- Publication number
- CN100370171C CN100370171C CNB2004100668461A CN200410066846A CN100370171C CN 100370171 C CN100370171 C CN 100370171C CN B2004100668461 A CNB2004100668461 A CN B2004100668461A CN 200410066846 A CN200410066846 A CN 200410066846A CN 100370171 C CN100370171 C CN 100370171C
- Authority
- CN
- China
- Prior art keywords
- inspection shaft
- pipeline
- inner lining
- under ground
- restoration method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
Description
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100668461A CN100370171C (zh) | 2004-09-29 | 2004-09-29 | 地下管道和检查井的非开挖整体修复方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100668461A CN100370171C (zh) | 2004-09-29 | 2004-09-29 | 地下管道和检查井的非开挖整体修复方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1755184A CN1755184A (zh) | 2006-04-05 |
CN100370171C true CN100370171C (zh) | 2008-02-20 |
Family
ID=36688636
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2004100668461A Expired - Fee Related CN100370171C (zh) | 2004-09-29 | 2004-09-29 | 地下管道和检查井的非开挖整体修复方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100370171C (zh) |
Families Citing this family (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101626884B (zh) * | 2007-01-18 | 2013-11-06 | 路博润高级材料公司 | 原位固化的管内衬 |
CN101799098A (zh) * | 2010-04-07 | 2010-08-11 | 郭恒德 | 管道修复用复合板块及采用该板块的管道修复方法 |
CN101846226B (zh) * | 2010-05-26 | 2011-07-27 | 林永志 | 大管道或沟渠嵌钉塑料板灌注树脂内衬修复的方法 |
CN102287603A (zh) * | 2011-08-11 | 2011-12-21 | 海宁管丽科技新材料有限公司 | 一种城市道路下排水支管修复用非开挖内衬修复方法 |
CN103542226B (zh) * | 2012-07-17 | 2016-03-02 | 中国长江三峡集团公司 | 一种修复大直径混凝土供水管道的方法 |
CN103615044B (zh) * | 2013-12-13 | 2015-03-11 | 中冶建工集团有限公司 | 一种小直径混凝土排水管道渗漏内套管封堵方法 |
CN103899879B (zh) * | 2014-04-16 | 2015-09-30 | 浙江凯胜园林市政建设有限公司 | 用于修复管道接口的修复装置及其修复方法 |
CN103982748B (zh) * | 2014-06-10 | 2015-12-30 | 武汉中地管通非开挖科技有限公司 | 一种改进型管道不锈钢内衬修复方法 |
CN104806843B (zh) * | 2015-03-12 | 2017-05-03 | 武汉中地大非开挖研究院有限公司 | 钢筒挂网喷涂砂浆复合内衬及压力管道非开挖修复的方法 |
NL2018224B1 (en) * | 2017-01-24 | 2018-08-01 | Mocs Beheer B V | Fitting element for use in rehabilitation of pipelines and method for producing the same |
CN110374140A (zh) * | 2018-04-13 | 2019-10-25 | 上海管丽建设工程有限公司 | 一种非开挖涂抹型检查井修复方法 |
CN110332409A (zh) * | 2019-07-24 | 2019-10-15 | 上海市城市建设设计研究总院(集团)有限公司 | 非开挖修复排水管道的方法及专用的不锈钢内衬修复结构 |
CN110701425B (zh) * | 2019-09-12 | 2022-06-10 | 上海井园市政工程有限公司 | 一种非开挖式管道修复方法 |
CN110630847A (zh) * | 2019-09-25 | 2019-12-31 | 南方工程检测修复技术研究院 | 一种含多种病害混凝土排水管道的非开挖整体修复方法 |
CN110715138A (zh) * | 2019-10-28 | 2020-01-21 | 南京华享环境科技有限公司 | 一种排水管道非开挖式修复方法 |
CN111765320B (zh) * | 2020-07-02 | 2021-11-19 | 温州市正龙市政建设有限公司 | 一种管道修复装置 |
CN112746661B (zh) * | 2020-12-30 | 2022-07-15 | 北京城市排水集团有限责任公司 | 一种小型排水方沟钢丝骨架复合加固修复系统及其施工方法 |
CN112901892B (zh) * | 2021-01-19 | 2022-03-15 | 上海通友市政工程有限公司 | 一种用于cipp翻转法的市政管道修复装置和方法 |
CN113863472B (zh) * | 2021-09-25 | 2023-02-28 | 广东德泽建设工程有限公司 | 一种预制内衬钢箱体污水井快速修复结构及其施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5520484A (en) * | 1995-02-03 | 1996-05-28 | Shonan Gosei-Jushi Seisakusho K.K. | Eversion nozzle, and a method for repairing an underground tubular conduit |
