CH139454A - Method of constructing buildings, apparatus for carrying out this method and building obtained by this method. - Google Patents

Method of constructing buildings, apparatus for carrying out this method and building obtained by this method.

Info

Publication number
CH139454A
CH139454A CH139454DA CH139454A CH 139454 A CH139454 A CH 139454A CH 139454D A CH139454D A CH 139454DA CH 139454 A CH139454 A CH 139454A
Authority
CH
Switzerland
Prior art keywords
posts
pillars
building
floor
facade
Prior art date
Application number
Other languages
French (fr)
Inventor
Perret Louis
Original Assignee
Perret Louis
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Perret Louis filed Critical Perret Louis
Publication of CH139454A publication Critical patent/CH139454A/en

Links

Description

  

  Procédé de construction des édifices, appareil pour la mise en     oeuvre    de ce procédé_  et édifice obtenu par ce procédé.    La présente invention a pour objet:  1  Un procédé     deconstruction    des édifices  à étages, caractérisé par le fait que Ton     cons-          ïruit    des piliers de     fondations,    puis que l'on  réunit ces piliers par des entretoises, ensuit  on établit des poteaux au voisinage immédiat  desdits piliers, on construit une partie ;

  des  édifices que l'on rend solidaires     desdits    po  teaux, on monte sur les piliers de fondations  des .appareils de levage, puis avec ces appa  reils on soulève les poteaux et la partie de       l'édifice    déjà     construite,    enfin on réunit par  ,des entretoises l'ensemble de poteaux voisins  ,de chaque pilier -de fondations -de façon  former l'un .des piliers de l'édifice.  



  2  Un appareil pour la mise en     #uvre    du  procédé     ci-dessus        comportant    des vérins à vis  et écrous fixés     respectivement    sur des piliers  verticaux.  



       3     Un édifice à étage obtenu par le     pro-          c4dé    ci-dessus.    A titre     ,d'exemple,    on a     représenté    au des  sin annexé un -appareil pour la mise en     oeuvre     du procédé et divers éléments intéressants -le  l'immeuble.  



  La     fig.    1 est une vue .de .l'appareil suivant  la ligne     B-C-D-E    de la     fig.    3;  La     fig.    2 est une vue     suivant    la ligne       A-B-C-D        @de    la     fig.    3;  La     fig.    3 est une vue en plan de     l'appn-          reil    suivant la ligne     F-G-H-I    de la       fig.    l;  La     fig.    4 est une vue en plan d'un pilier  de la     partie    médiane -de     l'édifice    construit;

    La     fig.    5 est une élévation partiellement       coupée    du pilier -de la     fig.    4;  La.     fig.    6 est une vue en plan d'un pilier  de     façade        @de        d'immeuble;     La     fig.    7 est     une    vue en plan d'un pilier       d'anble.     



  On effectuera une fouille de profondeur  convenable sur l'emplacement que doit occu  per l'édifice. Au fond de     celle=ci    on établira      soit une fondation continue, soit plusieurs  piles de maçonnerie sur lesquelles on éta  blira un appareil destiné à élever les étages  construits au fur et à mesure de leur cons  truction, tel que celui représenté au dessin  annexé.  



  Cet appareil comporte des poteaux ver  ticaux 5, que maintiennent des cadres infé  rieurs 1, 2 et supérieurs 6, 7. Ce     iderriier    sert  à     supporter    le ou les étages :construits pen  dant la     construction    d'un étage. Un plancher  de service 11, facilite la construction de ce  dernier.  



  Les panneaux destinés à constituer le  plancher     haut,de    l'étage supérieur sont posés  sur le plancher de service 11, en ayant soin  de laisser entre eux des espaces suffisants  pour le passage des poteaux 5 ,de l'appareil et       des    -diverses entretoises et contreventements  qui assurent leur     rigidité.    On assemble alors  les piliers de l'édifice aux angles des pan  neaux précédents. Tout l'ensemble est alors  soulevé au-dessus du cadre     supérieur    6, 7, sur  lequel repose le plancher dont les intervalles  entre panneaux sont alors garnis par des élé  ments moulés d'avance qui le complètent     .#4     assurent sa rigidité.  



  A ce moment, on établit définitivement  la couverture, terrasse, charpente, toiture,       ebc.,    avec tous ses :accessoires. On pourra ainsi  travailler ensuite sur le chantier à l'abri des  intempéries.  



