AU2016218512A1 - Substructure for an artificial lawn - Google Patents

Substructure for an artificial lawn Download PDF

Info

Publication number
AU2016218512A1
AU2016218512A1 AU2016218512A AU2016218512A AU2016218512A1 AU 2016218512 A1 AU2016218512 A1 AU 2016218512A1 AU 2016218512 A AU2016218512 A AU 2016218512A AU 2016218512 A AU2016218512 A AU 2016218512A AU 2016218512 A1 AU2016218512 A1 AU 2016218512A1
Authority
AU
Australia
Prior art keywords
substructure
sand
aforesaid
water
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
AU2016218512A
Inventor
Ronald KONING
Peter Van Reijen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Desso Sports BV
Original Assignee
Desso Sports BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Desso Sports BV filed Critical Desso Sports BV
Publication of AU2016218512A1 publication Critical patent/AU2016218512A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C13/00Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
    • E01C13/02Foundations, e.g. with drainage or heating arrangements
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C13/00Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
    • E01C13/08Surfaces simulating grass ; Grass-grown sports grounds

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a substructure for an artificial lawn, comprising a top layer of artificial grass fibres and a number of underlying layers including a base layer, one or more intermediate layers and possibly other layers. The aforesaid substructure preferably comprises a water-permeable shock-absorbing layer, wherein said shock-absorbing layer is separated from said top layer of artificial grass fibres by one or more intermediate layers, wherein said one or more intermediate layers are selected from the group consisting of crushed stone, lava and sand, or a combination thereof.

