WO2023197392A1 - Method for increasing roof-contacted filling rate of underground mine end sand discharging stope - Google Patents

Method for increasing roof-contacted filling rate of underground mine end sand discharging stope Download PDF

Info

Publication number
WO2023197392A1
WO2023197392A1 PCT/CN2022/092439 CN2022092439W WO2023197392A1 WO 2023197392 A1 WO2023197392 A1 WO 2023197392A1 CN 2022092439 W CN2022092439 W CN 2022092439W WO 2023197392 A1 WO2023197392 A1 WO 2023197392A1
Authority
WO
WIPO (PCT)
Prior art keywords
filling
stope
ore
zone
sand
Prior art date
Application number
PCT/CN2022/092439
Other languages
French (fr)
Chinese (zh)
Inventor
刘培正
尹升华
王雷鸣
刘哲
黄斌
吴世平
苗向彪
Original Assignee
中钢集团马鞍山矿山研究总院股份有限公司
华唯金属矿产资源高效循环利用国家工程研究中心有限公司
中钢集团南京华忻科技有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中钢集团马鞍山矿山研究总院股份有限公司, 华唯金属矿产资源高效循环利用国家工程研究中心有限公司, 中钢集团南京华忻科技有限公司 filed Critical 中钢集团马鞍山矿山研究总院股份有限公司
Priority to ZA2023/02412A priority Critical patent/ZA202302412B/en
Publication of WO2023197392A1 publication Critical patent/WO2023197392A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Definitions

  • the invention belongs to the technical field of underground mine mining, and specifically relates to a method for improving the filling and roofing of underground mine stopes. It is particularly suitable for mines using end sand discharge schemes for filling method mining, and can be used in solid mines such as non-ferrous, black, chemical, and gold mines. Widely used in underground mining.
  • filling tunnels and sand discharge pipelines are generally not arranged directly above the goaf, but are mostly arranged in the intercolumn at one end of the stope, and an end sand discharge scheme is adopted. Based on the following main factors, the phenomenon of incomplete filling is common and has never been solved well:
  • the filling slurry consolidates and settles.
  • the solid particles gradually sink due to the layered separation of the slurry, forcing most of the water to segregate on the surface of the filling body and be removed in the form of runoff, which will form between the surface of the filling body and the roof. space.
  • the filling body will still settle. Due to the dehydration and solidification of the slurry, the shrinkage rate of the filling body reaches 5% to 22%.
  • the discharge of cleaning water from the filling pipe, irregularity of the stope roof, and human factors will all affect the filling and roofing effect of the stope. Since the filling and top connection of the stope is directly related to the quality of the filling body and the production safety of the stope, if the filling and top connection is not good, it will cause the filling body or surrounding rock to fall off.
  • the purpose of the present invention is to provide a method to improve the sand discharge at the end of underground mines in view of the technical problems existing in the existing technology such as poor filling and capping, low filling and capping rate, low quality of filling body and impact on stope production safety.
  • Method of stope filling and top connection rate This method is based on the characteristics of end-end sand filling of stopes. On the premise of controlling the filling cost, it is possible to increase the stope filling and top connection rate, effectively control ground pressure activities, and ensure mining production. Safety.
  • a method of improving the top filling rate of sand caving stopes at the end of underground mines is implemented by adopting the following steps:
  • Ore transportation Use a scraper to transport the ore in the rock drilling tunnel through the mining tunnel and the ore loading approach to the slide shaft for unloading;
  • the height of the stope varies depending on the thickness and tendency of the ore body, but is generally 10 to 100m, and the width of the intercolumns is 10m to 20m.
  • the slope of the filling inclined shaft is consistent or substantially consistent with the inclination angle of the ore body, and the bottom plate of the filling inclined shaft is 1 to 2 m higher than the contact zone of the top plate of the ore body.
  • the farther away from the end sand discharge point the smaller the height of the sand discharge trough above the ore body roof contact zone, until the height of the sand discharge trough is equal to the ore body roof contact zone bring.
  • the stope can be divided into three zones along the direction of the ore body: Zone I, Zone II, and Zone III. Zones I, II, and III are from far to near the sand discharge point at the end. Refer to the filling material.
  • the gravity gradient of the slurry is usually between 4 and 8%.
  • the height of the sand discharge trough in Zone I is equal to the contact zone of the ore roof.
  • the height of the sand discharge trough in Zone II is 1.2 to 2.4m higher than the contact zone of the ore roof.
  • the height of the sand drop trough in Zone III is higher than the contact zone of the ore roof.
  • the contact zone of the ore body roof is 2.4 ⁇ 4.0m.
  • the height of the sand draining trough can be lower than the contact zone of the ore body roof, and the height of the sand draining trough in Zones II and III can be adjusted accordingly; in addition, the height difference of the sand draining trough in each zone can also be controlled by Smooth transition of blast hole depth.
  • the present invention is a method for improving the filling and top connection rate of sand caving stopes at the end of underground mines. After adopting the above technical solution, it has the following positive effects:
  • the blast hole is increased by 50 to 120m in a single stope, and the additional cost per ton of ore is less than 0.07 yuan.
  • the filling cost is controlled, filling efficiency is improved, and operation safety is ensured;
  • the average slope of the roof in the empty area is greater than the gravity slope of the slurry.
  • the stope is filled in stages, and the filling and top connection rate can reach 100%, which is more than 10% higher than the traditional filling scheme and is effectively controlled. Control ground pressure activities to ensure safety during the mining process.
  • Figure 1 is a front view of a method for improving the filling and top connection rate of the sand discharge stope at the end of an underground mine according to the present invention.
  • Figure 2 is a side cross-sectional view of area I in Figure 1;
  • Figure 3 is a side cross-sectional view of area II in Figure 1;
  • Figure 4 is a side cross-sectional view of area III in Figure 1;
  • Figure 5 is a side cross-sectional view of area IV in Figure 1;
  • Figure 6 is a production process flow chart of a method of improving the filling and top connection rate of the sand discharge stope at the end of an underground mine according to the present invention.
  • the reference numbers are: 1-stope; 2-column; 3-filling inclined shaft; 4-filling main pipe; 5-filling contact tunnel; 6-filling branch pipe; 7-rock drilling tunnel; 8-blast hole; 9- Sand discharge trough; 10-mine tunnel; 11-mine loading approach.
  • stope 1 is divided into three zones along the direction of the ore body: Zone I, Zone II and Zone III.
  • Zone I and Zone II Area III is from far to near from the end sand placing point, area III is in the range of 0 to 15m from the end sand placing point, area II is in the range of 15 to 30m from the end sand placing point, and the rest is area I.
  • the farther away from the end sand discharge point the smaller the height of the sand discharge trough 9 above the contact zone of the ore body roof, until the height of the sand discharge trough 9 is equal to the ore body Top plate contact strip.
  • the gravity slope of the filling slurry which is usually between 4 and 8%, take the length of stope 1 as an example, which is 45m, and divide stope 1 into three zones as an example. Zone I is 30 to 45m away from the sand discharge point.
  • the height of the sand discharge trough 9 is equal to the ore body roof contact zone; in zone II, which is 15 to 30m away from the sand release point, the sand release trough 9 is 1.2 to 2.4m higher than the ore roof contact zone, and in zone III, which is 0 to 15m away from the sand release point. area, the sand discharge trough 9 is 2.4 to 4.0m higher than the ore body roof contact zone.
  • zone I the cutting space at the end of zone I is the free surface, and retreat blasting is performed in zone II and zone III in the rock drilling tunnel 7.
  • Ore transportation Use a scraper to transport the ore in the rock drilling tunnel 7 through the ore exit tunnel 10 and the ore loading approach 11 to the slide shaft for unloading.
  • the present invention adopts a stepped sand discharging trough scheme.
  • sand discharging troughs of different heights are set up through the depth of the blast hole, so that the average slope of the roof of the empty area is greater than or equal to that of the material.
  • the self-flowing slope of the slurry can meet the requirements of natural roof connection, solve the problem of stope filling and roof connection, control the ground pressure activity, and ensure the safety of mining production.
  • the method of extending the blast hole is used to form a sand discharge trough with a small cross-section, which effectively controls the filling cost and the ore dilution rate.
  • the method of the invention has been industrially tested in a certain large-scale underground iron ore filling and mining, achieving 100% filling and top connection rate, achieving unexpected technical effects, and effectively ensuring safety in the mining process.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

