CH169277A - Method for installing rails, in particular tram rails, in a road body. - Google Patents

Method for installing rails, in particular tram rails, in a road body.

Info

Publication number
CH169277A
CH169277A CH169277DA CH169277A CH 169277 A CH169277 A CH 169277A CH 169277D A CH169277D A CH 169277DA CH 169277 A CH169277 A CH 169277A
Authority
CH
Switzerland
Prior art keywords
rail
rails
road
road body
sides
Prior art date
Application number
Other languages
German (de)
Inventor
Bertschinger Walo
Original Assignee
Bertschinger Walo
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bertschinger Walo filed Critical Bertschinger Walo
Publication of CH169277A publication Critical patent/CH169277A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/06Pavings adjacent tramways rails ; Pavings comprising railway tracks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Description

  

  Verfahren     znin    Einbar von Schienen, insbesondere Strassenbahnschienen,  in einen Strassenkörper.    Wenn Schienen, insbesondere     Strassen-          bahnschienen,    in der bisher üblichen Weise  fest in den     Strassenkörper    eingebaut werden,  treten innerhalb relativ kurzer Zeit sehr un  angenehme Schäden auf, die einen fortwäh  renden Unterhalt sowohl der Schienen, wie  auch der angrenzenden Beläge des Strassen  körpers bedingen. Diese schadhaften Stellen  sind bei Steinpflaster besonders schädlich,  weil dadurch der Anfang zum Ausspülen des  Pflastersandes gebildet ist.

   Die Wirkung  dieser Erscheinungen bleibt aber nicht nur  auf den unmittelbar die Schiene begrenzen  den Teil des     Strassenkörpers    beschränkt, son  dern setzt sich in dem ganzen, sich links und  rechts an die     Schiene    anschliessenden Stra  ssenbelag fort.  



  Alle diese Erscheinungen sind dadurch       bedingt,    dass infolge der beständigen Er  schütterungen der Schiene, dieselbe sich     lok-          kert    und von dem Strassenkörper selbst und  dem oben abschliessenden Belag sich ablöst.  Die hierdurch entstandenen Risse lassen nun    Wasser in den Schienenunterbau einsickern.  Je mehr die Schiene auf diese Weise ge  lockert wird,     desto    grösser sind somit auch  die Zerstörungserscheinungen im Schienen  unterbau und dem anschliessenden Belag.  



  Bei dem Verfahren zum Einbau von  Schienen in Strassenkörper gemäss vorliegen  der     Erfindung    sollen die vorstehend erwähn  ten     Übelstände    dadurch     vermieden    werden,  dass mindestens zu beiden     Seiten    des Steges  der Schiene ein mit dieser zusammenhängen  der Körper     hergestellt    wird,.und dass der  durch die Schiene und diesen Körper gebil  dete Schienenteil vom eigentlichen Strassen  körper durch eine Trennschicht isoliert wird.  Der erwähnte Schienenteil kann unabhängig  vom Strassenbelag arbeiten und gleichzeitig  die Stösse aufnehmen, so dass hier eine Zer  störung des Strassenkörpers vermieden ist.

    Die Trennschicht verhindert ferner das Ein  dringen von Wasser in den     Strassenkörper.     



  Auf der beiliegenden Zeichnung sind ver  schiedene, nach dem Verfahren gemäss vor-      liegender Erfindung in einen Strassenkörper  eingebaute Strassenbahnschienen beispiels  weise dargestellt.  



       Fig.    1 zeigt einen     Querschnitt    durch zwei  zusammengehörige, in einen Strassenkörper       eino-ebaute    Strassenbahnschienen und       @Fig.    2 bis 4 je ein     Querschnitt    einer     ab-          eänderten    Ausführungsform.  