Description

PCT/NL2016/050083 WO 2016/129995 1
Title: Substructure for an artificial lawn
Description
The present invention relates to a substructure for an artificial lawn, comprising a top layer of artificial grass fibres and a number of underlying layers including a base layer, one or more intermediate layers and possibly other layers.
In patent literature a number of publications are known in which a substructure is shown. From Dutch patent No. 1021171 there is thus known a substructure wherein an artificial lawn is made up of a comparatively hard underlayer, on which a flat layer of resilient and/or damping material is arranged, which layer may exhibit a thickness of about 6 - 35 mm, for example 10-14 mm. Arranged on the aforesaid resilient and/or damping layer is a top layer in the form of artificial turf consisting of a backing and synthetic grass blades connected thereto by tufting, knitting or weaving. The resilient and/or damping layer can be formed in different ways, for example by starting from a mixture of rubber granules, which are mixed with a liquid binder, for example polyurethane. A substructure for practicing the sport of golf is known per se from British patent publication GB 2,072,022.
International application WO 2006/007862 further discloses a substructure for a sports floor.
From Dutch patent No. 1013987 there is furthermore known a substructure arranged on a foundation layer for a sports field at least partially covered with natural grass, which substructure partially consists of rock wool.
Dutch patent No. 1016193 discloses an artificial lawn comprising a drainage layer made up of gravel, an underlayer arranged on top of the drainage layer, which underlayer comprises the earth that was originally dug off and subsequently removed, and an upper layer, in which fibres are present.
From European application EP 1 428 935 there is known a substructure for an artificial lawn in which a so-called "undersheet" of a geotextile material is laid over a prepared base, on which undersheet a layer of sand is arranged, on which subsequently a layer of rubber and finally a textile web are laid so as to thus form a so-called "envelope". The undersheet and the textile web are bonded together at their margins. Finally, an artificial lawn is installed on said substructure. PCT/NL2016/050083 WO 2016/129995 2
European application EP 0 093 008 discloses a base on which an envelope of a particular fabric is arranged, which envelope is filled with sand, for example, an underlayer comprising a sheet of bound rubber particles, on which underlayer an artificial lawn or a polyethylene foam layer can be provided. Depending on the sport to be practised, different sand grain sizes are used.
European application EP 1 462 572 relates to a substructure for sports floors, wherein a sand package is provided, in which a water distribution system is installed, which system comprises distribution pipes connected to a water reservoir.
From International application WO 2013009174 in the name of the present applicant there is known a substructure for an artificial lawn wherein an underlayer is present under a top layer of artificial grass fibres, which underlayer comprises a base layer, an intermediate layer located on top of said base layer and a sand layer located on top of said intermediate layer, wherein in particular the sand layer comprises at least two sublayers, wherein the first sublayer comprises a sand fraction having a particle size which is greater than the particle size of the sand fraction of the second sublayer.
Dutch patent NL 2009968 relates to a substructure for an artificial lawn, comprising a substantially water-impermeable insulation layer for draining the artificial lawn substantially in a horizontal direction and a drainage layer arranged on top of and/or in the insulation layer for draining the artificial lawn substantially in a vertical direction, such that an artificial lawn is positioned above the granulate layer, wherein the substructure construction further comprises a discharge system installed along the side edges. Rain water is thus discharged through the lava layer in a vertical direction up to the insulation layer, whereupon the water is laterally discharged in a substantially horizontal direction to drains provided at the side edges. Such drains are connected to a suction pipe and a pump via piping, wherein the discharged moisture is transported to a purification unit via a pressure pipe, after which the individual components are conveyed to reservoirs via conveyor pipes.
French patent publication FR 2 395 357 relates to a substructure for a sports field, comprising, in succession, a screed, a covering layer with a thickness of 25 mm, a dynamic layer with a thickness of 60 mm and a composite layer with a thickness of 100 mm, which aforementioned three layers are composed of the same type of material, viz crushed stone, lava or rubble, albeit in different grain sizes, viz. PCT/NL2016/050083 WO 2016/129995 3 0/3 mm, 3/16 mm and 16-32 mm, respectively. A drainage channel is provided at the edges or the circumference of such a substructure, whilst the area of the substructure is subdivided into zones of equal dimensions, in which a network of irrigation channels is provided. In the case of heavy rainfall, excess precipitation is discharged via the drainage channel. US patent application US 2004086664 relates to an artificial lawn comprising polypropylene monofilament-type artificial grass fibres.
German Offenlegungsschrift DE 38 35 880 relates to a resilient mat used in a substructure for practising sports.
Artificial lawns are generally used for a large number of sports, for example soccer and field hockey. In particular in the world of soccer the use of artificial grass will expand enormously. Because soccer is a contact sport with short sprints, sliding tackles and jumps, in particular when corners are taken, it is desirable that an artificial lawn exhibits a high degree of damping and resilience substantially similar to those of a natural substructure, viz a natural lawn. The substructure of a soccer field must further exhibit an optimally natural drainage behaviour, which implies that the formation of water puddles on the field in the case of rainfall is minimized. Furthermore, the top layer of such a soccer field must have the same "feel" as that of a natural lawn.
In the present artificial lawns on which soccer is played, the damping of the lawn depends substantially on the selection of the so-called infill material, for example ground rubber particles. With the passage of time, the damping of such a lawn will differ from the originally set value. Furthermore it is often necessary to provide certain places on the soccer field with extra amounts of infill material, which will lead to a non-homogeneous damping of the soccer field.
Another point of particular attention regarding sports fields whose top layer comprises artificial grass fibres, or possibly a combination of artificial grass fibres and natural grass, is the development of high temperatures. In particular in the case of sports fields situated in regions with a hot climate, the temperature of the lawn can run so high that playing on such a lawn is found to be objectionable by players. It is therefore desirable to develop a substructure for a sports field wherein the temperature of the lawn, in particular of the top layer thereof, can be controlled to a certain extent. PCT/NL2016/050083 WO 2016/129995 4
One aspect of the present invention is to provide a substructure for a sports field, in particular a sports field on which soccer is played, which substructure provides the sports field with damping characteristics which substantially correspond to those of a natural lawn.
Another aspect of the present invention is to provide a substructure for a sports field, in particular a sports field on which soccer is played, which substructure has a water management such that the formation of water puddles is minimised.