Disclosed in the present invention is a method for increasing a roof-contacted filling rate of an underground mine end sand discharging stope. The method comprises: arranging a stope (1) every 40-80 m in the direction of a mine body, and reserving pillars (2) between two adjacent stopes (1); arranging inclined filling shafts (3) in the pillars (2), hanging primary filling pipes (4) on roadway roofs of the inclined filling shaft (3), digging filling connecting roadways (5) from portions of the inclined filling shafts (3) close to the top areas of the stopes (1) to the stopes (1), and connecting secondary filling pipes (6) into the stopes (1); drilling a blast hole towards the stope in each partition in a rock drilling roadway, forming a stepped sand discharging tank in the top of the stope (1) through a method of deepening a blast hole area by area, performing backward blasting on an end sand discharging point in the rock drilling roadway, dropping ore into the rock drilling roadway, and transporting the ore to an ore pass for unloading through a scraper; and filling a goaf in stages after stope stoping is completed. The roof-contacted filling rate can reach 100%, ground pressure activities are effectively controlled, and the safety of the stoping process is ensured.

Description

一种提高地下矿山端部放砂采场充填接顶率的方法A method to improve the top-filling rate of sand-capping stopes at the end of underground mines 技术领域Technical field

本发明属于地下矿山开采技术领域,具体涉及一种提高地下矿山采场充填接顶的方法,特别适合充填法开采采用端部放砂方案的矿山,可在有色、黑色、化工、黄金等固体矿山地下开采中广泛应用。The invention belongs to the technical field of underground mine mining, and specifically relates to a method for improving the filling and roofing of underground mine stopes. It is particularly suitable for mines using end sand discharge schemes for filling method mining, and can be used in solid mines such as non-ferrous, black, chemical, and gold mines. Widely used in underground mining.

背景技术Background technique

随着采矿技术的进步和生态环境保护的要求,充填采矿法已经成为有色、黑色、化工、黄金等矿山开发利用的首选方法。国家矿山安全监察局2022年2月8日印发《关于加强非煤矿山安全生产工作的指导意见》的通知,明确“新建金属非金属地下矿山应当采用充填采矿法,不能采用的要进行严格论证。”充填采矿法最大的优点在于能够适应各种复杂多变及围岩条件较差的矿体开采,能够最大限度地提高采矿矿石回收率和降低贫化率,并能有效控制地压活动,保证安全生产,同时最大限度地实现对地表环境的保护。With the advancement of mining technology and the requirements of ecological environment protection, backfill mining has become the preferred method for the development and utilization of non-ferrous, ferrous, chemical, gold and other mines. The State Mine Safety Supervision Bureau issued a notice on February 8, 2022, “Guiding Opinions on Strengthening Safety Production in Non-Coal Mines”, which clarified that “newly built metal and non-metal underground mines should adopt the backfill mining method, and strict demonstrations must be conducted if it cannot be adopted. "The biggest advantage of the backfill mining method is that it can adapt to the mining of various complex and changeable ore bodies with poor surrounding rock conditions, can maximize the recovery rate of mining ore and reduce the dilution rate, and can effectively control ground pressure activities to ensure Safe production while maximizing the protection of the surface environment.

综合国内外矿山充填情况,考虑安全的因素,充填巷道及放砂管路一般不布置在采空区正上方,多布置在采场一端的间柱内,采取端部放砂方案。基于以下几方面主要因素,充填不接顶现象普遍存在,且始终未能很好解决:Based on the filling situation of mines at home and abroad, and considering safety factors, filling tunnels and sand discharge pipelines are generally not arranged directly above the goaf, but are mostly arranged in the intercolumn at one end of the stope, and an end sand discharge scheme is adopted. Based on the following main factors, the phenomenon of incomplete filling is common and has never been solved well:

(1)充填料浆固结沉降。一方面充填料浆充满空区后,由于料浆分层离析,固体颗粒逐渐下沉,迫使大部分水离析在充填体表面并以径流的方式脱除,将在充填体表面和顶板之间形成空间。另一方面固体颗粒间空隙中的重力水通过渗透方式排除后,充填体还会沉降。因料浆脱水固结造成充填体收缩率达5%~22%。(1) The filling slurry consolidates and settles. On the one hand, after the filling slurry fills the empty area, the solid particles gradually sink due to the layered separation of the slurry, forcing most of the water to segregate on the surface of the filling body and be removed in the form of runoff, which will form between the surface of the filling body and the roof. space. On the other hand, after the gravity water in the gaps between solid particles is eliminated through penetration, the filling body will still settle. Due to the dehydration and solidification of the slurry, the shrinkage rate of the filling body reaches 5% to 22%.

