CN100343155C - 塔吊起重臂空中解体施工方法 - Google Patents

塔吊起重臂空中解体施工方法 Download PDF

Info

Publication number
CN100343155C
CN100343155C CNB2005100387693A CN200510038769A CN100343155C CN 100343155 C CN100343155 C CN 100343155C CN B2005100387693 A CNB2005100387693 A CN B2005100387693A CN 200510038769 A CN200510038769 A CN 200510038769A CN 100343155 C CN100343155 C CN 100343155C
Authority
CN
China
Prior art keywords
crane arm
crane
node
arm
steel rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2005100387693A
Other languages
English (en)
Other versions
CN1673066A (zh
Inventor
李剑生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Guangyu Construction Group Co., Ltd.
Original Assignee
李剑生
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 李剑生 filed Critical 李剑生
Priority to CNB2005100387693A priority Critical patent/CN100343155C/zh
Publication of CN1673066A publication Critical patent/CN1673066A/zh
Application granted granted Critical
Publication of CN100343155C publication Critical patent/CN100343155C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种塔吊起重臂空中解体施工方法,包括在待拆卸的起重臂节与节之间的节点处将拆卸起重臂专用夹具卡装在起重机起重臂节与节结合处两侧的下弦上,并在待拆卸节点的前端安装辅助吊臂,用起升机构主卷扬机将平衡重块依次吊至地面,并通过起重机构主钢丝绳、辅助吊臂,完成节点分解程序,开动起重机构将分解臂放到地面;利用滑轮组、钢丝绳、卷扬机等将长、短拉杆逐段卸下;在拆卸起重臂与过渡节连接点时,先将塔吊主钢丝绳收回,再拆卸去起重臂与过渡节连接销轴,用拉住起重臂的滑轮组直接将剩余的起重臂放下,完成起重臂空中解体全过程。本发明可有效方便地对塔吊起重臂进行空中拆卸,且安全性高,费用小。