Another aspect of the present invention is to provide a substructure for a sports field, in particular sports field on which soccer is played, wherein the water level of the sports field can be controlled to a desired value.
Yet another aspect of the present invention is to provide a substructure for a sports field, in particular the sports field which soccer is played, wherein a substantially flat, stable base is obtained.
Yet another object of the present invention is to provide a substructure for a sports field wherein the temperature of the top layer of the sports field is more or less controllable, in particular wherein the occurrence of high-temperature is prevented.
The present invention thus relates to a substructure for an artificial lawn, comprising a top layer of artificial grass fibres and a number of underlying layers including a base layer, one or more intermediate layers and possibly other layers, wherein the aforesaid substructure is surrounded by an envelope, wherein said envelope is constructed so that the level of the water present within the envelope is vertically adjustable, wherein the adjustment of the aforesaid level can be carried out by using a pipe system positioned within the aforesaid envelope, through which pipe system water can be passed, wherein water can be withdrawn from the aforesaid substructure using the aforesaid pipe system, which water can exit to the aforesaid layers of the substructure.
The present inventors have found that one or more of the above aspects are met when such a substructure is used. To achieve a good vertical distribution of the water level in the substructure it is preferred that the aforesaid pipe system is located near the bottom side of the aforesaid envelope. From the viewpoint of a homogeneous distribution of the water level in the entire substructure, viz those in vertical (height) and in horizontal direction, it is desirable that the pipes PCT/NL2016/050083 WO 2016/129995 5 of the aforesaid pipe system are spaced a regular distance apart and that the pipe system extends substantially over the entire area of the aforesaid substructure. It has now been found to be possible to adjust the water level in the envelope such that the players of the artificial lawn will experience a surface temperature which is described as acceptable even in hot climatic regions. The "hot feet" sensation that is experienced with prior art artificial lawns is thus remedied.
To prevent damage to and clogging of the aforesaid pipe system it is desirable that the aforesaid pipe system is separated from said one or more layers by means of a water-permeable film.
In a special embodiment, the aforesaid substructure comprises a water-permeable shock-absorbing layer, wherein said shock-absorbing layer is separated from said top layer of artificial grass fibres by one or more intermediate layers. By providing a physical separation between the top layer of artificial grass fibres and the shock-absorbing layer, which separation concerns the presence of one or more intermediate layers, one or more of the aforesaid aspects are additionally met. The material for such an intermediate layer is selected from the group consisting of crushed stone, lava and sand, or a combination thereof.
Preferred materials for the shock-absorbing layer include: SBR rubber, ground plastic particles, polyethylene, polypropylene, polyamide, polyester or a mixture thereof, preferably polyethylene foam, possibly in combination with one or more binders. In certain embodiments it is desirable that the shock-absorbing layer is made up of a number of separate shock-absorbing layers. In other embodiments it is desirable that the shock-absorbing layer is made up of a single shock-absorbing layer.
The top layer of artificial grass fibres is preferably provided with a so-called infill material having a good water-permeability, preferably sand of the type that has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve. Said type of infill material is in particular suitable because of its good water-permeability, which aspect is of major importance in the present substructure, in particular as regards the simulation of "ebb and flow" yet to be discussed hereinafter.
It is in particular desirable that the aforesaid one or more intermediate layers comprise sand, wherein the sand comprising intermediate layer PCT/NL2016/050083 WO 2016/129995 6 is made up of at least two sublayers, wherein the first sublayer comprises a sand fraction having a particle size greater than that of the sand fraction of the second sublayer, wherein the first sublayer with the coarser sand fraction is positioned near the top layer. Such a composition of the sandy sublayers provides good water permeability and damping properties.
It is desirable that the sublayer comprising the coarser sand fraction is positioned near the top layer. Rainwater that will be discharged in downward direction through the top layer of artificial grass fibres will thus first pass the coarse sand fraction in the sand layer and subsequently the less coarse sand fraction. A good passage of rainwater is ensured. Moreover, the opposite direction of the movement of water in the substructure, viz from the bottom to the top, has found to be advantageous with such a distribution of fractions in the sand layer.
The present substructure in fact exhibits a simulation of "ebb and flow", which means that the water level in the substructure can rise and fall, wherein the water level can be adjusted as desired. It is desirable, therefore, that the layers present in the substructure make the transport of water possible. Such a transport of liquid through the substructure therefore has an upward direction of movement, viz in the direction of the top layer, and a downward direction of movement, viz away from the top layer, wherein the level or the position of the liquid in the substructure has been found to be precisely adjustable. The pipe system present in the substructure makes it possible to supply water to the substructure, so that the water level in the substructure, seen in vertical direction, will rise, or to withdraw water from the substructure, so that the water level will fall, seen in vertical direction. The pipe system is thus provided with openings, through which water surrounding the pipe system can enter the pipe system or, conversely, water can exit the pipe system. Because the aforesaid envelope surrounds the substructure on all sides, the water present in the substructure can be withdrawn from the substructure via said pipe system. In the case of very heavy precipitation, there is a possibility that the sports field will be flooded at the edges, in particular if the water-withdrawing capacity of the pipe system is insufficient. It will be apparent that the "upper side" of the substructure can be regarded as the surface on which sports are practised.
The particle size values mentioned herein also ensure a quick transport of water through the sand layer, which is desirable if an adjustment of the water level is aimed at. If a sand fraction comprising smaller particles than discussed PCT/NL2016/050083 WO 2016/129995 7 above is used, the water transport will experience a greater resistance, which will adversely affect the speed of response or response time of the water management system.
By using the aforesaid substructure configuration, a substructure is obtained which provides a stable base for the installation of an artificial lawn wherein the formation of holes and protrusions is minimised.
In such an embodiment it is preferable that the at least two sublayers of the aforesaid sand layer are separated from each other by means of a separation layer.
According to another embodiment it is preferable that the aforesaid one or more intermediate layers comprise sand, wherein said sand has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve. Such a sand composition exhibits very good water-permeability and damping characteristics.