  Bei allen dargestellten Ausführungsbei  spielen ist zu beiden Seiten des Steges einer  Strassenbahnschiene 1 ein mit dieser zusam  menhängender Körper 2 vorhanden, der  durch Ausfüllen des Raumes zwischen Schie  nenkopf und Schienenfuss mit Mörtel oder  Asphalt hergestellt ist. Statt auf diese  Weise, könnte dieser Körper auch als armier  ter Beton- oder Asphaltkörper für sich her  gestellt und     beidseitig    des Steges und unter  der Schiene an dieselbe angeschlossen sein.  



  Bei der     Ausführungsform    nach     Fig.    1 ist  zu beiden Seiten des Körpers 2 zwischen  demselben und dem Strassenbeton 3     bezw.     dem Belag 4 eine vom Schienenkopf bis un  terhalb des Schienenfusses reichende Asphalt  platte 5 eingesetzt, welche oben längs des  Schienenkopfes verläuft und denselben ab  dichtet. Der Strassenbelag 4 kann aus  Stampf- oder     Gussasphalt,    aus Steinpflaster,       Topeka    oder einer Art     Makadam        bestehen.     Zwischen dem Schienenfuss und dem Beton  ist ferner die übliche Schicht     Kramp-Beton    G  vorhanden.  



  Die Ausführungsform nach     Fig.    2 unter  scheidet sich von der Ausführung nach     Fig.    1  dadurch, dass an     Stelle    der     Asphaltplatte    5  zwischen dem Körper 2 und dem Schienen  kopf einerseits und dem Strassenkörper 3, 4  anderseits eine Fuge gebildet ist, die mit       Asphalt-Vergussmasse    ausgegossen ist. Auch  durch diese Asphaltschicht wird eine gute  Abdichtung am Schienenkopf erzielt.  



  Bei der Ausführungsform nach     Fig.    3 ist  zwischen dem Körper 2 und dem Strassen  beton 3 eine Asphaltplatte 5 eingesetzt, die  bis zum Schienenkopf reicht und zwischen  dem     Schienenkopf    und dem Strassenbelag 4  ist eine mit einer     Asphaltfugenvergussmasse     9 ausgegossene Fuge gebildet.    Die Ausführungsform nach     Fig.    4 unter  scheidet sich von der Ausführungsform nach       Fig.    1 dadurch,     da.ss    hier ausser. den beiden  seitlichen     Asphaltplatten    5 auch unter dem  Schienenfuss eine     Asphaltplatte    10 eingefügt  ist.  



  Dadurch, dass bei allen beschriebenen  Ausführungen eine Trennschicht zwischen  dem aus der Schiene 1 und dem Körper<B>22</B>  gebildeten Schienenteil und dem     Strassen-          körper    eingefügt ist, kann dieser     Schienenteil.     unabhängig vom eigentlichen Strassenkörper  arbeiten, und er nimmt gleichzeitig die .Stösse  auf, wodurch eine Beschädigung des Strassen  körpers weitgehend vermieden ist. Die  Trennschicht verunmöglicht ferner das Ein  dringen von Wasser in den Strassenkörper.



  Method for inserting rails, in particular tram rails, into a road body. If rails, especially tram rails, are permanently installed in the road body in the usual way, very unpleasant damage occurs within a relatively short time, which requires continuous maintenance of both the rails and the adjacent surfaces of the road body. These damaged areas are particularly harmful with stone paving, because they are the starting point for rinsing out the paving sand.

   The effect of these phenomena, however, is not limited to the part of the road that directly delimits the rail, but continues in the entire road surface that adjoins the rail on the left and right.



  All of these phenomena are due to the fact that, as a result of the constant vibrations of the rail, it loosens and becomes detached from the road itself and the covering at the top. The resulting cracks allow water to seep into the rail substructure. The more the rail is loosened in this way, the greater the signs of destruction in the rail substructure and the adjoining surface.



  In the method for installing rails in road bodies according to the present invention, the abovementioned inconveniences are to be avoided in that at least on both sides of the web of the rail a body is made connected to this, and that the body is made by the rail and this Body formed rail part is isolated from the actual road body by a separating layer. The mentioned rail part can work independently of the road surface and at the same time absorb the shocks, so that a destruction of the road body is avoided here.