  On     construit    alors sur le plancher de ser  vice 11, le plancher bas de l'étage supérieur.  On     monte    les piliers de l'édifice qui relieront  les deux planchers. L'étage ainsi terminé       comme    gros     oeuvre    est     alors    exhaussé au  moyen d'un appareil de levage tel que celui  décrit ci-dessous, de manière que son plancher  bas vienne .au-dessus du cadre supérieur     tle     l'appareil pour s'y reposer en supportant l'é  tage     construit.    Avant l'exhaussement, on a       placé    sur le plancher bas .les panneaux des  tinés à la façade;

   lorsque ce plancher     est;     arrivé à la hauteur     du.    premier étage, on re  lève lesdits panneaux et on les met en place,  par exemple :au moyen d'une :grue. On     éom-          plète    alors la     construction    notamment, en    mettant en place les cloisons, parquets, cana  lisations, peinture, vitrerie, etc.  



  On     procèdera    de la même manière pour  les étages suivants et pour leur exhausse  ment.  



  Cependant, il y a lieu de remarquer  qu'une fois le     rez-de..ch-aussée    de l'immeuble  construit, il     faudra    caler les piliers de l'édi  fice sur les piles de maçonnerie :du sous-sol.  



  Dans le cas :d'un édifice -de grandes di  mensions, on peut l'édifier par tranches ver  ticales successives.  



  Les travaux de construction sont parti  culièrement facilités par     l'appareil    représenté  au -dessin annexé, dont la, fi-. 1 est une vue  suivant la ligne     BCDE    de la     fig.    3, tandis  que la     fig.    2 en est une vue suivant la ligne       ABCD    de la     fig.    3, qui est elle-même une vue  en plan de l'appareil suivant la. ligne     I'GHI     de la     fig.    1.  



  L'appareil représenté au dessin annexé       comporte    un     poutrage    inférieur formé par des  entretoises longitudinales 1 et transversales       ?,    reposant sur les piles de maçonnerie 3 éta  blies au fond de la fouille 4. Sur ce     poutrage     sont     montés,des    poteaux 5, dont les têtes sont  maintenues par un second     poutra.ge    formé  également par -des entretoises longitudinales  6 et     transversales    7. C'est sur ce poutrage que  viendront     s'appuyer    le ou les étages     construits     au moyen de taquets 8.

   On pourra même  prévoir sur le poutrage     -des    chemins de rou  lement 12 pour une grue. La     rigidité    -de l'ap  pareil est -assurée par -des     contreventements          verticaux    9 entre     porteaux    5 et des contrefi  ches 10.  



  L'appareil comporte également un plan  cher     -de    service 11, placé légèrement au-des  sous du plancher de .l'étage en     construction     et formé par des poutrelles     longitudinales    et  transversales fixées aux poteaux 5.  



  Ces derniers supportent les dispositifs de  levage constitués par -des vis 14, maintenues  par le haut sur des consoles 16, et sur le bas  :desquelles sont     clavetés    des pignons coniques  17 entraînés par des arbres 18. Ces derniers  reçoivent leur mouvement soit :d'un arbre du       commande    générale entraîné par un moteur      quelconque 18, soit de dispositifs de     manaeu-          vre    à bras 19.  



  Sur les vis 14 peuvent se     @déplacer    Verti  calement sans tourner des     sabots    20, sur les  quels     viendront    s'appuyer les piliers     @de    l'édi  fice. Cet appareil d'ans lequel il n'y a_ ni     cà-          ble,    ni chaîne, offre une sécurité complète et  possède en outre l'avantage de l'irréversibi  lité absolue.  



  Sur les     @chemins    de roulements 12 peut se  déplacer horizontalement une grue servant  principalement à la pose des revêtements de  façade.  



  Le ou les étages construits reposeront     flanc     sur l'appareil par les taquets 8. Les piliers  -de l'étage en construction sont de préférence  assemblés aux .amorces des piliers déjà cons  truits -des étages supérieurs et sont en quel  que sorte suspendus à eux. Enfin le plan  cher de service 11 facilitera la pose du plan  cher de l'étage en construction, et pourra  comporter avantageusement -des voies de rou  lement pour faciliter les     man#uvres.    La       grue        permettra    notamment de poser des an  neaux de façade     rapidement    et d'une 'ma  nière générale les diverses parties     @âe    -la cons  truction.

   Enfin, le soulèvement     -les    étages  construits est assuré par le déplacement des  sabots 20 le long des vis 14, les sabots ve  nant prendre par     en--dessous    les poteaux de  l'étage qui vient d'être construit. Le     Soulève-          ment    est     commandé    soit par un moteur, soit  par une commande de secours à la main. Par       uite        d-u    .genre de commande des vis, on       pa.Lrra    soulever tous les sabots 20 d'une quan  tité égale. Au besoin on pourrait prévoir des       dispositifs    de rattrapage particulier.