(2)充填料浆自流坡度。充填料浆在采场流动过程中因其内骨料出现沉降,从一端充填管道放砂口到采场另一端将形成自流坡度,充填料浆流动性越差,其坡度就越大。当充填管道放砂口一端接顶时,由于自流坡度的影响,导致采场另一端不能完全接顶。以料浆浓度 60~68%为例,其自流坡度通常在4~8%之间,若充填采场长度50m,放砂口一端完全接顶时,另一端尚有2~4m空间未接顶。(2) The self-flow slope of the filling slurry. During the flow process of the stope, the aggregate in the filling slurry will settle, and a gravity gradient will form from the sand discharge port of the filling pipe at one end to the other end of the stope. The worse the fluidity of the filling slurry, the greater the slope. When one end of the sand discharge port of the filling pipe is connected to the roof, the other end of the stope cannot be completely connected to the roof due to the influence of the gravity gradient. Taking the slurry concentration of 60 to 68% as an example, its gravity slope is usually between 4 and 8%. If the length of the filling stope is 50m and one end of the sand discharge port is completely connected to the top, there will still be 2 to 4m of space at the other end that is not connected to the top. .

(3)充填料浆浓度过低和滤水速度慢。过低的料浆浓度,容易导致充填料离析分层,增大自然坡积角。同时大量的积存水难以及时排出,占据充填空间,阻碍充填接顶。(3) The filling slurry concentration is too low and the water filtering speed is slow. Too low slurry concentration can easily lead to segregation and stratification of filling materials and increase the natural slope angle. At the same time, a large amount of accumulated water is difficult to discharge in time, occupying the filling space, and hindering the filling to the top.

此外,充填管清洗水排入、采场顶板不规则以及人为因素均将影响采场充填接顶效果。由于采场充填接顶直接关系到充填体的质量,以及采场的生产安全,如果充填接顶不好,会造成充填体或围岩冒落。In addition, the discharge of cleaning water from the filling pipe, irregularity of the stope roof, and human factors will all affect the filling and roofing effect of the stope. Since the filling and top connection of the stope is directly related to the quality of the filling body and the production safety of the stope, if the filling and top connection is not good, it will cause the filling body or surrounding rock to fall off.

因此,如何提高采场充填接顶率,尤其提高端部放砂采场充填接顶,是充填法开采矿山面临和亟待解决的问题。Therefore, how to improve the stope filling and top connection rate, especially how to improve the end sand discharge stope filling and top connection, is a problem faced by filling mining mines and needs to be solved urgently.

发明内容Contents of the invention

本发明的目的就是针对现有技术存在的充填接顶不好、充填结顶率不高、充填体质量较低并影响采场生产安全的技术难题,而提供一种提高地下矿山端部放砂采场充填接顶率的方法,该方法针对采用端部放砂充填采场的特点,在控制充填成本的前提下,尽可能提高采场充填接顶率,有效控制地压活动,确保采矿生产安全。The purpose of the present invention is to provide a method to improve the sand discharge at the end of underground mines in view of the technical problems existing in the existing technology such as poor filling and capping, low filling and capping rate, low quality of filling body and impact on stope production safety. Method of stope filling and top connection rate. This method is based on the characteristics of end-end sand filling of stopes. On the premise of controlling the filling cost, it is possible to increase the stope filling and top connection rate, effectively control ground pressure activities, and ensure mining production. Safety.

为实现本发明的上述目的,本发明一种提高地下矿山端部放砂采场充填接顶率的方法采用以下步骤实施:In order to achieve the above object of the present invention, a method of improving the top filling rate of sand caving stopes at the end of underground mines is implemented by adopting the following steps:

1)沿矿体走向每隔40~80m布置一个采场,在采场内每13~18m形成1个分区,两相邻采场间留间柱;1) Arrange a stope every 40 to 80m along the direction of the ore body, form a partition every 13 to 18m in the stope, and leave spacing columns between two adjacent stopes;

2)完成采场采切工程:包括凿岩巷道、出矿巷道、装矿进路及相应的切割工程;凿岩巷道、出矿巷道、装矿进路位于采场的下部,凿岩巷道、装矿进路沿矿体走向布置,凿岩巷道与装矿进路之间通过出矿巷道连通;2) Complete the mining and cutting project of the stope: including rock drilling tunnel, mining tunnel, ore loading approach and corresponding cutting engineering; the rock drilling tunnel, mining tunnel, and ore loading approach are located in the lower part of the stope, and the rock drilling tunnel, The ore loading approach is arranged along the direction of the ore body, and the rock drilling tunnel and the ore loading approach are connected through the ore exit tunnel;

3)完成充填巷道及吊挂充填管路:在采场两端矿体顶板较高的间柱内布置充填斜井,将充填主管吊挂在充填斜井的巷道顶板,自充填斜井靠近采场顶部区域向采场掘充填联络巷道,并将充填支管接入 采场内;3) Complete the filling tunnel and hanging filling pipeline: Arrange the filling inclined shaft in the higher intercolumn of the ore body roof at both ends of the stope, hang the filling main pipe on the tunnel roof of the filling inclined shaft, and self-filling the inclined shaft close to the mining The top area of the field is excavated to fill the contact roadway to the stope, and the filling branch pipe is connected to the stope;

4)采场各分区放砂槽高度确定:在凿岩巷道内向各分区的采场凿炮孔,通过逐区加深炮孔深度的方法在采场顶部形成阶梯式放砂槽,各分区的放砂槽高度根据空区充填区域距端部放砂点距离的远近不同并结合充填料浆的自流坡度确定,以确保空区顶板平均坡度大于或等于充填料浆的自流坡度,以满足自然接顶要求;4) Determine the height of the sand discharge trough in each zone of the stope: drill blast holes into the stopes of each zone in the rock drilling tunnel, and form a stepped sand release trough on the top of the stope by deepening the depth of the blast holes zone by zone. The height of the sand trough is determined based on the distance between the empty area filling area and the end sand discharge point and the self-flow slope of the filling slurry to ensure that the average slope of the roof of the empty area is greater than or equal to the self-flow slope of the filling slurry to meet the natural roof connection Require;