Said intermediate layers and shock-absorbing layers may be separated from each other by a separation layer, in particular in order to prevent undesirable movement or mixing of sand fractions.
Examples of desired separation layers include cloth, fibre fabric, mat and geotextile. The separation layer is water-permeable and is preferably provided with perforations, so that transport of water can take place but movement of solid matter from one sublayer to the other sublayer is impeded.
In order to obtain in particular good damping properties it is desirable that the aforesaid shock-absorbing layer is embedded between two separate sand layers, wherein the two sublayers are preferably of the same type. In such an embodiment a number of shock-absorbing layers may be alternated with a number of sand layers by means of which the degree of damping of the final lawn can be controlled.
In certain embodiments, the shock-absorbing layer may comprise at least two separate shock-absorbing layers, for example three, four but in certain embodiments even five separate, shock-absorbing layers, wherein one or more intermediate layers, in particular sand layers, may be present between said shockabsorbing layers.
In the latter embodiment, such sand layers may be made up of at least two sublayers, wherein the first sublayer comprises a sand fraction having a PCT/NL2016/050083 WO 2016/129995 8 particle size greater than that of the sand fraction of the second sublayer, wherein the sublayer with the coarser sand fraction is located near the top layer.
In certain embodiments, on the other hand, it is desirable that the sand layer between the shock-absorbing layers has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve.
The particle size of the sublayer with the coarse fraction is preferably such that at least 80% of the particles have a particle size that ranges from 0 - 32 mm, preferably 1 - 32 mm, in particular 1 - 8 mm, more in particular 1 -4 mm.
The thickness of the sublayer with the coarse fraction is preferably 50 - 200 mm, in particular 75- 125 mm.
The second sublayer preferably comprises sand particles of which at least 80% have a particle size greater than 80 pm, preferably greater than 100 pm, in particular greater than 125 pm; the second sublayer in particular comprises sand particles of which at least 50% have a particle size greater than 125 pm, preferably greater than 150 pm, in particular greater than 200 pm.
The total thickness of layers located under the top layer of artificial grass fibres is in particular 40 - 150 cm.
The present substructure is thus surrounded by an envelope, wherein said envelope is constructed so that the water level within the envelope is vertically adjustable.
The aforesaid envelope is in particular made of a water-impermeable film, in particular a film selected from the group consisting of high density polyethylene (HDPE) and ethylene propylene diene monomer (EPDM).
For the transport of water through the package of layers of the present substructure it is desirable that a pipe system is present in one of the intermediate layers, preferably located under the aforesaid shock-absorbing layer (if present), through which pipe system water can be passed, wherein water can exit to the layers of the substructure.
The pipe system is in particular provided with pressure-reducing means for creating an underpressure in the pipe system, wherein the pipe system further comprises a water reservoir provided with one or more connection openings, an adjustable overflow for adjusting the water level in said reservoir, water level PCT/NL2016/050083 WO 2016/129995 9 measuring means and a controllable water supply with the necessary piping, pumps and valves.
The pressure reducing means in particular comprise water level reducing means for reducing the water level in the reservoir, wherein in particular the water level reducing means comprise a plunger pump.
The water reservoir is in particular incorporated in a circuit which further comprises a buffering vessel and an overflow, wherein the water reservoir is connected to the substructure via one or more connection openings, which connection openings abut the water-impermeable layer.
In a preferred situation, use can be made of solar energy and/or wind energy for driving the pumps, valves and control means.
The use of a substructure as described above, in particular if the substructure is surrounded by an envelope, makes it possible to irrigate the artificial grass fibres "from below", as it were. After all, the supply of water to the top layer of artificial grass fibres takes place via the sand layer located under the top layer, wherein in particular the intermediate layer is configured so that the water present in the sand layer cannot drain away to the layers under the sand layer. In addition to that, the aforesaid values for the grain analysis of the sand layer (carried out via a sieve setup in which several saves with different mesh widths are stacked one on top of the other, the layer that remains on the sieve in question is measured and the results are plotted in a graph) provide a good possibility of transporting water, viz as regards speed and retention capacity. Within that framework, coarser sand types are preferred. In addition to that it has been found that, using such a sand package, very flat layers can be obtained, which is desirable for playing football. Moreover, depressions or rutting will not occur when the structure is subjected to heavy loads from above, for example from vehicles moving thereover.
For supplying water to the "bottom side" of the top layer in this manner it is therefore desirable that a pipe system is present in one of the intermediate layers, through which pipe system water can exit to the layers thereabove. The pipe system is preferably positioned in a layer comprising a sand fraction that can be considered to be "fine", because in this way a quick response time is ensured. Such a position is also desirable in connection with the possibility of freezing, which makes it desirable to install the pipe system at some depth in the substructure, which situation may occur in particular during cold wintry periods in PCT/NL2016/050083 WO 2016/129995 10 certain countries. In another embodiment, on the other hand, it is also possible to position the pipe system in a sand layer comprising a coarser sand fraction.
The pipe system thus comprises pipes provided with regularly spaced perforations, wherein the water to be supplied to the artificial lawn can exit the pipe system via said perforations and subsequently accumulate more or less in the layers under the top layer of artificial grass fibres. It has been found that the preferred grain size of the sand particles makes it possible to adjust the water level in the sand layer such that an artificial lawn is obtained in which the water level, in combination with the damping level aimed at, makes playing on the lawn, in particular playing soccer, possible.
In order to prevent the water that is supplied to the layers via the pipe system from undesirably draining away to the underlying layers, it is preferable that such a layer is screened off at the bottom side thereof by means of a water-impermeable layer, preferably a film, for example a polyethylene film.
It is moreover desirable that the overall construction of the present substructure meets shock absorption and energy restitution requirements, because excessive springiness of an artificial lawn is found to be unpleasant and tiring by players. If the overall construction of the artificial lawn exhibits too much springiness, this will cause a ball that lands on the artificial lawn to bounce back too high and too fast in comparison with a natural lawn, which is undesirable. Moreover, players find running and making sprints thereon to be tiring and also unnatural. The present inventors have found that the special manner of positioning the shock-absorbing layer in the substructure makes it possible to construct a lawn in which the above problems are minimised.