JP2000257141A (ja) * | 1999-03-08 | 2000-09-19 | Public Works Research Center | 地下埋設管渠更新時に於けるサービス管の非開削復旧方法 |
US6401759B1 (en) * | 1998-12-22 | 2002-06-11 | Shonan Gosei-Jushi Seisakusho K.K. | Liner bag for manhole and method of lining a manhole |
US6416692B1 (en) * | 2000-03-10 | 2002-07-09 | Jeffrey L. Iwasaki-Higbee | Sewer system pipe repairs |
CN1470797A (zh) * | 2002-07-23 | 2004-01-28 | 株式会社湘南合成树脂制作所 | 管内衬施工方法 |
-
2004
- 2004-09-29 CN CNB2004100668461A patent/CN100370171C/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5520484A (en) * | 1995-02-03 | 1996-05-28 | Shonan Gosei-Jushi Seisakusho K.K. | Eversion nozzle, and a method for repairing an underground tubular conduit |
US6401759B1 (en) * | 1998-12-22 | 2002-06-11 | Shonan Gosei-Jushi Seisakusho K.K. | Liner bag for manhole and method of lining a manhole |
JP2000257141A (ja) * | 1999-03-08 | 2000-09-19 | Public Works Research Center | 地下埋設管渠更新時に於けるサービス管の非開削復旧方法 |
US6416692B1 (en) * | 2000-03-10 | 2002-07-09 | Jeffrey L. Iwasaki-Higbee | Sewer system pipe repairs |
CN1470797A (zh) * | 2002-07-23 | 2004-01-28 | 株式会社湘南合成树脂制作所 | 管内衬施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN1755184A (zh) | 2006-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100370171C (zh) | 地下管道和检查井的非开挖整体修复方法 | |
CN202391019U (zh) | 钢筋端部加粗灌浆接头 | |
CN104846810A (zh) | 自循环后注浆钻孔灌注桩施工方法 | |
CN103075013A (zh) | 一种建筑施工钢筋连接结构及连接方法 | |
CN106287001B (zh) | 压力钢管钢筋复合混凝土管及由其制成的管道和制作方法 | |
CN101666091A (zh) | 一种断裂管桩的填芯补强方法 | |
CN206299921U (zh) | 管道 | |
CN102518129B (zh) | 后压浆预应力空心方桩的制作方法 | |
CN107447747A (zh) | 一种预制地下连续墙及其施工方法 | |
JP5334379B2 (ja) | 送電鉄塔用中空鋼管増強工法 | |
JP2009085004A (ja) | 既設管路の補修方法およびそれに用いる補修材並びに管路 | |
CN109763391B (zh) | 病害道路单孔复合注浆加固基层和路基施工方法 | |
KR100836512B1 (ko) | 관로의 보수재, 보수 구조 및 그 보수 방법 | |
CN108253202A (zh) | 管道及其制备方法 | |
CN112301995A (zh) | 一种兼作降水注浆通道的预制复合加固体结构及施工方法 | |
JP2004278203A (ja) | 流体輸送施設の修復工法 | |
CN215632972U (zh) | 一种超大断面矩形顶管现场预制管节 | |
CN210141133U (zh) | 微盾构混凝土管涵修复加固结构 | |
JP4038496B2 (ja) | パイプイントンネル工法等における鞘管と新管間へのグラウト材の充填方法 | |
CN212375851U (zh) | 一种试桩荷载箱内裂缝注浆加筋联结装置 | |
CN217999610U (zh) | 用于暗挖隧道道床的定点注浆装置及注浆系统 | |
CN213805307U (zh) | 一种兼作降水注浆通道的预制复合加固体结构 | |
KR100518460B1 (ko) | 토목 및 도로공사에서의 하수관용 보강 거푸집 | |
CN107059865A (zh) | 预制高强芯体、压力型锚杆及其施工方法 | |
JP4536702B2 (ja) | 水路の改修方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Assignee: Guanli Environment Technology (Shanghai) Co., Ltd. Assignor: Sun Yueping Contract fulfillment period: 2009.6.17 to 2014.6.16 contract change Contract record no.: 2009310000165 Denomination of invention: Excavation-free integral restoration method of underground conduit and inspection well Granted publication date: 20080220 License type: Exclusive license Record date: 2009.8.19 |
|
LIC | Patent licence contract for exploitation submitted for record |
Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2009.6.17 TO 2014.6.16; CHANGE OF CONTRACT Name of requester: GUANLI ENVIRONMENTAL TECHNOLOGY ( SHANGHAI ) CO., Effective date: 20090819 |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080220 Termination date: 20160929 |