Description

塔吊起重臂空中解体施工方法
技术领域:
本发明涉及一种塔吊起重臂的解体方法。
背景技术:
随着时代的发展,建筑物形状及高度也随着变得更高、更特异,施工过程中所采用的垂直运输机械塔吊(例中国专利CN2414055),由于多种原因在施工完毕后发现无法进行常规拆卸。目前市场上大吨位汽车吊少且费用也高,有个别情况即使采用大吨位汽车吊(例CN2868965等)也无法进行辅助拆卸作业。而塔吊无法进行常规拆卸的部件是前臂(即起重臂)。
发明内容:
本发明的目的在于提供一种可有效方便地对塔吊起重臂进行空中拆卸的塔吊起重臂空中解体施工方法。
本发明的技术解决方案是:
一种塔吊起重臂空中解体施工方法,其特征是:包括下列步骤:①在起重臂第一节至待拆卸节点之间安装操作人员扣挂安全带的钢丝绳,拆卸工作时,将操作人员的安全带扣挂在该钢丝绳上;
选用拆卸起重臂专用夹具:夹具有左、右夹片,左、右夹片上设置夹槽,夹槽两侧板上装固定销,左、右夹片之间通过销轴可旋转式连接;
在待拆卸的起重臂节与节之间的节点处将上述夹具左、右夹片的夹槽分别卡装在起重机起重臂节与节结合处两侧的下弦上,用装在夹槽两侧板上的固定销固定,且在起重臂两侧下弦上各装一个夹具;并在待拆卸节点的前端安装辅助吊臂;
在平衡臂上安装拆卸平衡重块的支架,支架上装起吊平衡重块的滑轮组,利用起升机构主卷扬机将平衡重块依次吊至地面,平衡臂上保留一块平衡重;
将起重机构主钢丝绳通过辅助吊臂端部滑轮,并从起重臂前部滑轮、起重臂内部绕至待拆卸节点后方固定,将起重臂上的小车退到靠近塔身处,将小车固定好后拆除小车钢丝绳,用小车卷扬机将绳卷好;将起重臂上待拆卸节点两侧的下弦横杆用钢丝绳绕成一体;
拆去待拆卸节点处下弦节点销轴,再拆除该节点上弦节点销轴,开动起重机构主卷扬机,缓慢放松主绳使被分解部分绕夹具左、右夹片之间的销轴垂下;
拆除起重机构主钢丝绳固定端,抽出后将其栓牢在垂下的臂上端,将主钢丝绳收紧,并将专用夹具拆除,再解掉绕在节点两侧下弦横杆上的钢丝绳,该节点分解程序完成,开动起重机构将分解臂放到地面,然后将主绳收回;
②在起重臂长拉杆后侧通过滑轮组将起重臂拉住,将扣挂安全带的钢丝绳也移至长拉杆后方、拉紧,移动该钢丝绳的操作人员将安全带临时挂在滑轮组钢丝绳上,待扣挂安全带的钢丝绳张紧后,再将安全带扣挂在该扣挂安全带的钢丝绳上;
用卷扬机通过滑轮组将起重臂抬高至长拉杆上连接点靠在起重臂上弦杆上,用起重臂上小车的卷扬机钢丝绳扣住拉杆,开动小车卷扬机,使钢丝绳受力后卸出长拉杆销轴,然后开动小车卷扬机将拉杆缓慢放下,挂在塔帽上,解掉扣在拉杆上的钢丝绳并收回,再将拉杆逐段卸下;将起重臂放平;
③按步骤①的相同方法拆卸起重臂其他节点,拆卸时,先将步骤②中拉住起重臂的滑轮组移至待拆卸节点后方;
④按步骤②的相同方法拆卸起重臂短拉杆,拆卸时,先将步骤②中拉住起重臂的滑轮组移至短拉杆后方。
⑤在拆卸起重臂与过渡节连接点时,先将塔吊主钢丝绳收回,再拆卸去起重臂与过渡节连接销轴,用拉住起重臂的滑轮组直接将剩余的起重臂放下,完成起重臂空中解体全过程。
辅助吊臂与拉杆之间用拉绳连接。
本发明可有效方便地对塔吊起重臂进行空中拆卸,且安全性高,费用小。
附图说明:
下面结合附图和实施例对本发明作进一步说明。
图1是本发明专用夹具的结构视图。
图2是图1的左视图。
图3是图1的右视图。
图4、图5是拆卸起重臂节点时状态图。
图6、图7是拆卸长拉杆时状态图。
具体实施方式:
实施例:
一种塔吊起重臂空中解体施工方法,其特征是:包括下列步骤:
①在起重臂9第一节至待拆卸节点之间安装操作人员扣挂安全带的钢丝绳,拆卸工作时,将操作人员的安全带扣挂在该钢丝绳上;
选用拆卸起重臂专用夹具:夹具有左、右夹片1、2,左、右夹片1、2上设置夹槽3,夹槽3两侧板4、5上装固定销6,左、右夹片之间通过销轴7可旋转式连接,在夹槽侧板上装夹紧调节螺母8。
在待拆卸的起重臂节与节之间的节点处将上述夹具19左、右夹片1、2的夹槽3分别卡装在起重机起重臂节与节结合处两侧的下弦上,用装在夹槽两侧板上的固定销6固定,且在起重臂两侧下弦上各装一个夹具;并在待拆卸节点的前端安装辅助吊臂12,辅助吊臂12与拉杆14之间用拉绳15连接;
在平衡臂10上安装拆卸平衡重块的支架,支架上装起吊平衡重块的滑轮组,利用起升机构主卷扬机将平衡重块依次吊至地面,平衡臂10上保留一块平衡重;
将起重机构主钢丝绳11通过辅助吊臂12端部滑轮13,并从起重臂前部滑轮16、起重臂内部绕至待拆卸节点后方固定,将起重臂9上的小车17退到靠近塔身18处,将小车17固定好后拆除小车钢丝绳,用小车卷扬机将绳卷好;将起重臂9上待拆卸节点两侧的下弦横杆用钢丝绳绕成一体;
拆去待拆卸节点处下弦节点销轴,再拆除该节点上弦节点销轴,开动起重机构主卷扬机,缓慢放松主绳11使被分解部分绕夹具19左、右夹片之间的销轴7垂下;
拆除起重机构主钢丝绳11固定端,抽出后将其栓牢在垂下的臂上端,将主钢丝绳11收紧,并将专用夹具19拆除,再解掉绕在节点两侧下弦横杆上的钢丝绳,该节点分解程序完成,开动起重机构将分解臂放到地面,然后将主绳11收回;
②在起重臂长拉杆14后侧通过滑轮组20将起重臂9拉住,将扣挂安全带的钢丝绳也移至长拉杆14后方、拉紧,移动该钢丝绳的操作人员将安全带临时挂在滑轮组20钢丝绳上,待扣挂安全带的钢丝绳张紧后,再将安全带扣挂在该扣挂安全带的钢丝绳上;
用卷扬机通过滑轮组20将起重臂9抬高至长拉杆14上连接点靠在起重臂上弦杆上,用起重臂上小车17的卷扬机钢丝绳扣住拉杆14,开动小车卷扬机,使钢丝绳受力后卸出长拉杆销轴,然后开动小车卷扬机将拉杆14缓慢放下,挂在塔帽上,解掉扣在拉杆14上的钢丝绳并收回,再将拉杆逐段卸下;将起重臂9放平;
③按步骤①的相同方法拆卸起重臂其他节点,拆卸时,先将步骤②中拉住起重臂的滑轮组20移至待拆卸节点后方;
④按步骤②的相同方法拆卸起重臂短拉杆21,拆卸时,先将步骤②中拉住起重臂的滑轮组20移至短拉杆21后方。
⑤在拆卸起重臂与过渡节连接点时,先将塔吊主钢丝绳11收回,再拆卸去起重臂与过渡节连接销轴,用拉住起重臂的滑轮组20直接将剩余的起重臂9放下,完成起重臂空中解体全过程。