The pipe system that is used preferably comprises pressure reducing means for creating an underpressure in the pipe system, wherein the pipe system further comprises a water reservoir provided with one or more connection openings, an adjustable overflow for adjusting the water level in the reservoir, water level measuring means and a controllable water supply. In such a construction it is in particular desirable that the pressure reducing means comprise water level reducing means for reducing the water level in the reservoir, wherein the water level reducing means preferably comprise a plunger pump. The aforesaid pipe system is furthermore preferably provided with a control unit that is connected at least to said water level measuring means, said controllable water supply and said pressure PCT/NL2016/050083 WO 2016/129995 11 reducing means. Said construction is thus suitable for supplying water to the substructure; it has in particular been found to be possible to treat a large ground area therewith.
The present invention will now be explained by means of a number of schematically illustrated examples, in which regard it should be noted, however, that the schematic views shown in the appended figures should not be construed as limitative. Moreover, the figures are not drawn to scale.
Figure 1 is a schematic view of the substructure for an artificial lawn according to the present invention.
Figure 2 is a schematic view of a substructure for an artificial lawn according to the present invention.
Figure 3 is a schematic view of another substructure for an artificial lawn according to the present invention.
Figure 4 is a schematic view of another substructure for an artificial lawn according to the present invention.
Figure 5 is a schematic view of another substructure for an artificial lawn according to the present invention.
Figure 1 is a schematic view of a substructure 100 for an artificial lawn according to the present invention. The substructure 100 comprises a top layer 1 provided with artificial grass fibres 2, in which top layer 1 a so-called infill material 25 having a good water-permeability is present. The substructure 100 is surrounded by an envelope 26, which envelope 26 is constructed so that the water level within the envelope 26 is vertically adjustable, which adjustment of the aforesaid level can be carried out by means of a pipe system 16 positioned within the aforesaid envelope, through which pipe system 16 water can be passed, wherein water can be withdrawn from said substructure 100 by means of said pipe system 16, which water can exit to the aforesaid layers of the substructure 100. The pipe system 16 is located near the bottom side 18 of the envelope 26, in particular in the base layer 5, the pipes being spaced a regular distance apart, and extends over substantially the entire area of the substructure 100. The pipe system 16 is separated from the base layer 5 by a water-permeable film 15. The openings of the pipe system 16, which openings (not shown) are located at the circumferential side thereof and which make it possible to supply and discharge water, are thus protected against damage, for example, but also against the ingress of sand-like materials, which could lead to PCT/NL2016/050083 WO 2016/129995 12 clogging. The layer 3 comprises a material selected from the group consisting of crushed stone, lava and sand, or a combination thereof. The pipe system described in the present application is thus a single pipe system, by means of which the water level in the substructure can be adjusted. Since the pipes of the pipe system are spaced a regular distance apart, a good supply and discharge of water both in horizontal and in vertical direction is realised in the substructure. In this way a good, quick and precise control of the water level is possible.
Figure 2 shows a substructure 10 for an artificial lawn, comprising a top layer 1 in which artificial grass fibres 2 are present. Present in the top layer 1 is a so-called infill material 25 having a good water-permeability, preferably sand of the type that has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve. Located under the top layer 1 is an intermediate layer 3 selected from the group consisting of crushed stone, lava and sand, or a combination thereof. Located under the intermediate layer 3 is shock-absorbing layer 4, under which shock-absorbing layer 4 a base layer 5 is located. The base layer 5 is provided with a water-permeable film 15 at the bottom side, under which film 15 a number of drainage pipes 16 are located. The whole of top layer 1, intermediate layer 3, shock-absorbing layer 4 and base layer 5 is surrounded by a water-impermeable envelope 26, which envelope 26 is made of a film selected from the group consisting of high density polyethylene (HDPE) and ethylene propylene diene monomer (EPDM). The water level in the vertical column consisting of the top layer 1, the intermediate layer 3, the shock-absorbing layer 4 and the base layer 5 can be controlled and adjusted by supplying and discharging water via the drainage pipes 16. Reference numeral 27 schematically indicates a situation in which a slight overpressure is created in the drainage pipes 16, so that water can exit the drainage pipes 16. Because of the presence of the envelope 26, the exiting water can only move upward, in the direction of the top layer 1. It has thus been found to be possible to direct water exiting from the drainage pipes 16 toward the top layer 1, so that the players of the lawn will experience a natural moisture content. If desired, the water level thus achieved can subsequently be lowered again by creating a slight underpressure in the drainage pipes 16, so that water will be removed, resulting in a reduced water level in the package consisting of the top layer 1, the intermediate layer 3, the shock-absorbing layer 4 and the base layer 5. Said PCT/NL2016/050083 WO 2016/129995 13 water level can thus be adjusted and controlled by means of the pressure in the drainage pipes 16. The presence of said envelope thus ensures that the water exiting from the drainage pipes 16 cannot drain away undesirably. Such a natural moisture content makes it possible to approximate the natural characteristics of a natural lawn, especially as regards the sliding behaviour. In particular in the case of the sport of soccer, in which sliding tackles frequently occur, it is desirable that the surface on which the soccer is played does not put the players at a disadvantage. Although mention is made of artificial grass fibres in the top layer 1 in the present description, the top layer 1 may also comprise natural grass talks in addition to artificial grass fibres. Such a lawn, also referred to as hybrid lawn, is disclosed in US patent US 5,540,960 in the name of the present applicant, the contents of which are to be considered as fully incorporated herein. If desired, the top layer 1 may comprise so-called infill materials (not shown).
Figure 3 shows a substructure 20 for an artificial lawn, comprising a top layer 1 provided with artificial grass fibres 2. Present in the top layer 1 is a so-called infill material 25 having a good water-permeability, preferably of the type as described with reference to figure 2. Located under the top layer 1 is an intermediate layer 3, which is made up of two separate sand layers 6, 7. The sand layers 6, 7 can thus be regarded as two sublayers, wherein the first sublayer 6 comprises a sand fraction having a particle size greater than that of the sand fraction of the second sublayer 7, wherein the first sublayer 6 with the coarser sand fraction is located near the top layer 1. Located under the intermediate layer 3 is a shock-absorbing layer 4, under which shock-absorbing layer 4 a base layer 5 is located. The base layer 5 is provided with a water-permeable film 15 at the bottom side thereof, under which film 15 a number of drainage pipes 16 are located. The whole of top layer 1, intermediate layer 3, shock-absorbing layer 4 and base layer 5 is surrounded by a water-impermeable envelope 26, which envelope 26 is made of a film selected from the group consisting of high density polyethylene (HDPE) and ethylene propylene diene monomer (EPDM). Reference numeral 27 schematically indicates a situation in which a slight overpressure is created in the drainage pipes 16, so that water can exit the drainage pipes 16. Because of the presence of the envelope 26, the exiting water can only move upward, in the direction of the top layer 1. As already discussed with reference to figure 2, the special composition of the substructure and the PCT/NL2016/050083 WO 2016/129995 14 presence of drainage pipes 16 make it possible to realise a quick an precise adjustment of the water level in the substructure 20.