   La     -rue     peut     se,d        épl.acer    sur les diverses façades, à cet  effet, le chemin de roulement comporte des  rails mobiles dans les angles, de manière à  pouvoir se mettre successivement dans le pro  longement de deux chemins de     roulement          consécutifs    à 90 .  



  On emploie -des piliers dont la forme per  met la constitution d'une ossature     métallique     très robuste.    Ainsi les piliers situés au milieu de l'édi  fice ont été représentés en plan     fig.    4 et en  coupe élévation partielle     fig.    5.  



  Les piliers sont formés de quatre mon  tants verticaux 30 formés d'un laminé en  forme d'Y comme l'indique la     fig.    4; des en  tretoises 31, -de préférence recourbées comme  12 montre la fi g. 5 et venant     s'assembler    sur       ks    montants 30 assurent     l'indéformabilité    de  l'ensemble du pilier. Sur -ces derniers sont  fixés des panneaux 32 qui donnent au pi  lier sa forme extérieure. Cette forme de pi  lier laisse intérieurement le passage du po  teau 5 -de     l'a,p.pareil    et     ménage    le logement  des divers     cànalisations.     



  Les piliers de façade     peuvent    être réali  5és comme il a été représenté à .la     fig.    6 qui  montre une coupe de ces piliers. Des     mon-          (:a.nts    verticaux 30 sont reliés par des entre  toises 31, et recouverts par des     panneaux    3,3  et 34, tandis que des     .couvre-joints    35 et     î)16     obturent les     intervalles    entre les panneaux  courants.  



  Les piliers d'angle sont formés par des  montants verticaux 30, comme il a été repré  senté à .la     fig.    7, recouverts     @de    panneaux 33  et 37.



  Method for constructing buildings, apparatus for carrying out this method and building obtained by this method. The present invention relates to: 1 A method of constructing multi-storey buildings, characterized by the fact that foundation pillars are constructed, then these pillars are joined by spacers, then posts are established in the immediate vicinity. of said pillars, a part is built;

  of the buildings which are made integral with the said posts, lifting devices are mounted on the foundation pillars, then with these devices the posts and the part of the building already constructed are lifted, and finally, by, spacers the set of neighboring posts, of each pillar - of foundations - so as to form one. of the pillars of the building.



  2 An apparatus for carrying out the above process comprising screw jacks and nuts respectively fixed on vertical pillars.



       3 A two-storey building obtained by the above process. By way of example, there is shown in the attached drawings an apparatus for implementing the method and various interesting elements the building.



  Fig. 1 is a view of .l'apparatus taken along the line B-C-D-E of FIG. 3; Fig. 2 is a view along the line A-B-C-D @ of FIG. 3; Fig. 3 is a plan view of the apparatus taken along the line F-G-H-I of FIG. l; Fig. 4 is a plan view of a pillar of the middle part of the constructed building;

    Fig. 5 is a partially cutaway elevation of the pillar of FIG. 4; Fig. 6 is a plan view of a building facade pillar; Fig. 7 is a plan view of an anble pillar.



  A suitable depth excavation will be carried out on the site to be occupied by the building. At the bottom of this, either a continuous foundation or several masonry piles will be established on which an apparatus will be established for raising the floors built as they are being built, such as that shown in the attached drawing.



  This apparatus comprises vertical posts 5, which are maintained by lower frames 1, 2 and upper 6, 7. This iderriier is used to support the floor (s): built during the construction of a floor. A service floor 11 facilitates the construction of the latter.



  The panels intended to constitute the upper floor, of the upper floor are placed on the service floor 11, taking care to leave between them sufficient spaces for the passage of the posts 5, the device and the various spacers and bracings which ensure their rigidity. The pillars of the building are then assembled at the angles of the preceding panels. The whole assembly is then lifted above the upper frame 6, 7, on which the floor rests, the intervals between the panels of which are then filled with elements molded in advance which complete it. # 4 ensure its rigidity.



  At this time, we definitively establish the cover, terrace, frame, roof, ebc., With all its: accessories. We can then work on the site sheltered from bad weather.



  The lower floor of the upper floor is then built on service floor 11. The pillars of the building are mounted which will connect the two floors. The floor thus completed as a shell is then raised by means of a lifting device such as that described below, so that its low floor comes above the upper frame of the device to rest on it. by supporting the built floor. Before the raising, we placed on the low floor. The panels of the tines to the facade;

   when this floor is; arrived at the height of. first floor, we lift said panels and put them in place, for example: by means of a: crane. The construction is then completed, in particular, by putting in place partitions, parquet floors, ducts, painting, glazing, etc.