5)采场落矿:以采场端部放砂点另一端的切割空间为自由面,在凿岩巷道向端部放砂点后退式爆破,矿石落入凿岩巷道内;5) Ore falling in the stope: The cutting space at the other end of the sand placing point at the end of the stope is used as the free surface, and the rock drilling tunnel is blasted backward toward the end sand placing point, and the ore falls into the rock drilling tunnel;

6)矿石运搬:采用铲运机,将凿岩巷道内的矿石经出矿巷道、装矿进路运至溜井卸矿;6) Ore transportation: Use a scraper to transport the ore in the rock drilling tunnel through the mining tunnel and the ore loading approach to the slide shaft for unloading;

7)空区充填:采场回采结束后,封闭空区下部的通道,待封闭墙强度满足设计要求后,通过充填主管、充填支管对空区进行分次充填,确保充填效果。7) Filling of the empty area: After the stope mining is completed, the channel at the lower part of the empty area is closed. After the strength of the closing wall meets the design requirements, the empty area is filled in stages through the main filling pipe and the filling branch pipe to ensure the filling effect.

所述采场的高度因矿体厚度及倾向不同,一般为10~100m,间柱宽10m~20m。The height of the stope varies depending on the thickness and tendency of the ore body, but is generally 10 to 100m, and the width of the intercolumns is 10m to 20m.

进一步地,所述的充填斜井坡度与矿体倾角一致或基本一致,充填斜井的底板高于矿体顶板接触带1~2m。Further, the slope of the filling inclined shaft is consistent or substantially consistent with the inclination angle of the ore body, and the bottom plate of the filling inclined shaft is 1 to 2 m higher than the contact zone of the top plate of the ore body.

根据空区充填区域距端部放砂点距离的远近不同,距端部放砂点越远,放砂槽高于矿体顶板接触带的高度越小,直至放砂槽高度等于矿体顶板接触带。According to the distance between the empty area filling area and the end sand discharge point, the farther away from the end sand discharge point, the smaller the height of the sand discharge trough above the ore body roof contact zone, until the height of the sand discharge trough is equal to the ore body roof contact zone bring.

大多数情况下,可将采场沿矿体走向划分成Ⅰ区、Ⅱ区和Ⅲ区共3个分区,Ⅰ区、Ⅱ区、Ⅲ区距端部放砂点由远及近,参照充填料浆的自流坡度通常在4~8%之间,Ⅰ区放砂槽高度等于矿体顶板接触带,Ⅱ区放砂槽高于矿岩顶板接触带1.2~2.4m;Ⅲ区放砂槽高于矿体顶板接触带2.4~4.0m。若Ⅰ区矿体顶板区域的矿石品位较低,放砂槽高度可低于矿体顶板接触带,同时相应调整Ⅱ区和Ⅲ区放砂槽高度;另外各区放砂槽高差也可通过控制炮孔深度平滑过渡。In most cases, the stope can be divided into three zones along the direction of the ore body: Zone I, Zone II, and Zone III. Zones I, II, and III are from far to near the sand discharge point at the end. Refer to the filling material. The gravity gradient of the slurry is usually between 4 and 8%. The height of the sand discharge trough in Zone I is equal to the contact zone of the ore roof. The height of the sand discharge trough in Zone II is 1.2 to 2.4m higher than the contact zone of the ore roof. The height of the sand drop trough in Zone III is higher than the contact zone of the ore roof. The contact zone of the ore body roof is 2.4~4.0m. If the ore grade in the roof area of the ore body in Zone I is low, the height of the sand draining trough can be lower than the contact zone of the ore body roof, and the height of the sand draining trough in Zones II and III can be adjusted accordingly; in addition, the height difference of the sand draining trough in each zone can also be controlled by Smooth transition of blast hole depth.

本发明一种提高地下矿山端部放砂采场充填接顶率的方法采用以上技术方案后,具有下列积极效果:The present invention is a method for improving the filling and top connection rate of sand caving stopes at the end of underground mines. After adopting the above technical solution, it has the following positive effects:

1)采取延深炮孔方式形成放砂槽,单个采场增加炮孔50~120m,每吨矿增加成本不足0.07元。控制了充填成本,提高了充填效率,保障了作业安全;1) Adopt the method of extending the blast hole to form a sand discharge trough. The blast hole is increased by 50 to 120m in a single stope, and the additional cost per ton of ore is less than 0.07 yuan. The filling cost is controlled, filling efficiency is improved, and operation safety is ensured;

2)采取小断面放砂槽,单个采场超挖量260~550m 3,造成贫化率将增加,经统计贫化率增幅<1.5%。另外,混入的废石与其它贫化产生的废石,一并经过预选后作为建筑石料,抵销其相应成本。 2) Small-section sand discharge troughs are adopted, and the overexcavation volume of a single stope is 260-550m 3 , resulting in an increase in the dilution rate. According to statistics, the increase in the dilution rate is <1.5%. In addition, the mixed waste rocks and other waste rocks produced by dilution are pre-selected and used as building stones to offset their corresponding costs.

3)采用阶梯式放砂槽方案,空区顶板平均坡度大于料浆的自流坡度,采场采取分次充填方式,充填接顶率可达100%,较传统充填方案提高10%以上,有效控制了地压活动,保障回采过程中的安全。3) Using the stepped sand discharge trough scheme, the average slope of the roof in the empty area is greater than the gravity slope of the slurry. The stope is filled in stages, and the filling and top connection rate can reach 100%, which is more than 10% higher than the traditional filling scheme and is effectively controlled. Control ground pressure activities to ensure safety during the mining process.

附图说明Description of the drawings

图1为本发明一种提高地下矿山端部放砂采场充填接顶率的方法的主视图。Figure 1 is a front view of a method for improving the filling and top connection rate of the sand discharge stope at the end of an underground mine according to the present invention.