Figure 4 shows a substructure 30 for an artificial lawn, comprising a top layer 1 provided with artificial grass fibres 2. Present in the top layer 1 is a so-called infill material 25 having a good water-permeability, preferably of the type as described with reference to figure 2. Located under the top layer 1 is an intermediate layer 3 selected from the group consisting of crushed stone, lava and sand. Located under the intermediate layer 3 is a shock-absorbing layer 4, which shock-absorbing layer 4 is made up of a number of separate shock-absorbing layers 8, 9, under which a base layer 5 is located. The base layer 5 is provided with a water-permeable film 15 at the bottom side thereof, under which film 15 a number of drainage pipes 16 are located. The whole of top layer 1, intermediate layer 3, shock-absorbing layer 4 and base layer 5 is surrounded by a water-impermeable envelope 26, which envelope 26 is made of a film selected from the group consisting of high density polyethylene (HDPE) and ethylene propylene diene monomer (EPDM). Reference numeral 27 schematically indicates a situation in which a slight overpressure is created in the drainage pipes 16, so that water can exit the drainage pipes 16. Because of the presence of the envelope 26, the exiting water can only move upward, in the direction of the top layer 1. The water level in the vertical column consisting of the top layer 1, the intermediate layer 3, the shock-absorbing layer 4 and the base layer 5 can be controlled and adjusted in a precise and quick manner by supplying and discharging water via the drainage pipes 16.
Figure 5 shows a substructure 40 for an artificial lawn, comprising a top layer 1 provided with artificial grass fibres 2. Present in the top layer 1 is a so-called infill material 25 having a good water-permeability, preferably of the type as described with reference to figure 2. Located under the top layer 1 is an intermediate layer 3 selected from the group consisting of crushed stone, lava and sand. Located under the intermediate layer 3 are a number of alternately arranged intermediate layers 3 and shock-absorbing layers 4, which are positioned on top of a base layer 5. Such intermediate layers have been selected from the group consisting of crushed stone, lava and sand, or a combination thereof. In a special embodiment it is desirable that the shock-absorbing layer 4 is made up of a number of separate shock-absorbing layers (not shown). The base layer 5 is provided with a water-permeable film 15 at the bottom side thereof, under which film 15 a number of PCT/NL2016/050083 WO 2016/129995 15 drainage pipes 16 are located. The whole of top layer 1, intermediate layers 3, shock-absorbing layers 4 and base layer 5 is surrounded by a water-impermeable envelope 26, which envelope 26 is made of a film selected from the group consisting of high density polyethylene (HDPE) and ethylene propylene diene monomer (EPDM). Reference numeral 27 schematically indicates a situation in which a slight overpressure is created in the drainage pipes 16, so that water can exit the drainage pipes 16. Because of the presence of the envelope 26, the exiting water can only move upward, in the direction of the top layer 1. The water level in the vertical column consisting of the top layer 1, the intermediate layer 3, the shock-absorbing layers 4 and the base layer 5 can be controlled and adjusted in a precise and quick manner by supplying and discharging water via the drainage pipes 16. Although the substructure 40 as shown comprises a construction of intermediate layer 3, shockabsorbing layer 4, intermediate layer 3, shock absorbing layer 4, it is also desirable in certain embodiments that one or more shock absorbing layers 4 are made up of a number of separate shock-absorbing layers 8, 9, which separate shock-absorbing layers 8, 9 may in turn be separated from each other by an intermediate layer 3 or a base layer 5.
The present substructure as shown in a number of embodiments in figures 1-4 in fact shows a simulation of "ebb and flow", which means that the water level in the substructure can rise and fall, wherein the desired water level is adjustable.
For easy reference, the separation layers that may be positioned between the aforesaid layers are not shown in the figures. Examples of such separation layers are course, fibre fabric, mat and geotextile.
In figures 1-4, the operation of the drainage tubes 16 is not discussed, but it can take place in the manner as published in W02013/009174 in the name of the present applicant, the contents of which document may be considered as fully incorporated herein.
In WO2013/009174 the manner in which a drainage system is connected to a pipe that is in liquid communication with the substructure shown in figures 1-4 is described in great detail. Because of said liquid communication between the drainage system and the substructure, the height of the liquid level in the drainage system is an indication of the liquid level in the substructure. The drainage system is provided with a pipe, wherein the height of the water level in the PCT/NL2016/050083 WO 2016/129995 16 drainage system is determined by the positioning of the height of the pipe, which positioning is adjustable. Said pipe is in communication with an overflow via a conduit, which overflow is in communication with a buffer vessel via a conduit, which buffer vessel in in turn in communication with the drainage system via another 5 conduit.
If the water level in the substructure decreases to an undesirably low level, for example in the case of evaporation caused by radiation from the sun and wind, it is desirable that the intended water level be restored, viz. that water is supplied to the substructure. If the water level in the substructure has risen to 10 undesirably high level due to heavy rainfall, however, it is desirable that the intended water level in the substructure be restored. In the latter situation, the water level in the drainage system will rise and the "excess" water will be discharged from the drainage system as a result of the liquid communication between the substructure and the drainage system. The water to be discharged is directed to a so-called 15 overflow. In the overflow, the water discharged from the substructure is collected and subsequently directed to a buffer vessel, which is in particular intended to function as a water reservoir for adjusting and maintaining the water level in the substructure, and consequently also in the drainage system, to/at the desired level. Via a measuring and control system, the supply of water from the buffer vessel to the 20 drainage system is started when this is desirable.
It should be noted that the parts shown in figures 1-4 are not drawn to scale.
To obtain an optimum energy consumption it is desirable that the equipment used in the drainage system is driven via solar energy and/or wind 25 energy. It is also possible to use heating elements in the drainage system or in the buffer vessel and/or the overflow, which heating elements are preferably powered by solar energy and/or wind energy.

