040U (en) A kind of special discharge structure in walking road surface
CN205046437U (en) Chain formula ground of mating formation of permeating water
CN103999592A (en) Method for avoiding vegetation degradation of acid mine waste rock yard
CN202265793U (en) Ecological lakebed
CN105350630B (en) Oozed under a kind of urban rainwater is quick and reuse technology
CN103321185A (en) Ecological impermeable cement canal
CN109396177B (en) Ecological restoration structure of petroleum hydrocarbon-heavy metal composite pollution sludge, construction method thereof and restoration method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091223

Termination date: 20190411