    The separating layer also prevents water from entering the road.



  In the accompanying drawing, various tram rails built into a road body using the method according to the present invention are shown, for example.



       Fig. 1 shows a cross section through two related tram tracks and @Fig. 2 to 4 each have a cross section of a modified embodiment.



  In all of the illustrated Ausführungsbei play on both sides of the web of a tram rail 1 with this coherent body 2 is present, which is made by filling the space between the rail head and rail foot with mortar or asphalt. Instead of this, this body could also be made as a reinforced concrete or asphalt body for itself and connected to the same on both sides of the web and under the rail.



  In the embodiment of Fig. 1 is on both sides of the body 2 between the same and the road concrete 3 BEZW. the pavement 4 a from the rail head to un below the rail foot reaching asphalt plate 5 used, which runs along the top of the rail head and seals the same from. The road surface 4 can consist of rammed or mastic asphalt, stone paving, Topeka or a kind of macadam. The usual layer of Kramp concrete G is also present between the rail foot and the concrete.



  The embodiment according to FIG. 2 differs from the embodiment according to FIG. 1 in that instead of the asphalt slab 5 between the body 2 and the rail head on the one hand and the road body 3, 4 on the other hand, a joint is formed with asphalt potting compound is poured out. This asphalt layer also provides a good seal on the rail head.



  In the embodiment according to FIG. 3, an asphalt slab 5 is inserted between the body 2 and the road concrete 3, which extends to the rail head and between the rail head and the road surface 4 a joint filled with an asphalt joint sealing compound 9 is formed. The embodiment according to FIG. 4 differs from the embodiment according to FIG. 1 in that except here. the two lateral asphalt slabs 5, an asphalt slab 10 is also inserted under the rail foot.



  Because a separating layer is inserted between the rail part formed from the rail 1 and the body 22 and the road body in all the embodiments described, this rail part can. work independently of the actual road body, and at the same time it absorbs the .Shocks, whereby damage to the road body is largely avoided. The separating layer also makes it impossible for water to penetrate the road.

 

Claims (1)

PATENTANSPRUCH: Verfahren zum Einbau von Schienen, ins besondere Strassenbahnschienen, in einen Strassenkörper, dadurch gekennzeichnet, dass mindestens zu beiden Seiten des .Steges der Schiene ein mit dieser zusammenhängender Körper hergestellt wird, und dass der durch die Schiene und diesen Körper gebildete Schienenteil vom eigentlichen Strassenkörper durch eine Trennschicht isoliert wird. UNTERANSPRÜCHE: 1. Verfahren nach Patentanspruch, dadurch gekennzeichnet, dass die Trennschichten aus Asphalt hergestellt werden. PATENT CLAIM: A method for installing rails, in particular tram rails, in a road body, characterized in that at least on both sides of the .steges of the rail a connected body is made, and that the rail part formed by the rail and this body from the actual Road body is isolated by a separating layer. SUBClaims: 1. Method according to claim, characterized in that the separating layers are made from asphalt. \?. Verfahren nach Patentanspruch, dadurch gekennzeichnet, dass die Trennschichten längs und seitlich des Schienenkopfes ver laufend hergestellt werden, so dass sie zu gleich dessen Abdichtung bilden. 3. Verfahren nach Patentanspruch, dadurch gekennzeichnet, dass beidseitig des Schie nenteils zwischen demselben und dem Strassenkörper eine Platte eingesetzt wird. 4. Verfahren nach Patentanspruch, dadurch gekennzeichnet, dass beidseitig des Schie nenteils zwischen demselben und dem Strassenkörper eine Fuge gebildet wird, welche durch eine Vergussmasse ausgegos sen wird. \ ?. Method according to patent claim, characterized in that the separating layers are produced along and to the side of the rail head so that they also form its seal. 3. The method according to claim, characterized in that a plate is used on both sides of the rail part between the same and the road body. 4. The method according to claim, characterized in that a joint is formed on both sides of the rail part between the same and the road body, which is poured out by a casting compound. :5. Verfahren nach Patentanspruch und Un teranspruch ?, dadurch gekennzeichnet, da.ss beidseitig des Schienenteils zwischen demselben und dem Strassenkörper eine bis zum Schienenkopf reichende Platte eingesetzt und über dieser Platte längs des Schienenkopfes eine Fuge gebildet wird, welche mit einer Vergussmasse aus gegossen wird. 6. Verfahren nach Patentanspruch, dadurch gekennzeichnet, dass eine isolierende Trennschicht ausser beidseitig des Schie nenteils auch unter demselben hergestellt wird. : 5. Method according to claim and sub-claim?, Characterized in that a plate extending to the rail head is inserted on both sides of the rail part between the same and the road body and a joint is formed over this plate along the rail head, which is cast with a casting compound. 6. The method according to claim, characterized in that an insulating separating layer is produced under the same except on both sides of the rail part.
CH169277D 1933-09-19 1933-09-19 Method for installing rails, in particular tram rails, in a road body. CH169277A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH169277T 1933-09-19