Claims (29)

1. A substructure for an artificial lawn, comprising a top layer of artificial grass fibres and a number of underlying layers including a base layer, one or more intermediate layers and possibly other layers, characterised in that the aforesaid substructure is surrounded by an envelope, wherein said envelope is constructed so that the level of the water present within the envelope is vertically adjustable, wherein the adjustment of the aforesaid level can be carried out by using a pipe system positioned within the aforesaid envelope, through which pipe system water can be passed, wherein water can be withdrawn from the aforesaid substructure using the aforesaid pipe system, which water can exit to the aforesaid layers of the substructure.
2. A substructure according to claim 1, characterised in that the aforesaid pipe system is located near the bottom side of the aforesaid envelope.
3. A substructure according to either one or both of claims 1-2, characterised in that the pipes of the aforesaid pipe system are spaced a regular distance apart and that the pipe system extends substantially over the entire area of the aforesaid substructure.
4. A substructure according to one or more of the preceding claims, characterised in that the aforesaid pipe system is separated from said one or more layers by means of a water-permeable film.
5. A substructure according to one or more of the preceding claims, characterised in that aforesaid envelope is made of a water-impermeable film, in particular a film selected from the group consisting of high density polyethylene (HDPE) and ethylene propylene diene monomer (EPDM).
6. A substructure according to one or more of the preceding claims, characterised in that the aforesaid substructure comprises a water-permeable shockabsorbing layer, wherein said shock-absorbing layer is separated from said top layer of artificial grass fibres by one or more intermediate layers.
7. A substructure according to claim 6, characterised in that the shockabsorbing layer is made up of a number of separate shock-absorbing layers comprising one or more components selected from the group consisting of SBR rubber, ground plastic particles, polyethylene, polypropylene, polyamide, polyester or a mixture thereof, preferably polyethylene foam, possibly in combination with one or more binders.
8. A substructure according to one or more of the preceding claims, characterised in that the aforesaid one or more intermediate layers comprise sand, wherein the sand comprising intermediate layer is made up of at least two sublayers, wherein the first sublayer comprises a sand fraction having a particle size greater than that of the sand fraction of the second sublayer, wherein the first sublayer with the coarser sand fraction is positioned near the top layer.
9. A substructure according to claim 8, characterised in that the at least two sublayers of the aforesaid sand layer are separated from each other by means of a separation layer.
10. A substructure according to one or more of the preceding claims, characterised in that the aforesaid one or more intermediate layers comprise sand, wherein said sand has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve.
11. A substructure according to one or more of the preceding claims, characterised in that one or more of the aforesaid intermediate layers and/or shockabsorbing layers are separated from each other by a separation layer
12. A substructure according to one or more of claims 9-11, characterised in that the aforesaid separation layer is selected from the group consisting of cloth, fibre fabric, mat and geotextile.
13. A substructure according to one or more of claims 6-12, characterised in that the aforesaid shock-absorbing layer is embedded between two separate sand layers.
14. A substructure according to claim 13, characterised in that the two sand layers are of the same type.
15. A substructure according to one or more of claims 6-14, characterised in that the shock-absorbing layer is made up of at least two separate shock-absorbing layers.
16. A substructure according to claim 15, characterised in that one or more intermediate layers are present between the aforesaid shock-absorbing layers, wherein the aforesaid one or more intermediate layers comprise sand.
17. A substructure according to claim 16, characterised in that the aforesaid sand is made up of at least two sublayers, wherein the first sublayer comprises a sand fraction having a particle size greater than that of the sand fraction of the second sublayer, wherein the sublayer with the coarser sand fraction is located near the top layer.
18. A substructure according to claim 16, characterised in that the aforesaid sand has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve.
19. A substructure according to one or more of claims 8-18, characterised in that the particles of the sublayer with the coarse fraction have a particle size such that at least 80% of the particles have a particle size that ranges from 0 - 32 mm, preferably 1 - 32 mm, in particular 1-8 mm, more in particular 1 -4 mm.
20. A substructure according to one or more of claims 8-19, characterised in that the thickness of the sublayer with the coarse fraction is 50 -200 mm, in particular 75 - 125 mm.
21. A substructure according to one or more of claims 8-20, characterised in that the second sublayer comprises sand particles of which at least 80% have a particle size greater than 80 pm, preferably greater than 100 pm, in particular greater than 125 pm.
22. A substructure according to one or more of claims 8-21, characterised in that the second sublayer comprises sand particles of which at least 50% have a particle size greater than 125 pm, preferably greater than 150 pm, in particular greater than 200 pm.
23. A substructure according to one or more of the preceding claims, characterised in that the total thickness of layers located under the top layer of artificial grass fibres is 40 - 150 cm.
24. A substructure according to one or more of the preceding claims, characterised in that the pipe system is provided with pressure-reducing means for creating an underpressure in the pipe system, wherein the pipe system further comprises a water reservoir provided with one or more connection openings, an adjustable overflow for adjusting the water level in said reservoir, water level measuring means and a controllable water supply with the necessary piping, pumps and valves.
25. A substructure according to claim 24, characterised in that the pressure reducing means comprise water level reducing means for reducing the water level in the reservoir, wherein in particular the water level reducing means comprise a plunger pump.
26. A substructure according to either one or both of claims 24-25, characterised in that the water reservoir is in particular incorporated in a circuit which further comprises a buffering vessel and an overflow.
27. A substructure according to one or more of claims 24-26, characterised in that the water reservoir is connected to the substructure via one or more connection openings, which connection openings abut the water-impermeable layer.
28. A substructure according to one or more of claims 24-27, characterised in that use is made of solar energy and/or wind energy for driving the pumps, valves and control means.
29. A substructure according to one or more of the preceding claims 128, characterised in that the top layer is provided with a so-called infill material having a good water-permeability, preferably sand of the type that has a particle size distribution wherein 25 - 75 wt.% of the sand passes through a 0.250 mm sieve, in particular wherein 90 - 99 % of the sand passes through a 1 mm sieve.
AU2016218512A 2015-02-10 2016-02-05 Substructure for an artificial lawn Pending AU2016218512A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
NL2014271A NL2014271B1 (en) 2015-02-10 2015-02-10 Substructure for an artificial grass field.
NL2014271 2015-02-10
PCT/NL2016/050083 WO2016129995A1 (en) 2015-02-10 2016-02-05 Substructure for an artificial lawn

