ZA202302412B - Method for improving roof-contacted filling rate of end sand discharging stope in underground mines - Google Patents

Method for improving roof-contacted filling rate of end sand discharging stope in underground mines

Info

Publication number
ZA202302412B
ZA202302412B ZA2023/02412A ZA202302412A ZA202302412B ZA 202302412 B ZA202302412 B ZA 202302412B ZA 2023/02412 A ZA2023/02412 A ZA 2023/02412A ZA 202302412 A ZA202302412 A ZA 202302412A ZA 202302412 B ZA202302412 B ZA 202302412B
Authority
ZA
South Africa
Prior art keywords
stope
filling rate
sand discharging
underground mines
end sand
Prior art date
Application number
ZA2023/02412A
Inventor
Peizheng Liu
Shenghua Yin
Leiming Wang
Zhe Liu
Bin Huang
Shiping Wu
Xiangbiao Miao
Original Assignee
Sinosteel Maanshan General Institute Of Mining Res Co Ltd
Huawei National Engineering Res Center Of High Efficient Recycle And Utilization For Metallic Minera
Sinosteel Nanjing Huaxin Tech Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Maanshan General Institute Of Mining Res Co Ltd, Huawei National Engineering Res Center Of High Efficient Recycle And Utilization For Metallic Minera, Sinosteel Nanjing Huaxin Tech Co Ltd filed Critical Sinosteel Maanshan General Institute Of Mining Res Co Ltd
Publication of ZA202302412B publication Critical patent/ZA202302412B/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
ZA2023/02412A 2022-04-14 2023-02-23 Method for improving roof-contacted filling rate of end sand discharging stope in underground mines ZA202302412B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210393029.5A CN114753843B (en) 2022-04-14 2022-04-14 Method for improving filling and roof-contacting rate of sand-discharging stope at end part of underground mine
PCT/CN2022/092439 WO2023197392A1 (en) 2022-04-14 2022-05-12 Method for increasing roof-contacted filling rate of underground mine end sand discharging stope

Publications (1)

Publication Number Publication Date
ZA202302412B true ZA202302412B (en) 2023-05-31

Family

ID=82330855

Family Applications (1)

Application Number Title Priority Date Filing Date
ZA2023/02412A ZA202302412B (en) 2022-04-14 2023-02-23 Method for improving roof-contacted filling rate of end sand discharging stope in underground mines

Country Status (3)

Country Link
CN (1) CN114753843B (en)
WO (1) WO2023197392A1 (en)
ZA (1) ZA202302412B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117451976B (en) * 2023-12-25 2024-03-08 山东黄金矿业科技有限公司充填工程实验室分公司 Indoor experimental device for simulating filling of underground metal mine stope

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4265570A (en) * 1979-06-01 1981-05-05 Conoco, Inc. Mine roof control
CN100441831C (en) * 2003-12-11 2008-12-10 云南驰宏锌锗股份有限公司 Ladder type mining method using united pillars to support roof and partition stope
AU2013207575B2 (en) * 2012-07-20 2016-10-20 Jollan Kingsley Stope fill barrier
CN103615285B (en) * 2013-12-04 2015-11-04 南京银茂铅锌矿业有限公司 A kind of stope route arrangement and method being beneficial to Tight filling
CN109083644B (en) * 2018-08-16 2019-08-02 中南大学 A kind of safe and efficient mining methods of gently inclined medium thick orebody
CN109339783B (en) * 2018-11-15 2020-04-07 中国恩菲工程技术有限公司 Approach open stope subsequent filling mining method for gently inclined medium-thickness ore body
CN110359914B (en) * 2019-08-19 2021-01-15 中钢集团马鞍山矿山研究总院股份有限公司 Safe and low-cost combined sublevel mining method for gently inclined medium-thickness ore body
CN110886612A (en) * 2019-11-13 2020-03-17 铜陵有色金属集团股份有限公司 Mining method suitable for continuous mining of gently inclined medium-thickness ore body
CN110778316B (en) * 2019-11-19 2020-12-25 深圳市中金岭南有色金属股份有限公司 Sublevel rock drilling stage open stope subsequent filling mining method adopting arched-arch-shaped top pillar structure
CN113565508B (en) * 2021-08-03 2022-08-02 长沙矿山研究院有限责任公司 Open stope subsequent filling mining method for V-shaped top column subsection rock drilling stage of medium-thickness ore body
CN114087016B (en) * 2021-12-03 2023-09-26 武钢资源集团金山店矿业有限公司 Caving-to-filling mining isolation top column pre-control supporting method
CN114810072A (en) * 2022-04-14 2022-07-29 中钢集团马鞍山矿山研究总院股份有限公司 Structural arrangement mode for improving filling and roof-contacting rate of end sand-discharging stope

Also Published As

Publication number Publication date
CN114753843A (en) 2022-07-15
WO2023197392A1 (en) 2023-10-19
CN114753843B (en) 2023-01-20

Similar Documents

Publication Publication Date Title
ZA202302412B (en) Method for improving roof-contacted filling rate of end sand discharging stope in underground mines
CN104481540A (en) Method for controlling multiple coal mining hazards by high level borehole grouting
CN103758567B (en) A kind of breaking roof Collapsed zone grouting filling method
CN103742148B (en) The soft coal-mining method covering the descending waste filling of supporting of a kind of half-edge coal seam
CN101942999A (en) Coal mining method for high-dipping low seam
ZA202007716B (en) Comprehensive supporting method for a fully mechanized mining face of a coal mine
CN104500070B (en) Continuous coal mining machine paste filling mining method
CN105909287B (en) A kind of coal mine fully-mechanized mining working lead abutment pressure area deep hole grouting technique and method
MX2012009756A (en) Underground mining.
CN104481539A (en) Extruding blasting caving mining method for self-pulling slot
CN109869152B (en) Mining method for reserved roadway of coal and gas outburst coal seam
CN105422102B (en) A kind of vertical medium-length hole ore blast subsection access back-filling method
ZA202209148B (en) Grouting method for reinforcing surrounding rock of three-soft mining roadway
RU2352780C1 (en) Method of ore bodies development
CN106223955A (en) Rhombic bench cemented filling mining method
ZA202302570B (en) Combined mining method for underground mines
RU2439323C1 (en) Method to mine inclined ore deposits
CN113756868A (en) Geotechnical engineering underground side wall construction method
CN117449856A (en) Method for filling, roof protecting and displacement mining of bauxite under coal by lane
ZA202208485B (en) Method for diverting water from anchor-cable grouting hole for construction in rock brust mine
ZA202102300B (en) Grouting quality testing method for weak floor of coal mine rock roadway
RU2400625C1 (en) Method for combined development of mineral deposits
ZA202213114B (en) Mine underground filling mortar
CN111594183A (en) Coal seam deep hole blasting pressure relief method for improving blasting effect by using original pressure relief holes
ZA202302410B (en) Charging method for horizontal holes in underground mine fractured rock masses