  We will proceed in the same way for the following floors and for their raising.



  However, it should be noted that once the ground floor of the building has been constructed, the pillars of the building will have to be wedged on the masonry piles: from the basement.



  In the case of: a building of large dimensions, it can be erected in successive vertical sections.



  The construction work is particularly facilitated by the apparatus shown in the appended drawing, including the, fi-. 1 is a view along the line BCDE of FIG. 3, while fig. 2 is a view thereof along line ABCD of FIG. 3, which is itself a plan view of the apparatus according to the. I'GHI line of FIG. 1.



  The apparatus shown in the appended drawing comprises a lower beam formed by longitudinal 1 and transverse spacers?, Resting on the masonry piers 3 established at the bottom of the excavation 4. On this beam are mounted, posts 5, the heads of which are maintained by a second poutra.ge also formed by -longitudinal 6 and transverse spacers 7. It is on this beam that the floor or floors constructed by means of cleats 8 will rest.

   It is even possible to provide on the beams - rolling paths 12 for a crane. The rigidity of the device is ensured by vertical bracing 9 between gates 5 and braces 10.



  The apparatus also includes an expensive service plan 11, placed slightly below the floor of the floor under construction and formed by longitudinal and transverse beams fixed to the posts 5.



  The latter support the lifting devices consisting of -screws 14, held from above on consoles 16, and on the bottom: which are keyed bevel gears 17 driven by shafts 18. The latter receive their movement either: of a general control shaft driven by any motor 18, or by arm maneuvering devices 19.



  The screws 14 can move vertically without turning the shoes 20, on which the pillars of the building will rest. This device, in which there is no cable or chain, offers complete safety and has the further advantage of absolute irreversibility.



  A crane can move horizontally on the bearing paths 12, mainly used for laying the facade cladding.



  The constructed storey (s) will rest on the side of the apparatus by the cleats 8. The pillars of the storey under construction are preferably assembled with the primers of the pillars already constructed of the upper storeys and are in some way suspended from them. . Finally, the expensive service plan 11 will facilitate the installation of the expensive plan of the floor under construction, and may advantageously include rolling tracks to facilitate maneuvers. In particular, the crane will make it possible to install facade rings quickly and in general for the various parts of the construction.

   Finally, the lifting of the floors built is ensured by the movement of the shoes 20 along the screws 14, the shoes coming to take from below the posts of the floor which has just been built. Lifting is controlled either by a motor or by a manual emergency control. By uite d-u. Kind of control of the screws, we pa.Lrra raise all the shoes 20 by an equal amount. If necessary, special adjustment devices could be provided.

   The -street can be moved on the various facades, for this purpose, the track has movable rails in the corners, so as to be able to be placed successively in the extension of two consecutive tracks at 90 .



  Pillars are used whose shape allows the constitution of a very robust metal framework. Thus the pillars located in the middle of the building have been shown in plan fig. 4 and in section partial elevation FIG. 5.



  The pillars are formed from four vertical posts 30 formed from a Y-shaped laminate as shown in fig. 4; spacers 31, preferably curved as 12 shows in fi g. 5 and coming to be assembled on ks uprights 30 ensure the indeformability of the entire pillar. On these latter panels 32 are attached which give the piece its external shape. This form of pillar leaves internally the passage of the po teau 5 -de a, p.pareil and household housing the various cànalisations.



  The front pillars can be produced as shown in FIG. 6 which shows a section of these pillars. Mon- (: a.nts vertical 30 are connected by between bars 31, and covered by panels 3, 3 and 34, while .covers joints 35 and I) 16 close the gaps between the current panels.



  The corner pillars are formed by vertical uprights 30, as has been shown in .la fig. 7, covered with panels 33 and 37.

 

Claims (1)