图2为图1中Ⅰ区侧剖面图;Figure 2 is a side cross-sectional view of area I in Figure 1;

图3为图1中Ⅱ区侧剖面图;Figure 3 is a side cross-sectional view of area II in Figure 1;

图4为图1中Ⅲ区侧剖面图;Figure 4 is a side cross-sectional view of area III in Figure 1;

图5为图1中Ⅳ区侧剖面图;Figure 5 is a side cross-sectional view of area IV in Figure 1;

图6为本发明一种提高地下矿山端部放砂采场充填接顶率的方法的生产工艺流程图。Figure 6 is a production process flow chart of a method of improving the filling and top connection rate of the sand discharge stope at the end of an underground mine according to the present invention.

附图标记为:1-采场;2—间柱;3—充填斜井;4—充填主管;5—充填联络巷道;6—充填支管;7—凿岩巷道;8—炮孔;9—放砂槽;10—出矿巷道;11—装矿进路。The reference numbers are: 1-stope; 2-column; 3-filling inclined shaft; 4-filling main pipe; 5-filling contact tunnel; 6-filling branch pipe; 7-rock drilling tunnel; 8-blast hole; 9- Sand discharge trough; 10-mine tunnel; 11-mine loading approach.

具体实施方式Detailed ways

为更好地描述本发明,下面结合附图对本发明一种提高地下矿山端部放砂采场充填接顶率的方法做进一步详细描述。In order to better describe the present invention, a method for improving the top filling rate of sand caving stopes at the end of underground mines according to the present invention will be described in further detail below in conjunction with the accompanying drawings.

由图6所示的本发明一种提高地下矿山端部放砂采场充填接顶 率的方法的生产工艺流程图并结合图1、图2、图3、图4、图5看出,本发明一种提高地下矿山端部放砂采场充填接顶率的方法,采用以下步骤实施:It can be seen from the production process flow chart of a method for improving the filling and capping rate of sand discharge stopes at the end of underground mines according to the present invention shown in Figure 6 and combined with Figures 1, 2, 3, 4 and 5 that this method Invent a method to improve the top-filling rate of sand-capping stopes at the end of underground mines, and adopt the following steps to implement it:

1)沿矿体走向每隔40~80m布置一个采场1,在采场1内每13~18m形成1个分区,两相邻采场1间留间柱2;采场1高度10~100m,间柱2宽10m~20m。1) Arrange a stope 1 every 40 to 80m along the direction of the ore body, and form a partition every 13 to 18m in the stope 1. Leave a column 2 between two adjacent stopes; the height of the stope 1 is 10 to 100m. , the width of the intercolumn 2 is 10m~20m.

以采场1长度45m为例,在采场1内每15m形成1个分区,从而将采场1沿矿体走向划分成Ⅰ区、Ⅱ区和Ⅲ区共3个分区,Ⅰ区、Ⅱ区、Ⅲ区距端部放砂点由远及近,Ⅲ区距端部放砂点0~15m范围,Ⅱ区距端部放砂点15~30m范围,其余为Ⅰ区。Taking the length of stope 1 as 45m as an example, a zone is formed every 15m in stope 1. Therefore, stope 1 is divided into three zones along the direction of the ore body: Zone I, Zone II and Zone III. Zone I and Zone II , Area III is from far to near from the end sand placing point, area III is in the range of 0 to 15m from the end sand placing point, area II is in the range of 15 to 30m from the end sand placing point, and the rest is area I.

2)完成采场采切工程:包括凿岩巷道7、出矿巷道10、装矿进路11及相应的切割工程;凿岩巷道7、出矿巷道10、装矿进路11位于采场1的下部,凿岩巷道7、装矿进路11沿矿体走向布置,凿岩巷道7与装矿进路11之间通过出矿巷道10垂直连通。2) Complete the stope mining and cutting project: including rock drilling tunnel 7, mining tunnel 10, ore loading approach 11 and corresponding cutting engineering; rock drilling tunnel 7, mining tunnel 10, ore loading approach 11 are located in stope 1 In the lower part, the rock drilling tunnel 7 and the ore loading approach 11 are arranged along the direction of the ore body. The rock drilling tunnel 7 and the ore loading approach 11 are vertically connected through the ore exit tunnel 10.

3)完成充填巷道及吊挂充填管路:在采场1两端矿体顶板较高的间柱2内布置充填斜井3,将充填主管4吊挂在充填斜井3的巷道顶板,自充填斜井3靠近采场1顶部区域向采场1掘充填联络巷道5,并将充填支管6接入采场1内;所述的充填斜井3坡度与矿体倾角基本一致,充填斜井1的底板高于矿体顶板接触带1~2m。3) Complete the filling tunnel and hanging filling pipeline: arrange the filling inclined shaft 3 in the higher intercolumn 2 of the ore body roof at both ends of the stope 1, hang the filling main pipe 4 on the tunnel roof of the filling inclined shaft 3, and automatically The filling inclined shaft 3 is close to the top area of the stope 1, and the filling contact tunnel 5 is dug toward the stope 1, and the filling branch pipe 6 is connected to the stope 1; the slope of the filling inclined shaft 3 is basically consistent with the inclination of the ore body, and the filling inclined shaft 3 is basically consistent with the inclination of the ore body. The bottom plate of 1 is 1~2m higher than the contact zone of the ore body roof.

4)采场各分区放砂槽高度确定:在凿岩巷道7内向各分区的采场凿炮孔8,通过逐区加深炮孔8深度的方法在采场1顶部形成阶梯式放砂槽9,各分区的放砂槽9高度根据空区充填区域距端部放砂点距离的远近不同并结合充填料浆的自流坡度确定,以确保空区顶板平均坡度大于或等于充填料浆的自流坡度,以满足自然接顶要求。4) Determine the height of the sand discharge trough in each zone of the stope: Drill blast holes 8 into the stopes of each zone in the rock drilling tunnel 7, and form a stepped sand release trough 9 on the top of the stope 1 by deepening the depth of the blast holes 8 zone by zone. The height of the sand discharge trough 9 in each partition is determined based on the distance between the filling area of the empty area and the end sand discharge point and the gravity gradient of the filling slurry to ensure that the average slope of the roof of the void area is greater than or equal to the gravity gradient of the filling slurry. , to meet the requirements of natural top connection.