Publications (1)

Publication Number Publication Date
CH169277A true CH169277A (en) 1934-05-31

Family

ID=4421408

Family Applications (1)

Application Number Title Priority Date Filing Date
CH169277D CH169277A (en) 1933-09-19 1933-09-19 Method for installing rails, in particular tram rails, in a road body.

Country Status (1)

Country Link
CH (1) CH169277A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2799769A1 (en) * 1999-10-18 2001-04-20 Screg METHOD FOR CONTAINING BITUMINOUS ENROBES NEAR A RAIL AND DEVICE FOR IMPLEMENTING SAME

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2799769A1 (en) * 1999-10-18 2001-04-20 Screg METHOD FOR CONTAINING BITUMINOUS ENROBES NEAR A RAIL AND DEVICE FOR IMPLEMENTING SAME
EP1094156A1 (en) * 1999-10-18 2001-04-25 Screg Method and apparatus for confining a bituminous road covering around a rail

Similar Documents

Publication Publication Date Title
CH678200A5 (en)
EP0663470B1 (en) Process for obtaining a superstructure for railway tracks
US2286019A (en) Expansion joint
DE19620731A1 (en) Rigid track for rail vehicles across bridges
AT410329B (en) Ballastless superstructure
DE4401260C1 (en) Permanent waxy construction for railway tracks, esp. for high speed
CH169277A (en) Method for installing rails, in particular tram rails, in a road body.
DE3810700A1 (en) Method for producing a superstructure for railways
DE4423542A1 (en) Ballast for railway permanent way
EP0546380A1 (en) Railway track structure
DE2233263A1 (en) CONSTRUCTION PROCEDURES FOR UNDERPASSES (RAILWAYS, ROADS) IN PARTICULAR FOR CASES WHERE TRAFFIC MUST NOT BE INTERRUPTED ON THE ROUTE TO BE UNDERPASSED
DE19952803C2 (en) Superstructure for rail-bound public transport vehicles and method and device for its manufacture
AT525562B1 (en) Track layout and track layout system
DE3608344C2 (en)
DE443351C (en) Edge edging for expansion joints to be filled with bitumen or the like in otherwise jointless pavement
DE661279C (en) Insulated wooden sleeper bedding
EP1229169B1 (en) Joint sealing between a rail and a paved area and process of making the same
DE962440C (en) Road surface made of prestressed concrete, preferably made of pre-stressed pre-fabricated parts
DE1946712A1 (en) Insulation for level crossings
DE850457C (en) Overhead fastening made of reinforced concrete slabs for track systems
DE508171C (en) Tram track on which the rails are anchored with reinforcements tamped or cast on both sides
CH199994A (en) Railway superstructure.
DE1029403B (en) Overhead fastening made of reinforced concrete slabs for track systems
DE507641C (en) Tie rod cover for tram tracks
DE520713C (en) Bedding for tram rails