REVENDICATIONS I Procédé de construction des édifices à étages, caractérisé par le fait que l'on construit des piliers :de fondations, puis que l'on réunit ces piliers par -des entre toises, ensuite on établit -des poteaux an voisinage immédiat desdits piliers, on construit -u-ne partie de l'édifice que l'on rend solidaire desdits poteaux, -on monte sur les piliers -de fondations dies ,appareils .de levage, puis, avec ces appareils on sou lève lies poteaux et la. CLAIMS I Method of construction of multi-storey buildings, characterized by the fact that one builds pillars: foundations, then that one joins these pillars by - between measuring boards, then one establishes - of the posts in the immediate vicinity of said pillars , we build -a-part of the building which is made integral with said posts, -on climbs on the pillars -de foundations dies, .de lifting devices, then, with these devices we lift the poles and the. partie,del'édific.edéjà construite, enfin on réunit par des en tretoises l'ensemble -le poteaux voisins de chaque pilier de fondations de façon à former l'un des piliers @de ,l'édifice. II Appareil pour la mise en ceuvre .du pro cédé suivant la revendication I, compor tant -des vérins à vis et écrous à fixer respectivement sur des piliers verticaux de l'édifice. III Edifice à étage obtenu par le procédé faisant l'objet de la revendication I. part, of the edifice already built, finally the whole - the neighboring posts of each foundation pillar are joined together by tresters so as to form one of the pillars @de, the building. II Apparatus for the implementation of the process according to claim I, comprising -des screw jacks and nuts to be fixed respectively on vertical pillars of the building. III Two-storey building obtained by the process forming the subject of claim I. SOUS-REVENDICATION S 1 Procédé suivant la revendication I, ,dans le quel on construit deux poteaux auprès de chaque pilier de fondation de façade, puis on sou élève -ces deux poteaux -et ensuite on les réunit par des entretoises. 2 Procédé suivant la revendication I, dans le quel on construit quatre poteaux auprès ,de chacun des piliers .de fondation situés à l'intérieur -de l'édifice, puis on soulève ,ces quatre poteaux et ensuite on les réu nit par -des entretoises. SUB-CLAIM S 1 A method according to claim I, in which two posts are constructed near each facade foundation pillar, then one raises -these two posts -and then they are joined by spacers. 2 The method of claim I, in which four posts are built near each of the foundation pillars located inside the building -de, then these four posts are lifted and then they are reunited by -des spacers. ô Procédé suivant la revendication I, dans le quel les panneaux destinés à constituer la façade sont placés sur le dernier plancher construit lorsque ledit plancher est au ni veau .du sol, puis après soulèvement de l'édifice, les panneaux sont relevés et mis en place sur la façade. Appareil suivant la. revendication II, ca ractérisé par l'adjonction de dispositifs de transmission rigides qui relient entre eux les vérins. 5 Edifice suivant la. revendication III, -dans lequel les poteaux ont une section en forme @d'y. ô Method according to claim I, in which the panels intended to constitute the facade are placed on the last floor constructed when said floor is at ground level, then after lifting the building, the panels are raised and placed in place on the facade. Device according to the. claim II, characterized by the addition of rigid transmission devices which interconnect the jacks. 5 Building following the. claim III, -wherein the posts have a y-shaped section.
CH139454D 1927-12-09 1928-12-04 Method of constructing buildings, apparatus for carrying out this method and building obtained by this method. CH139454A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR139454X 1927-12-09

Publications (1)

Publication Number Publication Date
CH139454A true CH139454A (en) 1930-04-30

Family

ID=8874469

Family Applications (1)

Application Number Title Priority Date Filing Date
CH139454D CH139454A (en) 1927-12-09 1928-12-04 Method of constructing buildings, apparatus for carrying out this method and building obtained by this method.

Country Status (1)

Country Link
CH (1) CH139454A (en)

Similar Documents

Publication Publication Date Title
US4206162A (en) Method for constructing concrete enclosures by combination of liftplate-slipform method
CN104520521B (en) High-rise raises concept
BE1003666A3 (en) Framework for buildings.
EP0507623A1 (en) Building construction
US3462908A (en) Method for erecting buildings
US3920780A (en) Method of erecting a multi-story building and apparatus
FR2564504A1 (en) MODULAR CONSTRUCTION BOX AND FORMWORK FOR ITS PRODUCTION
CH139454A (en) Method of constructing buildings, apparatus for carrying out this method and building obtained by this method.
US4180233A (en) Building construction system
US1678504A (en) Building construction
BE356359A (en)
FR2658228A1 (en) Method for constructing reinforced concrete reservoirs, prefabricated elements for implementing the said method and machine for producing the said elements
FR2635550A1 (en) Method for raising buildings
US981824A (en) Foundation for buildings in earthquake localities.
FR1465539A (en) Building construction process
EP1801301B1 (en) Method of adding extra floors on a building
JPH01256636A (en) Construction method of building
US1159615A (en) Method of constructing plastic walls.
KR102452215B1 (en) Method of constructing an unit bathroom using the level adjustment apparatus
BE511396A (en)
JP3008054B2 (en) Horizontal material temporary fixing device
US1887835A (en) Means for erecting building structures
CN213742344U (en) Mud pouring device for civil air defense structure
GB1293689A (en) Improvements in or relating to methods of building
FR2574837A1 (en) Methods for constructing walls at the edge of floors of buildings