根据空区充填区域距端部放砂点距离的远近不同,距端部放砂点越远,放砂槽9高于矿体顶板接触带的高度越小,直至放砂槽9高度等于矿体顶板接触带。参照充填料浆的自流坡度通常在4~8%之间, 以采场1长度45m为例,并将采场1划分为3个分区为例,距离放砂点30~45m范围的Ⅰ区,放砂槽9高度等于矿体顶板接触带;距离放砂点15~30m范围的Ⅱ区,放砂槽9高于矿岩顶板接触带1.2~2.4m,距离放砂点0~15m范围的Ⅲ区,放砂槽9高于矿体顶板接触带2.4~4.0m。According to the distance between the empty area filling area and the end sand discharge point, the farther away from the end sand discharge point, the smaller the height of the sand discharge trough 9 above the contact zone of the ore body roof, until the height of the sand discharge trough 9 is equal to the ore body Top plate contact strip. Referring to the gravity slope of the filling slurry, which is usually between 4 and 8%, take the length of stope 1 as an example, which is 45m, and divide stope 1 into three zones as an example. Zone I is 30 to 45m away from the sand discharge point. The height of the sand discharge trough 9 is equal to the ore body roof contact zone; in zone II, which is 15 to 30m away from the sand release point, the sand release trough 9 is 1.2 to 2.4m higher than the ore roof contact zone, and in zone III, which is 0 to 15m away from the sand release point. area, the sand discharge trough 9 is 2.4 to 4.0m higher than the ore body roof contact zone.

5)采场落矿:以采场端部放砂点另一端的切割空间为自由面,在凿岩巷道7向端部放砂点后退式爆破,矿石落入凿岩巷道7内。5) Ore falling in the stope: The cutting space at the other end of the sand placing point at the end of the stope is used as the free surface, and the rock drilling tunnel 7 is blasted backwards toward the end sand placing point, and the ore falls into the rock drilling tunnel 7 .

以将采场1划分为3个分区为例,Ⅰ区端部的切割空间为自由面,在凿岩巷道7内向Ⅱ区和Ⅲ区后退式爆破Taking the stope 1 divided into three zones as an example, the cutting space at the end of zone I is the free surface, and retreat blasting is performed in zone II and zone III in the rock drilling tunnel 7.

6)矿石运搬:采用铲运机,将凿岩巷道7内的矿石经出矿巷道10、装矿进路11运至溜井卸矿。6) Ore transportation: Use a scraper to transport the ore in the rock drilling tunnel 7 through the ore exit tunnel 10 and the ore loading approach 11 to the slide shaft for unloading.

7)空区充填:采场回采结束后,封闭空区下部的通道,通过充填主管4、充填支管5对空区进行分次充填,确保充填效果。7) Filling of the empty area: After the stope mining is completed, the channel at the lower part of the empty area is closed, and the empty area is filled in stages through the filling main pipe 4 and the filling branch pipe 5 to ensure the filling effect.

本发明采用阶梯式放砂槽方案,根据充填区域距放砂点距离不同,结合充填料浆的自流坡度,通过炮孔深度设置不同高度的放砂槽,使空区顶板平均坡度大于或等于料浆的自流坡度,以满足自然接顶要求,解决采场充填接顶的难题,控制了地压活动,保障了采矿生产安全。同时,采用延深炮孔方式形成小断面的放砂槽,有效控制了充填成本和矿石贫化率。The present invention adopts a stepped sand discharging trough scheme. According to the different distances between the filling area and the sand discharging point, combined with the gravity slope of the filling slurry, sand discharging troughs of different heights are set up through the depth of the blast hole, so that the average slope of the roof of the empty area is greater than or equal to that of the material. The self-flowing slope of the slurry can meet the requirements of natural roof connection, solve the problem of stope filling and roof connection, control the ground pressure activity, and ensure the safety of mining production. At the same time, the method of extending the blast hole is used to form a sand discharge trough with a small cross-section, which effectively controls the filling cost and the ore dilution rate.

本发明方法已经分别在某大型地下铁矿充填开采中进行工业试验,实现充填接顶率100%,取得了意想不到的技术效果,有力地保障了回采过程中的安全。The method of the invention has been industrially tested in a certain large-scale underground iron ore filling and mining, achieving 100% filling and top connection rate, achieving unexpected technical effects, and effectively ensuring safety in the mining process.

Claims (5)