Claims (2)

1、一种塔吊起重臂空中解体施工方法,其特征是:包括下列步骤:①在起重臂第一节至待拆卸节点之间安装操作人员扣挂安全带的钢丝绳,拆卸工作时,将操作人员的安全带扣挂在该钢丝绳上;
选用拆卸起重臂专用夹具:夹具有左、右夹片,左、右夹片上设置夹槽,夹槽两侧板上装固定销,左、右夹片之间通过销轴可旋转式连接;
在待拆卸的起重臂节与节之间的节点处将上述夹具左、右夹片的夹槽分别卡装在起重机起重臂节与节结合处两侧的下弦上,用装在夹槽两侧板上的固定销固定,且在起重臂两侧下弦上各装一个夹具;并在待拆卸节点的前端安装辅助吊臂;
在平衡臂上安装拆卸平衡重块的支架,支架上装起吊平衡重块的滑轮组,利用起升机构主卷扬机将平衡重块依次吊至地面,平衡臂上保留一块平衡重;
将起重机构主钢丝绳通过辅助吊臂端部滑轮,并从起重臂前部滑轮、起重臂内部绕至待拆卸节点后方固定,将起重臂上的小车退到靠近塔身处,将小车固定好后拆除小车钢丝绳,用小车卷扬机将绳卷好;将起重臂上待拆卸节点两侧的下弦横杆用钢丝绳绕成一体;
拆去待拆卸节点处下弦节点销轴,再拆除该节点上弦节点销轴,开动起重机构主卷扬机,缓慢放松主绳使被分解部分绕夹具左、右夹片之间的销轴垂下;
拆除起重机构主钢丝绳固定端,抽出后将其栓牢在垂下的臂上端,将主钢丝绳收紧,并将专用夹具拆除,再解掉绕在节点两侧下弦横杆上的钢丝绳,该节点分解程序完成,开动起重机构将分解臂放到地面,然后将主绳收回;
②在起重臂长拉杆后侧通过滑轮组将起重臂拉住,将扣挂安全带的钢丝绳也移至长拉杆后方、拉紧,移动该钢丝绳的操作人员将安全带临时挂在滑轮组钢丝绳上,待扣挂安全带的钢丝绳张紧后,再将安全带扣挂在该扣挂安全带的钢丝绳上;
用卷扬机通过滑轮组将起重臂抬高至长拉杆上连接点靠在起重臂上弦杆上,用起重臂上小车的卷扬机钢丝绳扣住拉杆,开动小车卷扬机,使钢丝绳受力后卸出长拉杆销轴,然后开动小车卷扬机将拉杆缓慢放下,挂在塔帽上,解掉扣在拉杆上的钢丝绳并收回,再将拉杆逐段卸下;将起重臂放平;
③按步骤①的相同方法拆卸起重臂其他节点,拆卸时,先将步骤②中拉住起重臂的滑轮组移至待拆卸节点后方;
④按步骤②的相同方法拆卸起重臂短拉杆,拆卸时,先将步骤②中拉住起重臂的滑轮组移至短拉杆后方;
⑤在拆卸起重臂与过渡节连接点时,先将塔吊主钢丝绳收回,再拆卸去起重臂与过渡节连接销轴,用拉住起重臂的滑轮组直接将剩余的起重臂放下,完成起重臂空中解体全过程。
2、根据权利要求1所述的塔吊起重臂空中解体施工方法,其特征是:辅助吊臂与拉杆之间用拉绳连接。
CNB2005100387693A 2005-04-05 2005-04-05 塔吊起重臂空中解体施工方法 Expired - Fee Related CN100343155C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100387693A CN100343155C (zh) 2005-04-05 2005-04-05 塔吊起重臂空中解体施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100387693A CN100343155C (zh) 2005-04-05 2005-04-05 塔吊起重臂空中解体施工方法

Publications (2)

Publication Number Publication Date
CN1673066A CN1673066A (zh) 2005-09-28
CN100343155C true CN100343155C (zh) 2007-10-17

Family

ID=35045888

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100387693A Expired - Fee Related CN100343155C (zh) 2005-04-05 2005-04-05 塔吊起重臂空中解体施工方法