Publications (1)

Publication Number Publication Date
AU2016218512A1 true AU2016218512A1 (en) 2017-09-28

Family

ID=52774488

Family Applications (2)

Application Number Title Priority Date Filing Date
AU2016102418A Expired AU2016102418A4 (en) 2015-02-10 2016-02-05 Substructure for an artificial lawn
AU2016218512A Pending AU2016218512A1 (en) 2015-02-10 2016-02-05 Substructure for an artificial lawn

Family Applications Before (1)

Application Number Title Priority Date Filing Date
AU2016102418A Expired AU2016102418A4 (en) 2015-02-10 2016-02-05 Substructure for an artificial lawn

Country Status (6)

Country Link
US (1) US20180030670A1 (en)
EP (1) EP3256645B1 (en)
AU (2) AU2016102418A4 (en)
NL (1) NL2014271B1 (en)
WO (1) WO2016129995A1 (en)
ZA (1) ZA201706075B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017113307A1 (en) * 2017-06-16 2018-12-20 Intergreen Ag Sports field superstructure and sports field
CN108951358A (en) * 2018-08-15 2018-12-07 湖南优冠体育材料有限公司 A kind of high rebound curly wire chinampa runway
CN110258244B (en) * 2019-05-31 2024-04-02 深圳市创想体育设施工程有限公司 Intelligent artificial turf of easy dismouting
DE112020007041A5 (en) * 2020-04-09 2023-04-27 7SevenRelax Group GmbH Artificial turf system and method of making an artificial turf system
US20210388563A1 (en) * 2020-06-15 2021-12-16 Jason Warren Bell Geocell-Based Drainage Base for Synthetic Turf

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2727956A1 (en) * 1977-06-22 1979-01-18 Nikolaus Blank LAYER STRUCTURE FOR SPORTS AND PLAYGROUNDS THAT CAN BE DRAINED AND DRAINABLE UNDERGROUND AND ALL KINDS OF VEGETATION AREAS
GB2072022A (en) 1980-03-08 1981-09-30 Logan J L Variable putting surface
NZ203964A (en) 1982-04-27 1985-04-30 Nottingham County Council Artificial playing surface
DE3835880A1 (en) * 1988-10-21 1990-04-26 Sportboden Systeme Gmbh Resilient mat for ground coverings of sports and leisure areas
EP0373282A1 (en) * 1988-12-13 1990-06-20 "H.R.B. Chemie Hiroba Belgium" Process for constructing and keeping up a terrain, particularly a sports ground, and terrain constructed according to this process
NL9002244A (en) 1990-10-16 1992-05-18 Desseaux H Tapijtfab ARTIFICIAL GRASS FIELD.
US6551689B1 (en) * 1998-09-21 2003-04-22 Fieldturf Holdings Inc. Synthetic grass with resilient granular top surface layer
NL1013987C2 (en) 1999-12-29 2001-07-10 Arcadis Heidemij Realisatie B Sports pitch with grass playing surface and substrate stabilized by rock wool
NL1016193C2 (en) 2000-09-15 2002-03-18 Desseaux H Tapijtfab Method for installing an artificial grass field and such an artificial grass field.
NL1021171C2 (en) 2002-07-29 2004-01-30 Hugo De Vries Method for applying a passable surface, for example a playing field and surface formed in this way.
US6805936B2 (en) * 2002-11-04 2004-10-19 Reed Seaton Sports playing surfaces for realistic game play
GB2396117B (en) 2002-12-14 2006-06-28 Nottinghamshire Sports And Saf Improvements relating to the construction of playing surfaces
EP1462572A1 (en) 2003-03-26 2004-09-29 Anthony Harte A sports ground
US7244477B2 (en) * 2003-08-20 2007-07-17 Brock Usa, Llc Multi-layered sports playing field with a water draining, padding layer
WO2006007862A1 (en) 2004-07-16 2006-01-26 Gebr. Wunderlich Gmbh & Co. Kg Sports floor and method for producing an elastic cushioning layer
WO2008051553A2 (en) * 2006-10-24 2008-05-02 Fieldturf Tarkett Inc. Drainage system for synthetic grass system, method of installing a synthetic grass system and business method of providing a synthetic grass system
DE202009009767U1 (en) * 2009-07-17 2010-11-25 Moosdorf, Heidi riding surface
NL2008291C2 (en) 2011-07-13 2013-05-08 Desso Sports Systems N V SUPPORT FOR AN ARTIFICIAL GRASS FIELD.
NL2009968C2 (en) * 2012-12-12 2014-06-16 Oranjewoud Realisatie B V BASIC CONSTRUCTION FOR AN ARTIFICIAL GRASS FIELD, SPORTS FIELD PROVIDED THEREOF AND METHOD FOR THIS.
US10385520B2 (en) * 2014-12-19 2019-08-20 Ten Cate Thiolon B.V. Sports field construction

Also Published As

Publication number Publication date
US20180030670A1 (en) 2018-02-01
WO2016129995A1 (en) 2016-08-18
AU2016102418A4 (en) 2019-08-08
ZA201706075B (en) 2019-09-25
NL2014271B1 (en) 2016-10-13
EP3256645B1 (en) 2020-08-26
EP3256645A1 (en) 2017-12-20

Similar Documents

Publication Publication Date Title
AU2016102418A4 (en) Substructure for an artificial lawn
EP2494109B1 (en) Mixed turf
US20030039511A1 (en) Drainage system for artificial grass using spacing grid
US7563052B2 (en) Sports floor and method for constructing such a sports floor
WO2007018754A1 (en) Artificial turf system
DK2599916T3 (en) Riding or sports ground base and process for production thereof
EP2732097B1 (en) Substructure for an artificial lawn
EP2113045A1 (en) Drainage for sports surface
US20060051161A1 (en) Methods and apparatus for reducing sand erosion in golf course bunkers
JP2016089378A (en) Athletic field drainage structure
EP3332066B1 (en) Sports pitch and method of constructing same
NL2009968C2 (en) BASIC CONSTRUCTION FOR AN ARTIFICIAL GRASS FIELD, SPORTS FIELD PROVIDED THEREOF AND METHOD FOR THIS.
JP5520165B2 (en) Artificial lawn laying structure
EP4022130B1 (en) Arrangement for adjusting moisture content of the soil of a sports field
NL2007101C2 (en) SUPPORT FOR AN ARTIFICIAL GRASS FIELD.
AU2004285991B2 (en) Drainage for sports surface
CZ2010972A3 (en) Building system of external sports ground surface covered with synthetic grass
IE20040199A1 (en) System for maintaining surface quality of a synthetic sports ground

Legal Events

Date Code Title Description
DA3 Amendments made section 104

Free format text: THE NATURE OF THE AMENDMENT IS: APPLICATION IS TO PROCEED UNDER THE NUMBER 2016102418