一种提高地下矿山端部放砂采场充填接顶率的方法,其特征在于采用以下步骤实施:A method for improving the top-filling rate of sand-capping stopes at the end of underground mines, which is characterized by adopting the following steps: 1)沿矿体走向每隔40~80m布置一个采场(1),在采场(1)内每13~18m形成1个分区,两相邻采场(1)间留间柱(2);1) Arrange a stope (1) every 40 to 80m along the direction of the ore body, form a partition every 13 to 18m in the stope (1), and leave a spacing column (2) between two adjacent stopes (1) ; 2)完成采场采切工程:包括凿岩巷道(7)、出矿巷道(10)、装矿进路(11)及相应的切割工程;凿岩巷道(7)、出矿巷道(10)、装矿进路(11)位于采场(1)的下部,凿岩巷道(7)、装矿进路(11)沿矿体走向布置,凿岩巷道(7)与装矿进路(11)之间通过出矿巷道(10)连通;2) Complete the stope mining and cutting project: including rock drilling tunnel (7), mining tunnel (10), ore loading approach (11) and corresponding cutting engineering; rock drilling tunnel (7), mining tunnel (10) The ore loading approach (11) is located at the lower part of the stope (1). The rock drilling tunnel (7) and the ore loading approach (11) are arranged along the direction of the ore body. The rock drilling tunnel (7) and the ore loading approach (11) are ) are connected through the mining tunnel (10); 3)完成充填巷道及吊挂充填管路:在采场(1)两端矿体顶板较高的间柱(2)内布置充填斜井(3),将充填主管(4)吊挂在充填斜井(3)的巷道顶板,自充填斜井(3)靠近采场(1)顶部区域向采场(1)掘充填联络巷道(5),并将充填支管(6)接入采场(1)内;3) Complete the filling tunnel and hanging filling pipeline: arrange the filling inclined shaft (3) in the higher intercolumn (2) of the ore body roof at both ends of the stope (1), and hang the filling main pipe (4) on the filling The roadway roof of the inclined shaft (3) is self-filled. The inclined shaft (3) is close to the top area of the stope (1) and the filling contact tunnel (5) is dug toward the stope (1). The filling branch pipe (6) is connected to the stope (1). 1) within; 4)采场各分区放砂槽高度确定:在凿岩巷道(7)内向各分区的采场凿炮孔(8),通过逐区加深炮孔(8)深度的方法在采场(1)顶部形成阶梯式放砂槽(9),各分区的放砂槽(9)高度根据空区充填区域距端部放砂点距离的远近不同并结合充填料浆的自流坡度确定,以确保空区顶板平均坡度大于或等于充填料浆的自流坡度,以满足自然接顶要求;4) Determine the height of the sand discharge trough in each zone of the stope: drill blast holes (8) into the stopes of each zone in the rock drilling tunnel (7), and deepen the depth of the blast holes (8) zone by zone in the stope (1) A stepped sand discharging trough (9) is formed on the top. The height of the sand discharging trough (9) in each partition is determined according to the distance between the empty area filling area and the end sand discharging point and combined with the gravity slope of the filling slurry to ensure that the empty area The average slope of the roof is greater than or equal to the gravity slope of the filling slurry to meet the requirements of natural roof connection; 5)采场落矿:以采场端部放砂点另一端的切割空间为自由面,在凿岩巷道(7)向端部放砂点后退式爆破,矿石落入凿岩巷道(7)内;5) Ore falling in the stope: The cutting space at the other end of the sand placing point at the end of the stope is used as the free surface, and the rock drilling tunnel (7) is blasted backward toward the end sand placing point, and the ore falls into the rock drilling tunnel (7) Inside; 6)矿石运搬:采用铲运机,将凿岩巷道(7)内的矿石经出矿巷道(10)、装矿进路(11)运至溜井卸矿;6) Ore transportation: Use a scraper to transport the ore in the rock drilling tunnel (7) through the ore exit tunnel (10) and the ore loading approach (11) to the slide shaft for unloading; 7)空区充填:采场回采结束后,封闭空区下部的通道,通过充填主管(4)、充填支管(5)对空区进行分次充填。7) Filling of the empty area: After the stope mining is completed, the channel at the lower part of the empty area is closed, and the empty area is filled in batches through the filling main pipe (4) and the filling branch pipe (5). 如权利要求1所述的一种提高地下矿山端部放砂采场充填接顶率的方法,其特征在于:所述采场(1)高度10~100m,间柱(2)宽10m~20m。A method for improving the filling and capping rate of a sand-capping stope at the end of an underground mine as claimed in claim 1, characterized in that: the stope (1) is 10-100m in height, and the intercolumn (2) is 10m-20m wide . 如权利要求1或2所述的一种提高地下矿山端部放砂采场充填接顶率的方法,其特征在于:所述的充填斜井(3)坡度与矿体倾角一致,充填斜井(1)的底板高于矿体顶板接触带1~2m。A method for improving the filling and capping rate of sand mining stopes at the end of underground mines according to claim 1 or 2, characterized in that: the slope of the filling inclined shaft (3) is consistent with the inclination of the ore body, and the filling inclined shaft The bottom plate of (1) is 1~2m higher than the contact zone of the ore body roof. 如权利要求3所述的一种提高地下矿山端部放砂采场充填接顶率的方法,其特征在于:根据空区充填区域距端部放砂点距离的远近不同,距端部放砂点越远,放砂槽(9)高于矿体顶板接触带的高度越小,直至放砂槽(9)高度等于矿体顶板接触带。A method for improving the top-filling rate of the sand discharge stope at the end of an underground mine as claimed in claim 3, characterized in that: according to the distance between the empty area filling area and the end sand discharge point, the distance from the end sand discharge point is different. The further the point is, the smaller the height of the sand discharge trough (9) above the ore body roof contact zone is, until the height of the sand discharge trough (9) is equal to the ore body roof contact zone. 如权利要求4所述的一种提高地下矿山端部放砂采场充填接顶率的方法,其特征在于:将采场(1)沿矿体走向划分成Ⅰ区、Ⅱ区和Ⅲ区共3个分区,Ⅰ区、Ⅱ区、Ⅲ区距端部放砂点由远及近,Ⅰ区放砂槽(9)高度等于矿体顶板接触带;Ⅱ区放砂槽(9)高于矿岩顶板接触带1.2~2.4m;Ⅲ区放砂槽(9)高于矿体顶板接触带2.4~4.0m。A method for improving the filling and capping rate of a sand-capping stope at the end of an underground mine as claimed in claim 4, characterized in that: the stope (1) is divided into a total of area I, area II and area III along the direction of the ore body. There are 3 zones, Zone I, Zone II and Zone III are from far to near from the end sand discharge point. The height of the sand discharge trough (9) in Zone I is equal to the contact zone of the ore body roof; the height of the sand discharge trough (9) in Zone II is higher than the ore body roof contact zone. The rock roof contact zone is 1.2-2.4m; the sand discharge trough (9) in zone III is 2.4-4.0m higher than the ore body roof contact zone.
PCT/CN2022/092439 2022-04-14 2022-05-12 Method for increasing roof-contacted filling rate of underground mine end sand discharging stope WO2023197392A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
ZA2023/02412A ZA202302412B (en) 2022-04-14 2023-02-23 Method for improving roof-contacted filling rate of end sand discharging stope in underground mines

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210393029.5A CN114753843B (en) 2022-04-14 2022-04-14 Method for improving filling and roof-contacting rate of sand-discharging stope at end part of underground mine
CN202210393029.5 2022-04-14

Publications (1)

Publication Number Publication Date
WO2023197392A1 true WO2023197392A1 (en) 2023-10-19

Family

ID=82330855

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/092439 WO2023197392A1 (en) 2022-04-14 2022-05-12 Method for increasing roof-contacted filling rate of underground mine end sand discharging stope

Country Status (3)

Country Link
CN (1) CN114753843B (en)
WO (1) WO2023197392A1 (en)
ZA (1) ZA202302412B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117451976A (en) * 2023-12-25 2024-01-26 山东黄金矿业科技有限公司充填工程实验室分公司 Indoor experimental device for simulating filling of underground metal mine stope