Country Status (1)

Country Link
CN (1) CN100343155C (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102152102A (zh) * 2010-12-25 2011-08-17 杭州科曼萨杰牌建设机械有限公司 塔式起重机的空中解臂方法及其解臂装置
CN107444935B (zh) * 2017-06-19 2020-05-01 五冶集团上海有限公司 一种卸船机悬臂大梁拉杆拆除的防冲撞方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2637314A1 (fr) * 1988-09-30 1990-04-06 Peltier Marcel Dispositif de securite a ligne de vie
JPH0761773A (ja) * 1993-08-20 1995-03-07 Koshihara:Kk ジブクレーン
JP2000272876A (ja) * 1999-03-26 2000-10-03 Ishikawajima Transport Machinery Co Ltd 折り畳み式ジブクレーン
JP2001022607A (ja) * 1999-07-12 2001-01-26 Mitsubishi Electric Corp ネットワーク型波形表示装置
WO2004087557A1 (en) * 2003-04-02 2004-10-14 Terex-Demag Gmbh & Co. Kg Two-piece main boom for a latice-boom crane and method for erection thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2637314A1 (fr) * 1988-09-30 1990-04-06 Peltier Marcel Dispositif de securite a ligne de vie
JPH0761773A (ja) * 1993-08-20 1995-03-07 Koshihara:Kk ジブクレーン
JP2000272876A (ja) * 1999-03-26 2000-10-03 Ishikawajima Transport Machinery Co Ltd 折り畳み式ジブクレーン
JP2001022607A (ja) * 1999-07-12 2001-01-26 Mitsubishi Electric Corp ネットワーク型波形表示装置
WO2004087557A1 (en) * 2003-04-02 2004-10-14 Terex-Demag Gmbh & Co. Kg Two-piece main boom for a latice-boom crane and method for erection thereof

Also Published As

Publication number Publication date
CN1673066A (zh) 2005-09-28

Similar Documents

Publication Publication Date Title
CN108002250B (zh) 一种屋面吊装置和起重机和起重臂的拆卸方法
CN101177959A (zh) 幕墙单元吊装设备及其施工方法
CN105621280B (zh) 安装和拆卸起重臂的装置和方法
CN1955102A (zh) 动臂变幅式起重机的架设方法和系统
CN102409838A (zh) 移动操作平台及利用移动操作平台的屋面吊顶施工方法
CN111764629A (zh) 斜屋面免配重吊篮安装和拆卸方法
CN111021749A (zh) 一种清水混凝土外墙挂板简易提升机构及其施工方法
CN217555581U (zh) 钢结构多节柱自动脱钩装置
CN100343155C (zh) 塔吊起重臂空中解体施工方法
CN106835994B (zh) 移动式施工挂篮及过桥墩方法
CN110282559A (zh) 一种混凝土墙体吊装装置
CN205527435U (zh) 安装和拆卸起重臂的装置
JP2008222382A (ja) 据付用昇降装置移動方法
CN206625131U (zh) 移动式施工挂篮
CN1224690A (zh) 液压电梯的主绳索更换方法及其所使用的固定工具
CN202000647U (zh) 电梯井提升脚手架的底座装置
CN112723151B (zh) 一种装配式钢结构建筑整体屋顶吊装安装方法
JP3576338B2 (ja) ケーブル端部の定着装置およびその使用方法
CN215711332U (zh) 一种墙面板吊装架
CN217708653U (zh) 一种能够自拆的辅助吊装装置
CN2042492U (zh) 装修起重两用升降平台
CN217418025U (zh) 一种绞盘安装装置及电线杆用起吊系统
CN217555687U (zh) 包覆材料车间电动葫芦部件更换起吊装置
CN200967707Y (zh) 无能耗防脱自动摘吊钩
CN1282812C (zh) 穿越有巨型外伸桁架的整体提升模板系统及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JIANGSU GUANGYU CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: LI JIANSHENG

Effective date: 20110328

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 226401 NANTONG FIVE NEW SOURCE OF CONSTRUCTION + ENGINEERING CO., LTD., NO.58, RENHE SOUTH ROAD, MATANG, RUDONG COUNTRY, JIANGSU PROVINCE TO: 214500 NO. 230, JIANGPING ROAD, JINGJIANG CITY, JIANGSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110328

Address after: 214500 No. 230, Ping Jiang Road, Jiangsu, Jingjiang

Patentee after: Jiangsu Guangyu Construction Group Co., Ltd.

Address before: For example, 226401 of Jiangsu province Rudong County Renhe Road No. 58 Nantong five Xinyuan Engineering Co. Ltd.

Patentee before: Li Jiansheng

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20071017

Termination date: 20200405