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115263321B (en) * 2022-08-09 2024-12-27 紫金(长沙)工程技术有限公司 A tunnel construction method capable of improving the filling and top connection rate of goaf areas

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4265570A (en) * 1979-06-01 1981-05-05 Conoco, Inc. Mine roof control
CN103615285A (en) * 2013-12-04 2014-03-05 南京银茂铅锌矿业有限公司 Stope route arrangement mode and method beneficial to roof-contacted filling
CN109339783A (en) * 2018-11-15 2019-02-15 中国恩菲工程技术有限公司 The route open stope afterwards filling mining method of gently inclined medium thick orebody
CN110359914A (en) * 2019-08-19 2019-10-22 中钢集团马鞍山矿山研究院有限公司 A kind of safe, inexpensive combined section mining methods of gently inclined medium thick orebody
CN110886612A (en) * 2019-11-13 2020-03-17 铜陵有色金属集团股份有限公司 Mining method suitable for continuous mining of gently inclined medium-thickness ore body
CN113565508A (en) * 2021-08-03 2021-10-29 长沙矿山研究院有限责任公司 Open stope subsequent filling mining method for V-shaped top column subsection rock drilling stage of medium-thickness ore body
CN114810072A (en) * 2022-04-14 2022-07-29 中钢集团马鞍山矿山研究总院股份有限公司 Structural arrangement mode for improving filling and roof-contacting rate of end sand-discharging stope

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100441831C (en) * 2003-12-11 2008-12-10 云南驰宏锌锗股份有限公司 Ladder type mining method using united pillars to support roof and partition stope
AU2013207575B2 (en) * 2012-07-20 2016-10-20 Jollan Kingsley Stope fill barrier
CN109083644B (en) * 2018-08-16 2019-08-02 中南大学 A kind of safe and efficient mining methods of gently inclined medium thick orebody
CN110778316B (en) * 2019-11-19 2020-12-25 深圳市中金岭南有色金属股份有限公司 Sublevel rock drilling stage open stope subsequent filling mining method adopting arched-arch-shaped top pillar structure
CN114087016B (en) * 2021-12-03 2023-09-26 武钢资源集团金山店矿业有限公司 A method for pre-control support of isolated top pillars in caving-to-fill mining

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4265570A (en) * 1979-06-01 1981-05-05 Conoco, Inc. Mine roof control
CN103615285A (en) * 2013-12-04 2014-03-05 南京银茂铅锌矿业有限公司 Stope route arrangement mode and method beneficial to roof-contacted filling
CN109339783A (en) * 2018-11-15 2019-02-15 中国恩菲工程技术有限公司 The route open stope afterwards filling mining method of gently inclined medium thick orebody
CN110359914A (en) * 2019-08-19 2019-10-22 中钢集团马鞍山矿山研究院有限公司 A kind of safe, inexpensive combined section mining methods of gently inclined medium thick orebody
CN110886612A (en) * 2019-11-13 2020-03-17 铜陵有色金属集团股份有限公司 Mining method suitable for continuous mining of gently inclined medium-thickness ore body
CN113565508A (en) * 2021-08-03 2021-10-29 长沙矿山研究院有限责任公司 Open stope subsequent filling mining method for V-shaped top column subsection rock drilling stage of medium-thickness ore body
CN114810072A (en) * 2022-04-14 2022-07-29 中钢集团马鞍山矿山研究总院股份有限公司 Structural arrangement mode for improving filling and roof-contacting rate of end sand-discharging stope

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117451976A (en) * 2023-12-25 2024-01-26 山东黄金矿业科技有限公司充填工程实验室分公司 Indoor experimental device for simulating filling of underground metal mine stope
CN117451976B (en) * 2023-12-25 2024-03-08 山东黄金矿业科技有限公司充填工程实验室分公司 Indoor experimental device for simulating filling of underground metal mine stope

Also Published As

Publication number Publication date
ZA202302412B (en) 2023-05-31
CN114753843B (en) 2023-01-20
CN114753843A (en) 2022-07-15

Similar Documents

Publication Publication Date Title
CN109083644B (en) A kind of safe and efficient mining methods of gently inclined medium thick orebody
CN102011589B (en) Stope bottom structure suitable for underground two-step mining and production process thereof
CN102704934B (en) High-yield and low-cost subsequent filling mining method for underground mine
CN106894817B (en) A kind of mechanization Upward slicing wedging mixed filling mining codes
CN110259451B (en) A kind of high-efficiency mining method with pre-controlled roof for gently sloping medium-thick orebodies
CN106869933B (en) A method of block is filled to stop adopting coal pillar width in conjunction with reduction super high seam
CN103437769B (en) Combination is reproduced structure medium-length hole ore blast and is worked in coordination with cable bolting afterwards filling mining method
CN102155228A (en) Fully-segmented presplitting squeezing primary-blasting mining method
CN104405436B (en) A kind of method improving ore body Tight filling rate
CN110295908B (en) A kind of undulating and segmented roadway gently sloping medium-thick orebody mining method
CN107829742B (en) Caving-filling-open stope-caving mining method
CN112796758B (en) Open stoping subsequent filling mining method at deep hole stage in high-section no-cutting raise pull groove
CN103628878B (en) Under breaking surrounding rock ore body to route layering without segmentation tunnel filling mining methods
CN104060991A (en) Upward cut-and-fill mining method for in-vein slope ramp of gentle dip thin vein
CN103437768B (en) Pre-set space filling mining method without top column and bottom column
WO2023197392A1 (en) Method for increasing roof-contacted filling rate of underground mine end sand discharging stope
CN108625855B (en) Mining method under filling body
CN109339785B (en) A kind of intensive mining methods of gently inclined medium thick orebody multiple-unit combination
CN113202475A (en) Filling caving mining method
CN103437766B (en) In-situ fragmentation mining method
CN104806243B (en) A kind of wedge shape switching transition method of open air trestle exploitation
CN110080774A (en) Mine Dry-placed fill mining is fallen based on the vertical medium-length hole retrusive of high-dipping ore block
CN103982186B (en) The vertical Inclined strips sublevel caving of oper cylinler retrusive
CN102635357A (en) Pillarless phased caving method with top tailing crushed stone filling and sectional water injection binding
CN104989408A (en) Safe and high-efficiency mining method for metal mine in mountainous area

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22937034

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE